Tender For Short Term Maintenance Contract (Stmc) Estimate For Kundheigola To Baghbar Road Via Koradaposi,Jharaberani,Tungamal From Ch 0/000Km To Ch4/500 Km,Kundheigola To Utunia Via Khandadhuan From Ch0/000Km To Ch12/183 Km & Aunli To Tutabari Road
Tender Overview
Project Description
Tender for Short Term Maintenance Contract (Stmc) Estimate For Kundheigola To Baghbar Road Via Koradaposi,Jharaberani,Tungamal From Ch 0/000Km To Ch4/500 Km,Kundheigola To Utunia Via Khandadhuan From Ch0/000Km To Ch12/183 Km & Aunli To Tutabari Road From 0/000 Km To 8/183 Km In The District Of Debagarh, Odisha For The Financial Year 2026-27 ( Package-1)
BOQ
| Sl. No. | Item Description |
| 1 | Road MaintenanceRestoration of rain cuts with soil, moorum, gravel or a mixture of these, clearing the loose soil, benching for 300 mm width, laying fresh material in layers not exceeding 250 mm and compacting with plate compactor or power rammers to restore the original alignment, levels and slopes as per MORT&H specification cluse no 3002 and as per direction of the Engineer-in-chargeKundheigola to Baghbar road from ch 0/000KM to ch4/500KM |
| 2 | Kundheigola to Utunia road from ch 0/000km to ch 12/183 km. |
| 3 | Aunli to Tutabari road from ch 0/000KM to ch 8/183KM |
| 4 | Removal of rank vegetation/weeds and undesirable vegetation from shoulders,embankment slopes up to ROW(bothsides) complete in all respects including breaking of clods,rough dressing and disposal of waste material and vegetation at a place outside ROW as per direction of Engineer-In-Charge and as per maintenance standards Clause no 3.1.(Frequency of cleaning will be one time in a quarter)a) Shoulders including side slopes of embankment upto toe line both sides of the carriageway.(Frequency of cleaning will be four times in a year, however limited to only areas prone to growth of rank/undesirable vegetation and weeds)Kundheigola to Baghbar road from ch 0/000KM to ch4/500KM |
| 5 | Kundheigola to Utunia road from ch 0/000km to ch 12/183 km. |
| 6 | Aunli to Tutabari road from ch 0/000KM to ch 8/183KM |
| 7 | Providing compacted granular materials in shoulder / diversion road by using moorum having required P.I. value with sand admixture if required, spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with rotavator at OMC and compacting with vibratory roller to achieve the desired density, as per approved Drawing & Technical Specifications and as per Clause - 407 of MoRT&H Specifications for Road & Bridge works (5th Revision) including cost, conveyance, royality & other taxes of materials, cost of labour, machinery, T&P etc complete..Kundheigola to Baghbar road from ch 0/000KM to ch4/500KM |
| 8 | Kundheigola to Utunia road from ch 0/000km to ch 12/183 km. |
| 9 | Aunli to Tutabari road from ch 0/000KM to ch 8/183KM |
| 10 | Road SafetyProviding and laying of hot applied thermoplastic compound 2.5 mm thick including reflectorising glass beads @ 250 gms per sqm area, thickness of 2.5 mm is exclusive of surface applied glass beads as per IRC:35 .The finished surface to be level, uniform and free from streaks and holes.Kundheigola to Baghbar road from ch 0/000KM to ch4/500KM |
| 11 | Kundheigola to Utunia road from ch 0/000km to ch 12/183 km. |
| 12 | Aunli to Tutabari road from ch 0/000KM to ch 8/183KM |
| 13 | Pavement RepairsProviding and Applying Primer Coat with bitumen emulsion (SS) on prepared surface of granular base including cleaning the road surface and spreading primer @ 0.60kg per sqm using mechanical means as per Technical Specifications and as per Clause -501 & 502 of MoRT&H Specifications for Road & Bridge works (5th Revision) including cost, conveyance & other taxes of materials, cost of labour, machinery, T&P etc complete.Kundheigola to Baghbar road from ch 0/000KM to ch4/500KM |
| 14 | Kundheigola to Utunia road from ch 0/000km to ch 12/183 km. |
| 15 | Aunli to Tutabari road from ch 0/000KM to ch 8/183KM |
| 16 | Labour for scraping cleaning the road surface applyling tack coat using 3 Kg of bitumen for 10 Sqm and laying 37.5mm thick built up spray grouting in one layer using 0.45 Cum of 25mm to 40mm size hard granite metal and 12 Kg penetration grade of bitumen for 10 Sqm with 0.12 Cum of 12mm size hard granite chips as key stone for 10 Sqm spreading over and laying including heating pouring and spreading over and spreading bitumen metal and chips and rolling with PRR including hire and running charges of PRR and all other machinereis but excluding cost and conveyance of bitumen, metal and chips complete as per specification and direction of Engineer-in-charge.Kundheigola to Baghbar road from ch 0/000KM to ch4/500KM |
| 17 | Kundheigola to Utunia road from ch 0/000km to ch 12/183 km. |
| 18 | Aunli to Tutabari road from ch 0/000KM to ch 8/183KM |
| 19 | Filling Pot-holes and Patch Repairs with Providing & applying tack coat with rapid setting (RS-1) Bitumen Emulsion on prepared surface including cleaning of road surface and spraying tack coat @ 0.20 K.g / Sqm using mechanical means as per Cluse No. 501, 503 and Section 900 and all relevant sections/ clauses of the Mort&h specification for road and bridgeworks of Ministry of Road Transfport& Highway (5th Revision) & Including all cost i.e cost of all materials, all labour, all T&P, royalty etc complete in all respect and as per direction of the Engineer- in- charge.Kundheigola to Baghbar road from ch 0/000KM to ch4/500KM |
| 20 | Kundheigola to Utunia road from ch 0/000km to ch 12/183 km. |
| 21 | Aunli to Tutabari road from ch 0/000KM to ch 8/183KM |
| 22 | Filling Pot-holes and Patch Repairs with SDBC .Providing 25mm compacted thick S.D.B.C. of grading -2 using crushed stone Gr.-2 materials & 60/70 penetration grade of bitumen preparing preemixed materials with bituminous binder with hot mix plant, transported to site, laid over a previously prepared surface with paver finisher to the required grade, level and alignment and rolled to achieve the desired compaction as per clauses 501 and 508 of MoRT&H Specifications for Road & Bridge works (5th Revision) including cost, conveyance, royality & other taxes of materials, cost of labour, machinery, T&P etc completKundheigola to Baghbar road from ch 0/000KM to ch4/500KM |
| 23 | Kundheigola to Utunia road from ch 0/000km to ch 12/183 km. |
| 24 | Aunli to Tutabari road from ch 0/000KM to ch 8/183KM Please Enable Macros to View BoQ information |
AI Tender Summary
Tender Timeline
Tender Published
Tender notice published.
CompletedBid Submission Deadline
Online submission via eProcurement portal.
Upcoming · 10 daysBid Opening Date
Technical bids will be opened and evaluated.
Upcoming · 11 daysTender Documents