Tender For Renovation Works Of U.N. Brahma Memorial High School Under The Scheme Dharti Aaba Janjatiya Gram Utkarsh Abhiyan (Dajgua), Tribal Affairs (Plain) For The Financial Year 2026-27.
Tender Value
71.99 Lakhs
Estimated cost
Bid Submission
07 Oct 2026
10 days left
EMD
1.44 Lakhs
Bank guarantee accepted
Document Fee
1500
Non-refundable
Tender Type
Online
Tender Overview
Organization
Tender ID
Competition Type
NCB
Bidding Type
Tender
Location / State
Kokrajhar → Assam
EMD Exemption
Available
Quantity
Not Available
Website
Contact Person
Address
Project Description
Tender for Renovation Works Of U.N. Brahma Memorial High School Under The Scheme Dharti Aaba Janjatiya Gram Utkarsh Abhiyan (Dajgua), Tribal Affairs (Plain) For The Financial Year 2026-27.
BOQ
| Sl. No. | Item Description |
| 1 | Construction of Boundary WallEarth work in excavation by mechanical means (Hydraulic excavator) / manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift upto 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m.2.8.1 All kinds of soil. |
| 2 | Dry brick pitching half brick thick in drains including supply of bricks and preparing the surface complete :16.12.1 With common burnt clay F.P.S. (non modular) bricks of class designation 7.5 |
| 3 | Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level :4.1.5 1:3:6 (1 Cement : 3 coarse sand (zone-III) : 6 graded stone aggregate 20 mm nominal size) |
| 4 | Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete upto plinth level.5.22.1 Mild steel and Medium Tensile steel bars |
| 5 | Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete above plinth level.5.22A.1 Mild steel and Medium Tensile steel bars |
| 6 | Centering and shuttering including strutting, propping etc. and removal of form for :5.9.1 Foundations, footings, bases of columns, etc. for mass concrete |
| 7 | 5.9.5 Lintels, beams, plinth beams, girders, bressumers and cantilevers |
| 8 | Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level :5.1.3 1:2:4 (1 cement : 2 coarse sand (zone-III) : 4 graded stone aggregate 20 mm nominal size) |
| 9 | Reinforced cement concrete work in walls (any thickness), including attached pilasters, buttresses, plinth and string courses, fillets, columns, pillars, piers, abutments, posts and struts etc. above plinth level up to floor five level, excluding cost of centering, shuttering, finishing and reinforcement :5.2.2 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) : 3 graded stone aggregate 20 mm nominal size) |
| 10 | Half brick masonry with common burnt clay F.P.S. (non modular) bricks of class designation 7.5 in superstructure above plinth level up to floor V level.6.13.2 Cement mortar 1:4 (1 cement :4 coarse sand) |
| 11 | 12 mm cement plaster of mix :13.4.2 1:6 (1 cement: 6 coarse sand) |
| 12 | 15 mm cement plaster on rough side of single or half brick wall of mix:13.5.2 1:6 (1 cement: 6 coarse sand) |
| 13 | Applying one coat of water thinnable cement primer of approved brand and manufacture on wall surface :13.43.1 Water thinnable cement primer |
| 14 | Finishing walls with water proofing cement paint of required shade :13.44.1 New work (Two or more coats applied @ 3.84 kg/10 sqm) |
| 15 | Construction of Iron Gate (A)Earth work in excavation by mechanical means (Hydraulic excavator) / manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift upto 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m.2.8.1 All kinds of soil. |
| 16 | Dry brick pitching half brick thick in drains including supply of bricks and preparing the surface complete :16.12.1 With common burnt clay F.P.S. (non modular) bricks of class designation 7.5 |
| 17 | Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level :4.1.5 1:3:6 (1 Cement : 3 coarse sand (zone-III) : 6 graded stone aggregate 20 mm nominal size) |
| 18 | Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete upto plinth level.5.22.6 Thermo-Mechanically Treated bars of grade Fe-500D or more. |
| 19 | Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete above plinth level.5.22A.6 Thermo-Mechanically Treated bars of grade Fe-500D or more. |
| 20 | Centering and shuttering including strutting, propping etc. and removal of form for :5.9.1 Foundations, footings, bases of columns, etc. for mass concrete |
| 21 | 5.9.6 Columns, Pillars, Piers, Abutments, Posts and Struts |
| 22 | 5.9.5 Lintels, beams, plinth beams, girders, bressumers and cantilevers |
| 23 | Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level :5.1.2 1:1.5:3 (1 cement : 1.5 coarse sand (zone-III): 3 graded stone aggregate 20 mm nominal size) |
| 24 | Reinforced cement concrete work in walls (any thickness), including attached pilasters, buttresses, plinth and string courses, fillets, columns, pillars, piers, abutments, posts and struts etc. above plinth level up to floor five level, excluding cost of centering, shuttering, finishing and reinforcement :5.2.2 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) : 3 graded stone aggregate 20 mm nominal size) |
| 25 | 12 mm cement plaster of mix :13.4.2 1:6 (1 cement: 6 coarse sand) |
| 26 | Steel work welded in built up sections/ framed work, including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer using structural steel etc. as required. 10.25.2 In gratings, frames, guard bar, ladder, railings, brackets, gates and similar works |
| 27 | Construction of Iron Gate (B) 3 Nos.Earth work in excavation by mechanical means (Hydraulic excavator) / manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift upto 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m.2.8.1 All kinds of soil. |
| 28 | Dry brick pitching half brick thick in drains including supply of bricks and preparing the surface complete :16.12.1 With common burnt clay F.P.S. (non modular) bricks of class designation 7.5 |
| 29 | Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level :4.1.5 1:3:6 (1 Cement : 3 coarse sand (zone-III) : 6 graded stone aggregate 20 mm nominal size) |
| 30 | Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete upto plinth level.5.22.6 Thermo-Mechanically Treated bars of grade Fe-500D or more. |
| 31 | Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete above plinth level.5.22A.6 Thermo-Mechanically Treated bars of grade Fe-500D or more. |
| 32 | Centering and shuttering including strutting, propping etc. and removal of form for :5.9.1 Foundations, footings, bases of columns, etc. for mass concrete |
| 33 | 5.9.6 Columns, Pillars, Piers, Abutments, Posts and Struts |
| 34 | 5.9.5 Lintels, beams, plinth beams, girders, bressumers and cantilevers |
| 35 | Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level :5.1.2 1:1.5:3 (1 cement : 1.5 coarse sand (zone-III): 3 graded stone aggregate 20 mm nominal size) |
| 36 | Reinforced cement concrete work in walls (any thickness), including attached pilasters, buttresses, plinth and string courses, fillets, columns, pillars, piers, abutments, posts and struts etc. above plinth level up to floor five level, excluding cost of centering, shuttering, finishing and reinforcement :5.2.2 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) : 3 graded stone aggregate 20 mm nominal size) |
| 37 | 12 mm cement plaster of mix :13.4.2 1:6 (1 cement: 6 coarse sand) |
| 38 | Steel work welded in built up sections/ framed work, including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer using structural steel etc. as required. 10.25.2 In gratings, frames, guard bar, ladder, railings, brackets, gates and similar works |
| 39 | Earth FillingExcavating, supplying and filling of local earth (including royalty) by mechanical transport upto a lead of 5km also including ramming and watering of the earth in layers not exceeding 20 cm in trenches, plinth, sides of foundation etc. complete. Please Enable Macros to View BoQ information |
AI Tender Summary
Tender Timeline
Sep 16, 2026
11:30 IST
Tender Published
Tender notice published.
CompletedOct 07, 2026
17:00 IST
Bid Submission Deadline
Online submission via eProcurement portal.
Upcoming · 10 daysOct 07, 2026
Bid Opening Date
Technical bids will be opened and evaluated.
Upcoming · 10 daysTender Documents
Download All (ZIP) ↓
Disclaimer