Tender For Selection Of Acid Gas Removal Technology Licenser For The Proposed Coal To Sng Project At Juna Kunada Ocm, Majri Area, Wcl Coalfields

Issued by Government Departments · Chandrapur, Maharashtra
Tender Value
Ref. Documents
Estimated cost
Bid Submission
20 Nov 2026
52 days left
EMD
50 Lakhs
Bank guarantee accepted
Document Fee
Ref. Documents
Non-refundable
Tender Type
Online

Tender Overview

Competition Type
NCB
Bidding Type
Tender
Location / State
Chandrapur → Maharashtra
EMD Exemption
Not Available
Quantity
Not Available

Project Description

Tender for Selection Of Acid Gas Removal Technology Licenser For The Proposed Coal To Sng Project At Juna Kunada Ocm, Majri Area, Wcl Coalfields

BOQ

Name of Work:- Selection of Acid Gas Removal Technology Licenser for the Proposed Coal to SNG Project at Juna Kunada OCM, Majri Area, WCL Coalfields
Sl. No. Item Description
1Acid Gas Removal Technology Licenser Package
2Cost to Company (Net Present Value (NPV) at a discount rate of 10% for 25 years of operation), based on the quotation submitted by the Bidder.
32.0 Break up of Supply items for completion of scope of work
4Appendix-XI (5) - Prices for Supply of Proprietary Items / Equipment
5Proprietary equipment-1
6Proprietary equipment-2
7Proprietary equipment-3
8Proprietary equipment-4
9Proprietary equipment-5
10Proprietary equipment-6
11Proprietary equipment-7
12Proprietary equipment-8
13Proprietary equipment-9
14Proprietary equipment-10
15Proprietary equipment-11
16Proprietary equipment-12
17Proprietary equipment-13
18Proprietary equipment-14
19Proprietary equipment-15
20Proprietary equipment-16
21Proprietary equipment-17
22Proprietary equipment-18
23Proprietary equipment-19
24Proprietary equipment-20
25Proprietary equipment-21
26Proprietary equipment-22
27Proprietary equipment-23
28Proprietary equipment-24
29Proprietary equipment-25
30Proprietary equipment-26
31Proprietary equipment-27
32Proprietary equipment-28
33Proprietary equipment-29
34Proprietary equipment-30
35Proprietary equipment-31
36Proprietary equipment-32
37Proprietary equipment-33
38Proprietary equipment-34
39Proprietary equipment-35
40Proprietary equipment-36
41Proprietary equipment-37
42Proprietary equipment-38
43Proprietary equipment-39
44Proprietary equipment-40
45Proprietary equipment-41
46Proprietary equipment-42
47Proprietary equipment-43
48Proprietary equipment-44
49Proprietary equipment-45
50Proprietary equipment-46
51Proprietary equipment-47
52Proprietary equipment-48
53Proprietary equipment-49
54Proprietary equipment-50
55Proprietary equipment-51
56Proprietary equipment-52
57Proprietary equipment-53
58Proprietary equipment-54
59Proprietary equipment-55
60Proprietary equipment-56
61Proprietary equipment-57
62Proprietary equipment-58
63Proprietary equipment-59
64Proprietary equipment-60
65Commissioning Spares
66Mandatory Spares
67Special Tools & Tackles
68Spares not covered from 1.61 to 1.63 Subtotal (1)
69Appendix-XI (6) - Prices for Supply of First Charge of Catalysts, Chemicals, Adsorbents, Absorbents, Additives (As Applicable)
70First charge cost - Base Catalysts, Chemicals, Adsorbents, Absorbents, and Additive including 3% handling/contingency losses (as applicable) Catalyst-1 Catalyst-2 Catalyst-3 Catalyst-4 Chemical-1 Chemical-2 Chemical-3 Chemical-4 Chemical-5 Chemical-6 Chemical-7 Chemical-8 Chemical-9
71First charge cost - Precious metals for Catalysts, Chemicals, Adsorbents, Absorbents, and Additive (as applicable) Catalyst-1 : xyz Catalyst-1: abc Catalyst-3 Catalyst-4 Chemical-1 Chemical-2 Chemical-3 Chemical-4 Chemical-5 Chemical-6 Chemical-7 Chemical-8 Chemical-9
72Other First charge cost, if any Item-1 Item-2 Subtotal (2) Break up of Service items for completion of scope of work
73Appendix-XI (1) - Prices towards License, Basic Design Engineering Package (BDEP)
74License fee for grant of license; complete in all respects in accordance with provisions of Bidding Document and its amendments on Lump-sum basis
75Fee for preparation and supply of Basic Design Engineering Package (BDEP); complete in all respects in accordance with provisions of Bidding Document and its amendments on Lump-sum basis. Subtotal (1)
76Appendix-XI (2) - Prices for Mandatory Service and Break-Up of Man-Days Mandatory Services for items listed below in accordance with provisions of Bidding Document and its amendments, considering 300 man-days (inclusive of travel time and excluding non-working Sundays as holidays)
77Assistance during pre-commissioning/ commissioning activities at project site.
78Conducting performance guarantee test runs at project site.
79HAZOP and SIL studies during detail engineering stage atOwner/Consultant's office.
803D model review (30%, 60% and 90%) at owner /contractor's office
81Review & Approval of detailed engineering documents including fabrication drawing and vendor data for critical equipment. The list of such equipment shall be specified in BDEP.
82P&ID walkthrough after mechanical completion including all Critical Equipments like furnaces, towers, vessels, compressors etc. required for achieving guaranteed yields
83Participation in Factory Acceptance Test (FAT) Subtotal (2) (The Bidder has to ensure total man-days is equal to 300)
84Appendix-XI (3) - Prices for Training Training to Owner’s personnel on process design, operation, maintenance, analytical procedures, product & applications training etc. as indicated below as per requirements of Bidding Document and its amendments (Lumpsum amount
85Five (5) working days Theoretical training at Bidder’s office/facilities for two batches of 5 persons each.
86Industrial training in a substantially similar operating plant selected by Bidder for up to ten (10) persons for two (2) weeks (10 working days)
87One week classroom training for maximum thirty (30) persons at Owner’s office/ plant
88Laboratory analysis training to chemists for five days classroom training at owners office/plant up to five (5) persons
89Refresher Training before commissioning of the unit for 2 days for 2 batches of 15 persons each at OWNER’S office at Plant Subtotal (3)
90Appendix-XI (4) - Schedule of Personnel Rates – Additional Services Additional Services (personnel rates for services rendered), if any
91Engineeringa) Development of APC Strategiesb) Development of specification for process simulatorsc) Any other activity/ service related to project implementation At Licensor’s Office Outside India By Licensor Personnel (Deputed from Licensor’s office outside India of the Bidder) In India (Per Manday) Licensor’s personnel deputed for providing remote assistance (eg: video conference)
92Inspectiona) Procurement/ Inspection/ expediting of critical equipmentb) Supervision during constructionc) Inspection at vendor’s shop floor/ prequalification of vendorsd) Any other activity/ service related to project implementation At Licensor’s Office Outside India By Licensor Personnel (Deputed from Licensor’s office outside India of the Bidder) In India (Per Manday) Licensor’s personnel deputed for providing remote assistance (eg: video conference) Subtotal (4)
932.0 Operating Cost Estimate Format To produce shifted Syngas(CO+H2 equi.) of 336,000 Nm3/hr with H2:CO ratio ≥3.6
94Power
95HP Gaseous Oxygen
96HP Gaseous Nitrogen
97LP Gaseous Nitrogen
98HP Superheated Steam
99HP Saturated Steam
100MP Steam
101LP Steam
102Make-up water
103Cooling water
104Boiler feed water
105Demineralized Water
106Service / Drinking water
107Instrument Air
108Plant Air
109Credit - HP Superheated Steam generation
110Credit - HP Saturated Steam generation
111Credit - MP Steam generation
112Credit - LP Steam generation
113Administrative overhead
114Insurance
115Repair & maintenance incl. spares
116Additional items supplied by Licenser (if required)
117Additional items supplied by Licenser (if required)
118Revenue Capital cost Estimate Particulars Total Rs. Appendix-XI (5) - Prices for Supply of Proprietary Items / Equipment 0.0 Appendix-XI (6) - Prices for Supply of First Charge of Catalysts, Chemicals, Adsorbents, Absorbents, Additives (As Applicable) 0.0 License fee for grant of license; complete in all respects in accordance with provisions of Bidding Document and its amendments on Lump-sum basis 0.0 Fee for preparation and supply of Basic Design Engineering Package (BDEP); complete in all respects in accordance with provisions of Bidding Document and its amendments on Lump-sum basis. 0.0 Appendix-XI (2) - Prices for Mandatory Service and Break-Up of Man-Days 0.0 Appendix-XI (3) - Prices for Training 0.0 Additional Services 0.0 Total Quote from Bidder 0.0 Prices for Supply of Non-Proprietary Items / Equipment Total Equipment Cost 0.0 Piping Supply Cost 0.25 0.0 Piping Construction Cost 0.5 0.0 Electrical Supply Cost 0.1 0.0 Electrical Construction Cost 0.3 0.0 Instrumentation Supply Cost 0.1 0.0 Instrumentation Construction Cost 0.3 0.0 Spare cost 0.03 0.0 Mechanical Works Cost 0.1 0.0 Civil & Structural Cost 0.25 0.0 Painting & Insulation Cost 0.04 0.0 Total Capex for NPV Calculation 0.0 Operating cost estimate Annual operating hours 7920.0 Parameter UoM Quantity (Guaranteed) Unit rate(Rs / UoM) Annual Cost, Rs. Crore Remarks Variable Cost Cost above material 0.0 0.0 0.0 0.0 0.0 Power kWh/hr 0.0 8.5 0.0 HP Gaseous Oxygen kg/hr 0.0 5.25 0.0 HP Gaseous Nitrogen kg/hr 0.0 1.5 0.0 LP Gaseous Nitrogen kg/hr 0.0 1.0 0.0 HP Superheated Steam kg/hr 0.0 1.25 0.0 HP Saturated Steam kg/hr 0.0 1.0 0.0 MP Steam m3/hr 0.0 1.17 0.0 LP Steam m3/hr 0.0 1.03 0.0 Make-up water m3/hr 0.0 3.0 0.0 Cooling water m3/hr 0.0 1.1 0.0 Boiler feed water m3/hr 0.0 1.1 0.0 Demineralized Water m3/hr 0.0 150.0 0.0 Service / Drinking water m3/hr 0.0 100.0 0.0 Instrument Air m3/hr 0.0 0.5 0.0 Plant Air m3/hr 0.0 0.5 0.0 Additional items supplied by Licenser (if required) Unit/hour 0.0 0.0 0.0 Additional items supplied by Licenser (if required) Unit/hour 0.0 0.0 0.0 Credit Credit - HP Superheated Steam generation kg/hr 0.0 -1.25 0.0 Credit - HP Saturated Steam generation kg/hr 0.0 -1.0 0.0 Credit - MP Steam generation kg/hr 0.0 -1.17 0.0 Credit - LP Steam generation kg/hr 0.0 -1.03 0.0 Subtotal 0.0 Fixed Cost Administrative overhead 0.005 Rs. Crore/yr 0.0 Insurance 0.002 Rs. Crore/yr 0.0 Repair & maintenance incl. spares 0.03 Rs. Crore/yr 0.0 Subtotal 0.0 Total Annual Cost 0.0 Revenue Estimate 0.0 0.0 0.0 0.0 0.0 Total 0.0 NPV Calculation Inflation Year-on-year inflation on Capex 0.028 Year-on-year inflation on Steam 0.05 Inflation index 1.0 2.0 3.0 4.0 5.0 6.0 7.0 8.0 9.0 10.0 11.0 12.0 13.0 14.0 15.0 16.0 17.0 18.0 19.0 20.0 21.0 22.0 23.0 24.0 25.0 26.0 27.0 28.0 29.0 Capex 1.0 1.03 1.06 1.09 1.12 1.15 1.18 1.21 1.24 1.27 1.31 1.35 1.39 1.43 1.47 1.51 1.55 1.59 1.63 1.68 1.73 1.78 1.83 1.88 1.93 1.98 2.04 2.1 2.16 Steam 1.0 1.05 1.1 1.16 1.22 1.28 1.34 1.41 1.48 1.55 1.63 1.71 1.8 1.89 1.98 2.08 2.18 2.29 2.4 2.52 2.65 2.78 2.92 3.07 3.22 3.38 3.55 3.73 3.92 Capital cost payment Schedule License fee for grant of license; complete in all respects in accordance with provisions of Bidding Document and its amendments on Lump-sum basis 0.3 0.35 0.35 Fee for preparation and supply of Basic Design Engineering Package (BDEP); complete in all respects in accordance with provisions of Bidding Document and its amendments on Lump-sum basis. 0.6 0.1 0.3 Appendix-XI (2) - Prices for Mandatory Service and Break-Up of Man-Days 0.25 0.25 0.25 0.25 Appendix-XI (3) - Prices for Training 1.0 Additional Services 0.25 0.25 0.25 0.25 Appendix-XI (5) - Prices for Supply of Proprietary Items / Equipment 0.3 0.4 0.3 Appendix-XI (6) - Prices for Supply of First Charge of Catalysts, Chemicals, Adsorbents, Absorbents, Additives (As Applicable) 1.0 Prices for Supply of Non-Proprietary Items / Equipment 0.3 0.4 0.3 Piping Supply Cost 0.3 0.4 0.3 Piping Construction Cost 0.3 0.4 0.3 Electrical Supply Cost 0.3 0.4 0.3 Electrical Construction Cost 0.3 0.4 0.3 Instrumentation Supply Cost 0.3 0.4 0.3 Instrumentation Construction Cost 0.3 0.4 0.3 Spare cost 0.3 0.4 0.3 Mechanical Works Cost 0.3 0.4 0.3 Civil & Structural Cost 0.3 0.4 0.3 Painting & Insulation Cost 0.3 0.4 0.3 Project Development/Construction Project Operations Cashflow partilculars 1.0 2.0 3.0 4.0 5.0 6.0 7.0 8.0 9.0 10.0 11.0 12.0 13.0 14.0 15.0 16.0 17.0 18.0 19.0 20.0 21.0 22.0 23.0 24.0 25.0 26.0 27.0 28.0 29.0 (in Rs.) Capex outflow License fee for grant of license; complete in all respects in accordance with provisions of Bidding Document and its amendments on Lump-sum basis 0.0 0.0 0.0 0.0 Fee for preparation and supply of Basic Design Engineering Package (BDEP); complete in all respects in accordance with provisions of Bidding Document and its amendments on Lump-sum basis. 0.0 0.0 0.0 0.0 Appendix-XI (2) - Prices for Mandatory Service and Break-Up of Man-Days 0.0 0.0 0.0 0.0 Appendix-XI (3) - Prices for Training 0.0 0.0 0.0 0.0 Additional Services 0.0 0.0 0.0 0.0 Appendix-XI (5) - Prices for Supply of Proprietary Items / Equipment 0.0 0.0 0.0 0.0 Appendix-XI (6) - Prices for Supply of First Charge of Catalysts, Chemicals, Adsorbents, Absorbents, Additives (As Applicable) 0.0 0.0 0.0 0.0 Prices for Supply of Non-Proprietary Items / Equipment 0.0 0.0 0.0 0.0 Piping Supply Cost 0.0 0.0 0.0 0.0 Piping Construction Cost 0.0 0.0 0.0 0.0 Electrical Supply Cost 0.0 0.0 0.0 0.0 Electrical Construction Cost 0.0 0.0 0.0 0.0 Instrumentation Supply Cost 0.0 0.0 0.0 0.0 Instrumentation Construction Cost 0.0 0.0 0.0 0.0 Spare cost 0.0 0.0 0.0 0.0 Mechanical Works Cost 0.0 0.0 0.0 0.0 Civil & Structural Cost 0.0 0.0 0.0 0.0 Painting & Insulation Cost 0.0 0.0 0.0 0.0 Annual Operating Cost Cost above material 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 Power 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 HP Gaseous Oxygen 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 HP Gaseous Nitrogen 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 LP Gaseous Nitrogen 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 HP Superheated Steam 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 HP Saturated Steam 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 MP Steam 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 LP Steam 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 Make-up water 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 Cooling water 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 Boiler feed water 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 Demineralized Water 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 Service / Drinking water 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 Instrument Air 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 Plant Air 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 Credit Credit - HP Superheated Steam generation 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 Credit - HP Saturated Steam generation 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 Credit - MP Steam generation 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 Credit - LP Steam generation 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 Fixed Cost Administrative overhead 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 Insurance 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 Repair & maintenance incl. spares 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 Annual Revenue 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 Net Cashflow 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 Net Present Value 0.0 APPENDIX - XI (8) - LIST OF PROPRIETARY EQUIPMENT WITH INDICATIVE SPECIFICATION Tender Inviting Authority: GM-Business Development (CIL), Coal India Limited Name of Work: Selection of Acid Gas Removal Technology Licenser for the Proposed Coal to SNG Project at Juna Kunada OCM, Majri Area, WCL Coalfields Contract No: CIL/BD/CTC/AGR/SCG/2026/17 Date: 23/09/2026 Name of the Bidder/ Bidding Firm / Company : Please Enter The Bidder Name in BoQ1 Sheet Notes1. The Bidder shall furnish the list of Proprietary Equipment along with indicative specifications, including key parameters, basic dimensions, Material of Construction (MOC), and weight.2. Bidders may insert additional rows by copying and pasting the existing rows, if required. However, it must be strictly ensured that the original format and structure of the document remain unaltered. FORM APPENDIX XI (8)(This BOQ template must not be modified/replaced by the bidder and the same should be uploaded after filling the relevent columns, else the bidder is liable to be rejected for this tender. Bidders are allowed to enter the Bidder Name and Values only) Sl.No. Item No. Item Name Indicative Specification (key parameters, basic dimensions, MOC & weight)
119Item 1
120Item 2
121Item 3
122Item 4
123Item 5
124Item 6
125Item 7
126Item 8
127Item 9
128Item 10
129Item 11
130Item 12
131Item 13
132Item 14
133Item 15
134Item 16
135Item 17
136Item 18
137Item 19
138Item 20
139Item 21
140Item 22 APPENDIX - XI (9) - LIST OF NON-PROPRIETARY EQUIPMENT WITH INDICATIVE SPECIFICATION & PRICE Tender Inviting Authority: GM-Business Development (CIL), Coal India Limited Name of Work: Selection of Acid Gas Removal Technology Licenser for the Proposed Coal to SNG Project at Juna Kunada OCM, Majri Area, WCL Coalfields Contract No: CIL/BD/CTC/AGR/SCG/2026/17 Date: 23/09/2026 Name of the Bidder/ Bidding Firm / Company : Please Enter The Bidder Name in BoQ1 Sheet Notes1. The Bidder shall furnish an itemized list of Non-Proprietary Items along with indicative specifications.2. The cost of Non-Proprietary Items shall not be included in the Bidder’s quoted Supply Price.3. Bidders may insert additional rows by copying and pasting the existing rows, if required. However, it must be strictly ensured that the original format and structure of the document remain unaltered.4. The Bidder shall indicate “0” (Zero) in all non-applicable/empty cells. No cell shall be left blank.5.Indicative prices for Non-Proprietary Items, wherever available with the Bidder, shall be furnished for the Owner’s cost estimation. The Owner/Owner-appointed Technical Consultant reserves the right to review and revise such indicative prices based on in-house estimates. If the Indicative price is not available, bidder to follow Note 4 mentioned above. FORM APPENDIX XI (9)(This BOQ template must not be modified/replaced by the bidder and the same should be uploaded after filling the relevent columns, else the bidder is liable to be rejected for this tender. Bidders are allowed to enter the Bidder Name and Values only) Sl.No. Item No. Quoted Currency in INR Item Name Indicative Specification (key parameters, basic dimensions, MOC & weight) Indicative Price in INR, where available with the Bidder
141Item 1
142Item 2
143Item 3
144Item 4
145Item 5
146Item 6
147Item 7
148Item 8
149Item 9
150Item 10
151Item 11
152Item 12
153Item 13
154Item 14
155Item 15
156Item 16
157Item 17
158Item 18
159Item 19
160Item 20
161Item 21
162Item 22
163Item 23
164Item 24 Please Enable Macros to View BoQ information

AI Tender Summary

OUR REF NO 57673668
AUTHORITY Government Departments
TENDER VALUE Ref. Documents
LAST DATE 20-11-2026
Authority
Authority Name Coal India Limited
Work Description Tender for Selection Of Acid Gas Removal Technology Licenser For The Proposed Coal To Sng Project At Juna Kunada Ocm, Majri Area, Wcl Coalfields
Basic Detail
Tender No CIL/BD/CTC/AGR/SCG/2026/17
Bidding Type Tender
Location
City Chandrapur
State Maharashtra
Key Dates
Publish Date 23 Sep 2026
Submission Date 20 Nov 2026
Open Date 21 Nov 2026
Finance
Tender Value Ref. Documents
Tender Fee Ref. Documents
EMD 50 Lakhs
Exemption Not Available
Document List
49c51888-26f2-430d-8cfb-dce909d56db4.html
BOQ_378956.xls
Tendernotice_1 (34).pdf
Tendernotice_2 (4).pdf
Tendernotice_3 (1).pdf
TPS_378956.xls

Unlock Full AI Tender Summary

Get instant access to the complete AI-generated analysis — scope, eligibility, timeline & more.

Instant Access Secure Free
Your details are secure and used only for document delivery.

Tender Timeline

Sep 23, 2026
11:30 IST

Tender Published

Tender notice published.

Completed
Nov 20, 2026
17:00 IST

Bid Submission Deadline

Online submission via eProcurement portal.

Upcoming · 52 days
Nov 21, 2026

Bid Opening Date

Technical bids will be opened and evaluated.

Upcoming · 53 days

Tender Documents

Download All (ZIP) ↓
html

49c51888-26f2-430d-8cfb-dce909d56db4.html

xls

BOQ_378956.xls

pdf

Tendernotice_1 (34).pdf

pdf

Tendernotice_2 (4).pdf

pdf

Tendernotice_3 (1).pdf

xls

TPS_378956.xls

Disclaimer

We takes all possible care for accurate & authentic tender information. However users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender

TenderDetail
Loading tenders