Tender For Special Repair To Lifts At 3 Wing C Area Under Ge (Af) Palam, Delhi Cantt-10
Tender Overview
Project Description
Tender For Special Repair To Lifts At 3 Wing C Area Under Ge (Af) Palam, Delhi Cantt-10
Corrigendum
| Sr No | Corrigendum Date | Corrigendum | Type | New Submission Date |
|---|---|---|---|---|
| 1 | 14-Sep-2026 | Corrigendum No 1 | Date | 30-Sep-2026 |
| 2 | 14-Sep-2026 | Corrigendum No 1 | Date | 30-Sep-2026 |
BOQ
| Sl. No. | Item Description |
| 1 | Phase-ITaking down/out unserviceable controller panel & Supply, installation, testing and commissioning of Micro Processor and latest technology based controller along with travelling cable and complete shaft harness, all necessary accessories wiring and all connected accessories for VVVF drive of 7.5KW, 380/480 volts, 50HZ as per sample suitable for 8 passengers Lift in replacement of controller, wiring fixture along with accessories, new ARD along with accessories for 08 passengers lift 544 kg of serving Ground plus Eight floors ( total nine landing) with electric power operated door and comprising with the following complete all as specified and as directed. Make:- OTIS, Kone, ECE, Evaan(i) Automatic call register & execution system.(ii) Automatic attendant system.(iii) Automatic closure of fan if the lift is not in operation for more than 45 seconds.(iv) Overload/low voltage /single phase rotations.(v) Automatic phase reversal system.(vi) Cooling fan for air circulation in controller.(vii) Read switch, limit switch & decoder etc with wiring.(viii) Hooter with battery fixed at ground floor with proper wiring with control panel.(ix) Arrangement of fireman switch at ground floor with wiring complete. |
| 2 | Note for Item No 1:- (a) The controller should be compatible to run the lift G+8 floors (Total nine landing) having fan and sufficient space for VVVF drive. (b) Main VVVF drive should be provided with calibration pad & proper mounting in controller along with any other connections as required. (c) Any other arrangement/alteration for smooth functioning of lift should be done by contractor without any extra cost. (d) The control wiring shall be secured confirmed to standard wiring practice & it should be proper fixing on wall/in duct cover with clamping, saddling etc complete. (e) Contractor shall be required to connect; transfer & interrupt power supply & protect the motor against over load. (f) During the execution of work any civil/cement work done by contractor with own arrangement and no extra cost. (g) Rate quoted by the contractor are deemed to be inclusive of minor spares. |
| 3 | Supply, fixing, testing and commissioning of ARD 1.5 KW (Automatic rescue device) with panel and including necessary internal wiring suitable for 8 passenger lifts 544kg (G+8) including ARD batteries of suitable capacities complete all as specified and as directed.Make: - OTIS, Kone, ECE, Evaan |
| 4 | Supply, fixing, testing and commissioning of full landing operating panel (LOP) after taking out old unserviceable one complete with latest Brail push button along with all connected accessories completely suitable for 8 passenger lifts 544kg (G+8) complete all as specified and as directed.Make: - OTIS, Kone, ECE or Evaan |
| 5 | Supply, fixing, testing and commissioning of full SS Cabin operating panel (COP) after taking out old unserviceable one complete with luminous braill buttons with coloured LCD display push box along with all connected accessories suitable for 8 passenger lifts 544kg (G+8) complete all as specified and as directed. Make: - OTIS, Kone, ECE or Evaan |
| 6 | Supply, fixing, testing and commissioning of Car cabin of size WxDxH (1100mmX1300mmX2200mm) and automatic centre opening door in SS honey comb finish after taking out old unserviceable one complete with car door header, Car seal, door operator V3F with complete accessories including hand rail on one side of car cabin, floor annunciator with music/arrival chime. Car cabin made out of minimum 16 SWG (1.5mm thickness) stainless steel (Vandal finish) as well as car cabin roof covered with 18 SWG SS (hair line finish), cabin flooring made of chequered plate 5 mm thickness complete and Car cabin having a minimum fire resistance of 1 hr suitable for 8 passenger lifts 544kg (G+8) complete all as specified and as directed.Make:- OTIS, Kone, ECE or Evaan |
| 7 | Supply, fixing, testing and commissioning of Landing door standard steel finish 1.2mm thickness after taking out old unserviceable one complete with necessary fittings and landing door header, landing door seal a minimum fire resistance of 1 hr suitable for 8 passenger lifts 544kg (G+8) complete all as specified and as directed.Make:- OTIS, Kone, ECE or Evaan |
| 8 | Supply, fixing, testing and commissioning of OSG unit including pit pully and OSG rope of suitable size along with all connected accessories serving G+8 after taking out old unserviceable one suitable for 8 passenger lifts 544kg (G+8) complete all as specified and as directed.Make:- OTIS, Kone, ECE or Evaan |
| 9 | Taking down and supply and fixing full length IR door sensor 12V/.2A with 20 Nos diodes, pattern of 96 cris-cross beams meeting the requirements of EN 811-20 with IP -65 rating and housed in slim aluminium profile suitable for 8 passenger lifts 544kg (G+8) complete all as specified and as directed.Make:- OTIS, Kone, ECE or Evaan |
| 10 | Taking down and supply and fixing main steel rope 10 mm dia for four groove sheave serving G+8 floor with nuts bolts, clamps/thimbles suitable for 8 passenger lifts 544kg (G+8) complete all as specified and as directed.Make: Usha Martin or equivalent |
| 11 | Taking down old worn Main sheave and supply and fixing new lift Main sheave four groove as per existing (grooved pully) made of cast iron for smooth and balance vertical movement serving G+8 floor suitable for 8 passenger with nuts bolts, clamps/thimbles suitable for 8 passenger lifts 544kg (G+8) complete all as specified and as directed |
| 12 | Opening of gear box of 8 passenger Lift serving G+8 floor for overhauling/servicing by removing the same from machine/housing cleaning the same including pinion, shafts, bearing and all other ancillary components by suitable means to remove old gear oil/grease rust and foreign/external contaminants and then greasing lubricating all the bearings with suitable volume pump with adequate quantity of gear oil and grease and refitting the same with proper alignment including replacement of damaged nuts, bolts & washers by new one as per BIS specifications, replacement of gaskets/oil seal for making the gear box leakproof complete all as specified and as directed. Note for Item Nos 1 to 11:- Lift shall comrise all safety measures as specified in relevant IS code and NBC. |
| 13 | Phase-II Maintenance of lifts after special repair complete (AMC of lift from OEM)M&L for comprehensive maintenance/repair and servicing of 08 passenger lift installation fully comprehensive (i.e. all in all) regular maintenance for round the clock of the lift including regular servicing, inspections preventive maintenance by trained technician and repair of the installations with bear the cost of repair/replacement of any of the worn out part without any additional charges for 12 Months from date of completion complete all as specified and as directed. |
| 14 | Phase-II Maintenance of lifts after special repair complete (AMC of lift from OEM)All as per item no. 12.00 here-in-before but for 12 Months to 24 months from date of completion complete all as specified and as directed. Please Enable Macros to View BoQ information |
| 15 | Phase-II Maintenance of lifts after special repair complete (AMC of lift from OEM)All as per item no. 12.00 here-in-before but for 12 Months to 24 months from date of completion complete all as specified and as directed. Please Enable Macros to View BoQ information |
AI Tender Summary
Tender Timeline
Tender Published
Tender notice published.
CompletedCorrigendum-1 Issued
Clarifications on tender conditions and amendments issued.
TodayCorrigendum-2 Issued
Clarifications on tender conditions and amendments issued.
TodayBid Submission Deadline
Online submission via eProcurement portal.
TodayBid Opening Date
Technical bids will be opened and evaluated.
Upcoming · 5 daysTender Documents