Tender for Dismantle,Transportation & Installation Of Pony Belt Driveheads From (1)D-19 B/G Face To D-20 B/G,10Th D/R Jn. (2)D-18 T/G,10Th D/R Jn. To D-19 T/G In 10Th Rise In Xvi(T) Seam At 500Mh In Moonidih Colliery, W.J. Area
BOQ
| Sl. No. | Item Description |
| 1 | Dismantle,Transportation & Installation of Pony belt driveheads from (1)D-19 B/G Face to D-20 B/G,10th D/R Jn. (2)D-18 T/G,10th D/R Jn. To D-19 T/G in 10th Rise in XVI(T) seam at 500MH in Moonidih Colliery, W.J. Area |
| 2 | Dismantalling of Pony drive head at D-19 B/G face at chainage 525m Analysis: Manshift required = 8 unskilled manshift/shift Cost/shift= 8*1437.6 =Rs11500.8/shift |
| 3 | Manual Transportation of jib drum,gear box,motor of pony drivehead from D-19 B/G Face (525m inside from 10th D/R) to D-20 B/G,10th D/R jn. i.e.Total distance=725m Analysis: Manshift required for manual transportation of one item/60m =10 unskilled manshift/shift Cost/mt/item= 10*1437.60/60 =Rs.239.6/mt/item Total items=3 no.;Therefore cost/mt=(Rs 239.6 *3)=Rs 718.8/mt |
| 4 | Manual Transportation of Drive frames of pony drivehead from D-19 B/G Face (525m inside from 10th D/R) to D-20 B/G,10th D/R jn. i.e.(Total Distance=725m) i.e.Total distance=725m Analysis: Manshift required for manual transportation of pony frames =8 unskilled manshift/shift Cost/shift= 8*1437.6 = Rs 11500.8/shift |
| 5 | Manual Transportation of starter and starting cable of pony drivehead from D-19 B/G Face (525m inside from 10th D/R) to D-20 B/G,10th D/R jn. i.e.(Total Distance=725m) Analysis: Manshift required for transportation of starter =8 unskilled manshift/shift Cost/shift= 8*1437.6 =Rs11500.8/shift |
| 6 | Installation of Pony Drivehead at D-20 B/G,10th D/R jn. Analysis: Unskilled manshift required/shift=8 cost/shift=8*1437.6 =Rs11500.8/shift |
| 7 | Dismantalling of Pony drive head at D-18 T/G,10th D/R Jn. Analysis: Manshift required = 8 unskilled manshift/shift Cost/shift=8*1437.6 =Rs11500.8/shift |
| 8 | Manual Transportation of jib drum,gear box,motor of pony drivehead from D-18 T/G,10th D/R Jn. to D-19 T/G in 10th D/R i.e.(Total Distance=240m) i.e.Total distance=240m Analysis: Manshift required for manual transportation of one item/60m =10 unskilled manshift/shift Cost/mt/item= 10*1437.60/60 =Rs.239.6/mt/item Total items=3 no.;Therefore cost/mt=(Rs 239.6 *3)=Rs 718.8/mt |
| 9 | Manual Transportation of Drive frames of pony drivehead from D-18 T/G,10th D/R Jn. to D-19 T/G in 10th D/R i.e.(Total Distance=240m) i.e.Total distance=240m Analysis: Manshift required for manual transportation of pony frames =8 unskilled manshift/shift Cost/shift= 8*1437.6 =Rs11500.8/shift |
| 10 | Manual Transportation of starter and starting cable of pony drivehead from D-18 T/G,10th D/R Jn. to D-19 T/G in 10th D/R i.e.(Total Distance=240m) Analysis: Manshift required for transportation of starter =8 unskilled manshift/shift Cost/shift= 8*1437.6 =Rs11500.8/shift |
| 11 | Installation of Pony Drivehead at D-19 T/G in 10th D/R Analysis: Unskilled manshift required/shift=8 Cost/shift= 8*1437.6 =Rs11500.8/shift |
| 12 | Transporting manually 300mt belt structure of 1000mm belt conveyor from E-9/TG (up to 300mt chainage) XVI(B)& stacking at D-19/B.G Along 9th rise through track. i) Channel=122no. @40chenel/Arm trolley=3.05 say 3 Arm trolley ii) Bracket=81nos. @12Bracket/Arm trolley=6.75 Say 7 Arm trolley. iii) Leg post=48nos. @12 Leg post/Arm trolley=4 Arm trolley. iv)top & Bottom Roller=163nos. @100 Roller/Arm trolley=1.63 Say 2 Arm trolley Total=15 Arm trolley Analysis: Manshaft required =6 Unskilled manshift* 2 Shift/2 Trolley I.e, (2shiftx6x1437.6)/2 =Rs.8625.6/Trolley |
| 13 | Add CP 15% as per clause 4.17.1 of Civil Eng. Manual & BCCL SOR |
| 14 | CMPF, Pension and admin. Charge of Employee Un Skilled surface |
| 15 | Total impact of GST for the purpose of CTC Please Enable Macros to View BoQ information |
AI Tender Summary
Tender Timeline
Tender Published
Tender notice published.
CompletedBid Submission Deadline
Online submission via eProcurement portal.
Upcoming · 4 daysBid Opening Date
Technical bids will be opened and evaluated.
Upcoming · 7 daysTender Documents
Download All (ZIP) ↓We takes all possible care for accurate & authentic tender information. However users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender