Water Resources and Irrigation Government Departments Closing in 3 days TDR #57889970

Tender For Supply , Construction, Trial Run And Commissioning Of 15 Kld Grey Water Treatment Unit At Rit P Ady Gp, Kottayam District

Issued by Government Departments · Kottayam, Kerala
Tender Value
50.71 Lakhs
Estimated cost
Bid Submission
18 Nov 2026
3 days left
EMD
50000
Bank guarantee accepted
Document Fee
2500
Non-refundable
Tender Type
Online

Tender Overview

Competition Type
NCB
Bidding Type
Tender
Location / State
Kottayam → Kerala
EMD Exemption
Not Available
Quantity
Not Available

Project Description

Tender for Supply , Construction, Trial Run And Commissioning Of 15 Kld Grey Water Treatment Unit At Rit P Ady Gp, Kottayam District

Corrigendum

Sr No Corrigendum Date Corrigendum Type New Submission Date
1 17-Oct-2026 DATE EXTENSION Date 11-Nov-2026
2 06-Nov-2026 EXTENSION Date 18-Nov-2026
3 17-Oct-2026 DATE EXTENSION Date 11-Nov-2026

BOQ

Name of Work:- Supply , Construction, trial run and commissioning of 15 KLD grey water treatment Unit at RIT P ady GP, Kottayam District
Sl. No. Item Description
1INITIAL COLLECTION TANK
2Clearing grass and removal of the rubbish up to a distance of 50 m outside the periphery of the area
3Earth work in excavation by mechanical means (Hydraulic excavator) /manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift up to 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m.All kinds of soil
4Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:2:4 (cement : 2 coarse sand (zone-III)derived from natural sources : 4 graded stone aggregate 20 mm nominal size derived from natural sources)
5Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level:1:1:5:3 (1 cement 1.5 coarse sand :3 graded stone aggregate 20 mm nominal size derived from natural sources)
6Centering and shuttering including strutting, etc. and removal of form for:Foundations, footings, bases of columns, etc for mass concrete
7Centering and shuttering including strutting, etc. and removal of form for:Walls (any thickness) including attached pilasters, butteresses, plinth and string courses etc.
8Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete upto plinth levelThermo - Mechanically Treated bars of grade Fe-500D or more
912 mm cement plaster mix:1:4( 1 cement : 4 fine sand)
1012 mm cement plaster finished with a floating coat of neat cement of mix:1:3 ( 1 cement : 3 fine sand)
11Finishing walls with water proofing cement paint of required shade:New work (Two or more coats applied @ 3.84 kg/10 sqm)
12Supplying and fixing CI manhole cover of size 60cmx60cm with locking arrangements ncluding cost and conveyance of all material and labour charges etccomplete
13NOWA platform and protection work
14Clearing grass and removal of the rubbish up to a distance of 50 m outside the periphery of the area
15Earth work in excavation by mechanical means (Hydraulic excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including dressing of sides and ramming of bottom ,lift upto 1.5m, including getting out and disposal of excavated earth lead upto 50 m and lift upto 1.5 m, as directed by Engineer-in-charge.All kinds of soil
16Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:2:4 (cement : 2 coarse sand (zone-III)derived from natural sources : 4 graded stone aggregate 20 mm nominal size derived from natural sources)
17Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level:1:1:5:3 (1 cement 1.5 coarse sand :3 graded stone aggregate 20 mm nominal size derived from natural sources)
18Centering and shuttering including strutting, etc. and removal of form for:Foundations, footings, bases of columns, etc for mass oncrete
19Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete upto plinth levelThermo - Mechanically Treated bars of grade Fe-500D or more
20Filling with contractor's own earth ( excluding rock) in trenches, plinth, sides of foundations etc. in layers not exceeding 20 cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift up to 1.5 m as per direction of site Engineer-in-charge
2112 mm cement plaster of mix:1:4 ( 1 cement : 4 fine sand)
22Finishing walls with water proofing cement paint of required shade:New work (Two or more coats applied @ 3.84 kg/10 sqm)
23Providing corrugate G.S. sheet roofing including vertical/ curved surface fixed with polymer coated J or L hooks, bolts and nuts 8 mm diameter with bitumen and G.I. limpet washers or with G.I. limpet washers filled with white lead, including a coat of approved steel primer and two coats of approved paint on overlapping of sheets complete ( up to any pitch in horizontal / vertical or curved surfaces), excluding the cost of purlins, rafters and trusses and including cutting to size and shape wherever required.0.63 mm thick with zinc coating not less than 275 gm/m2
24Providing and fixing hard drawn steel wire fabric of size 75 x25 mm mesh or other suitable size wire mesh to be fixed & firmly anchored to the concrete surface by means of \\"L\\" shaped mild steel shear key welded with existing reinforcement including the cost of materials, labour, tool & plants as approved by Engineer-incharge.
25Steel work in built up tubular (round, square or rectangular hollow tubes etc.) trusses etc., including cutting, hoisting, fixing position and applying a priming coat of approved steel primer, including welding and bolted with special shaped washers etc. complete.Hot finished welded type tubes
26supplying and installation of NOWA including all accessories,required pumpsets and painting etc complete
27WET LAND
28Clearing grass and removal of the rubbish up to a distance of 50 m outside the periphery of the area cleared.
29Earth work in excavation by mechanical means (Hydraulic excavator) /manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift up to 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m. All kinds of soil
30Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:2:4 (cement : 2 coarse sand (zone-III)derived from natural sources : 4 graded stone aggregate 20 mm nominal size derived from natural sources)
31Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level:1:1:5:3 (1 cement 1.5 coarse sand :3 graded stone aggregate 20 mm nominal size derived from natural sources)
