Tender For Repair And Restoration Works Of All Sannathis, Mandabam, Entrance Rajagopuram, Construction Of Compound Wall And Provide Cut Stone Flooring At Pragaram In Arulmigu Nayanavaratheshwarar Temple, Kankoduththavanitham Village, Koothanallur Taluk An
Tender Overview
Project Description
Tender For Repair And Restoration Works Of All Sannathis, Mandabam, Entrance Rajagopuram, Construction Of Compound Wall And Provide Cut Stone Flooring At Pragaram In Arulmigu Nayanavaratheshwarar Temple, Kankoduththavanitham Village, Koothanallur Taluk And Thiruvarur District.
Corrigendum
| Sr No | Corrigendum Date | Corrigendum | Type | New Submission Date |
|---|---|---|---|---|
| 1 | 21-Sep-2026 | one | Other | 05-Oct-2026 |
BOQ
| Sl. No. | Item Description |
| 1 | Earth work excavation for foundation (for narrow excavation) in all soils and sub-soils and to full depth as may be directed except in rock requiring blasting inclusive of shoring shuttering, bailing out water wherever necessary and depositing the surplus earth within the compound in places shown by the departmental officers with an initial lead of 10 mts and initial lift of 2 mts. and clearing and levelling the site, etc., complete complying with standard specification |
| 2 | Earth work open excavation in all soils and sub-soils and to full depth as may be directed except in rock requiring blasting inclusive of shoring shuttering, bailing out water wherever necessary and depositing the excavated earth with a lead of 10 mts. within the compound in places shown by the departmental officers and clearing and levelling the site, etc., complete complying with standard specification. |
| 3 | Supplying and filling in foundation, basement, etc with filling sand in layers of not more than 15 cm thick well watered, rammed and consolidated etc. complete complying with standard specification and as directed by the departmental officers. |
| 4 | Cement concrete 1:5:10 (One of cement five of sand and ten of HBG jelly )for foundation using 40mm gauge HBG jelly inclusive of shoring strutting and baling out water where ever necessary ramming curing etc.,complete in respects complying with relevant St |
| 5 | Supplying and erecting centering for sides and soffits including necessary supports and strutting upto 3.29 M height for plane surfaces as detailed below in all floors with all cross bracings using Mild Steel sheets of size 90 x 60 cm and 10 BG stiffened with welded Mild Steel angle of size 25mm x 25mm x 3 mm for boarding laid over silver oak joists of size 10cm x 6.50 cm spaced at abote 90 cm centre to centre and supported by casurina props of 10cm to 13 cm dia spaced at not more than 75 cm centre to centre etc. complete complying with the standard specificaiton. (Payment for centering shall be given after the concrete is laid) |
| 6 | For foundation |
| 7 | Column centering |
| 8 | Providing and laying position,Standardised concrete mi M-20 Grade in accordance with IS :456-2000,using 20mm and down graded hard brocken granite stone jelly for all Rcc items of works with minimum cement content of 3250 kg/cum and maximum water cement ratio of 0.55,inculding admiture (plasticiser / super plasticiser) in recommended proportions as per IS:9103 to accelerate, retart setting of concrete, improve workablity without imparing strengh and durability with about (5 cum)7730 kg. of 20mm machine crushed stone jelly and with about (3.3 cu.m)5156 kg of 10-12 mm machine crushed stone jelly and with about(4.79 cu.m)7670 kg of Sand ,but eculding cost of reinforcement grill and fabricating charges,centering and shuttering and also inculding laying, vibrating with mechanical vibrtors,finishing,curing,etc,complete complying with standred specification and ass directed by the departmentel officers.the coarse and fine aggregates to be used shoul comply with the requirments of IS standreds.(No separate payment will be made by the Department for the excess usage of materials.) |
| 9 | Foundation and Basement |
| 10 | For Ground floor |
| 11 | Supplying, fabricating and placing in position Mild Steel / Ribbed Tor Steel grills for all RCC works as per design given including cost of steel and G.I. binding wire in all floors etc. complete complying with standard specification. (Contractor has to make his own arrangements for the supply of steel and binding wire) |
| 12 | Brick work using Country Bricks of size 8-3/4\\" x 4-1/4\\" X2-3/4\\"\\" in Cement Mortar 1:5 (One cement and five sand) including cost and conveyance of all materials and labour charges and all other incidental charges etc completc complying with standard specification. |
| 13 | For Foundation & Basement |
| 14 | For superstructure |
| 15 | Scaffolding charges for Vimanams and Gopurams with casurina posts coconut or palm trees wherever necessary for main, form work and providing with net lawn / PVC mesh coverings, providing ladder arrangements, country wood plank for working, inspection etc. complete, hire charges only for erection, maintenance and removing the same on completion of the work 1sq,ft. - Vimanam /Gopuram upto 15'-0\\" Height |
| 16 | Vimanam Upto 15' ht |
| 17 | Vimanam Upto 25' ht |
| 18 | Gopuram Upto 50' ht |
| 19 | Providing water jet washing in the granite portion by using appropriate equipements with all its accessories etc.from the granite surface and making it into original surface including cost and conveyance of hire charges for all tools and plants and final clearing etc complete |
| 20 | Pointing the cut stone joints with LM 1:1.5 including cost of special tiles such brush and watering, curing etc, complete complying with standard specification and as directed by the departmental officers. |
| 21 | Clean removal of cement plaster from wall surface including all incidental charges complete etc. |
| 22 | Scraping the decayed lime plaster from the surface of Vimanams and Gopurams, carefully including isolated bricks or brickwork without damaging the vari vargams, racking out the joints, cleaning the surface with water, including all working in heights, hire charges for special tools, brushes complete superficial area including all folds - 100sft. |
| 23 | Brick masonry Lime Mortar 1:2 using Stock bricks including all varivargams, moulds, sthambams, mukapathrams, koodu, nasi and all ornamental brick work complete, all pancharams, agarais, karnakoodus, etc., forming core walls of Rajagopuram/ Vimanams complete including cost and conveyance of all materials including cement, all the labour charges including marking pathies shaping of the bricks, lifting of all the materials to required heights, curing and all extra for working in heights etc., complete 100 cft - Vimanam / Gopuram of height up to 15' 0\\" (excluding kalkaram) |
| 24 | Providing Vargapoochu over the corewalls of Vimanams / Gopurams, with Lime mortar 1:1.5 complete including shaping the mukhapathram, mahanasi, Koodu all ornamentals works to proper shape by embedding broken bricks of shaped/chiseled bricks, rough-plastering with Lime mortar 1:1.5 and finishing with final ornamental plastering and nayam theervani including cost and conveyance of all materials, labour therefore, lifting of materials, all working in heights, curing with water etc, complete including all extra for folding and including clearing from the vimanams/gopurams 100sft superficial area. |
| 25 | Plastering with Cement Mortar 1:5 (One cement and Five Sand), 12mm thick in all floors including curing etc. complete complying with standard specification and as directed by the departmental officers. |
| 26 | Thorough scrapping of old plastered surface for White Washing, Colour Washing & Distempering include cost of all materials for brushes etc , labour charges complete complying with standard specifications . |
| 27 | Painting with multicolour (Panchavarnam) good Emulsion paints complete for the Vinamans/Gopurams, inculding cost and conveyence of all materials, lobour charges inculding Artist painter, working in heights, lifting of material, cost of brushes etc, complete-which including all extra for foldings-100sft, superficial area. - Vimanam / gopuram of ht. Up to 15' excluding Kalkaram |
| 28 | Vimanam of ht. Up to 15'0\\" excluding Kalkaram |
| 29 | Vimanam of ht. Up to 25'0\\" excluding Kalkaram |
| 30 | Vimanam of ht. Up to 50'0\\" excluding Kalkaram |
| 31 | Painting two coats with approved ready mixed water based emulsion paint with one coat of primer over the cement plastered wall surface ceiling and other new surface including clearing preparing the surface curing in all floors including brushes etc., complete. |
| 32 | Flooring with cut stone slab of size 600mmX600mm and other sizes suitable for site requirement not less than 100mm thick with machine cut edges and top surface dressed as directed by the departmental officers including cost and conveyance of materials to site and lobour charges for paving and Pointing With Lime Mortor1:1.5 etc complete. |
| 33 | For Outer |
| 34 | Dismantling, clearing away and carefully stacking materials useful for re-use for One Course of Pressed Tile Roof finish in cement mortar including all incidental charges etc complete. |
| 35 | Finishing the top of roof with one course of machine pressed tiles of size 230mm x 230mm x 20mm of approved quality set in Cement Mortar 1:3 (One Cement and Three Crushed stone Sand) 12mm thick mixed with water proofing compound conforming to ISS at 2% by weight of cement used and the joints pointed neatly to full depth of tiles with the same cement mortar mixed with red oxide and water proofing compound including curing etc., complete complying with standard specification and as directed by the departmental officers |
| 36 | Supplying & fixing Teak wood temple type door including all materials, labour charges for manufacturing and fixing in position including all furniture fittings etc complete with std. Specifications |
| 37 | Up to 7' height |
| 38 | Above 7' height |
| 39 | Best varnish two coats for wood works etc, complete complying with standard specifications. |
| 40 | Clean removal of old paint from the surface iron work and Repainting old iron works such as gate, steel doors windows ventilators with two coats of approved quality and color of synthetic enamel paint over Zinc chromite primer in all floor etc, complete complying with standard specifications. |
| 41 | Supplying and fixing Mild steel Grill gate including cost conveyance of all materials and fixing in position including priming coat etc., complete |
| 42 | Painting new iron works such as steel doors, windows, ventilators, window bars, balustrades etc., with two coats of best approved first quality and colour of synthetic enamel paint over the existing red oxide in one coat of Zinc chromite in all floors etc., complete complying with standard specification. |
| 43 | Add GST 18% Please Enable Macros to View BoQ information |
AI Tender Summary
Tender Timeline
Tender Published
Tender notice published.
CompletedCorrigendum-1 Issued
Clarifications on tender conditions and amendments issued.
Upcoming · 4 daysBid Submission Deadline
Online submission via eProcurement portal.
Upcoming · 4 daysTender Documents
Download All (ZIP) ↓We takes all possible care for accurate & authentic tender information. However users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender