Tender For Constrcution Of Foundation Of One Number 220 Kv Bay At Durgapur 220 Kv Sub-Station Under Durgapur 400 Kv Area Office
Tender Value
80.36 Lakhs
Estimated cost
Bid Submission
28 Sep 2026
16 days left
EMD
1 Lakhs
Bank guarantee accepted
Document Fee
Ref. Documents
Non-refundable
Tender Type
Online
Tender Overview
Organization
Tender ID
Competition Type
NCB
Bidding Type
Tender
Location / State
Paschim Bardhaman → West Bengal
EMD Exemption
Not Available
Quantity
Not Available
Website
Contact Person
Address
Project Description
Tender for Constrcution Of Foundation Of One Number 220 Kv Bay At Durgapur 220 Kv Sub-Station Under Durgapur 400 Kv Area Office
BOQ
| Sl. No. | Item Description |
| 1 | Constrcution of foundation of one number 220 KV bay at Durgapur 220 KV Sub-station under Durgapur 400 KV Area Office WBSETCL |
| 2 | Clearing jungle including uprooting of rank vegetation, grass, brush wood, trees and saplings of girth up to 30 cm measured at a height of 1 m above ground level and removal of rubbish up to a distance of 50 m outside the periphery of the area cleared. |
| 3 | Earth work in excavation by mechanical means (Hydraulic excavator) / manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, for all lift, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m. for all kind of soil |
| 4 | Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundations etc. in layers not exceeding 20cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 and for all lift. |
| 5 | Supplying and filling in plinth with sand under floors, including watering, ramming, consolidating and dressing complete. |
| 6 | Close timbering over areas including strutting, shoring and packing cavities (wherever required) etc. complete. (Measurements to be takenof the face area timbered): Depth not exceeding 1.5 m |
| 7 | Depth exceeding 1.5 m but not exceeding 3 m |
| 8 | 1:3:6 (1 Cement : 3 coarse sand (zone-III) derived from natural sources : 6 graded stone aggregate 20 mm nominal size derived from natural sources) |
| 9 | Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level : 1:1.5:3 (1 cement : 1.5 coarse sand (zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources) |
| 10 | Reinforced cement concrete work in walls (any thickness), including attached pilasters, buttresses, plinth and string courses, fillets, columns, pillars, piers, abutments, posts and struts etc. above plinth level up to floor five level, excluding cost of centering, shuttering, finishing andreinforcement : 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) derived fromnatural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources) |
| 11 | Steel reinforcement for R.C.C. work ready to use “cut and bend” rebars of approved make from factory/workshop to construction site including placing in position and binding all complete upto plinth level Thermo-Mechanically Treated bars of grade Fe-500D ormore |
| 12 | Steel reinforcement for R.C.C. work ready to use “cut and bend” rebars of approved make from factory/workshop to construction site including placing in position and binding all complete above plinth level Thermo-Mechanically Treated bars of grade Fe-500D ormore |
| 13 | Centering and shuttering including strutting, propping etc. and removal of form work for : Foundations, footings, bases for columns |
| 14 | Columns, Pillars, Piers, Abutments, Posts and Struts |
| 15 | Dry brick on edge flooring in required pattern with bricks of class designation 7.5 on a bed of 12 mm mud mortar, including filling joints with fine sand Zone IV with common burnt clay non modular bricks. |
| 16 | Brick work with common burnt clay F.P.S. (non modular) bricks of class designation 7.5 in foundation and plinth in: cement mortar 1:6 |
| 17 | Cement Plaster in Coarse sand, 1:6 , 12 mm thick |
| 18 | Neat cement punning |
| 19 | Demolishing R.C.C. work manually/ by mechanical means includingstacking of steel bars and disposal of unserviceable material within 50 metres lead as per direction of Engineer - in- charge. |
| 20 | Demolishing brick work manually/ by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer-in-charge. In cement mortar |
| 21 | Demolishing cement concrete manually/ by mechanical means including disposal of material within 50 metres lead as per direction of Engineer - in - charge. Nominal concrete 1:4:8 or leaner mix (including equivalentdesign mix) |
| 22 | Structural steel work riveted, bolted or welded in built up sections, trusses and framed work, including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer all complete. |
| 23 | Supplying and laying Polythene Sheet (150gm/sq.m.)over damp proof course or below flooring or roo fterracing or in foundation or in foundation trenches. |
| 24 | Brick edging in full brick width and half brick depth including excavation, refilling and disposal of surplus earth lead upto 50 metres. |
| 25 | Carriage for 5.0 km lead by Mechanical Transport including loading, Unloading and stacking for rubbish .(Original rate is 231.93 . The estimated rate is including 18% GST , Overhead charges 5% & contractors profit 10 %) |
| 26 | Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level 1:5:10 (1 cement : 5 coarse sand (zone-III) derived fromnatural sources : 10 graded stone aggregate 40 mmnominal size derived from natural sources) |
| 27 | Supplying and stacking at site. 53 mm to 22.4 mm size stone aggregate |
| 28 | Laying, spreading and compacting stone aggregate of specified sizes in uniform thickness as per direction of E.I.C SELECT GST Please Enable Macros to View BoQ information |
AI Tender Summary
Tender Timeline
Sep 11, 2026
11:30 IST
Tender Published
Tender notice published.
CompletedSep 28, 2026
17:00 IST
Bid Submission Deadline
Online submission via eProcurement portal.
Upcoming · 16 daysSep 30, 2026
Bid Opening Date
Technical bids will be opened and evaluated.