32Reinforced cement concrete work in walls (any thickness), including attached pilasters, buttresses, plinth and string courses, fillets, columns, pillars, piers, abutments, posts and struts etc. up tot floor five level excluding cost of centering, shuttering, finishing and reinforcement :1:1.5:3( 1 cement : 1.5 coarse sand : 3 graded stone aggregate 20 mm nominal size derived from natural sources)
33Centering and shuttering including strutting, etc. and removal of form for:Foundations, footings, bases of columns, etc for mass oncrete
34Centering and shuttering including strutting, etc. and removal of form for:Walls (any thickness) including attached pilasters, utteresses, plinth and string courses etc.
35Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete upto plinth levelThermo - Mechanically Treated bars of grade Fe-500D or more
3612 mm cement plaster of mix:1:4 ( 1 cement : 4 fine sand)
3712 mm cement plaster finished with a floating coat of neat cement of mix:1:3 ( 1 cement : 3 fine sand)
38Finishing walls with water proofing cement paint of required shade:New work (Two or more coats applied @ 3.84 kg/10 sqm)
39Supplying, sieving, stacking and spreading 40mm broken stone in the gallery trenches as per standard norms including cost of all materials.
40Supplying, sieving, stacking and spreading 20mm to 12.5mm broken stone in the gallery trenches as per standard norms including cost of all materials.
41Supplying of 2 to 6 mm and 6 to 12 mm size fine pebble (pebbles shall be hard, clean, free from clay, dust and other impurities), stacking in standard heaps for measurement including cost, conveyance up to 5 km and labour charges for stacking, spreading, testing and as per the directions of the department officers etc. complete as per CPHEEO specifications.
42PROVIDING PLANT FOR WET LAND
43FINAL COLLECTION TANK
44Clearing grass and removal of the rubbish up to a distance of 50 m outside the periphery of the area
45Earth work in excavation by mechanical means (Hydraulic excavator) /manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift up to 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m.All kinds of soil
46Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:2:4 (cement : 2 coarse sand (zone-III)derived from natural sources : 4 graded stone aggregate 20 mm nominal size derived from natural sources)
47Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level:1:1:5:3 (1 cement 1.5 coarse sand :3 graded stone aggregate 20 mm nominal size derived from natural sources)
48Centering and shuttering including strutting, etc. and removal of form for:Walls (any thickness) including attached pilasters, butteresses, plinth and string courses etc.
49Centering and shuttering including strutting, etc. and removal of form for:Foundations, footings, bases of columns, etc for mass concrete
50Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete upto plinth levelThermo - Mechanically Treated bars of grade Fe-500D or more
5112 mm cement plaster of mix:1:4 ( 1 cement : 4 fine sand)
5212 mm cement plaster finished with a floating coat of neat cement of mix:1:3 ( 1 cement : 3 fine sand)
53Finishing walls with water proofing cement paint of required shade:New work (Two or more coats applied @ 3.84 kg/10 sqm)
54Supplying and installing Manhole cover with frame inluding all charges for hire material and labour as per the direction of departmental officer in charge
55PLUMBING WORK
56Supply of HDPE Pipe PE 100 (IS 4984/1995), 10kg, 75mm Outer Dia.
57Supply of HDPE Pipe PE 100 (IS 4984/1995), 10kg, 90mm Outer Dia.
58Supply of HDPE Pipe PE 100 (IS 4984/1995), 10kg, 110mm Outer Dia
59Supply of HDPE Pipe PE 100 (IS 4984/1995), 10kg, 140mm Outer Dia.
60Supply of HDPE Pipe PE 100 (IS 4984/1995), 10kg, 160mm Outer Dia.
61Supply of HDPE Pipe PE 100 (IS 4984/1995), 10kg, 200mm Outer Dia.
62Supply of PVC Pipe, 6kg/cm2, 75mm Dia.
63Supply of PVC Pipe, 6kg/cm2, 90mm Dia.
64Supply of PVC Pipe, 6kg/cm2, 110mm Dia.
65Laying uPVC pipes of class 2 to class 6 and specials, lowering to the trenches already made, placing in position aligning the pipeline to the lines and levels and jointing the pipes and specials with solvent cement and testing the pipeline with water to the required test pressure (excluding cost of pipes and specials): 75 mm nominal outside diameter pipes.
66Laying HDPE pipes (IS : 4984) on land portion including conveying within initial lead and aligning the pipes, electro-fusion welding using automatic or semi-automatic electrofusion machines, testing the pipeline thus fabricated to suit the hydraulic working pressure and after testing, aligning the pipeline, lowering the pipe in position into the trenches already made, testing the line to suitable pressure with potable water before back filling and levelling the trenches including all labour charge, hire for appliances etc., complete but excluding cost of pipe and fittings: 90mm Nominal Outer Diameter pipes.
67Laying HDPE pipes (IS : 4984) on land portion including conveying within initial lead and aligning the pipes, electro-fusion welding using automatic or semi-automatic electrofusion machines, testing the pipeline thus fabricated to suit the hydraulic working pressure and after testing, aligning the pipeline, lowering the pipe in position into the trenches already made, testing the line to suitable pressure with potable water before back filling and levelling the trenches including all labour charge, hire for appliances etc., complete but excluding cost of pipe and fittings: 110mm Nominal Outer Diameter pipes.
68Laying HDPE pipes (IS : 4984) on land portion including conveying within initial lead and aligning the pipes, electro-fusion welding using automatic or semi-automatic electrofusion machines, testing the pipeline thus fabricated to suit the hydraulic working pressure and after testing, aligning the pipeline, lowering the pipe in position into the trenches already made, testing the line to suitable pressure with potable water before back filling and levelling the trenches including all labour charge, hire for appliances etc., complete but excluding cost of pipe and fittings: 140mm Nominal Outer Diameter pipes.
69Laying HDPE pipes (IS : 4984) on land portion including conveying within initial lead and aligning the pipes, electro-fusion welding using automatic or semi-automatic electrofusion machines, testing the pipeline thus fabricated to suit the hydraulic working pressure and after testing, aligning the pipeline, lowering the pipe in position into the trenches already made, testing the line to suitable pressure with potable water before back filling and levelling the trenches including all labour charge, hire for appliances etc., complete but excluding cost of pipe and fittings: 160mm Nominal Outer Diameter pipes.
70Laying HDPE pipes (IS : 4984) on land portion including conveying within initial lead and aligning the pipes, electro-fusion welding using automatic or semi-automatic electrofusion machines, testing the pipeline thus fabricated to suit the hydraulic working pressure and after testing, aligning the pipeline, lowering the pipe in position into the trenches already made, testing the line to suitable pressure with potable water before back filling and levelling the trenches including all labour charge, hire for appliances etc., complete but excluding cost of pipe and fittings: 200mm Nominal Outer Diameter pipes.
71Laying uPVC pipes of class 2 to class 6 and specials, lowering to the trenches already made, placing in position aligning the pipeline to the lines and levels and jointing the pipes and specials with solvent cement and testing the pipeline with water to the required test pressure (excluding cost of pipes and specials): 90 mm nominal outside diameter pipes.
72Laying uPVC pipes of class 2 to class 6 and specials, lowering to the trenches already made, placing in position aligning the pipeline to the lines and levels and jointing the pipes and specials with solvent cement and testing the pipeline with water to the required test pressure (excluding cost of pipes and specials): 110 mm nominal outside diameter pipes.
73Excavating trenches of required width for pipes, cables, etc., including excavation for sockets, and dressing of sides, ramming of bottoms, depth up to 1.5m, including getting out the excavated soil, and then returning the soil as required, in layers not exceeding 20cm in depth, including consolidating each deposited layer by ramming, watering, etc., and disposing of surplus excavated soil as directed, within a lead of 50m, in all kinds of soil.
74Recharge pit and Soak pit
75Clearing grass and removal of the rubbish up to a distance of 50 m outside the periphery of the area cleared.
76Earth work in excavation by mechanical means (Hydraulic excavator) /manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift up to 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m.All kinds of soil
77Supplying, sieving, stacking and spreading 40mm broken stone in the gallery trenches as per standard norms including cost of all materials.
78Installation of precast ring of dia 1.2 m and depth 30 cm
79Supplying, sieving, stacking and spreading 20mm to 12.5mm broken stone in the gallery trenches as per standard norms including cost of all materials.
80Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level:1:1:5:3 (1 cement 1.5 coarse sand :3 graded stone aggregate 20 mm nominal size derived from natural sources)
81Centering and shuttering including strutting, etc. and removal of form for:Walls (any thickness) including attached pilasters, butteresses, plinth and string courses etc.
82Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete upto plinth levelThermo - Mechanically Treated bars of grade Fe-500D or more
83Inspection Chamber
84Earth work in excavation by mechanical means (Hydraulic excavator) /manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including ressing of sides and ramming of bottoms, lift up to 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m.All kinds of soil
85Providing and laying in position cement oncrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:2:4 (cement : 2 coarse sand (zone-III)derived from natural sources : 4 graded stone aggregate 20 mm nominal size derived from natural sources)
86Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level:1:1:5:3 (1 cement 1.5 coarse sand :3 graded stone aggregate 20 mm nominal size derived from natural sources)
87Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete upto plinth levelThermo - Mechanically Treated bars of grade Fe-500D or more
88Centering and shuttering including strutting, etc. and removal of form for:Walls (any thickness) including attached pilasters, butteresses, plinth and string courses etc.
8912 mm cement plaster finished with a floating coat of neat cement of mix:1:3 ( 1 cement : 3 fine sand)
90Supplying and installing Manhole cover with frame inluding all charges for hire material and labour as per the direction of departmental officer in charge
91PROTECTION WALL
92Clearing grass and removal of the rubbish up to a distance of 50 m outside the periphery of the area cleared.
93Earth work in excavation by mechanical means (Hydraulic excavator) /manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift up to 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m.All kinds of soil
94Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:2:4 (cement : 2 coarse sand (zone-III)derived from natural sources : 4 graded stone aggregate 20 mm nominal size derived from natural sources)
95Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level:1:1:5:3 (1 cement 1.5 coarse sand :3 graded stone aggregate 20 mm nominal size derived from natural sources)
96Reinforced cement concrete work in walls (any thickness), including attached pilasters, buttresses, plinth and string courses, fillets, columns, pillars, piers, abutments, posts and struts etc. up tot floor five level excluding cost of centering, shuttering, finishing and reinforcement :1:1.5:3( 1 cement : 1.5 coarse sand : 3 graded stone aggregate 20 mm nominal size derived from natural sources)
97Centering and shuttering including strutting, etc. and removal of form for:Foundations, footings, bases of columns, etc for mass oncrete
98Centering and shuttering including strutting, etc. and removal of form for:Walls (any thickness) including attached pilasters, utteresses, plinth and string courses etc.
99Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete upto plinth levelThermo - Mechanically Treated bars of grade Fe-500D or more Please Enable Macros to View BoQ information

AI Tender Summary

OUR REF NO 57889970
AUTHORITY Government Departments
TENDER VALUE 50.71 Lakhs
LAST DATE 18-11-2026
Authority
Authority Name Kerala Rural Water Supply And Sanitation Agency
Work Description Tender for Supply , Construction, Trial Run And Commissioning Of 15 Kld Grey Water Treatment Unit At Rit P Ady Gp, Kottayam District
Basic Detail
Tender No KRWSA/IDKI/TEN/SBM/02/26
Bidding Type Tender
Location
City Kottayam
State Kerala
Key Dates
Publish Date 06 Nov 2026
Submission Date 18 Nov 2026
Open Date 20 Nov 2026
Finance
Tender Value 50.71 Lakhs
Tender Fee 2500
EMD 50000
Exemption Not Available
Document List
BOQ_1489733.xls
c71986e9-cc37-4b01-b076-55f51e78c233.html
NITPAMPADY.pdf
Tendernotice_1.pdf

Unlock Full AI Tender Summary

Get instant access to the complete AI-generated analysis — scope, eligibility, timeline & more.

Instant Access Secure Free
Your details are secure and used only for document delivery.

Tender Timeline

Nov 06, 2026
11:30 IST

Tender Published

Tender notice published.

Completed
Nov 11, 2026
18:00 IST

Corrigendum-1 Issued

Clarifications on tender conditions and amendments issued.

Completed
Nov 18, 2026
18:00 IST

Corrigendum-2 Issued

Clarifications on tender conditions and amendments issued.

Upcoming · 3 days
Nov 11, 2026
18:00 IST

Corrigendum-3 Issued

Clarifications on tender conditions and amendments issued.

Completed
Nov 18, 2026
17:00 IST

Bid Submission Deadline

Online submission via eProcurement portal.

Upcoming · 3 days
Nov 20, 2026

Bid Opening Date

Technical bids will be opened and evaluated.

Upcoming · 5 days

Tender Documents

Download All (ZIP) ↓
xls

BOQ_1489733.xls

html

c71986e9-cc37-4b01-b076-55f51e78c233.html

pdf

NITPAMPADY.pdf

pdf

Tendernotice_1.pdf

Disclaimer

We takes all possible care for accurate & authentic tender information. However users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender