Project Description
Tender for Supply And Laying Of Water Supply Pipe Line From Main Source To Reserve Chamber Point For Upper Jagar Of Giom In The District Of Kendujhar. (Under Csr Scheme). (Re-Tender)
Corrigendum
| Sr No | Corrigendum Date | Corrigendum | Type | New Submission Date |
|---|---|---|---|---|
| 1 | 05-Sep-2026 | CORRIGENDUM-1 | Technical Bid | 17-Sep-2026 |
BOQ
| Sl. No. | Item Description |
| 1 | Civil works |
| 2 | Supply and Laying of 80 mm Outer dia G.I pipe conforming to IS : 1239 Part-1 as per specification complete including all accessories, materials as required for the work as per the direction of Engineer in Charge. (Make: Tata / Jindal) |
| 3 | Providing joints by welding with two welding beads/pass, conforming to IS:816-1998 (Single 60° Butt weld) to MS pipes and fittings at site by using welding generator including testingof joints, as per specification complete and direction of EIC. |
| 4 | Providing flanged joints (Full-faced Flanges) conforming to IS : 3114-1994 for jointing pvc pipes and other conventional pipes and fittings of the following nominal diameters including testing of joints, cost of bolts and nuts and rubber insertion as per specification and direction of EIC. |
| 5 | Supplying and Fixing of single Air Relief Valve conforming to IS 14845:2000 for water works purposes for the following diameters including drilling the water main (Cast Iron pipes with metal straps) as per specification and direction of EIC. 25mm dia single air valve (Make: Leader / Shakti) |
| 6 | Excavation, loading, unloading and carriage by mechanical means of all kinds soil including stoney earth, gravel and moorum etc. interspread with boulder upto 1/2 Cum size with all lifts and delifts including trimming of slopes and bed to design section and depositing the excavated materials away from work site as per specification and as directed by the Engineer-in-charge within an initial lead of 1Km from the place of excavation complete. |
| 7 | Earth work in excavation of foundation trenches in all kinds of soil including moorum, stone earth, earth maxed with boulders (except sheet rock and rock boulders requiring blasting) including dressing and levelling the bed and depositing the excavated materials at places away from the work site with all leads, lifts, T&P required for the work complete as per direction of EIC. |
| 8 | Sand filling in foundation and plinth with good river sand including laying, watering and ramming in 23 Cm. (9”) thick layers with all leads and lifts comp. inclusive of all cost of labour , T&P required for the work etc. complete as per direction of EIC. |
| 9 | Cement Concrete (1:3:6) using c.b.h.g. metal of approved quality from appd. Quarry including lowering, laying concrete to required levels laid in layers not exceeding 0’6” thick including cost, conveyance, royalties and all type of taxes of all materials, watering and curing and cost of all labour, T& P required for the work etc. complete. |
| 10 | R.C.C M-20 grade concrete with 20mm & down graded hard crusher broken granite chips including hoisting and laying concrete, watering and curing for three weeks centering and shuttering and finishing the exposed surfaces smooth, providing beads or grooves where necessary including cost, conveyance, royalty of all material, dismantling the centering, shuttering work after the period as specified by the EIC and cost of all labour, T&P required for the work comp. in all respect, excluding cost of reinforcement, binding wires and labour charges for bending, binding and tying the grills. IN COLUMN |
| 11 | R.C.C M-20 grade concrete with 20mm & down graded hard crusher broken granite chips including hoisting and laying concrete, watering and curing for three weeks centering and shuttering and finishing the exposed surfaces smooth, providing beads or grooves where necessary including cost, conveyance, royalty of all material, dismantling the centering, shuttering work after the period as specified by the EIC and cost of all labour, T&P required for the work comp. in all respect, excluding cost of reinforcement, binding wires and labour charges for bending, binding and tying the grills. IN Roof Slab |
| 12 | Supplying HYSD bars of approved quality size and grade and cutting, bending, binding and tying the grills in proper position as required for the RCC work in all floors, including cost, conveyance of HYSD bars Fe500 and binding wires of 18 to 20 gauge and cost of labour,T & P and other materials complete in all respect as directed by the EIC. |
| 13 | C.C. of prop. (1:2:4) in foundation and all floors using 12mm size hard crusher broken granite chips of approved quality from approved quarry including lowering, laying concrete to required levels laid in layers not exceeding 150mm thick including cost, conveyance, royalties of all materials, watering and curing and cost of all labour, T&P required for the work etc. comp as per direction of EIC. |
| 14 | Flyash Brick masonry in C.M. (1:6) in foundation and plinth after immersing the bricks having crushing strength of 75Kg/Cm to 100Kg/Cm in water for 24 hours in foundation and plinth and basement, ornamental molding and other similar type of works with all necessary projections, splays , corbelling, cutting, champing , including cost of conveyance, royalties and taxes of all materials, T&P and labour required for the work etc. comp. in all respect. |
| 15 | 12 mm (½\\") thick C.P. (1:6) for finished smooth to inside/outside surface of brick walls in all floors after racking out the joints including watering and curing etc. complete with cost, conveyance, royalty and taxes of all materials and cost of all labour, T&P, scaffolding required for the work comp as per specification & direction of EIC. |
| 16 | 12mm thick C.P.(1:4) with neat cement punning for finished smooth to masonry surface of brick walls after racking out the joints including watering and curing etc. comp. with cost conveyance, royalty of all materials and cost of all labour, T&P scaffolding required for the work complete as per the direction of EIC |
| 17 | Earth Filling in foundation and plinth with excavated earth or moorum or extra good earth from outside including laying, watering and ramming in 23 Cm. (9”) thick layers with all leads and lifts comp. inclusive of all cost of labour , T&P required for the work etc. complete as per direction of EIC. Please Enable Macros to View BoQ information |
AI Tender Summary
Tender Timeline
Tender Published
Tender notice published.
CompletedCorrigendum-1 Issued
Clarifications on tender conditions and amendments issued.
Upcoming · 2 daysBid Submission Deadline
Online submission via eProcurement portal.
Upcoming · 2 daysTender Documents
Download All (ZIP) ↓We takes all possible care for accurate & authentic tender information. However users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender