Tender For Construction Of 132Kv Gss Rvpn Moolana (Jaisalmer)
Tender Value
Ref. Documents
Estimated cost
Bid Submission
06 Oct 2026
11 days left
EMD
49187
Bank guarantee accepted
Document Fee
2950
Non-refundable
Tender Type
Online
Tender Overview
Organization
Tender ID
Competition Type
NCB
Bidding Type
Tender
Location / State
Jaisalmer → Rajasthan
EMD Exemption
Available
Quantity
Not Available
Website
Contact Person
Address
Project Description
Tender for Construction Of 132Kv Gss Rvpn Moolana (Jaisalmer)
Corrigendum
| Sr No | Corrigendum Date | Corrigendum | Type | New Submission Date |
|---|---|---|---|---|
| 1 | 23-Sep-2026 | Important Dates for sale bid | Date | 06-Oct-2026 |
BOQ
| Sl. No. | Item Description |
| 1 | Construction of 132 KV GSS Moolana (Jaisalmer) |
| 2 | EARTH MESH WORK Laying of earth mesh with 25/28 mm dia, M.S. Rod at a depth of 0.80 meter from top level of foundation including, excavation of trench of required depth and back filling of the same transportation of M.s Rod from site store to location, welding of M.S Rod to M.S.Rod along the length at crossing and with earth electrode as per drawing application of bitumen compound and covering with bitumen impregnated tape on all welded joints, for the type of soil prevalent at 0.80metre below top level of foundation( M.S Rod of above sizes & M.S Flat required shall be made available by RVPN. a)In case electricity is made available by RVPN without charges iii)Soft Rock |
| 3 | Laying of eathing risers of 50x6mm/50x10mm/50x12mm size M.S Flat at a depth of 0.80 meter from top level of foundation ,including excavation of trench of required depth and black filling of the same ,transportation of M.S Flat from site store to location preparation of risers ,bending as per requirement (after heating if necessary), fixing on and welding /bolting to equipment /structure and peaks of structures, laying in the trench, welding to the earth mesh of M.S. Road as per drawing including welding of extra length, if required ,application of bitumen compound and covering with bitumen impregnated tape on all welded joints ,painting of all surface of risers above ground level with red oxide and green paint for the type of soil prevalent at 0.80 & meter below top level of foundation (M.S pod of above sizes &M.S flat as required shall be made available by RVPN. a)In case electricity is made available by RVPN without charges. iii)Soft Rock |
| 4 | placing drawing of earth electrode of 25/28mm dia M.S. Rod of length 3.30 metre(app.) to a depth of 3.80 from top level of foundation including, excavation of pit of required depth and back filling of the same transportation of M.s Rod from site store to location,cutting of M.S Rod to desired length preparation of one end as spike if necessary, welding of earth electrode to earth mesh of M.S.Rod as per drawing application of bitumen compound and covering with bitumen impregnated tape on all welded joints, for the type of soil prevalent at 3.80metre below top level foundation( M.S Rod of above sizes & M.S Flat required shall be made available by RVPN. a)In case electricity is made available by RVPN without charges. iii)Soft Rock |
| 5 | placing of earth electrode of 25/28mm dia M.S. Rod of length 7.50metre(app.) to a depth of 8.00meter from top level of foundation including of 200mm dia earth pit having throughout bore of 200mm dia a depth of 8.00meter from top level of foundation in all types of rocks by DTH system and over burden ,including back filling of pit with bentonites slurry (with cost of bentonites slurry ), including its preparation ,transportation of M.S rod and bentonites from site store to location ,cutting of M.S rod desired length welding of earth electrode to earth mesh of M.S.Road as per drawing application of bitumen compound and covering with bitumen impregnated tape on all welded joints,( M.S Rod of above sizes & M.S Flat required shall be made available by RVPN.) a)In case electricity is made available by RVPN without charges. |
| 6 | ERECTION OF SUB-STATION STRUCTURES columns, beams ,lighting mast and equipment structure(excluding circuit breaker and Capacitor bank) of all types including transportation of structure members, nuts &bolts, washers etc from site store to location their assembly, placing on foundation, fixing of template, with foundation bolts as required leveling and preparing for grouting as required but excluding grouting erection after grouting and tightening & punching of nuts &bolts (maximum length of structures up to 20 Mtrs.) |
| 7 | BUS- BAR WORK ;-STRINGING OF 220KV,132KV,33KV&11KVbus bar of ACSR conductor , including transportation of conductor ,disc insulator and tension hardware from site store to location laying and cutting required length of conductor, cleaning and assembly of disc insulator as required along with fitting of bolted type or compression type tension hardware as made available (compression machine shall be provided by RVPN on rent free basis )making up at one end, stringing of conductors between the beams with specified sag and tension ,also equalizing sag and fitting spacer T-clamps for twin conductor for three phases of conductors in each bus-section , ii) Single ACSR Zebra |
