Tender For S : Running Contract (New Connection For Jhatpat/Nivesh Mitra/Peyjal/Shifting And Other) For Deposited Works For 2026-27 As Per Resspo Norms. Edsd-Utraula(Urban)/Utraula(Rural) & Rehra Under Edd Tulsipur.
Tender Value
10 Lakhs
Estimated cost
Bid Submission
23 Sep 2026
4 days left
EMD
10000
Bank guarantee accepted
Document Fee
1180
Non-refundable
Tender Type
Online
Tender Overview
Organization
Tender ID
Competition Type
NCB
Bidding Type
Tender
Location / State
Shravasti → Uttar Pradesh
EMD Exemption
Not Available
Quantity
Not Available
Website
Contact Person
Address
Project Description
Tender for S : Running Contract (New Connection For Jhatpat/Nivesh Mitra/Peyjal/Shifting And Other) For Deposited Works For 2026-27 As Per Resspo Norms. Edsd-Utraula(Urban)/Utraula(Rural) & Rehra Under Edd Tulsipur.
BOQ
| Sl. No. | Item Description |
| 1 | The work of safe carriage of the following material from Balrampur store center to work site under the jurisdiction of LT/11 KV under EDD Balrampur. Approx. distance upto 70 Km. Including safe loading and unloading. |
| 2 | PCC Pole 8.5 meter long. |
| 3 | PCC Pole 09 meter long. |
| 4 | PCC Pole 11 Mtr Long |
| 5 | STP 11 Mtr Long |
| 6 | STP 13 Mtr Long |
| 7 | Line material i.e., cross arm/ pin insulator/stay/earthing rod/Ms Channel/MS Angle/Disc Fitting/Disc Insulators etc |
| 8 | 11 KV XLPE Cable Size 3x70sqmm |
| 9 | 11 KV XLPE Cable Size 3x120sqmm |
| 10 | 11 KV XLPE Cable Size 3x185sqmm |
| 11 | ACSR Weasel Conductor |
| 12 | ACSR Rabbit Conductor |
| 13 | 3 Phase Arial Bunched Conductor |
| 14 | 1 Phase Arial Bunched Conductor |
| 15 | Distribution Box 1 Phase |
| 16 | Distribution Box 3 Phase |
| 17 | 11 KV Cable Box Size 3x70sqmm |
| 18 | 11 KV Cable Box Size 3x120sqmm |
| 19 | 11 KV Cable Box Size 3x185sqmm |
| 20 | 11 KV fuse Set |
| 21 | Straight Through |
| 22 | 11/0.4 KV 3 Phase 25 KVA T/F |
| 23 | 11/0.4 KV 3 Phase 63 KVA T/F |
| 24 | 11/0.4 KV 3 Phase 100 KVA T/F |
| 25 | 11 KV Pilfer proof Metering cubical and CT PT Unit |
| 26 | 11 KV VCB incoming/outgoing |
| 27 | Erection of new PCC Single/Double pole in H.T/L.T lines including fitting of all accessories as per RESSPO Norms. |
| 28 | PCC Pole 8.5 Mtr Long Single Pole |
| 29 | PCC Pole 8.5 Mtr Long Double Pole |
| 30 | PCC Pole 09 Mtr Long Single Pole. |
| 31 | PCC Pole 09 Mtr Long Double Pole. |
| 32 | PCC Pole 11 Mtr Long Single Pole. |
| 33 | PCC Pole 11 Mtr Long Double Pole. |
| 34 | ST Pole 11 Mtr Long Single Pole. |
| 35 | ST Pole 11 Mtr Long Double Pole. |
| 36 | ST Pole 13 Mtr Long Single Pole. |
| 37 | Grouting with 1:4:8 mixture in size(450x450x1500mm.) including cost of cement/Concreate & sand Required as per RESSPO Norms |
| 38 | PCC Pole 8.5 Mtr Long Single Pole |
| 39 | PCC Pole 8.5 Mtr Long Double Pole |
| 40 | PCC Pole 09 Mtr Long Single Pole. |
| 41 | PCC Pole 09 Mtr Long Double Pole. |
| 42 | PCC Pole 11 Mtr Long Single Pole. |
| 43 | PCC Pole 11 Mtr Long Double Pole. |
| 44 | ST Pole 11 Mtr Long Single Pole. |
| 45 | ST Pole 11 Mtr Long Double Pole. |
| 46 | ST Pole 13 Mtr Long Single Pole. |
| 47 | Dismantling of PCC/ST Pole due to line shifting/damagedcomplete in all respect |
| 48 | ST Pole 9 Mtr Long Single Pole. |
| 49 | ST Pole 9 Mtr Long Double Pole. |
| 50 | ST Pole 11 Mtr Long Single Pole. |
| 51 | ST Pole 11 Mtr Long Double Pole. |
| 52 | ST Pole 11 Mtr Long Tri Pole. |
| 53 | ST Pole 11 Mtr Long Four Pole. |
| 54 | LT ABC (3x95+1x70+1x16) SQ. MM |
| 55 | LT ABC (3x120+1x95+1x16) SQ. MM |
| 56 | Dismantling of Old and damaged conductor complete in all respect |
| 57 | Dismantling of Existing Distribution Transformer forincreasing capacity/Shifting complete in all respect |
| 58 | 11/0.4 KV 3 Phase 25 KVA T/F |
| 59 | 11/0.4 KV 3 Phase 63 KVA T/F |
| 60 | 11/0.4 KV 3 Phase 100 KVA T/F |
| 61 | Laying, Stringing & Sagging of Following Conductorcomplete in all respect |
| 62 | ACSR Weasel Conductor |
| 63 | ACSR Rabbit Conductor |
| 64 | 3 Phase Arial Bunched Conductor |
| 65 | 1 Phase Arial Bunched Conductor |
| 66 | Erection and fixing of Overhead Line By XLPE Cable Complete in all respect. |
| 67 | 11 KV XLPE Cable Size 3x70 sqmm |
| 68 | 11 KV XLPE Cable Size 3x120 sqmm |
| 69 | 11 KV XLPE Cable Size 3x185 sqmm |
| 70 | Mounting of CT PT unit on double pole complete in all respect. |
| 71 | Installation of 11 KV Pilfer Proof Metering Cubicle in metering room complete in all respect |
| 72 | 11 KV VCB incoming/outgoing installation |
| 73 | Under ground laying of Following cable in Single circuit on river sand to Double pole situated at both sides of road complete in all respect. Minimum depth should be 0.75 Mtr and cable should be covered by bricks from three sides. |
| 74 | 11 KV XLPE Cable Size 3x70 sqmm |
| 75 | 11 KV XLPE Cable Size 3x120 sqmm |
| 76 | 11 KV XLPE Cable Size 3x185 sqmm |
| 77 | Under ground laying of Following cable in Single circuit by drill method to Double pole situated at both sides of NH/SH/Railway Crossing (with HDPE Pipe if required) complete in all respect. |
| 78 | 11 KV XLPE Cable Size 3x70 sqmm |
| 79 | 11 KV XLPE Cable Size 3x120 sqmm |
| 80 | 11 KV XLPE Cable Size 3x185 sqmm |
| 81 | Hoisting of Following size 11 KV & 33 KV XLPE Cable on double pole with GI pipe of size 6 \\" dia 4 Mtr long including the jumpering complete with clamps , nut and bolts |
| 82 | 11 KV XLPE Cable Size 3x70 sqmm |
| 83 | 11 KV XLPE Cable Size 3x120 sqmm |
| 84 | 11 KV XLPE Cable Size 3x185 sqmm |
| 85 | Supply & Laying of G.I. Pipe at various places i.e road crossing & Hoisting etc. complete in all respect (GI pipe would be Provided by contractor at his own cost) |
| 86 | Supply & Laying of HDPE Pipe at various places i.e road crossing & Hoisting etc. complete in all respect (HDPE pipe would be Provided by contractor at his own cost). |
| 87 | The work of Driving the earthing electrode and making connections with 6 S.W.G. GI wire as per RESSPO Norms |
| 88 | Chemical earthing of T/F & Fencing including all materials (chemical, gi pipe, gi strip, nut bolt, etc) |
| 89 | Earthing of distribution T/F for body & neutral upto water level with GI Pipe of 1.5\\" Dia. Including GI strip size 35x6 mm. (all material will be supplied by Contractor). |
| 90 | The work of digging of pits, erection of Stay Clamp, Insulator etc. |
| 91 | Grouting of stays, 1:4:8 cc ratio (600x600x300mm.) as per RESPO norms. |
| 92 | Installation of 11 KV Pilfer Proof Metering Cubicle in metering room complete in all respect |
| 93 | Mounting of Following Capacity Transformers as per norms complete in all respect |
| 94 | 25 KVA T/F |
| 95 | 63 KVA T/F |
| 96 | 100 KVA T/F |
| 97 | Fixing of Distribution Box complete in all respect |
| 98 | Guarding at road crossing complete in all respect |
| 99 | Errection & Fixing of Cable box |
| 100 | 11 KV Cable Box Size 3x70sqmm |
| 101 | 11 KV Cable Box Size 3x120sqmm |
| 102 | 11 KV Cable Box Size 3x185sqmm |
| 103 | Straight Through 11 KV Cable Box Size 3x70sqmm,3X120sqmm,3x185sqmm) |
| 104 | Cutting of Tree Branch Comming Near Line |
| 105 | Supply & Fixing of Following Items to complete the work (If Not available in stores) |
| 106 | LT Clamps |
| 107 | Nut & Bolt off size |
| 108 | F Clamp |
| 109 | LT Fuse Set Protection unit for tf with SMC Box |
| 110 | X-Arm Holding Clamp |
| 111 | Clamps for top, t-off & other channel etc. |
| 112 | Stay Clamps |
| 113 | Three Phase Distribution Box Clamp (LS) |
| 114 | Dead End Clamp |
| 115 | Eye Hook |
| 116 | J Hook |
| 117 | Barbed Wire |
| 118 | Number Plate |
| 119 | Al. Lugs 70 Sqmm mm |
| 120 | Al. Lugs 150 Sqmm mm |
| 121 | 11 KV DO Fuse Set |
| 122 | Garding Angle |
| 123 | Garding Angle Clamp with Nut & Bolt |
| 124 | Suspension Clamp for XLPE Overhead |
| 125 | Danger Board |
| 126 | Stone Pad |
| 127 | M.S. Top Channel |
| 128 | M.S. T-off Channel |
| 129 | MS angle T/F Base |
| 130 | Dropper Channel |
| 131 | Safe back carriage of Distribution Transformer from work site to Balrampur Store approx. distance upto 50 Km including safe loading & unloading. |
| 132 | A.B. Cable Scrap |
| 133 | Iron Scrap |
| 134 | STP Pole Scrap |
| 135 | ACSR Weasel Conductor Scrap Please Enable Macros to View BoQ information |
AI Tender Summary
Tender Timeline
Sep 17, 2026
11:30 IST
Tender Published
Tender notice published.
CompletedSep 23, 2026
17:00 IST
Bid Submission Deadline
Online submission via eProcurement portal.
Upcoming · 4 daysSep 24, 2026
Bid Opening Date
Technical bids will be opened and evaluated.
Upcoming · 5 daysTender Documents
Download All (ZIP) ↓
Disclaimer
We takes all possible care for accurate & authentic tender information. However users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender