Tender For Errection, Maintenance And Dismantling Of Pantoon Bridge On The Yamuna Rever Between Muhammadabad (Kevat Ka Purwa), Kaushambi District, And Paduwa (Pratappur) Ghat, Prayagraj District (Fy 2026-27)
Tender Value
33 Lakhs
Estimated cost
Bid Submission
21 Sep 2026
8 days left
EMD
3.30 Lakhs
Bank guarantee accepted
Document Fee
944
Non-refundable
Tender Type
Online
Tender Overview
Organization
Tender ID
Competition Type
NCB
Bidding Type
Tender
Location / State
Kaushambi → Uttar Pradesh
EMD Exemption
Not Available
Quantity
Not Available
Website
Contact Person
Address
Project Description
Tender for Errection, Maintenance And Dismantling Of Pantoon Bridge On The Yamuna Rever Between Muhammadabad (Kevat Ka Purwa), Kaushambi District, And Paduwa (Pratappur) Ghat, Prayagraj District (Fy 2026-27)
BOQ
| Sl. No. | Item Description |
| 1 | Supply of wooden Anchor of size 2.4X1.8X3.1 m with 10 & 15 cm eucalyptus balli including cost of ballies, nails, all labour and T&P etc, required for proper completion of work as per direction or E/I. (MR) |
| 2 | Supply of nails of approved quality 15-30 cm long including its cost, carriage, loading, unloading, and stacking at site etc. complete as per direction of E/I. |
| 3 | Supply of Bagai Badh good quality and good condition including cost of material, taxes, carriage etc. for proper completion of work as per direction of E/I. |
| 4 | Supply of PP Rope good quality and good condition including cost of material, taxes, carriage etc. for proper completion of work as per direction of E/I. |
| 5 | Supply of eucoliptus ballies 10 cm dia. |
| 6 | Supply of Nut Bolts including cost of material loading unloading cartage stacking and all taxes at store. 300x30 |
| 7 | Supply of Nut Bolts including cost of material loading unloading cartage stacking and all taxes at store. 150x30 |
| 8 | Supply of Nut Bolts including cost of material loading unloading cartage stacking and all taxes at store. 300x16 |
| 9 | Supply of Nut Bolts including cost of material loading unloading cartage stacking and all taxes at store. MS Washer |
| 10 | Earth work in cutting or in embankment for cambering of approach link road including filling pits and kagar cutting due to erosions of Yamuna river in proper longitudinal and side grade and slope as per level given at site including cost of all labour and T&P. Dressing and disposal of earth by head load on spoil bank & River on shore as directed by the E/i etc. required for proper completion of work. |
| 11 | Cartage and Laying of R.S. Joist (5.20 Rm) from store to pontoon bridge site including loading unloading labour T&P etc. and placing as per direction of E/I required for proper completion of work |
| 12 | Cartage and Laying of Railing Posts from store to pontoon bridge site including loading unloading labour T&P etc. and placing as per direction of E/I required for proper completion of work |
| 13 | Cartage and Laying of Sal Sleeper from store to pontoon bridge site including loading unloading labour T&P etc. and placing as per direction of E/I required for proper completion of work |
| 14 | Cartage and Laying of Sal Edging from store to pontoon bridge site including loading unloading labour T&P etc. and placing as per direction of E/I required for proper completion of work |
| 15 | Cartage and Laying of Chequered Plates from store to pontoon bridge site including loading unloading labour T&P etc. and placing as per direction of E/I required for proper completion of work |
| 16 | Cartage and Laying of following materials from store to pontoon bridge site including loading unloading labour T&P etc. and placing as per direction of E/I required for proper completion of work Other Material such as PP Rope, Coir Rope Washer M.Z. Plate wire rope and Nut Bolts etc. |
| 17 | Errection / Construction of Pile Culvert including carriage of decking material & ballies including piling after making shoes complete (labour only) |
| 18 | Dragging the pontoon from dry bed to the river Bank to River Water pulling and rolling them in the water to bringh in the proper position and making pairs of two pontoons with girder and anchoring them in D/s of mantoons bridge including all labour T&P etc required for proper completion of the work as per direction of E/I |
| 19 | Carriage of pontoon pair from the place of anchoring down streem side of bridge to the bridge alignment in water and fixing the same with other pontoon pair of bridge including all labour T&P etc required for proper completion of the work as per direction of E/I |
| 20 | Laying of wooden anchors in the river on the up stream/ Down stream side of the pontoon bridge site including their weaving by bagai badh and packing with sand filled bags (average 60 bags) before laying and fixing to pontoon with rope ad per direction of Engineer Incharege including all labour T&P etc required for proper completion of the work as per direction of E/I |
| 21 | Two coat painting of railing post including paint and labour etc. |
| 22 | Fixing of 10mm railing wire in three row through hole of railing post and holes of verticals ballies post and making wire stay of each row and tighting with the help of railing wire clamp as direction of E/I |
| 23 | Supply and spreading of Kansa poola 5 cm thick over bridge/ pile road way before filling of 7.5 cm thick Kapsa soil including cartage of Kapsa soil from a distance of 1.00 Km. either side of bridge/pile & spreading ramming and dressing the surface as per direction of Engineer Incharge for proper completion of work. |
| 24 | Supply of local sand including digging, cartage (2.00 km) loading unloading stacking etc complete in non sandy area as per direction of E/I |
| 25 | Laying and spreading of local sand on bridge and approach road below chequred plate on non sandy area only labour rate (Not more than 10 cm thick) |
| 26 | Making stay on both side of pontoon bridge with the help of 20 mm Wire rope (labour rate only) |
| 27 | Making barrier on both sides of bridge head as per direction of E/I |
| 28 | Bundaling with the help of 10 cm horizontal ballies and 15 cm vertical ballies@ 50 cm c/c etc complete |
| 29 | Supply of sand filled cement bags of good quality and good condition duly filled with local sand and property stiching with Calcutta sutli for filling anchor, bandling etc, work including cost of all material labour carriage T&P etc and placing as per direction of E/I. |
| 30 | Leveling and dressing of road surface including cutting / filling including labour, T&P completion of work as per direction of E/I |
| 31 | Dismantling of R.S. Joist (5.20 Rm) of pontoon bridge, pile and approach link road including cartage of these material from site of work to central store and also including loading unloading stacking properly and also including ass taxes all labour and work T&P required for proper completion of work as per direction of E/I. |
| 32 | Dismantling of Railing Posts of pontoon bridge, pile and approach link road including cartage of these material from site of work to central store and also including loading unloading stacking properly and also including ass taxes all labour and work T&P required for proper completion of work as per direction of E/I. |
| 33 | Dismantling of Sal Sleeper of pontoon bridge, pile and approach link road including cartage of these material from site of work to central store and also including loading unloading stacking properly and also including ass taxes all labour and work T&P required for proper completion of work as per direction of E/I. |
| 34 | Dismantling of Sal Edging of pontoon bridge, pile and approach link road including cartage of these material from site of work to central store and also including loading unloading stacking properly and also including ass taxes all labour and work T&P required for proper completion of work as per direction of E/I. |
| 35 | Dismantling of Chequered Plates of pontoon bridge, pile and approach link road including cartage of these material from site of work to central store and also including loading unloading stacking properly and also including ass taxes all labour and work T&P required for proper completion of work as per direction of E/I. |
| 36 | Dismantling of Other Material such as PP Rope, Coir Rope Washer M.Z. Plate wire rope and Nut Bolts etc. of pontoon bridge, pile and approach link road including cartage of these material from site of work to central store and also including loading unloading stacking properly and also including ass taxes all labour and work T&P required for proper completion of work as per direction of E/I. |
| 37 | cartage of pantoons by Truck/Trailor temp. Store to site of work including loading, unloading with the help of crane, labour, T&P etc as per direction of E/I. |
| 38 | Maintenance of chaqured plate and road of 3 row for 6 Month (6 Months xRs 32500) |
| 39 | Maintenance of pantoon bridge length of bridge including pile on either side period: Start to end (6 Months x 260) Please Enable Macros to View BoQ information |
AI Tender Summary
Tender Timeline
Sep 08, 2026
11:30 IST
Tender Published
Tender notice published.
CompletedSep 21, 2026
17:00 IST
Bid Submission Deadline
Online submission via eProcurement portal.
Upcoming · 8 daysSep 21, 2026
Bid Opening Date
Technical bids will be opened and evaluated.