| 8 | BUS- BAR WORK:- STRINGING OF 220KV,132KV,33KV&11KVbus bar of ACSR conductor , including transportation of conductor ,disc insulator and tension hardware from site store to location laying and cutting required length of conductor, cleaning and assembly of disc insulator as required along with fitting of bolted type or compression type tension hardware as made available (compression machine shall be provided by RVPN on rent free basis )making up at one end, stringing of conductors between the beams with specified sag and tension ,also equalizing sag and fitting spacer T-clamps for twin conductor for three phases of conductors in each bus-section iii) Double ACSR Zebra |
| 9 | JUMPERS OF ACSR CONDUCTOR (3NOS Y- type )between bus to equipment or between equipment to equipment or between bus to bus, including transportation of conductor ,disc insulators and hardware from site store to location ,cleaning and assembly of disc insulator as required, along with fitting of suspension hardware and erection as required cutting required length of conductor making connection ,fixing of spacers & spacer T- Clamps as required ,tightening of clamps/ conductors, dressing etc, for three phases. i) Single ACSR Zebra/Panther Conductor |
| 10 | STRINGING of earth wire (size 7/3.15mm or 7/4.00mm) including transportation of earth wire, tension hardware’s Etc, from site store to location laying and cutting required length of earth wire flitting of bolted type or compression type hardware as made available (compression machine shall be provided by RVPN rent free basis) making up at one end stringing of earth wire between structure peaks with specified sag and tension ,jumpering and connecting earth bonds single earth wire |
| 11 | ERECTION OF SUB-STATION EQUIPMENT :i)Erection of 33/0.4kv or 11/0.4kv station transformer up to 500 KVA on existing masonry platform including transportation of transformer & accessories from site store to location eerection of Horn Gap fuse set, jump ring from isolator to Horn Gap to transformer. |
| 12 | ii)Filtration of the transformer, if required (Additional cost) |
| 13 | Erection of current transformer/potential transformer/capacitive voltage transformer/ series reactor/residual voltage transformer/neutral current transformer with clamp & connectors, on already erected steel structure including transportationfrom site store to location fabrication of base fram ,fixing of terminal connectors ,tightening of nuts & bolts etc , complete in all respect ii) 132KV CT/PT/CVT |
| 14 | Erection of current transformer/potential transformer/capacitive voltage transformer/ series reactor/residual voltage transformer/neutral current transformer with clamp & connectors, on already erected steel structure including transportationfrom site store to location fabrication of base fram ,fixing of terminal connectors ,tightening of nuts & bolts etc , complete in all respect iii) 33KV or 11KV CT/PT |
| 15 | Erection of lightening Arrestor on already erected steel structure including transportation of lightening arrestor ,clamps & connectors surge counter etc. from site store to location fabrication of base frame fixing of terminal connectors ,surge counter, tightening of nuts and bolts etc. complete in all respect. ii) 132KV |
| 16 | Erection of lightening Arrestor on already erected steel structure including transportation of lightening arrestor ,clamps & connectors surge counter etc. from site store to location fabrication of base frame fixing of terminal connectors ,surge counter, tightening of nuts and bolts etc. complete in all respect. iii) 33KV&11KV |
| 17 | Erection of isolators on already erected steel structure including transportation of base frame ,PIs contacts mechanism box clamps & connectors etc, from site store to location ,minor fabrication as required ,and fixing of terminal connectors, etc Adjustment /alignment of isolator and its earth blade ,if provided for their smooth operation and final adjustment if required after jumpering. ii) )132KV a)Without Earth blade |
| 18 | Erection of isolators on already erected steel structure including transportation of base frame ,PIs contacts mechanism box clamps & connectors etc, from site store to location ,minor fabrication as required ,and fixing of terminal connectors, etc Adjustment /alignment of isolator and its earth blade ,if provided for their smooth operation and final adjustment if required after jumpering. ii) )132KV b)With Single Earth Blade |
| 19 | Erection of isolators on already erected steel structure including transportation of base frame ,PIs contacts mechanism box clamps & connectors etc, from site store to location ,minor fabrication as required ,and fixing of terminal connectors, etc Adjustment /alignment of isolator and its earth blade ,if provided for their smooth operation and final adjustment if required after jumpering iii)33KV&11KV a)Without Earth blade |
| 20 | Erection of isolators on already erected steel structure including transportation of base frame ,PIs contacts mechanism box clamps & connectors etc, from site store to location ,minor fabrication as required ,and fixing of terminal connectors, etc Adjustment /alignment of isolator and its earth blade ,if provided for their smooth operation and final adjustment if required after jumpering iii)33KV&11KV b)With Single Earth Blade |
| 21 | Erection of Wave trap on already erected structure beam, including transportation of wave trap ,disc insulators, hardware, clamps and connectors ,etc. from site store to location ,cleaning & assembly of disc insulators along with fitting of suspension arrangement and erection, fixing of terminal connectors etc. ii)132KV |
| 22 | Erection of 2x33KV or 2x11KV capacitor Bank ,with series reactor &residual voltage transformer /neutral current transformer ,including transportation of equipment ,structure member ,nuts & bolts washers, clamps & connectors etc from site store to location, assembly of structure, their placing on foundation leveling and preparing for grouting as required, but excluding grouting, assembly of capacitor bank cell on frame as required & their connection as per manufacturer’s drawings fixing of terminal connectors etc. |
| 23 | Erection of 220 KV or 132KV or 33 KV circuit breaker , including transportation of equipment, structures member ,nuts& bolts ,clamps & connectors accessories etc. from site store to location ,assembly of support structure, their placing on foundation ,leveling and preparing for grouting as required ,but excluding grouting .Assembly /placing of support columns /poles mechanism box/control cubicle ,and other accessories as per manufacturers drawing. Fitting of SF 6 gas pipe line , fabrication of air.oil pipe line as required, Electrical wiring from pole to control cubicle, fixing of terminal connectors as required ,but excluding commissioning of CB ,all type of operating mechanism, as required. ii)132KV |
| 24 | Erection of 220 KV or 132KV or 33 KV circuit breaker , including transportation of equipment, structures member ,nuts& bolts ,clamps & connectors accessories etc. from site store to location ,assembly of support structure, their placing on foundation ,leveling and preparing for grouting as required ,but excluding grouting .Assembly /placing of support columns /poles mechanism box/control cubicle ,and other accessories as per manufacturers drawing. Fitting of SF 6 gas pipe line , fabrication of air.oil pipe line as required, Electrical wiring from pole to control cubicle, fixing of terminal connectors as required ,but excluding commissioning of CB ,all type of operating mechanism, as required iii) 33 KV |
| 25 | Erection of Post Insulators on already erected structure including transportation of P.I’s nuts &Bolts ,clamps & Connectors etc. from site store to location ,fabrication of base frame & assembly if required, fixing of clamps ,etc. ii)132KV |
| 26 | Erection of Post Insulators on already erected structure including transportation of P.I’s nuts &Bolts ,clamps & Connectors etc. from site store to location ,fabrication of base frame & assembly if required, fixing of clamps ,etc. iii)33KV or 11KV |
| 27 | Erection of 132KV Class EHV Transformer (tank already placed on foundation with wheels), including transportation of accessories from site store to location ,erection of HV,IV,LV & Neutral bushing main & OLTC conservators, radiators, equalizing pipe line marshaling kiosk, etc. as per manufacturer’s drawing ,preparation of oil, oil filling dehydration of transformer (filter machine, oil tank & operating staff shall be provided by RVPN), electrical wiring from individual equipment, e. g, Buchholz relay ,MOLG, OSR, etc to marshalling kiosk ,etc. but excluding testing & commissioning of transformer. a) If electricity is available & arranged by RVPN without charges. i) Transformer received oil filled. |
| 28 | Erection of Control & Relay panel complete in all respect, including transportation from site store to control room , placing on foundation /cable trench as per layout, interconnection between control & relay panel and with existing panel fixing of site /top covers and doors earthing to existing earth strip in control room, connection of bus wiring to existing panel and between control and relay panel as required. ii)Duplex panel |
| 29 | Erection of Control & Relay panel complete in all respect, including transportation from site store to control room , placing on foundation /cable trench as per layout, interconnection between control & relay panel and with existing panel fixing of site /top covers and doors earthing to existing earth strip in control room, connection of bus wiring to existing panel and between control and relay panel as required iii)Simplex panel, Dc panel, RTCC panel, PLCC panel, etc |
| 30 | Erection of Control & Relay panel complete in all respect, including transportation from site store to control room , placing on foundation /cable trench as per layout, interconnection between control & relay panel and with existing panel fixing of site /top covers and doors earthing to existing earth strip in control room, connection of bus wiring to existing panel and between control and relay panel as required iv) L.T Panel |
| 31 | Erection of Marshalling Kiosk/Line Matching Unit (LMU)/Line matching& distribution Unit (LMDU) complete in all respect including transportation from site store to location , placing on foundation/ cable trench as per layout, preparing for grouting of foundation bolts but excluding grouting etc. i)220KV/132KVMarshalling Kiosk |
| 32 | Erection of Marshalling Kiosk/Line Matching Unit (LMU)/Line matching& distribution Unit (LMDU) complete in all respect including transportation from site store to location , placing on foundation/ cable trench as per layout, preparing for grouting of foundation bolts but excluding grouting etc. ii)33KV /11KV Marshalling Kiosk |
| 33 | Erection of Battery chargers complete in all respect including transportation from site store to location placing on foundation/ cable trench as per layout, etc. ii)110Volt DC,200AH |
| 34 | BATTERY SET Assembly, erection and commissioning of Maintenance Free VRLA type Battery set including transportation of cells, battery stand electrolyte ,nuts & bolts and accessories from site store to battery room , assembly of wooden stand ,placing the cells on stand ,making their interconnection initial charging and Discharging and final charging as per procedure recommended by Battery manufacturer. a)If electricity is available & arranged by RVPN without charges. ii)110Volt DC,200AH |
| 35 | LAYING AND TERMINATION OF CABLES: Control Cable: i)Laying of P.V.C insulated unarmoured / armoured control cable of 1.1KV grade with copper conductor in cable trenches as per specification as required, including transportation of cable drums from site store to locations ,laying in cable trenches, cutting to required length, placing them on cable racks/cable trays /cable batten & dressing ,including removing and re-fixing trench covers as required making necessary connections, testing, cable marking on both the terminating ends, etc. as required for all sizes from 2cx2.5 sq.mm to 20cx2.5sq.mm and 4cx4sq.mm.and 4cx6sq mm. a)Unarmoured control cable |
| 36 | ii) Fixing of control cable in position with single compression nickel plated brass cable glands confirming to IS :12943 &having three matel washers and one rubber ring, including preparation of cable and drilling of corresponding holes in gland plates etc. as required,& including cost of cable glands, for each cable gland of size. a)19mm unarmoured control cable |
| 37 | ii) Fixing of control cable in position with single compression nickel plated brass cable glands confirming to IS :12943 &having three matel washers and one rubber ring, including preparation of cable and drilling of corresponding holes in gland plates etc. as required,& including cost of cable glands, for each cable gland of size. c)25mm unarmoured control cable |
| 38 | ii) Fixing of control cable in position with single compression nickel plated brass cable glands confirming to IS :12943 &having three matel washers and one rubber ring, including preparation of cable and drilling of corresponding holes in gland plates etc. as required,& including cost of cable glands, for each cable gland of size. e)32mm unarmoured control cable |
| 39 | iii) Termination of wires of cables with copper conductor using copper terminal ends (pin or ring type) as required of Dowell’s or equivalent make as approved by the Engineer –in- charge duly crimped with crimping tool, including making wire ends ready for crimping , ferruling & dressing of wires etc. as required, including cost of terminal ends for all wires, for each cable at both ends for cables of the following sizes. a)2x2.5mm |
| 40 | iii) Termination of wires of cables with copper conductor using copper terminal ends (pin or ring type) as required of Dowell’s or equivalent make as approved by the Engineer –in- charge duly crimped with crimping tool, including making wire ends ready for crimping , ferruling & dressing of wires etc. as required, including cost of terminal ends for all wires, for each cable at both ends for cables of the following sizes b)3x2.5mm |
| 41 | iii) Termination of wires of cables with copper conductor using copper terminal ends (pin or ring type) as required of Dowell’s or equivalent make as approved by the Engineer –in- charge duly crimped with crimping tool, including making wire ends ready for crimping , ferruling & dressing of wires etc. as required, including cost of terminal ends for all wires, for each cable at both ends for cables of the following sizes f)12x2.5mm |
| 42 | iii) Termination of wires of cables with copper conductor using copper terminal ends (pin or ring type) as required of Dowell’s or equivalent make as approved by the Engineer –in- charge duly crimped with crimping tool, including making wire ends ready for crimping , ferruling & dressing of wires etc. as required, including cost of terminal ends for all wires, for each cable at both ends for cables of the following sizes h)18x2.5mm |
| 43 | In case all the wires of any cable are not got terminated, then a deduction at the rate Rs 6.00 shall be made for each end of wires not terminated. i)4x4mm Please Enable Macros to View BoQ information |
AI Tender Summary
Tender Timeline
Sep 23, 2026
11:30 IST
Tender Published
Tender notice published.
Completed
Oct 06, 2026
18:00 IST
Corrigendum-1 Issued
Clarifications on tender conditions and amendments issued.
Upcoming · 11 daysOct 06, 2026
17:00 IST
Bid Submission Deadline
Online submission via eProcurement portal.
Upcoming · 11 daysOct 07, 2026
Bid Opening Date
Technical bids will be opened and evaluated.