Bids Are invited for Custom Bid For Services - ---- - Supply Of Material With Inspected Provided By Contractor , Stone Pad 300*300*75 Mm , 11 Kv Cross Arm , 11 Kv Cross Arm Cl , Garding Angle , Garding Cl , G.I Wire 6 Swg , G.I Wire 8 Swg , Cross Cl
Tender Overview
Project Description
Bids Are invited for Custom Bid For Services - ---- - Supply Of Material With Inspected Provided By Contractor , Stone Pad 300*300*75 Mm , 11 Kv Cross Arm , 11 Kv Cross Arm Cl , Garding Angle , Garding Cl , G.I Wire 6 Swg , G.I Wire 8 Swg , Cross Cl , F Brackat For 11 Kv , M.S Nut Bolt & Washers All Size , Concriting Of Support , Number Plate With Cl , Danger Board With Cl , Concriting Of Stay , All Paint , Red Oxide Paint , I Rag Bolt , Barbed Wire , P.G Cl For Dog Conductor , Cl With N&B , Repairing Of Power T/F Plinth , Pipe Earthing Up To Water Leval For Vcb And T/F , 140 Mm Od Pn-4 Pe-80 Grade Uv Stabilizcd Hdpe Pipe As Per Is:4984 In 6 Mter , G.I Pipe 8 Dia , Aluminium Tape , Top Channel 125X65x6x2240 , 11 Kv Xlpe Cable Jointing Kit 3X185 Sqmm , I/D & O/D Cable Jointing Kit Suitable For 3X185 Mm Sq Xlpe Cable , Dropper Channel M.S 100X50x6x2028 Mm , M.S Angle 75X75x6x2028mm For Bracing Set With 04 No Cl S Each Set , The Route Survey Prior To Commencement Of Line Ascertain The Actual Site Conditions And To Finalise The Technically Feasible Line Route, Pole Locations, Various Crossings/Obstructions And Right Of Way. , Digging Of Pits Of Size 0.45X1.25X 1.75 Mtr For Erection Of Stp 11.0 Mtr. Long (Single Pole). , Erection Of Double Pole Of Stp 11 Mtr. Long , Erection Of Single Pole Stp 11.0 Mtr Long . , Mounting And Fitting Of V-Type Cross Arm,11 Kv Pin, Pin Insulator, Danger Board Complte In All Respect As Per Drawing Of Respo On Single Stp Pole 11 Mtr Long Only 11 Mtr. S.T.P. Pole & 11 Kv Pin Insulator, Shall Be Provided By Department & All Other Material Cross Arms & Cross Arm Cl , Danger Board Etc. Provided By Contractor. , Mounting And Fitting Of V-Type Cross Arm, Danger Board Complete In All Respect As Per Drawing Of Respo On Single Stp Pole 11 Mtr Long Only 11 Mtr. S.T.P. Pole Shall Be Provided By Department & All Other Material Cross Arms & Cross Arm Cl , Danger Board Etc. Provided By Contractor. , Fabrication, Mounting And Fitting Of Top Channel, Bracing Made By M.S. Angle,11 Kv Pin & Pin Insulator, Disc Insulator And Disc Fitting On Double Pole. Stp Pole 11 Mtr. Long, 11 Kv Pin Insulator & 11 Disc Insulator Shall Be Provided By Department. & Other Material Top Channel With Cl , Bracing Angle With Cl , Danger Board With Cl ,E-Cl , Pg Cl Etc. Provided By Contractor. , Digging Of Pits Of Size 0.60X 0.60X1.2 Mtr Grouting The Stay Rod Anchor Plates 0.45X 0.45X 0.45 Mtr With Cement, Jamuna Sand And Brick Ballast Ratio 1:4:8 As Per Drawing No. Res-16, Cement, Sand, Brick, Ballast Shall Be Provided By Contractor. , Complete Fitting Of Stay Rod And Fastening Stay Wire Including Fitting Of Stay Cl , Turn Buckle, And Making Ring Of Stay Wire On Both Ends In Seven Stands 9 To 12 Long. Stay Cl , Turn Buckle Stay Cl Shall Be Provided By Contractor. Only Stay Rod, Stay Wire & Stay Insulator Shall Be Provided By Department. , Earthing Of Single Stp Pole By Digging 1.00 Mtr Deep Pit And Driving The Electrodes Of Ms Earth Road And Connecting All The Metallic Parts Of Poles With Earthing Rod By G.I. Wire And Filling Pits With Soil After Completion Of Earthing.Earth Wire/ G.I. Wire M.S.Rod Shall Be Provided By Department. , Painting Of Single Stp Pole 11 Mtr Long (Red Oxide & Alluminium Paint Shall Be Provided By Contractor. , Grouting Of Single Stp Pole 11 Mtr Long With Cement, Send & Brick Bllast Ratio 1:4:8 Size 0.45*0.45*1.5 Mtr Deep Under The Ground As Per Drawing No R.E.S-6 With Muffing 1 Ft. Minium Cement Send Bricks Ballast Shall Be Provided By Contractor. , Work Of Road, Canals, Telephones And H.T.Line Crossing By Providing Gurding Angles/ Channels On Supports And Fabrication And Fitting Of Guarding Net As Per Drawing No. 48 With G.I. Wire No. 8/10Swg. Guarding Cl Turn Buckle Shall Be Provided By Contractor Only G.I Wire Garding Angle Provided By Department. , Laying & Stringling Of A.C.S.R. Rabit Conductor With The Help Of Aluminium Roller By Hanging Three Nos. On Each Support In A Manner Taking Sufficient Care To Ensure Safety Of A.C.S.R. Rabit Conductor Against Rubbing On Ground Precaution For Safety Of Crops Is Also To Be Taken. The Work Includes Jointing Of Conductor By Providing Jointing Sleaves Stringing Of Conductor Upto Correct Sag And Binding Of Conductor With Insulators On Each Support.The Contractor Shall Provide Jointing Sleeve,Binding Wire.All Work To Be Carried Out Stricktly As Per Respo Norm. , Jumpring Of 11 Kv Line On D/P Using P.G. Cl Rabbit To Rabbit & Binding Of Jumper On Pin Insulator, P.G. Cl Provided By The Contractor. , Laying & Stringling Of 11 Kv Xlpe Cable 3*185 Sqmm By Overhead Double Circut 11 Kv Line With Fitting 11 Kv V-Cross Arm With The Help Of Aluminium Roller By Hanging. On Each Support In A Manner Taking Sufficient Care To Ensure Safety Of Xlpe Cable 3*185 Sqmm Against Rubbing On Ground Precaution For Safety Of Crops Is Also To Be Taken. All Work To Be Carried Out Stricktly As Per Respo Norm. , Laying & Stringling Of 11 Kv Xlpe Cable 3*185 Sqmm By Underground Double Circut With Hdpe Pipe Method (Tenchless) 3 Mtr. Deep To Earth For Difference Places Near S/S To Lehra Chauraha, 2 Nos. 33 Kv Line Crossing & Nhai Crossing On Each Support In A Manner Taking Sufficient Care To Ensure Safety Of Xlpe Cable 3*185 Sqmm Against Rubbing On Ground Precaution For Safety Of Crops Is Also To Be Taken. All Work To Be Carried Out Stricktly As Per Respo Norm. Hdpe Pipe 140 Mm Od Pn-4 P-80 Grade Uv Establisied Hdpe Pipe As Per Is 4984 In 6 Mtr., Cable Jointing Kit & Alluminium Lug Provided By Contractor. , Hosting & Stringling Of 11 Kv Xlpe Cable 3*185 Sqmm Loop & Air On Dp Both Side Difference Places Near S/S To Lehra Chauraha, 2 Nos. 33 Kv Line Crossing & Nhai Crossing. On Each Support In A Manner Taking Sufficient Care To Ensure Safety Of Xlpe Cable 3*185 Sqmm Against Rubbing On Ground Precaution For Safety Of Crops Is Also To Be Taken. All Work To Be Carried Out Stricktly As Per Respo Norm. Provided By Contractor. , Road Restoration Charge , Laying & Stringling Of 11 Kv Xlpe Cable 3*185 Sqmm Loop & Air On Dp. On Each Support In A Manner Taking Sufficient Care To Ensure Safety Of Xlpe Cable 3*185 Sqmm Against Rubbing On Ground Precaution For Safety Of Crops Is Also To Be Taken. All Work To Be Carried Out Stricktly As Per Respo Norm. On Metering Provided By Contractor. , Jumpring Of 11 Kv Line On D/P Using Alluminium Lug Xlpe Cable To Xlpe Cable & Alluminium Lug, Rabbit To Rabbit Conductor & Binding Of Jumpring On Pin Insulator Alluminium Lug & Pg Cl Provided By The Contractor. , Termination Of Cable Boxes Of Size 3*185 Sqmm For Xlpe Cable Boxes I/D & O/G Will Be Of Heat Shink Indoor Type And Outdoor Type Cable Boxes Will Be Provided By Contractor. , Loading Carriage And Unloading Of Following Line Materials From Central Store Odhpura To Dump Site Store. The Materials Will Be Provided As Per Availability And In Piece Meal. , 3*185 Sqmm. Al Xple Cable , Stp 11 Mrt Long , Acsr Rabit Conductor , Dog Conductor , 11 Kv Ct/Pt Pole Mounting Unit , 11 Kv Tvm , Incomming Vcb 600/300/5A 350Mva 1250A , Outgoing Vcb 200/100/5A 350Mva 1250A , 3 Ph.-4 Wire Static Tvm 11 Kv , 11 Kv Pilfer Proff Metering Cubical , Installation Of 3Ph-4W Static Tvm 11 Kv T&P And Labour Provided By Contractor , Installation & Commisioning Of 11 Kv Pilfer Proff Metering Cubical T&P And Labour Provided By Contractor , Other Centrally Procured Items As Per Requirement For Construction Of Line.(11 Kv Disc With Fitting, X-Arm,11 Kv Pin Insulator With Pin ,Stay Rod,Earth Rod,M.S.Rod,G.I.Wire Etc.) , Trimming Of Tree Branches Big/Small Tree Branches Which Is Lying On 11 Kv Feeder Allignment Of 11 Kv Line , A) Small , (B) Big , Received Back Material From Site To Store Hathras After Completion According To Executed Estimate. , Supply Of Materials Provided By Contractor , 11 Kv Cable Jointing Kit 3X185 Mm.Sq. , Pipe Earthing Upto Water Level For Vcb And T/F , Repairing Of Existing T/F Plinth Size 4.46 X 3.46 X 1.0 Mtr. , Dismantling Of Switchyard Fencing For Safe Shifting Of Old 5 Mva Power T/Fs , Safe Shifting & Dragging Of Old 5 Mva T/F From Inside To Out Side Of Switch Yard After Detaching Its Accessories I.E. Radiator, Conservator Etc And Empting The T/F I.E Taking Out The T/F Oil And Disconnecting All 33 Kv And 11 Kv Connections As Well As Dismantling Of 11 Kv Cable Stand And Neutral Stand. All Tools & T&P Shall Be Provided By The Contractor. , Special Earthing Of Neutral And Body Of 10Mva T/F With The Help Of 3 Nos.G.I. Pipe 2 Dia. Length 60 Feet. G.I. Pipe For Making Of Delta, 1 No For Body And 1 No For Neutral Earthing Complete In All Respect And Connected With 50X6 M.M Gi Strip. G.I. Pipe, G.I. Strip Etc. Required For Completion Of Work In All Respect Shall Be Provided By The Contractor. , Earthing Of 11 Kv Indoor Equipments, With The Help Of 3 Nos.G.I. Pipe 2 Dia. Length 60 Feet. G.I. Pipe For Making Of Delta Switch Gears As Per Respo Drawing. With G.I. Strip Of Size 50X6 Mm, Aall Respect Shall Be Provided By The Contractor. , Installation Of 11 Kv Vcb In The Switch Gear Room, By Grouting Base Channel 100 X 50 X 6 X 1000Mm. Fixing Of 11 Kv Switchgears Rag Bolt, Mounting Of P.T. On Incoming & 11 Kv Tvm, 11 Kv Ct/Pt Pole Mounted Unit. , (A) 11 Kv Incomming , (B) 11 Kv O/G Vcb , (C) 11 Kv Tvm , (D) 11 Kv Ct/Pt Pole Mounted Unit , Laying Of 11 Kv 3 X 185 Sqmm. Xlpe Power Cable By Digging 0.75 Mtr. Deep Trench, Putting Layer Of Sand In The Bottom, Ramming It, Laying Of Cable Over It Rmt And Covering The Cable From Sides And Top By Laying Bricks, Finally Covering The Same By Earth And Levelling Of The Same, All The Materials, Except Cable, Will Be Provided By The Contractor. Rates May Be Quoted Per Rmt , Termination Of Cable Boxes Of Size 3*185 Sqmm For Xlpe Cable Boxes I/D & O/G Will Be Of Heat Shink Indoor Type And Outdoor Type Cable Boxes Will Be Provided By Contractor. , Following Items Shall Also Be Provided By The Contractor At The Sub-Station. , (A) Hand Gloves , (B) Rubber Matting , (C) Fire Bucket With Stand
BOQ
| Sl. No. | Item Title | Item Description |
| 1 | Supply of Material with inspected provided by Contractor | Supply of Material with inspected provided by Contractor |
| 2 | Stone Pad 300*300*75 mm | Stone Pad 300*300*75 mm |
| 3 | 11 KV Cross Arm | 11 KV Cross Arm |
| 4 | 11 KV Cross Arm Clamp | 11 KV Cross Arm Clamp |
| 5 | Garding Angle | Garding Angle |
| 6 | Garding Clamp | Garding Clamp |
| 7 | G.I Wire 6 SWG | G.I Wire 6 SWG |
| 8 | G.I Wire 8 SWG | G.I Wire 8 SWG |
| 9 | Cross Clamp | Cross Clamp |
| 10 | F Brackat for 11 KV | F Brackat for 11 KV |
| 11 | M.S Nut Bolt & Washers All Size | M.S Nut Bolt & Washers All Size |
| 12 | Concriting of Support | Concriting of Support |
| 13 | Number Plate with Clamp | Number Plate with Clamp |
| 14 | Danger Board with Clamp | Danger Board with Clamp |
| 15 | Concriting of Stay | Concriting of Stay |
| 16 | All Paint | All Paint |
| 17 | Red Oxide Paint | Red Oxide Paint |
| 18 | I Rag Bolt | I Rag Bolt |
| 19 | Barbed wire | Barbed wire |
| 20 | P.G Clamp for Dog Conductor | P.G Clamp for Dog Conductor |
| 21 | Clamp with N&B | Clamp with N&B |
| 22 | Repairing of Power T/F Plinth | Repairing of Power T/F Plinth |
| 23 | Pipe Earthing up to water leval for VCB and T/F | Pipe Earthing up to water leval for VCB and T/F |
| 24 | 140 mm OD PN-4 PE-80 Grade UV Stabilizcd HDPE Pipe as per IS:4984 in 6 Mter | 140 mm OD PN-4 PE-80 Grade UV Stabilizcd HDPE Pipe as per IS:4984 in 6 Mter |
| 25 | G.I Pipe 8 dia | G.I Pipe 8 dia |
| 26 | Aluminium Tape | Aluminium Tape |
| 27 | Top Channel 125x65x6x2240 | Top Channel 125x65x6x2240 |
| 28 | 11 KV XLPE Cable Jointing Kit 3x185 Sqmm | 11 KV XLPE Cable Jointing Kit 3x185 Sqmm |
| 29 | I/D & O/D Cable Jointing Kit suitable for 3x185 mm Sq XLPE Cable | I/D & O/D Cable Jointing Kit suitable for 3x185 mm Sq XLPE Cable |
| 30 | Dropper Channel M.S 100x50x6x2028 mm | Dropper Channel M.S 100x50x6x2028 mm |
| 31 | M.S ANGLE 75x75x6x2028mm For Bracing Set with 04 no Clamps each Set | M.S ANGLE 75x75x6x2028mm For Bracing Set with 04 no Clamps each Set |
| 32 | The route survey prior to commencement of line ascertain the actual site conditions and to finalise the technically feasible line route, pole locations, various crossings/obstructions and Right of way. | The route survey prior to commencement of line ascertain the actual site conditions and to finalise the technically feasible line route, pole locations, various crossings/obstructions and Right of way. |
| 33 | Digging of pits of size 0.45x1.25x 1.75 mtr for erection of STP 11.0 mtr. long (single pole). | Digging of pits of size 0.45x1.25x 1.75 mtr for erection of STP 11.0 mtr. long (single pole). |
| 34 | Erection of double pole of STP 11 mtr. long | Erection of double pole of STP 11 mtr. long |
| 35 | Erection of single pole STP 11.0 mtr long . | Erection of single pole STP 11.0 mtr long . |
| 36 | Mounting and fitting of V-type cross arm,11 KV pin, pin insulator, Danger board complte in all respect as per drawing of RESPO on single STP pole 11 mtr long only 11 Mtr. S.T.P. pole & 11 KV Pin Insulator, shall be provided by department & all other material cross arms & Cross Arm clamp, Danger board etc. provided by contractor. | Mounting and fitting of V-type cross arm,11 KV pin, pin insulator, Danger board complte in all respect as per drawing of RESPO on single STP pole 11 mtr long only 11 Mtr. S.T.P. pole & 11 KV Pin Insulator, shall be provided by department & all other material cross arms & Cross Arm clamp, Danger board etc. provided by contractor. |
| 37 | Mounting and fitting of V-type cross arm, Danger board complete in all respect as per drawing of RESPO on single STP pole 11 mtr long only 11 Mtr. S.T.P. pole shall be provided by department & all other material cross arms & Cross Arm clamp, Danger board etc. provided by contractor. | Mounting and fitting of V-type cross arm, Danger board complete in all respect as per drawing of RESPO on single STP pole 11 mtr long only 11 Mtr. S.T.P. pole shall be provided by department & all other material cross arms & Cross Arm clamp, Danger board etc. provided by contractor. |
| 38 | Fabrication, mounting and fitting of top channel, bracing made by m.s. angle,11 KV pin & pin insulator, disc insulator and disc fitting on double pole. STP Pole 11 Mtr. Long, 11 KV Pin Insulator & 11 Disc Insulator shall be provided by Department. & Other Material Top channel with clamp, Bracing Angle with clamp, Danger board with clamp ,E-clamp , PG clamp etc. provided by contractor. | Fabrication, mounting and fitting of top channel, bracing made by m.s. angle,11 KV pin & pin insulator, disc insulator and disc fitting on double pole. STP Pole 11 Mtr. Long, 11 KV Pin Insulator & 11 Disc Insulator shall be provided by Department. & Other Material Top channel with clamp, Bracing Angle with clamp, Danger board with clamp ,E-clamp , PG clamp etc. provided by contractor. |
| 39 | Digging of pits of size 0.60x 0.60x1.2 mtr grouting the stay rod anchor plates 0.45x 0.45x 0.45 mtr with cement, Jamuna sand and brick ballast ratio 1:4:8 as per drawing No. RES-16, Cement, sand, brick, ballast shall be provided by contractor. | Digging of pits of size 0.60x 0.60x1.2 mtr grouting the stay rod anchor plates 0.45x 0.45x 0.45 mtr with cement, Jamuna sand and brick ballast ratio 1:4:8 as per drawing No. RES-16, Cement, sand, brick, ballast shall be provided by contractor. |
| 40 | Complete fitting of stay rod and fastening stay wire including fitting of stay clamp, turn buckle, and making ring of stay wire on both ends in seven stands 9” to 12” long. Stay clamp, Turn buckle Stay Clamp shall be provided by contractor. Only Stay Rod, Stay wire & Stay Insulator shall be provided by department. | Complete fitting of stay rod and fastening stay wire including fitting of stay clamp, turn buckle, and making ring of stay wire on both ends in seven stands 9” to 12” long. Stay clamp, Turn buckle Stay Clamp shall be provided by contractor. Only Stay Rod, Stay wire & Stay Insulator shall be provided by department. |
| 41 | Earthing of single STP pole by digging 1.00 mtr deep pit and driving the electrodes of MS earth road and connecting all the metallic parts of poles with earthing rod by G.I. wire and filling pits with soil after completion of earthing.earth wire/ G.I. wire M.S.rod shall be provided by department. | Earthing of single STP pole by digging 1.00 mtr deep pit and driving the electrodes of MS earth road and connecting all the metallic parts of poles with earthing rod by G.I. wire and filling pits with soil after completion of earthing.earth wire/ G.I. wire M.S.rod shall be provided by department. |
| 42 | Painting of single STP pole 11 mtr long (Red oxide & Alluminium paint shall be provided by contractor. | Painting of single STP pole 11 mtr long (Red oxide & Alluminium paint shall be provided by contractor. |
| 43 | Grouting of single STP pole 11 mtr long with cement, send & brick bllast ratio 1:4:8 size 0.45*0.45*1.5 mtr deep under the ground as per drawing no r.e.s-6 with muffing 1 ft. minium cement send bricks ballast shall be provided by contractor. | Grouting of single STP pole 11 mtr long with cement, send & brick bllast ratio 1:4:8 size 0.45*0.45*1.5 mtr deep under the ground as per drawing no r.e.s-6 with muffing 1 ft. minium cement send bricks ballast shall be provided by contractor. |
| 44 | Work of road, canals, telephones and H.T.line crossing by providing gurding angles/ channels on supports and fabrication and fitting of guarding net as per drawing No. 48 with G.I. wire No. 8/10SWG. guarding clamp turn buckle shall be provided by contractor only G.I wire garding angle provided by department. | Work of road, canals, telephones and H.T.line crossing by providing gurding angles/ channels on supports and fabrication and fitting of guarding net as per drawing No. 48 with G.I. wire No. 8/10SWG. guarding clamp turn buckle shall be provided by contractor only G.I wire garding angle provided by department. |
| 45 | Laying & stringling of A.C.S.R. Rabit conductor with the help of aluminium roller by hanging three nos. on each support in a manner taking sufficient care to ensure safety of A.C.S.R. Rabit conductor against rubbing on ground precaution for safety of crops is also to be taken. The work includes jointing of Conductor by providing jointing sleaves stringing of conductor upto correct sag and binding of conductor with insulators on each support.The contractor shall provide jointing sleeve,Binding wire.All work to be carried out stricktly as per RESPO Norm. | Laying & stringling of A.C.S.R. Rabit conductor with the help of aluminium roller by hanging three nos. on each support in a manner taking sufficient care to ensure safety of A.C.S.R. Rabit conductor against rubbing on ground precaution for safety of crops is also to be taken. The work includes jointing of Conductor by providing jointing sleaves stringing of conductor upto correct sag and binding of conductor with insulators on each support.The contractor shall provide jointing sleeve,Binding wire.All work to be carried out stricktly as per RESPO Norm. |
| 46 | Jumpring of 11 KV line on D/P using P.G. Clamp Rabbit to Rabbit & binding of jumper on Pin insulator, P.G. Clamp provided by the contractor. | Jumpring of 11 KV line on D/P using P.G. Clamp Rabbit to Rabbit & binding of jumper on Pin insulator, P.G. Clamp provided by the contractor. |
| 47 | Laying & stringling of 11 KV XLPE Cable 3*185 sqmm by overhead double circut 11 KV Line with fitting 11 KV V-Cross Arm with the help of aluminium roller by hanging. on each support in a manner taking sufficient care to ensure safety of XLPE Cable 3*185 sqmm against rubbing on ground precaution for safety of crops is also to be taken. All work to be carried out stricktly as per RESPO Norm. | Laying & stringling of 11 KV XLPE Cable 3*185 sqmm by overhead double circut 11 KV Line with fitting 11 KV V-Cross Arm with the help of aluminium roller by hanging. on each support in a manner taking sufficient care to ensure safety of XLPE Cable 3*185 sqmm against rubbing on ground precaution for safety of crops is also to be taken. All work to be carried out stricktly as per RESPO Norm. |
| 48 | Laying & stringling of 11 KV XLPE Cable 3*185 sqmm by underground double circut with HDPE Pipe method (tenchless) 3 mtr. deep to earth for difference places near s/s to lehra chauraha, 2 Nos. 33 KV Line Crossing & NHAI Crossing on each support in a manner taking sufficient care to ensure safety of XLPE Cable 3*185 sqmm against rubbing on ground precaution for safety of crops is also to be taken. All work to be carried out stricktly as per RESPO Norm. HDPE pipe 140 mm OD PN-4 P-80 Grade UV establisied HdPE pipe as per IS 4984 in 6 mtr., cable jointing kit & alluminium lug provided by contractor. | Laying & stringling of 11 KV XLPE Cable 3*185 sqmm by underground double circut with HDPE Pipe method (tenchless) 3 mtr. deep to earth for difference places near s/s to lehra chauraha, 2 Nos. 33 KV Line Crossing & NHAI Crossing on each support in a manner taking sufficient care to ensure safety of XLPE Cable 3*185 sqmm against rubbing on ground precaution for safety of crops is also to be taken. All work to be carried out stricktly as per RESPO Norm. HDPE pipe 140 mm OD PN-4 P-80 Grade UV establisied HdPE pipe as per IS 4984 in 6 mtr., cable jointing kit & alluminium lug provided by contractor. |
| 49 | Hosting & stringling of 11 KV XLPE Cable 3*185 sqmm loop & air on DP both side difference places near s/s to lehra chauraha, 2 Nos. 33 KV Line Crossing & NHAI Crossing. on each support in a manner taking sufficient care to ensure safety of XLPE Cable 3*185 sqmm against rubbing on ground precaution for safety of crops is also to be taken. All work to be carried out stricktly as per RESPO Norm. provided by contractor. | Hosting & stringling of 11 KV XLPE Cable 3*185 sqmm loop & air on DP both side difference places near s/s to lehra chauraha, 2 Nos. 33 KV Line Crossing & NHAI Crossing. on each support in a manner taking sufficient care to ensure safety of XLPE Cable 3*185 sqmm against rubbing on ground precaution for safety of crops is also to be taken. All work to be carried out stricktly as per RESPO Norm. provided by contractor. |
| 50 | Road Restoration Charge | Road Restoration Charge |
| 51 | Laying & stringling of 11 KV XLPE Cable 3*185 sqmm loop & air on DP. on each support in a manner taking sufficient care to ensure safety of XLPE Cable 3*185 sqmm against rubbing on ground precaution for safety of crops is also to be taken. All work to be carried out stricktly as per RESPO Norm. on metering provided by contractor. | Laying & stringling of 11 KV XLPE Cable 3*185 sqmm loop & air on DP. on each support in a manner taking sufficient care to ensure safety of XLPE Cable 3*185 sqmm against rubbing on ground precaution for safety of crops is also to be taken. All work to be carried out stricktly as per RESPO Norm. on metering provided by contractor. |
| 52 | Jumpring of 11 KV line on D/P using alluminium Lug XLPE Cable to XLPE Cable & alluminium Lug, Rabbit To Rabbit Conductor & binding of jumpring on pin insulator alluminium lug & PG Clamp provided by the contractor. | Jumpring of 11 KV line on D/P using alluminium Lug XLPE Cable to XLPE Cable & alluminium Lug, Rabbit To Rabbit Conductor & binding of jumpring on pin insulator alluminium lug & PG Clamp provided by the contractor. |
| 53 | Termination of cable boxes of size 3*185 sqmm for XLPE Cable Boxes I/D & O/G will be of heat Shink indoor type and outdoor type cable boxes will be provided by contractor. | Termination of cable boxes of size 3*185 sqmm for XLPE Cable Boxes I/D & O/G will be of heat Shink indoor type and outdoor type cable boxes will be provided by contractor. |
| 54 | Loading carriage and unloading of following line materials from central store odhpura to dump site store. The materials will be provided as per availability and in piece meal. | Loading carriage and unloading of following line materials from central store odhpura to dump site store. The materials will be provided as per availability and in piece meal. |
| 55 | 3*185 Sqmm. AL XPLE Cable | 3*185 Sqmm. AL XPLE Cable |
| 56 | STP 11 mrt long | STP 11 mrt long |
| 57 | ACSR Rabit Conductor | ACSR Rabit Conductor |
| 58 | Dog Conductor | Dog Conductor |
| 59 | 11 kv CT/PT Pole Mounting Unit | 11 kv CT/PT Pole Mounting Unit |
| 60 | 11 kv TVM | 11 kv TVM |
| 61 | Incomming VCB 600/300/5A 350mva 1250A | Incomming VCB 600/300/5A 350mva 1250A |
| 62 | Outgoing VCB 200/100/5A 350mva 1250a | Outgoing VCB 200/100/5A 350mva 1250a |
| 63 | 3 Ph.-4 Wire Static TVM 11 KV | 3 Ph.-4 Wire Static TVM 11 KV |
| 64 | 11 KV Pilfer proff metering cubical | 11 KV Pilfer proff metering cubical |
| 65 | Installation of 3ph-4w static TVM 11 KV T&P and labour provided by contractor | Installation of 3ph-4w static TVM 11 KV T&P and labour provided by contractor |
| 66 | Installation & commisioning of 11 KV Pilfer proff metering cubical T&P and labour provided by contractor | Installation & commisioning of 11 KV Pilfer proff metering cubical T&P and labour provided by contractor |
| 67 | Other centrally procured items as per requirement for construction of line.(11 KV Disc with fitting, X-arm,11 KV Pin Insulator with pin ,stay rod,earth rod,M.S.rod,G.I.wire etc.) | Other centrally procured items as per requirement for construction of line.(11 KV Disc with fitting, X-arm,11 KV Pin Insulator with pin ,stay rod,earth rod,M.S.rod,G.I.wire etc.) |
| 68 | Trimming of tree branches Big/small tree branches which is lying on 11 KV feeder allignment of 11 KV Line | Trimming of tree branches Big/small tree branches which is lying on 11 KV feeder allignment of 11 KV Line |
| 69 | a) Small | a) Small |
| 70 | (b) Big | (b) Big |
| 71 | Received Back material from site to store hathras after completion according to executed estimate. | Received Back material from site to store hathras after completion according to executed estimate. |
| 72 | Supply of Materials Provided By Contractor | Supply of Materials Provided By Contractor |
| 73 | 11 kv Cable Jointing kit 3x185 mm.sq. | 11 kv Cable Jointing kit 3x185 mm.sq. |
| 74 | Pipe Earthing Upto Water Level for VCB And T/F | Pipe Earthing Upto Water Level for VCB And T/F |
| 75 | Repairing of Existing T/F plinth size 4.46 x 3.46 x 1.0 Mtr. | Repairing of Existing T/F plinth size 4.46 x 3.46 x 1.0 Mtr. |
| 76 | Dismantling of Switchyard fencing for safe shifting of old 5 MVA power T/Fs | Dismantling of Switchyard fencing for safe shifting of old 5 MVA power T/Fs |
| 77 | Safe Shifting & dragging of old 5 MVA T/F from inside to out side of Switch Yard after detaching its accessories i.e. Radiator, conservator etc and empting the T/F i.e taking out the T/F oil and disconnecting all 33 KV and 11 KV connections as well as dismantling of 11 KV cable stand and neutral stand. All tools & T&P shall be provided by the contractor. | Safe Shifting & dragging of old 5 MVA T/F from inside to out side of Switch Yard after detaching its accessories i.e. Radiator, conservator etc and empting the T/F i.e taking out the T/F oil and disconnecting all 33 KV and 11 KV connections as well as dismantling of 11 KV cable stand and neutral stand. All tools & T&P shall be provided by the contractor. |
| 78 | Special earthing of neutral and body of 10MVA T/F with the help of 3 Nos.G.I. pipe 2\\" dia. length 60 feet. G.I. pipe for making of delta, 1 no for body and 1 no for neutral earthing complete in all respect and connected with 50x6 m.m GI Strip. G.I. Pipe, G.I. Strip etc. required for completion of work in all respect shall be provided by the Contractor. | Special earthing of neutral and body of 10MVA T/F with the help of 3 Nos.G.I. pipe 2\\" dia. length 60 feet. G.I. pipe for making of delta, 1 no for body and 1 no for neutral earthing complete in all respect and connected with 50x6 m.m GI Strip. G.I. Pipe, G.I. Strip etc. required for completion of work in all respect shall be provided by the Contractor. |
| 79 | Earthing of 11 KV indoor equipments, with the help of 3 Nos.G.I. pipe 2\\" dia. length 60 feet. G.I. pipe for making of delta switch gears as per RESPO Drawing. with G.I. Strip of Size 50x6 mm, aall respect shall be provided by the Contractor. | Earthing of 11 KV indoor equipments, with the help of 3 Nos.G.I. pipe 2\\" dia. length 60 feet. G.I. pipe for making of delta switch gears as per RESPO Drawing. with G.I. Strip of Size 50x6 mm, aall respect shall be provided by the Contractor. |
| 80 | Installation of 11 KV VCB in the switch gear room, by grouting base channel 100 x 50 x 6 x 1000mm. Fixing of 11 KV switchgears rag bolt, mounting of P.T. on incoming & 11 KV TVM, 11 KV CT/PT Pole Mounted Unit. | Installation of 11 KV VCB in the switch gear room, by grouting base channel 100 x 50 x 6 x 1000mm. Fixing of 11 KV switchgears rag bolt, mounting of P.T. on incoming & 11 KV TVM, 11 KV CT/PT Pole Mounted Unit. |
| 81 | (a) 11 KV Incomming | (a) 11 KV Incomming |
| 82 | (b) 11 KV O/G VCB | (b) 11 KV O/G VCB |
| 83 | (c) 11 KV TVM | (c) 11 KV TVM |
| 84 | (d) 11 KV CT/PT Pole Mounted Unit | (d) 11 KV CT/PT Pole Mounted Unit |
| 85 | Laying of 11 KV 3 x 185 Sqmm. XLPE power cable by digging 0.75 Mtr. deep trench, putting layer of sand in the bottom, ramming it, laying of cable over it RMT and covering the cable from sides and top by laying bricks, finally covering the same by earth and levelling of the same, all the materials, except cable, will be provided by the contractor. Rates may be quoted per RMT | Laying of 11 KV 3 x 185 Sqmm. XLPE power cable by digging 0.75 Mtr. deep trench, putting layer of sand in the bottom, ramming it, laying of cable over it RMT and covering the cable from sides and top by laying bricks, finally covering the same by earth and levelling of the same, all the materials, except cable, will be provided by the contractor. Rates may be quoted per RMT |
| 86 | Termination of cable boxes of size 3*185 sqmm for XLPE Cable Boxes I/D & O/G will be of heat Shink indoor type and outdoor type cable boxes will be provided by contractor. | Termination of cable boxes of size 3*185 sqmm for XLPE Cable Boxes I/D & O/G will be of heat Shink indoor type and outdoor type cable boxes will be provided by contractor. |
| 87 | Following items shall also be provided by the contractor at the Sub-station. | Following items shall also be provided by the contractor at the Sub-station. |
| 88 | (a) Hand Gloves | (a) Hand Gloves |
| 89 | (b) Rubber Matting | (b) Rubber Matting |
| 90 | (c) Fire bucket with stand | (c) Fire bucket with stand |
AI Tender Summary
Tender Timeline
Tender Published
Tender notice published.
CompletedBid Submission Deadline
Online submission via eProcurement portal.
Upcoming · 13 daysBid Opening Date
Technical bids will be opened and evaluated.
Upcoming · 14 daysTender Documents
Download All (ZIP) ↓We takes all possible care for accurate & authentic tender information. However users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender