Tender For Providing Of Balance Water Supply Pipe Line And Providing Of functional house hold tap connection Detailed Project Report For Providing Sewerage Facility And Sewage Treatment Plant Providing Sewerge Facility ,Construction Of 2.50
Tender Overview
Project Description
Tender for Providing Of Balance Water Supply Pipe Line And Providing Of functional house hold tap connection Detailed Project Report For Providing Sewerage Facility And Sewage Treatment Plant Providing Sewerge Facility ,Construction Of 2.50 Mld Stp Augmentation Of W/S Scheme Dahar
Corrigendum
| Sr No | Corrigendum Date | Corrigendum | Type | New Submission Date |
|---|---|---|---|---|
| 1 | 23-Oct-2026 | Date Extension | Date | 30-Oct-2026 |
BOQ
| Sl. No. | Item Description |
| 1 | Supply , erection, jointing and commissioning of 10 sqmm ISI marked alluminium cable in trenches under ground for campus lightening including all labour jointing material complete in all respect. Supply erection testing of reputed make LED light 100 wats with fittings and accessories complete in all repects. Provision for suitable size switches boads along with switches including all material and labour complete in all respect. |
| 2 | Providing and fixing in position UPVC SWR Bend (110 m x 110 m) as per SI Manufacture of reputed firm complete in all respect. |
| 3 | Providing and fixing in position UPVC SWR Reducer (110 m x 90 m) as per SI Manufacture of reputed firm complete in all respect. |
| 4 | Providing and fixing in position UPVC SWR Door Foot Bend (110 m x 110 m) as per SI 13592 of E.D.C Manufacture of any other reputed firm complete in all respect. |
| 5 | COPPER CABLE: Supply, erection, testing and commissioning of IS marked 3 core Copper Cables, Solid Copper conductor up to 6sqmm and balance Stranded Copper, XLPE Insulated, cores laid up, PVC Inner sheathed, Armoured (Glavanised wire for cables up to 10x1.5sqmm, 8x2.5sqmm, 2x10sqmm, 3x10sqmm, 4x6sqmm and balance all galvanized steel strip), extruded PVC type ST2 Outer Sheathed, /1100 V grade as per IS 7098 (Part 1) 1988 with up to date amendments along with all accessories like thimble lugs etc for motors as per entire satisfaction of Engineer-in-charge complete in all respect. Make:Finolex / Havells / RR Cables. (35 Sqmm size) |
| 6 | COPPER CABLE: Supply, erection, testing and commissioning of IS marked 3 core Copper Cables, Solid Copper conductor up to 6sqmm and balance Stranded Copper, XLPE Insulated, cores laid up, PVC Inner sheathed, Armoured (Glavanised wire for cables up to 10x1.5sqmm, 8x2.5sqmm, 2x10sqmm, 3x10sqmm, 4x6sqmm and balance all galvanized steel strip), extruded PVC type ST2 Outer Sheathed, /1100 V grade as per IS 7098 (Part 1) 1988 with up to date amendments along with all accessories like thimble lugs etc for motors as per entire satisfaction of Engineer-in-charge complete in all respect. Make:Finolex / Havells / RR Cables. (50 Sqmm size) |
| 7 | `HT Metering Panel: Supply Indoor Type 11KV VCB Control Cubical Panel with vertical Isolation Type Breaker as per Relevant IS as amended up to Date and Additional Specifications, having Capacities as Mentioned Below, Single break trip free mechanism, manually charged and Auto/Manually closing breaker suitable for use on 11kv, 3 phase 50hz AC, Supply with short circuit fault level of 500 Amps Capacity, breaker featured with local ON/OFF indicator with hand trip device, spring release coil, shunt trip coil and auxiliary switch of 2NO plus 2NC and equipped with following switchgears and accessories including making suitable structure arrangement for installation, control wiring and connections etc. as reqd. (1 IC plus 2 OG)a). VCB, 11KV, 630Amp, 50KA.b). 1ph 11KV/110 Volts PT (indoor type) Class 0.2 Accuracy and 100 VA burden -3 no’s.c). 33KV indoor dead type dual core dual ratio 3CTs of ratio 200-100/5-5 A of 15 VA burden, PS 5 P10 and accuracy class 0.2.d). Control panel- Cubicle type control panel suitable for floor mounting made out of 1.63 mm CR sheet duly powder coated and with following relays.e). Microprocessor based numerical relay for O/L, E/F and SC Protection suitable for above.f). Master trip relay -2 no’s.g). Indicator type Annunciator panel with buzzer.h). Digital Volt Meter- 0-11 KV.i). Digital Amp Meter- 0-100 Amp.j). RYB/ Trip/Closing/Spring charged indicator lamp.k). Fault Annunciator panel for O/L, WTI, OTI and Buchhloz Relay Alarm And Trip Auxiliary relay.l). TNC Switch for Operation.m). Multifunction Meter EM6400NG.n). TCS Relay for Safe` |
| 8 | PANEL BOARDS FOR MOTORS: Supply, erection, testing and commissioning of wall mounted electrical LT Panel board, fabricated from 16 SWG CRCA sheet duly stouten with suitable angle iron frame work and completely powder coated of suitable size deep having following items for 1 Non clog Submersible Pumping a) Main switch suitable ampere 1 No. (LandT Siemens, ABB) b) CT 100/3 = 1 Nos. (AE/ KAPPA/ LandT) c) Digital Multi function meter = 1 No. d) SPP = 1 No. of approved make e) Motor starter, star delta 1 No (LandT Siemens, ABB) f) VSS 1 No. and ASS 1 Nos. of approved make. g) Capacitor KVAR as per site requirement = 1 No. h) Indicating Lamp = One Set i) Change over switch of suitable Amp = 1 No. (Each) 600 LPM X20.00 Mtr Head |
| 9 | STEEL BRIDGE: Design and construction of Structural steel bridge in built up sections, trusses and framed work, cutting, hoisting, fixing in position and applying a priming and final coat of approved steel primer / paint including design and construction of bridge foundation, thrust block and all other components complete in all respect for crossing the drain for laying the 250 mm i/d DI pipe line complete in all respect as per direction and satisfaction of Engineer-in-charge. |
| 10 | COPPER CABLE: Supply, erection, testing and commissioning of IS marked 3 core Copper Cables, Solid Copper conductor up to 6sqmm and balance Stranded Copper, XLPE Insulated, cores laid up, PVC Inner sheathed, Armoured (Glavanised wire for cables up to 10x1.5sqmm, 8x2.5sqmm, 2x10sqmm, 3x10sqmm, 4x6sqmm and balance all galvanized steel strip), extruded PVC type ST2 Outer Sheathed, /1100 V grade as per IS 7098 (Part 1) 1988 with up to date amendments along with all accessories like thimble lugs etc for motors as per entire satisfaction of Engineer-in-charge complete in all respect. Make: Indian Cables Ltd./ Finolex / Havells / Polycab / RR Cables.(35 Sqmm size) |
| 11 | PANEL BOARDS FOR MOTORS: Supply, erection, testing and commissioning of wall mounted electrical LT Panel board, fabricated from 16 SWG CRCA sheet duly stouten with suitable angle iron frame work and completely powder coated of suitable size deep having following items for 1 Non clog Submersible Pumping a) Main switch suitable ampere 1 No. (LandT Siemens, ABB) b) CT 100/3 = 1 Nos. (AE/ KAPPA/ LandT) c) Digital Multi function meter = 1 No. d) SPP = 1 No. of approved make e) Motor starter, star delta 1 No (LandT Siemens, ABB) f) VSS 1 No. and ASS 1 Nos. of approved make. g) Capacitor KVAR as per site requirement = 1 No. h) Indicating Lamp = One Set i) Change over switch of suitable Amp = 1 No. (Each) 6200 LPM X 15.00 HEAD |
| 12 | PANEL BOARDS FOR MOTORS: Supply, erection, testing and commissioning of wall mounted electrical LT Panel board, fabricated from 16 SWG CRCA sheet duly stouten with suitable angle iron frame work and completely powder coated of suitable size deep having following items for 1 Non clog Submersible Pumping a) Main switch suitable ampere 1 No. (LandT Siemens, ABB) b) CT 100/3 = 1 Nos. (AE/ KAPPA/ LandT) c) Digital Multi function meter = 1 No. d) SPP = 1 No. of approved make e) Motor starter, star delta 1 No (LandT Siemens, ABB) f) VSS 1 No. and ASS 1 Nos. of approved make. g) Capacitor KVAR as per site requirement = 1 No. h) Indicating Lamp = One Set i) Change over switch of suitable Amp = 1 No. (Each) 2100 LPM X 15.00 HEAD |
| 13 | PANEL BOARDS FOR MOTORS: Supply, erection, testing and commissioning of wall mounted electrical LT Panel board, fabricated from 16 SWG CRCA sheet duly stouten with suitable angle iron frame work and completely powder coated of suitable size deep having following items for 1 Non clog Submersible Pumping a) Main switch suitable ampere 1 No. (LandT Siemens, ABB) b) CT 100/3 = 1 Nos. (AE/ KAPPA/ LandT) c) Digital Multi function meter = 1 No. d) SPP = 1 No. of approved make e) Motor starter, star delta 1 No (LandT Siemens, ABB) f) VSS 1 No. and ASS 1 Nos. of approved make. g) Capacitor KVAR as per site requirement = 1 No. h) Indicating Lamp = One Set i) Change over switch of suitable Amp = 1 No. (Each) 3700 LPM X 25.00 HEAD |
| 14 | PANEL BOARDS FOR MOTORS: Supply, erection, testing and commissioning of wall mounted electrical LT Panel board, fabricated from 16 SWG CRCA sheet duly stouten with suitable angle iron frame work and completely powder coated of suitable size deep having following items for 1 Non clog Submersible Pumping a) Main switch suitable ampere 1 No. (LandT Siemens, ABB) b) CT 100/3 = 1 Nos. (AE/ KAPPA/ LandT) c) Digital Multi function meter = 1 No. d) SPP = 1 No. of approved make e) Motor starter, star delta 1 No (LandT Siemens, ABB) f) VSS 1 No. and ASS 1 Nos. of approved make. g) Capacitor KVAR as per site requirement = 1 No. h) Indicating Lamp = One Set i) Change over switch of suitable Amp = 1 No. (Each) 1300 LPM X 25.00 m. HEAD |
| 15 | COPPER CABLE: Supply, erection, testing and commissioning of IS marked 3 core Copper Cables, Solid Copper conductor up to 6sqmm and balance Stranded Copper, XLPE Insulated, cores laid up, PVC Inner sheathed, Armoured (Glavanised wire for cables up to 10x1.5sqmm, 8x2.5sqmm, 2x10sqmm, 3x10sqmm, 4x6sqmm and balance all galvanized steel strip), extruded PVC type ST2 Outer Sheathed, /1100 V grade as per IS 7098 (Part 1) 1988 with up to date amendments along with all accessories like thimble lugs etc for motors as per entire satisfaction of Engineer-in-charge complete in all respect. Make: Indian Cables Ltd./ Finolex / Havells / Polycab / RR Cables. (10 Sqmm size) |
| 16 | COPPER CABLE: Supply, erection, testing and commissioning of IS marked 3 core Copper Cables, Solid Copper conductor up to 6sqmm and balance Stranded Copper, XLPE Insulated, cores laid up, PVC Inner sheathed, Armoured (Glavanised wire for cables up to 10x1.5sqmm, 8x2.5sqmm, 2x10sqmm, 3x10sqmm, 4x6sqmm and balance all galvanized steel strip), extruded PVC type ST2 Outer Sheathed, /1100 V grade as per IS 7098 (Part 1) 1988 with up to date amendments along with all accessories like thimble lugs etc for motors as per entire satisfaction of Engineer-in-charge complete in all respect. Make: Indian Cables Ltd./ Finolex / Havells / Polycab / RR Cables. (16 Sqmm size) |
| 17 | COPPER CABLE: Supply, erection, testing and commissioning of IS marked 3 core Copper Cables, Solid Copper conductor up to 6sqmm and balance Stranded Copper, XLPE Insulated, cores laid up, PVC Inner sheathed, Armoured (Glavanised wire for cables up to 10x1.5sqmm, 8x2.5sqmm, 2x10sqmm, 3x10sqmm, 4x6sqmm and balance all galvanized steel strip), extruded PVC type ST2 Outer Sheathed, /1100 V grade as per IS 7098 (Part 1) 1988 with up to date amendments along with all accessories like thimble lugs etc for motors as per entire satisfaction of Engineer-in-charge complete in all respect. Make: Indian Cables Ltd./ Finolex / Havells / Polycab / RR Cables. (25 Sqmm size) |
| 18 | PANEL BOARDS FOR MOTORS: Supply, erection, testing and commissioning of wall mounted electrical LT Panel board, fabricated from 16 SWG CRCA sheet duly stouten with suitable angle iron frame work and completely powder coated of suitable size deep having following items for 1 Non clog Submersible Pumping a) Main switch suitable ampere 1 No. (LandT Siemens, ABB) b) CT 100/3 = 1 Nos. (AE/ KAPPA/ LandT) c) Digital Multi function meter = 1 No. d) SPP = 1 No. of approved make e) Motor starter, star delta 1 No (LandT Siemens, ABB) f) VSS 1 No. and ASS 1 Nos. of approved make. g) Capacitor KVAR as per site requirement = 1 No. h) Indicating Lamp = One Set i) Change over switch of suitable Amp = 1 No. (Each) 900 LPM X 25.00 M Head |
| 19 | PANEL BOARDS FOR MOTORS: Supply, erection, testing and commissioning of wall mounted electrical LT Panel board, fabricated from 16 SWG CRCA sheet duly stouten with suitable angle iron frame work and completely powder coated of suitable size deep having following items for 1 Non clog Submersible Pumping a) Main switch suitable ampere 1 No. (LandT Siemens, ABB) b) CT 100/3 = 1 Nos. (AE/ KAPPA/ LandT) c) Digital Multi function meter = 1 No. d) SPP = 1 No. of approved make e) Motor starter, star delta 1 No (LandT Siemens, ABB) f) VSS 1 No. and ASS 1 Nos. of approved make. g) Capacitor KVAR as per site requirement = 1 No. h) Indicating Lamp = One Set i) Change over switch of suitable Amp = 1 No. (Each) 2600 LPM X 25.00 M Head |
| 20 | PANEL BOARDS FOR MOTORS: Supply, erection, testing and commissioning of wall mounted electrical LT Panel board, fabricated from 16 SWG CRCA sheet duly stouten with suitable angle iron frame work and completely powder coated of suitable size deep having following items for 1 Non clog Submersible Pumping a) Main switch suitable ampere 1 No. (LandT Siemens, ABB) b) CT 100/3 = 1 Nos. (AE/ KAPPA/ LandT) c) Digital Multi function meter = 1 No. d) SPP = 1 No. of approved make e) Motor starter, star delta 1 No (LandT Siemens, ABB) f) VSS 1 No. and ASS 1 Nos. of approved make. g) Capacitor KVAR as per site requirement = 1 No. h) Indicating Lamp = One Set i) Change over switch of suitable Amp = 1 No. (Each) 800 LPM X 20.00 M Head |
| 21 | PANEL BOARDS FOR MOTORS: Supply, erection, testing and commissioning of wall mounted electrical LT Panel board, fabricated from 16 SWG CRCA sheet duly stouten with suitable angle iron frame work and completely powder coated of suitable size deep having following items for 1 Non clog Submersible Pumping a) Main switch suitable ampere 1 No. (LandT Siemens, ABB) b) CT 100/3 = 1 Nos. (AE/ KAPPA/ LandT) c) Digital Multi function meter = 1 No. d) SPP = 1 No. of approved make e) Motor starter, star delta 1 No (LandT Siemens, ABB) f) VSS 1 No. and ASS 1 Nos. of approved make. g) Capacitor KVAR as per site requirement = 1 No. h) Indicating Lamp = One Set i) Change over switch of suitable Amp = 1 No. (Each) 300 LPM X 20.00 M Head |
| 22 | PANEL BOARDS FOR MOTORS: Supply, erection, testing and commissioning of wall mounted electrical LT Panel board, fabricated from 16 SWG CRCA sheet duly stouten with suitable angle iron frame work and completely powder coated of suitable size deep having following items for 1 Non clog Submersible Pumping a) Main switch suitable ampere 1 No. (LandT Siemens, ABB) b) CT 100/3 = 1 Nos. (AE/ KAPPA/ LandT) c) Digital Multi function meter = 1 No. d) SPP = 1 No. of approved make e) Motor starter, star delta 1 No (LandT Siemens, ABB) f) VSS 1 No. and ASS 1 Nos. of approved make. g) Capacitor KVAR as per site requirement = 1 No. h) Indicating Lamp = One Set i) Change over switch of suitable Amp = 1 No. (Each) 4200 LPM X 15.00 M Head |
| 23 | PANEL BOARDS FOR MOTORS: Supply, erection, testing and commissioning of wall mounted electrical LT Panel board, fabricated from 16 SWG CRCA sheet duly stouten with suitable angle iron frame work and completely powder coated of suitable size deep having following items for 1 Non clog Submersible Pumping a) Main switch suitable ampere 1 No. (LandT Siemens, ABB) b) CT 100/3 = 1 Nos. (AE/ KAPPA/ LandT) c) Digital Multi function meter = 1 No. d) SPP = 1 No. of approved make e) Motor starter, star delta 1 No (LandT Siemens, ABB) f) VSS 1 No. and ASS 1 Nos. of approved make. g) Capacitor KVAR as per site requirement = 1 No. h) Indicating Lamp = One Set i) Change over switch of suitable Amp = 1 No. (Each) 2500 LPM X 25.00 M Head |
| 24 | PANEL BOARDS FOR MOTORS: Supply, erection, testing and commissioning of wall mounted electrical LT Panel board, fabricated from 16 SWG CRCA sheet duly stouten with suitable angle iron frame work and completely powder coated of suitable size deep having following items for 1 Non clog Submersible Pumping a) Main switch suitable ampere 1 No. (LandT Siemens, ABB) b) CT 100/3 = 1 Nos. (AE/ KAPPA/ LandT) c) Digital Multi function meter = 1 No. d) SPP = 1 No. of approved make e) Motor starter, star delta 1 No (LandT Siemens, ABB) f) VSS 1 No. and ASS 1 Nos. of approved make. g) Capacitor KVAR as per site requirement = 1 No. h) Indicating Lamp = One Set i) Change over switch of suitable Amp = 1 No. (Each) 1800 LPM X 25.00 M Head |
| 25 | ANNEXE BUILDING: Construction of HT / LT Panel room, PLC room, Blower room and Lab cum Office building, Toilet block including doors, windows, finishing, electric, and sanitary fittings complete in all respect as per drawings approved by SE. The building will be built up with RCC frame structure and brick work as per specifications mentioned in attached additional documents including operation and maintenance cum defect liability period of 6 years after successful completion of 3 months trial run period. |
| 26 | STP (SEWAGE TREATMENT PLANT): 2.50 MLD: Design, construction, erection, testing and commissioning of 2.50 MLD capacity Sewage Treatment Plant based on Sequential Batch Reactor (SBR) including Electrical, Mechanical, Piping and Instrumentation work with PLC and SCADA arrangement for STP integrated with MPS and other works contingent thereto including 3 months successful trial-run and thereafter 6 Years Defect Liability-cum-Maintenance Period as per detail and specifications mentioned in DNIT along with following provisions 1.1 2 No. High Mast of 9 mtr GI Octagonal pole of 4 mm thickness (T=100 mm, B=200mm, Base Plate = 320 x 320 x 20 mm), Window at 500 mm from Base Plate with 6 No. LED suitable size, outdoor type energy efficient lamps on each pole, 20 no. LED outdoor light with 7 m. high GI pole along road / path including all accessories, cable, wire etc complete in all respect. 1.2 Supply and fixing of 1 No. 3.65 m wide SS 304 main Gate along with1.25 m. wide wicket gate at STP to the entire satisfaction of Engineer-in-charge. (Total weight not less than 500 kg). 1.3 EWQMS (Effluent water quality monitoring system): Supply, Installation, Testing, Commissioning, Operation and Comprehensive Annual Maintenance of effluent quality monitoring system at 2.50 MLD capacity STP for online (continuous) measurement of PH, Total Suspended Solids (TSS), Chemical Oxygen Demand (COD), Biological Oxygen Demand (BOD) by single analyzer with various sensors (spectral measurement in the UV-VIS range 200-720mm) performing reagent and chemical free analysis with automatic cleaning of censor, signal cables and power cables, local data acquisition and display of data on continuous basis for up linking the data to CPCB, HSPCB and PHED, TUV approved complete in all respect as per Central Pollution Control Board (CPCB) guidelines for online continuous monitoring system for effluents. 1.3.1 Multi-parameter measuring converter, for connecting up to 18 intelligent sensors Scope including 8 analog inputs / outputs (4 inputs and 4 outputs) (0/4-20Ma), wide- range power supply Optical COD/BOD and TSS probe with spectral processing of the UV-VIS range, for measurement in the outlet / effluent of 2.50 MLD capacity STP with integrated with automatic cleaning complete in all respect. 1.3.2 Robust digital pH/ORP sensor for pH/ORP electrodes, with built-in pre-amplifier and temperature sensor with Automatic Temperature Compensation (ATC) Cable length 100 Meter (minimum) complete in all respect. 1.3.3 Sensor adapter cable for all intelligent sensors, with IP68 water proof connection to the intelligent Sensor Net system. Cable length 100 meter (minimum) complete in all respect. 1.3.4 Data transfer to CPCB, HSPCB and PHED servers complete in all respect. 1.3.5 Providing GSM 3G, 4G modem with mobile network connectivity including network including complete in all respect. `1.4 Providing and installation of online flow measurement at inlet , outlet and byepass including suitable size flow meter complete in all respect` 1.5 Conveyance of treated effluent from chlorine contact tank to effluent collection tank through suitable size DI K9 pipe along with cost of pipe, sluice valves, specials, material and labour complete in all respect including Operation and Maintenance cum defect liability period for 06 years after successful completion of 3 Months trial run period,, |
| 27 | MPS (MAIN PUMPING STATION): Design, construction and commissioning of MPS for 2.50 MLD average flow with peak factor 3 including RCC Inlet chamber, screening chamber, wet well sump complete in all respect other works contingent thereto including 3 months successful trial-run and thereafter 6 Years Defect Liability-cum-Maintenance Period as per detail and specifications mentioned in DNIT along with following provisions 1.1 Providing, fixing and commissioning of 3 non clog sewage submersible pumping sets as per IS marked ie. 1 of 6300, 1 of 4200 and 1 of 2100 LPM having minimum head of 15 m along with making all arrangement including sluice valves, Non return valves, specials, flanged individual and common delivery pipes, suitable size LT panel boards and suitable size cable from LT panel to pumps, all safety devices, automatic capacitor bank, complete in all respect as per specification mentioned in attached additional documents. 1.2 Suitable size (as per design) K9 DI pipe at MPS for interconnecting the structures including welding and screwing of flanges, ISI marked D.I. fittings, sluice valves, non returning valves as per requirements even for bye-pass arrangements complete in all respect 1.3 Suitable size (as per design and requirement) Gear Operated Sluice Gate with SS Spindle (SS 410) and seats (SS 304) for screens and partition of tank as per design. 1.4 Supply and installation of 1 mechanical and 1 manual coarse screen (SS 304) suitable for 2.50 MLD average flow with peak factor of 3.0 complete in all respect. 1.5 Conveyance of raw sewage from MPS to inlet chamber of STP through suitable size (as per design) DI pipe along with cost of DI pipe, sluice valves, specials, material and labour complete in all respect. 1.6 All the pumping machinery, panel board, Level sensor etc shall be controlled by PLC and SCADA and shall be synchronized with PLC panels at MPS and STP site through broadband internet facility. 1.7 Raw sewage will be available near boundary wall within the premises of proposed MPS but the conveyance of sewage from this terminal point to the inlet chamber of MPS through DI K9 pipe of suitable diameter as per design is included in the Turnkey contract. The Level of the MPS / STP will be as per bed level of existing incoming sewer at MPS including Operation and Maintenance cum defect liability period for 06 years after successful completion of 3 Months trial run period,, |
| 28 | CCTV CAMERAS:- Providing, supplying, Installing, testing, and commissioning of 8 CCTV Cameras (4 Cameras for STP, , 2 No. cameras for MPS, 2 No. for IPS) with all necessary components and all other works contingent thereto as per the detailed scope of work and specifications provided in the Bid Document, complete in all respect and to the satisfaction of the Engineer-in-Charge. i) CCTV cameras shall be installed within 96 hours of signing the agreement, along with 90 days of recording on a Network Video Recorder (NVR), 53-inch LED screen, 16-channel NVR at the STP site, 8-channel NVR at the MPS site, and 8-channel NVR at the IPS site, including connectors, Ethernet cables or Wi-Fi, poles, and power supply with online real-time output facility. The cameras at all sites i.e. MPS and STP shall be synchronized at the STP site. ii) At the STP and MPS sites: 3 No. PTZ speed dome cameras with 360-degree rotation and 50X zoom, 5 No. 12mm lens size cameras, and 2 No. 3.6mm lens size cameras. Make: - CP Plus Internet Protocol minimum 5 MP WDR, Night vision color mode 2.4.2 12 mm very focal with extra IR CCTV Cameras should be installed and commissioned before starting execution of work including operation and Maintenance cum defect liability period of 6 years after successful completion of 3 months trial run period. |
| 29 | Operation and Maintenance cum defect Liability period for 6 Years after successful completion of 3 Months trial run period for complete scope of work mentioned in DNIT i.e Distribution system, 2.50 MLD STP, MPS, 3 No. IPS and their allied Civil Structures, Pumping Machineries, Head works pipelines, Civil/Electrical/Mechanical complete in all respect. The cost will be charged to Annual Maintenance estimate. |
| 30 | Civil Work |
| 31 | HSR Items Please Enable Macros to View BoQ information |
AI Tender Summary
Tender Timeline
Tender Published
Tender notice published.
CompletedCorrigendum-1 Issued
Clarifications on tender conditions and amendments issued.
Upcoming · 6 daysBid Submission Deadline
Online submission via eProcurement portal.
Upcoming · 6 daysBid Opening Date
Technical bids will be opened and evaluated.
Upcoming · 6 daysTender Documents
Download All (ZIP) ↓We takes all possible care for accurate & authentic tender information. However users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender