Tender For Special Repair Works Comprising White Washing, Colour Washing, Cement Painting Of The Integrated Office Building, Special Repair Works To The Superintending Engineers Room, Conversion Of The Meeting Room Into A Video Conference Hall Including F
Tender Overview
Project Description
Tender For Special Repair Works Comprising White Washing, Colour Washing, Cement Painting Of The Integrated Office Building, Special Repair Works To The Superintending Engineers Room, Conversion Of The Meeting Room Into A Video Conference Hall Including False Ceiling Works And Wall Paneling, And Providing Paver Block Pavement For The Eb Control Room At Twad Board Integrated Office Complex, Tiruchirapalli District (Completion Period : 4 Months And Free Maintenance Period : 6 Months)
BOQ
| Sl. No. | Item Description |
| 1 | TAMIL NADU WATER SUPPLY AND DRAINAGE BOARD EXECUTIVE ENGINEER, URBAN DIVISION, TRICHY Name of work:- Special repair works comprising White Washing, Colour Washing, Cement Painting of the Integrated Office Building, Special repair works to the Superintending Engineer's room, Conversion of the Meeting room into a Video Conference hall including False Ceiling Works and Wall Paneling, and Providing Paver Block pavement for the EB Control Room at TWAD Board Integrated Office Complex, Tiruchirapalli District (Completion period : 4 Months and Free Maintenance period : 6 Months) SCHEDULE - A (E – Tendering System) BILL OF QUANTITY |
| 2 | White Washing, Colour Washing and Cement Painting of Integrated building complex at Training Centre |
| 3 | White washing two coats using fine screened shell lime for the plastered surface for Roof ceiling including the cost of material labour charges etc., complete and as directed by TWAD Board Officers. |
| 4 | Colour washing two coats with approved colour and quality, Inside of the room including the cost of materials, labour charges, cleaning and preparation of the surface and curing etc., complete and as directed by TWAD Board Officers. |
| 5 | Colour washing with Cement paint in the Outer surface of the MTL building including all materials and labour cost etc as directed by TWAD Officers. |
| 6 | Painting the doors, windows & Ventilators on both sides with readymixed enamed paint two coats over priming coat of approved quality and colour including thorought scrapping clean removal of dirt etc., complete complying with standard specification including cost of paint and brushes, labour charges etc., and as directed by TWAD Board Officers. The colour and quality has to be approved by TWAD Board Officers. |
| 7 | Providing Pavor Block for accesing the EB Control Room at Integrated Building Complex, TWAD Board, Trichy |
| 8 | Earth work excavation for foundation in Hard stiff clay, stiff black cotton, hard red earth, shales murram, gravel, stoney earth and earth mixed with small size boulders SS.20B and Sand, silt or other loose soil, wet sand or silt not under water, light black cotton soil, sandy loam ordinary soil and to full depth as may be directed except in hardrock requiring blasting inclusive of shoring shuttering and baling out water and cleaning and levelling the site etc., complete - Open Earth Work Excavation |
| 9 | Supplying and filling in foundation and basement with Crushed Stone Sand (M- Sand) in layers of not more than 15cm thick well rammed watered and compacted etc., complete complying with standard specification. |
| 10 | Plain Cement concrete 1:4:8 (one cement, four sand, eight aggregate) using 40mm gauge hand broken granite stone jelly for foundation including dewatering if found necessary and laid in layers of not more than 15 cm thick and compacted,etc., complete complying with standard specfication. |
| 11 | Supplying and erecting steel centering including necessary supports for plane surfaces for Reinforced Cement Concrete works such as column footings, column pedestals, plinth beams, grade beams, staircase steps, etc. which require only nominal strutting using mild steel sheets of size 90cm x 60cm and 10 BG stiffened with welded mild steel angles of size 25mm x 25mm x 3 mm for boarding, laid over silver oak joists of size 10cm x 6.5cm spaced at about 75cm centre to centre or at suitable intervals etc. complete in all floors complying with standard specifcation - Plinth Beam |
| 12 | Plain Cement Concrete 1:2:4 (one cement, two fine aggregates and four coarse aggregates) using 20mm size ISS HBG metal including cost and conveyance of all materials to site and labour charges and all incidential charges such as water providing etc., complete as per standard specification |
| 13 | Supplying and laying Rubberised interlocking Paver block M40 grade Providing and laying of 63mm thick high strength type conforming IS 15658-2006 of rubberized interlocking paver lock in size of minimum compressive strength of 40N/mm2 in uniform shape of approved make to be laid in flurring bone pattern with Stone Dust cushion below the uniform shap of approved non skitting surface in the top and the rate including levelling the base preparation of pavers as sub base, Stone Dust cushion 150mm thick laying out of pavement cut the pieces to fix the edge vibring the pavers,sweeping tranporting loading unloading of laying paver block as per standard specification,. |
| 14 | Conversion of Meeting Room into Video Conferencing Room |
| 15 | CRACK WORK |
| 16 | The scope includes idenification of cracks on wall surfaces, widening the cracks in \\"V\\" shape, cleaning and removing all loose particles, applying crack filler/putty leveling the surface, |
| 17 | PEST CONTROL |
| 18 | The work includes thorugh treatment of the premises for control of cockroaches, ants, termites, rodents, mosquitoes, and other common pest using approved eco-friendly chemicals/insecticieds. The process involves spraying, gel application, baiting , and other suitable methods as per site requiremetns to ensure a hygienic and pest-free environment. |
| 19 | WINDOWS PACKING |
| 20 | The scope includes sealing the gap around window frames using high-quality, weatherproof silicone sealant. The work involves cleaning the surfaces, applying masking tape, filling joints/ gapls uniformly with silicone, and finishing smoothly to ensure air, dust, and water |
| 21 | WALL PANELLING FOR WINDOW |
| 22 | Providing and fixing panelling made of 19mm BWP plywood finished with 1mm laminate on visible side |
| 23 | FALSE CEIIING |
| 24 | Supply and installation of Perforated Glass Fiber Reinforced (GFR) Gypsum Concealed Acoustics false Ceilings, GFR gypsum panel, backlined with acoustical fleece, having random circular perforations of 8mm dia, 15mm dia and 20mm dia 5% open area having 4x14mm slotted perforations @ 10x20mm pitch, in H8 Pattern 15% open area size 1200x2400x12.5mm,square edge, volume density of base board 650 Kgs/m3, weight 8Kgs/m2 installed by uing Strut ceiling framework. The Strut ceiling framework system shall include Strut WC25, fully knurled, sectional thickness0.5mm, length 3600mm, unequal flanges of 20 &30mm and web of 25mm, fixed along the perimetersof the wall with nylon sleeves and suitable fasteners at every 300mm centers. Then suspend Strut MC45, fully knurled, sectional thickness 0.8mm, length 3600mm, equal flanges of 15mm and web 45mm from the soffit at 1200mm centers with Strut SA25, fully knurled, Suspender angle with sectional thickness 0.45mm, unequal flanges of 25 & 10mm such that free end of Strut MC45 rests on Strut WC25 along perimeter of wall. Extra support to be added near jointing of two MC45 so that end cantilever should not be more than 150mm. Strut CC25, fully knurled, sectional thickness 0.55mm, length 3600mm, web 50mm, depth of 25mm and equal flanges 15mm is fastened to the Strut MC45 perpendicularly at 600mm centers for upto RH70, at 400mm centers for RH70-RH90 and at 300mm centers for >RH90 and inserted inside the Strut WC25 at the perimeter Snazz Cosmos panel is installed on the Strut CC25 with suitable fasteners at 600/400/300mm centres. The longer edges of panels should be perpendicular to length of Strut CC25. All edges should be chamfered for V-Groove 4mm gap should be maintained between adjacent boards on all sides and should be filled and finished with Seam AJC and tape Apply one coat of white primer with roller brush venly across the board surface to achieve uniform colour. The system is backlined with the acoustical infill Synthetic polyfiber 5x50. TechParameters Fire (Class) -1 & P Acoustics - NRC upto 0.75 (For E600” Mounting) Climate (“C, RH)-50, 70 Light reflectance (%) - Paint dependent Green (VOC, RC %) -Low, 25 as directed by the department officers. (PWD SOR: M-2970) |
| 25 | FLUTED WALL PANELLING |
| 26 | Supply, installation, of decorative fluted wall panelling using high-quality MDF/ply/WPC/PU-Coated panels (as specified), fixed over suitable frame work/adhesive with proper alignment. The panels shall be cut, jointed and finished neatly to achieve a seamless fluted appearence. All Joints and edges to be finished smooth and even, ensuring durability and an elegant aesthetic finish as per approved design. |
| 27 | LIGHTS |
| 28 | PROFILE LIGHT Supply, installation, testing and commissioning of false ceiling LED Profile lighting system including alumininum profiles, LED strips, diffusers, drivers, conduits, and wiring as per approved drawings and IS Standards. The work includes cutting and fixing of alumininum channels in false ceiling, mounting of LED strips with proper heat dissipation, connection to power supply through drivers, testing for uniform illumination, and ensuring neat finish and reliable operation of the lighting system |
| 29 | 18 W LED 300K Round type recessed fitting with LED Surface Light |
| 30 | BLDC Ceiling Fan 1200mm(48”) Sweep 300mm Down Rod |
| 31 | Fan step regulater 100 W- 1 Module - Higher end |
| 32 | ELECTRICAL ITEMS |
| 33 | Supply and delivery of 4 sq.mm PVC insulated copper cable |
| 34 | 20A Single pole- Plug and socket in sheet steel enclosure, without MCB |
| 35 | Supply and delivery of flush type 5A socket |
| 36 | 16 A 3 pin Switch socket- 3 Module |
| 37 | AIR CONDITIONER |
| 38 | Supply and Installation of air conditioner-1.5 T R split type AC unit 5 star rated |
| 39 | CURTAINS |
| 40 | Supply and delivery of vertical blinds premium |
| 41 | Special Repair works to the Superintending Engineer's Room |
| 42 | FALSE CEILNG |
| 43 | Supply and installation of Perforated Glass Fiber Reinforced (GFR) Gypsum Concealed Acoustics false Ceilings, GFR gypsum panel, backlined with acoustical fleece, having random circular perforations of 8mm dia, 15mm dia and 20mm dia 5% open area having 4x14mm slotted perforations @ 10x20mm pitch, in H8 Pattern 15% open area size 1200x2400x12.5mm,square edge, volume density of base board 650 Kgs/m3, weight 8Kgs/m2 installed by uing Strut ceiling framework. The Strut ceiling framework system shall include Strut WC25, fully knurled, sectional thickness0.5mm, length 3600mm, unequal flanges of 20 &30mm and web of 25mm, fixed along the perimetersof the wall with nylon sleeves and suitable fasteners at every 300mm centers. Then suspend Strut MC45, fully knurled, sectional thickness 0.8mm, length 3600mm, equal flanges of 15mm and web 45mm from the soffit at 1200mm centers with Strut SA25, fully knurled, Suspender angle with sectional thickness 0.45mm, unequal flanges of 25 & 10mm such that free end of Strut MC45 rests on Strut WC25 along perimeter of wall. Extra support to be added near jointing of two MC45 so that end cantilever should not be more than 150mm. Strut CC25, fully knurled, sectional thickness 0.55mm, length 3600mm, web 50mm, depth of 25mm and equal flanges 15mm is fastened to the Strut MC45 perpendicularly at 600mm centers for upto RH70, at 400mm centers for RH70-RH90 and at 300mm centers for >RH90 and inserted inside the Strut WC25 at the perimeter Snazz Cosmos panel is installed on the Strut CC25 with suitable fasteners at 600/400/300mm centres. The longer edges of panels should be perpendicular to length of Strut CC25. All edges should be chamfered for V-Groove 4mm gap should be maintained between adjacent boards on all sides and should be filled and finished with Seam AJC and tape Apply one coat of white primer with roller brush venly across the board surface to achieve uniform colour. The system is backlined with the acoustical infill Synthetic polyfiber 5x50. TechParameters Fire (Class) -1 & P Acoustics - NRC upto 0.75 (For E600” Mounting) Climate (“C, RH)-50, 70 Light reflectance (%) - Paint dependent Green (VOC, RC %) -Low, 25 as directed by the department officers. (PWD SOR: M-2970) |
| 44 | LIGHTS |
| 45 | PROFILE LIGHT Supply, installation, testing and commissioning of false ceiling LED Profile lighting system including alumininum profiles, LED strips, diffusers, drivers, conduits, and wiring as per approved drawings and IS Standards. The work includes cutting and fixing of alumininum channels in false ceiling, mounting of LED strips with proper heat dissipation, connection to power supply through drivers, testing for uniform illumination, and ensuring neat finish and reliable operation of the lighting system |
| 46 | 18 W LED 300K Round type recessed fitting with LED Surface Light |
| 47 | BLDC Ceiling Fan 1200mm(48”) Sweep 300mm Down Rod |
| 48 | Fan step regulater 100 W- 1 Module - Higher end |
| 49 | ELECTRICAL ITEMS |
| 50 | Supply and delivery of 4 sq.mm PVC insulated copper cable |
| 51 | 20A Single pole- Plug and socket in sheet steel enclosure, without MCB |
| 52 | Supply and delivery of flush type 5A socket |
| 53 | 16 A 3 pin Switch socket- 3 Module |
| 54 | CURTAINS |
| 55 | Supply and delivery of vertical blinds premium |
| 56 | Sub Total |
| 57 | GST @ 18% Please Enable Macros to View BoQ information |
AI Tender Summary
Tender Timeline
Tender Published
Tender notice published.
CompletedBid Submission Deadline
Online submission via eProcurement portal.
Upcoming · 12 daysBid Opening Date
Technical bids will be opened and evaluated.
Upcoming · 13 daysTender Documents
Download All (ZIP) ↓We takes all possible care for accurate & authentic tender information. However users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender