Power Government Departments Closing in 0 days TDR #57230049

Bids Are invited for Operation And Maintenance Of Electrical Systems/Electrical Installations - Increasing Capacity Of 100Kva To 250Kva Dt And Erection Of 33 11 Kv Line Strengthening Work On Semi Turnkey Basis In Business Plan 2026 Under The Area Of

Issued by Government Departments · Agra, Uttar Pradesh
Tender Value
84.21 Lakhs
Estimated cost
Bid Submission
10 Sep 2026
0 days left
EMD
84300
Bank guarantee accepted
Document Fee
Ref. Documents
Non-refundable
Tender Type
Gem

Tender Overview

Competition Type
NCB
Bidding Type
Tender
Location / State
Agra → Uttar Pradesh
EMD Exemption
Not Available
Quantity
1

Project Description

Bids Are invited for Operation And Maintenance Of Electrical Systems/Electrical Installations - Increasing Capacity Of 100Kva To 250Kva Dt And Erection Of 33 11 Kv Line Strengthening Work On Semi Turnkey Basis In Business Plan 2026 Under The Area Of Edd Fatehabad Agra - (Part-A) Supply & Erection Providing & Fixing Of 11Kv X Arm Cl , Providing & Fixing Of 33Kv X Arm Cl , Providing & Fixing Of Stone Pad , Providing & Fixing Of Cl With Nut & Bolt , Providing & Fixing Of 33Kv F Bracket , Providing & Fixing Of 11Kv F Bracket , Providing & Fixing Of F Cl , Providing & Fixing Of Ms Angle , Providing & Fixing Of Hdpe Pipe , Providing & Fixing Of I Hook , Providing & Fixing Of Suspencion Cl With Eye Hook , Providing & Fixing Of 33Kv Pvc Pipe , Providing & Fixing Of Dropper Channel , Providing & Fixing Of Pg Cl , Providing & Fixing Of 11 Kv Top Channel , Providing & Fixing Of 33 Kv Top Channel , Providing & Fixing Of Shakel Insulator , Providing & Fixing Of T Off Channel , Providing & Fixing Of T- Off Channel With Cl , Providing & Fixing Of Lt Cl For Pcc , Providing & Fixing Of Number Plate , Providing & Fixing Of Gaurding Cl , Providing & Fixing Of Danger Bourd With Nut Bolt , Providing & Fixing Of Gaurding Angle Holding Cl , Providing & Fixing Of Nut & Bolt , Providing & Fixing Of Piercing Connector , Providing & Fixing Of Db Cl , Providing & Fixing Of Dead & Cl , Providing & Fixing Of Holding Cl For Fuse Set , Providing & Fixing Of Lt Lug 250/400/630 Etc , Providing & Installation Of Henley Type Tailless Unit Protection Cubical Panel 500 A 650 V For 250 Kva Dt , Providing & Fixing Of Ms Channel , Providing & Fixing Of Boot &Sleve , Providing & Fixing Of Gaurding Angle , (Part-B) Carriage & Erection Carriage Of Pcc Pole 8.5 Mtr. Long. From Electricity Store Centretajganj Agra To Work Of Site Through Kacha And Pakka Road Including The Work Of Its Loading And Unloading At The Respective Ends Including The Cost Of Arrangement Of Labour, T&P, Carrier Etc. Required For Proper Completion Of Work..(Distance 00-50Kms.) , Carriage Of Pcc Pole 11 Mtr. Long. From Electricity Store Centretajganj Agra To Work Of Site Through Kacha And Pakka Road Including The Work Of Its Loading And Unloading At The Respective Ends Including The Cost Of Arrangement Of Labour, T&P, Carrier Etc. Required For Proper Completion Of Work..(Distance 00-50Kms.) , Carriage Of St Pole 11/13 Mtr. Long. From Electricity Store Centretajganj Agra To Work Of Site Through Kacha And Pakka Road Including The Work Of Its Loading And Unloading At The Respective Ends Including The Cost Of Arrangement Of Labour, T&P, Carrier Etc. Required For Proper Completion Of Work..(Distance 00-50Kms.) , Carriage Of 250 Kva T/F Fromelectricity Store Centretajganj Agra To Work Of Site Through Kacha And Pakka Road Including The Work Of Its Loading And Unloading At The Respective Ends Including The Cost Of Arrangement Of Labour, T&P, Carrier Etc. Required For Proper Completion Of Work..(Distance 00-50Kms.) , Carriage Of 63 Kva T/F Fromelectricity Store Centretajganj Agra To Work Of Site Through Kacha And Pakka Road Including The Work Of Its Loading And Unloading At The Respective Ends Including The Cost Of Arrangement Of Labour, T&P, Carrier Etc. Required For Proper Completion Of Work..(Distance 00-50Kms.) , Cartiage Of 33Kv /11Kv Xlpe Cable 3*300 Sqmm , 11Kv Xlpe Cable 3X185sqmm , Lt Xlpe Cable 3.5*70Sqmm, Lt Xlpe Cable 3.5 Core 250/400/630Sqmm (1070Mtr) Lt Xlpe Single Core Cable 250/400/630Sqmm (744Mtr) From Electricity Store Centretajganj Agra To Work Of Site Through Kacha And Pakka Road Including The Work Of Its Loading And Unloading At The Respective Ends Including The Cost Of Arrangement Of Labour, T&P, Carrier Etc. Required For Proper Completion Of Work.(Distance 00-50Kms.) , Carriage Of Following Material From Electricity Store Centretajganj Agra To Dump Site Through The Kacha And Pakka Road Including The Work Of Its Loading And Unloading At The Respective Ends Including The Cost Of Arrangement Of Labour, T&P, Carrier Etc. Required For Proper Completion Of Work.(Distance 00-50 Kms.) Abc 3*50/120Sqmm (5305Mtr) 33/11 Kv X Arm V Type (1011 Nos), 33/11Kv Disc Insulator With Fitting (394 Nos) 11Kv Pin Insulator (3019 Nos), Stay Set (251 Nos ) Earthing Complete (1107 Nos), Weasal Conductor (31932 Mtr) Rabbit Conductor (3100 Mtr) Gaurding Wire (2154 Kg), Jointing Kit 3*185 Indoor/Outdoor (6 Nos), Jointing Kit 3.5*70 (4 Nos), 33/11Kv Jointing Kit 3*300 (6 Nos), 11Kv Do Fuse Set (25 Nos), Distribution Box (141Nos) Barbed Wire Gi (30Kg) , Cable Box 3*300 Incoming/Outgoing/ Straight Through (4 Nos), And Other Meterials As Per Package , Erection And Grouting Of Single Pole 8.5 Mtr. Long Pcc Poles In 1:2:4 Ratio (Cement, Sand And Bricks Balast) Including Fixing Of All Accessories Alongwith Stone Pad As Per Respo Norms Labour, T &P And Carrier, Grouting Material Etc. Required For Proper Completion Of Work Shall Be Done By The Contractor At His Own Cost. , Erection And Grouting Of Double Pole 8.5 Mtr. Long Pcc Pole In 1:2:4 Ratio (Cement, Sand And Bricks Balast) Including Fixing Of All Accessories Alongwith Stone Pad As Per Respo Norms Labour, T &P And Carrier, Grouting Material Etc. Required For Proper Completion Of Work Shall Be Done By The Contractor At His Own Cost. , Erection And Grouting Of 11 Mtr. Long Pcc Pole In 1:2:4 Ratio (Cement, Sand And Bricks Balast) Including Fixing Of All Accessories Alongwith Stone Pad As Per Respo Norms Labour, T &P And Carrier, Grouting Material Etc. Required For Proper Completion Of Work Shall Be Done By The Contractor At His Own Cost. , Erection And Grouting Of St Pole 11/13 Mtr. Long Single In 1:2:4 Ratio (Cement, Sand And Bricks Balast) Including Fixing Of All Accessories Alongwith Stone Pad As Per Respo Norms.Labour, T &P And Carrier, Grouting Material Etc. Required For Proper Completion Of Work Shall Be Done By The Contractor At His Own Cost. , Construction Of Plinth For 250 Kva Transformer Of Size 6X6x3.6 Above The Ground Lable And 1 Feet Below The Ground. At The Bottom There Shall Be Cc Pad Of Brick Ballast Of Size 5X5x3 Thick In Ratio 1:3:6 [Cement, Sand And Brick Ballast]. The First Class Brick Wall Work Shall Be 9 Thick In Ratio 1:4 [Cement And Sand]. The Hollow Portion Among The Wall Shall Be Filled Up With The Brick Ballast. On The Top Of The Wall Of Plint There Shall Be Rcc Work In Ratio 1:3:6 [Cement, Sand And Grit Stone] By Using 12 Mm Dai Ms Bar At Distance Of 9. There Shall Be Plastering All Over The Plinth 12 Mm Thick In Ratio 1:4 [Cement And Sand] Above The Ground Level. Proper Watering And Curing Of The Plinth Shall Be Carried Out As Per Direction Of Supervising Engineer. , Fencing Of 250 Kva T/Fs As Per Following Specification -Fabrication Of 50X50x6 Mm Size Ms Angle Frame Of Size 3000X2400mm With 450 Mm Long Angle For Grouting The Frame And Fixing Of 2X1.5, 10 Swg Welded Wire Mesh With Ms Strip Of 24X5mm Size All Round The Frame And Drilling 9 Mm Holes Insides Of Frames At As Distance Of 300Mm For Jointing Of Frame With The Help Of Boslts And Nuts Including Cost Of Material. The Width Of Panal May Vary As Per Site Conditions, Grouting And Fixing Of Angle Iron Frames In Ratio 1:2:4 (Cement, Coarse Sand And Stone Ballast ) In The Pocket Of 150X150x150mm All Round The Plinth And Bolting Of Frames With 25X8 Mm Size Bolts And Nuts, Making Main Gate In Front Of The Plinth Of Size 3000X2400 Mm By Making Two Leaves Of Size 3000X1200mm Size And Grouting The Same In Ratio And Method Mentioned At Item (B) Above Fixing With Hinges With Dandlas For Locking System & Painting Of Entire Wire Mesh Angle Iron Etc. With Bus Green Super Enamelled Pain In Two Coats On The Primer Two Coats Of Red Oxide. , Earthing With Strip Of 250 Kva Distribution Transformer By Maintenance Free Earthing Electrods (Chemical) By Digging Pits 6 Dia 3Mtr. Deep Including Inserting Pipe In Pipe Technology Concept Involve Two Mild Steel Pipes One Inserted Inside The Other Of Size ;- 1. Inner Pip Dia Meter 50 Mm. 2. Outer Pipe Dia Meter 100 Mm. Length Of The Both Pipe Shall Be 3000 Mm. The M.S.Pipe Shall Be Isi Mark Of Class B As Per Is 1239. Thickness Of The Pipe Shall Be 12 Swg. The Empty Space In The Pipe Shall Be Filled With The Specially Developed Crystalline Material Conductiv Mixture Such As Copper And Aluminimum Powder.Conductive Carbon And Bonding Material Etc. Mixed In Diffrent Proportions. Conductive Mixture Contents Shall Be 70 % Carbon Powder & 30% Metal Powder Preferably Pure Copper Or Aluminum Material Along With The Required Quantity Of Bonding Materials. Granule Size Of The Carbon & Metal Powder Shall Be 100 Mesh. The Mixture If Forced (Pressurized) Inside The Earth Electrode In Empty Space Of Inner Pipe & In Empty Space Between The Inner & Outer Pipe Of The Earth Electrode, In Paste Form And After Soldification Of The Same The Bottom End Cap As Well As Top End Cap Is Provided. The Mixture Shall Be Pressed By Machine In The Pipe. Precaution Shall Be Taken Has To Have No Air Gap Inside The Pipe While Pressing. The Back Fill Compound (Earth Enhancment Material ) Shall Be Superior Conductive Material That Improves Earthing Effectiveness Especially In Areas Of Poor Conductivity Such As Rocky Ground, Sandy Soil & Areas Of Moisture Varation. It May Contain Conductive Cement (20%) Graphite Carbon Powder(50%), Hydrous Aluminum Siliacate (10%), Sodium Montmorillonite (20%) Etc. It Shall Be Placed Around Earth Electrode In The Earth Pit To Improve The Conductive Of Earth Electrode & Ground Contact Area. Mild Steel Electro Galavanized Flat 50X6 Mm Shall Welded To Earth Electrode Pips & Connected With Trasnformer Neutral And Body As Below With The Hlep Of Steel Nut & Bolt Or Through Welding As Per Requirment Of Site, To Gi Pipe And Filling Of Chemical Mixutre Around The Gi Pipe Upto 3 Mtr. Including Making Of Chamber & Connecting The Top Of The Inserted Pipe With Transformer Body & Neutral Through M.S.Flat 50X6mm With The Help Of Nut & Bolt Or Through Welding And Making A Main Hole Of Size 2×2 And Covering The Same By A Stone Pad For The Purpose Of Poring Water For Moisture. , Installation For 250 Kva T/F On Plinth In Proper Alignment Direction & Making Ht/Lt Connection All Cost Of Labour And T&P Which Required For Completion Of Work. , Mounting & Installation Of 63 Kva T/F On Plinth In Proper Alignment Direction & Making Ht/Lt Connection All Cost Of Labour And T&P Which Required For Completion Of Work. , Laying Of Lt Xlpe Lt Xlpe Cable 3.5 Core 250/400/630Sqmm,Lt Xlpe Single Core Cable 250/400/630Sqmm As Per Respo Norms And Direction By Superivising Engineer. , Fixing Of Distribution Box With Cl On Errected Pole For Giving Supply To Consumer By Connecting Consumer Cables. , Fixing Of Pole Earthing Complete As Per Respo Norms Including The Cost Of Arrangement Of Labour, T&P, Carrier Etc. Required For Proper Completion Of Work. , Laying, Sagging, Stringing, Binding And Jumpering Of Acsr Weasal Conductor/ Dog Conductor/ Rabbit Conductor In 33/11Kv Line As Per Respo Manual And As Per Direction Of Supervising Engineer. It Includes The Cost Of Labour, T & P, Carrier Etc Reauired For Proper Completion Of Work. , Laying Sagging Stringing And Binding And Jumpering Of Conductor In Lt Line As Per Respo Manual And As Per Direction Of Supervising Engineer. It Includes The Cost Of Labour, T & P, Carrier Etc Reauired For Proper Completion Of Work. Abc 3X50/120Sqmm , Laying Of 33/11 Kv Xlpe Cable 3X300 Sqmm Through H.D.P.E.Pipe By Drill Machine/H.D.D. Machine Including The Cost Of Arrangment Of Labour, T&P & Drill Machine/H.D.D. Machine At A Depth As Per Railway Norms. Below The Railway Crossing. , Laying Of Lt Xlpe Cable 3.5X70 Sqmm Overhead With Making Loop As Per Respo Norms And Direction By Superivising Engineer. , Concreting Of Stay Erection Complete In All Respect As Direction By Supervising Engineer. All Required Material Provided By Contractor At His Own Cost , Laying Of 33 Kv Xlpe Cable 3X300 Sqmm Through Gi Pipe And Mounting On Double Pole As Per Respo Norms And Direction By Superivising Engineer. , Laying Of 11 Kv Xlpe Cable 3X185 Sqmm/3X300sqmm Through H.D.P.E.Pipe By Drill Machine/H.D.D. Machine Including The Cost Of Arrangment Of Labour, T&P & Drill Machine/H.D.D. Machine At A Depth As Per Railway Norms. Below The Railway Crossing. , Filling Of 11 Kv Jointing Kit 3X300/ 3X185/ 3.5X70 Sqmm Od/Id And Making Connection As Per Direction By Supervising Engineer. , Filling Of 33 Kv Jointing Kit 3X300 Sqmm Od/Id And Making Connection As Per Direction By Supervising Engineer. , Installation Of 11Kv Do Fuse Set Complete As Direction By Supervising Engineer. , Installation Of Stay Set Complete As Direction By Supervising Engineer. , Erection Of Gaurding Below 33/11Kv Overhead Line Using 6 Swg Gi Wire Complete With Gaurding Engle Cl S Nut & Bolt Binding And All Necessary Complete In All Respects As Per Respo Norms , Dismentling & Removal Of 100 Kva T/F And Recived Back To Ele. Store Center Taj Agra , Dismentling, Removal Of Old & Used Scrap Material And Received Back To Ele. Store Center Taj Agra Including Loading, Unloading Both Ends (0-50Km)

Corrigendum

Sr No Corrigendum Date Corrigendum Type New Submission Date
1 07-Sep-2026 10-Sep-2026

BOQ

Sl. No. Item TitleItem Description
1(Part-A) Supply & Erection Providing & Fixing of 11kv X arm clamp(Part-A) Supply & Erection Providing & Fixing of 11kv X arm clamp
2Providing & Fixing of 33kv X arm clampProviding & Fixing of 33kv X arm clamp
3Providing & Fixing of Stone padProviding & Fixing of Stone pad
4Providing & Fixing of Clamp with nut & boltProviding & Fixing of Clamp with nut & bolt
5Providing & Fixing of 33kv F BracketProviding & Fixing of 33kv F Bracket
6Providing & Fixing of 11kv F BracketProviding & Fixing of 11kv F Bracket
7Providing & Fixing of F ClampProviding & Fixing of F Clamp
8Providing & Fixing of MS AngleProviding & Fixing of MS Angle
9Providing & Fixing of HDPE PipeProviding & Fixing of HDPE Pipe
10Providing & Fixing of I hookProviding & Fixing of I hook
11Providing & Fixing of Suspencion clamp with eye hookProviding & Fixing of Suspencion clamp with eye hook
12Providing & Fixing of 33kv PVC PipeProviding & Fixing of 33kv PVC Pipe
13Providing & Fixing of Dropper ChannelProviding & Fixing of Dropper Channel
14Providing & Fixing of PG ClampProviding & Fixing of PG Clamp
15Providing & Fixing of 11 kv Top channelProviding & Fixing of 11 kv Top channel
16Providing & Fixing of 33 kv Top channelProviding & Fixing of 33 kv Top channel
17Providing & Fixing of Shakel InsulatorProviding & Fixing of Shakel Insulator
18Providing & Fixing of T off ChannelProviding & Fixing of T off Channel
19Providing & Fixing of T- off Channel with clampProviding & Fixing of T- off Channel with clamp
20Providing & Fixing of LT Clamp for pccProviding & Fixing of LT Clamp for pcc
21Providing & Fixing of Number PlateProviding & Fixing of Number Plate
22Providing & Fixing of Gaurding clampProviding & Fixing of Gaurding clamp
23Providing & Fixing of Danger Bourd with nut boltProviding & Fixing of Danger Bourd with nut bolt
24Providing & Fixing of Gaurding Angle holding clampProviding & Fixing of Gaurding Angle holding clamp
25Providing & Fixing of Nut & boltProviding & Fixing of Nut & bolt
26Providing & Fixing of Piercing connectorProviding & Fixing of Piercing connector
27Providing & Fixing of DB clampProviding & Fixing of DB clamp
28Providing & Fixing of Dead & ClampProviding & Fixing of Dead & Clamp
29Providing & Fixing of Holding clamp for fuse setProviding & Fixing of Holding clamp for fuse set
30Providing & Fixing of LT lug 250/400/630 etcProviding & Fixing of LT lug 250/400/630 etc
31PROVIDING & Installation of Henley Type Tailless Unit Protection Cubical Panel 500 A 650 V FOR 250 KVA DTPROVIDING & Installation of Henley Type Tailless Unit Protection Cubical Panel 500 A 650 V FOR 250 KVA DT
32PROVIDING & FIXING OF MS CHANNELPROVIDING & FIXING OF MS CHANNEL
33PROVIDING & FIXING OF Boot &slevePROVIDING & FIXING OF Boot &sleve
34Providing & Fixing of Gaurding AngleProviding & Fixing of Gaurding Angle
35(Part-B) Carriage & Erection Carriage of PCC Pole 8.5 Mtr. Long. from Electricity Store CentreTajganj Agra to work of site through Kacha and Pakka road including the work of its loading and unloading at the respective ends including the cost of arrangement of labour, T&P, carrier etc. required for proper completion of work..(Distance 00-50Kms.)(Part-B) Carriage & Erection Carriage of PCC Pole 8.5 Mtr. Long. from Electricity Store CentreTajganj Agra to work of site through Kacha and Pakka road including the work of its loading and unloading at the respective ends including the cost of arrangement of labour, T&P, carrier etc. required for proper completion of work..(Distance 00-50Kms.)
36Carriage of PCC Pole 11 Mtr. Long. from Electricity Store CentreTajganj Agra to work of site through Kacha and Pakka road including the work of its loading and unloading at the respective ends including the cost of arrangement of labour, T&P, carrier etc. required for proper completion of work..(Distance 00-50Kms.)Carriage of PCC Pole 11 Mtr. Long. from Electricity Store CentreTajganj Agra to work of site through Kacha and Pakka road including the work of its loading and unloading at the respective ends including the cost of arrangement of labour, T&P, carrier etc. required for proper completion of work..(Distance 00-50Kms.)
37Carriage of ST Pole 11/13 Mtr. Long. from Electricity Store CentreTajganj Agra to work of site through Kacha and Pakka road including the work of its loading and unloading at the respective ends including the cost of arrangement of labour, T&P, carrier etc. required for proper completion of work..(Distance 00-50Kms.)Carriage of ST Pole 11/13 Mtr. Long. from Electricity Store CentreTajganj Agra to work of site through Kacha and Pakka road including the work of its loading and unloading at the respective ends including the cost of arrangement of labour, T&P, carrier etc. required for proper completion of work..(Distance 00-50Kms.)
38Carriage of 250 KVA T/F fromElectricity Store CentreTajganj Agra to work of site through Kacha and Pakka road including the work of its loading and unloading at the respective ends including the cost of arrangement of labour, T&P, carrier etc. required for proper completion of work..(Distance 00-50Kms.)Carriage of 250 KVA T/F fromElectricity Store CentreTajganj Agra to work of site through Kacha and Pakka road including the work of its loading and unloading at the respective ends including the cost of arrangement of labour, T&P, carrier etc. required for proper completion of work..(Distance 00-50Kms.)
39Carriage of 63 KVA T/F fromElectricity Store CentreTajganj Agra to work of site through Kacha and Pakka road including the work of its loading and unloading at the respective ends including the cost of arrangement of labour, T&P, carrier etc. required for proper completion of work..(Distance 00-50Kms.)Carriage of 63 KVA T/F fromElectricity Store CentreTajganj Agra to work of site through Kacha and Pakka road including the work of its loading and unloading at the respective ends including the cost of arrangement of labour, T&P, carrier etc. required for proper completion of work..(Distance 00-50Kms.)
40Cartiage of 33kv /11kv XLPE CABLE 3*300 SQMM , 11kv XLPE Cable 3x185sqmm , LT XLPE Cable 3.5*70sqmm, LT XLPE Cable 3.5 core 250/400/630sqmm (1070mtr) LT XLPE single core cable 250/400/630sqmm (744mtr) from Electricity Store CentreTajganj Agra to work of site through Kacha and Pakka road including the work of its loading and unloading at the respective ends including the cost of arrangement of labour, T&P, carrier etc. required for proper completion of work.(Distance 00-50Kms.)Cartiage of 33kv /11kv XLPE CABLE 3*300 SQMM , 11kv XLPE Cable 3x185sqmm , LT XLPE Cable 3.5*70sqmm, LT XLPE Cable 3.5 core 250/400/630sqmm (1070mtr) LT XLPE single core cable 250/400/630sqmm (744mtr) from Electricity Store CentreTajganj Agra to work of site through Kacha and Pakka road including the work of its loading and unloading at the respective ends including the cost of arrangement of labour, T&P, carrier etc. required for proper completion of work.(Distance 00-50Kms.)
41Carriage of following material from Electricity Store CentreTajganj Agra to dump site through the Kacha and Pakka road including the work of its loading and unloading at the respective ends including the cost of arrangement of labour, T&P, carrier etc. required for proper completion of work.(Distance 00-50 Kms.) ABC 3*50/120SQMM (5305MTR) 33/11 kv x arm v type (1011 nos), 33/11kv disc insulator with fitting (394 nos) 11kv pin insulator (3019 nos), stay set (251 nos ) Earthing complete (1107 nos), weasal conductor (31932 mtr) rabbit conductor (3100 mtr) gaurding Wire (2154 kg), Jointing kit 3*185 indoor/outdoor (6 nos), Jointing kit 3.5*70 (4 nos), 33/11kv jointing kit 3*300 (6 nos), 11kv DO fuse set (25 nos), Distribution Box (141nos) Barbed Wire GI (30kg) , Cable box 3*300 incoming/outgoing/ straight through (4 nos), and other meterials as per packageCarriage of following material from Electricity Store CentreTajganj Agra to dump site through the Kacha and Pakka road including the work of its loading and unloading at the respective ends including the cost of arrangement of labour, T&P, carrier etc. required for proper completion of work.(Distance 00-50 Kms.) ABC 3*50/120SQMM (5305MTR) 33/11 kv x arm v type (1011 nos), 33/11kv disc insulator with fitting (394 nos) 11kv pin insulator (3019 nos), stay set (251 nos ) Earthing complete (1107 nos), weasal conductor (31932 mtr) rabbit conductor (3100 mtr) gaurding Wire (2154 kg), Jointing kit 3*185 indoor/outdoor (6 nos), Jointing kit 3.5*70 (4 nos), 33/11kv jointing kit 3*300 (6 nos), 11kv DO fuse set (25 nos), Distribution Box (141nos) Barbed Wire GI (30kg) , Cable box 3*300 incoming/outgoing/ straight through (4 nos), and other meterials as per package
42Erection and grouting of Single Pole 8.5 Mtr. long PCC poles in 1:2:4 ratio (cement, sand and bricks balast) including fixing of all accessories alongwith stone pad as per RESPO norms Labour, T &P and carrier, grouting material etc. required for proper completion of work shall be done by the contractor at his own cost.Erection and grouting of Single Pole 8.5 Mtr. long PCC poles in 1:2:4 ratio (cement, sand and bricks balast) including fixing of all accessories alongwith stone pad as per RESPO norms Labour, T &P and carrier, grouting material etc. required for proper completion of work shall be done by the contractor at his own cost.
43Erection and grouting of Double Pole 8.5 Mtr. long PCC Pole in 1:2:4 ratio (cement, sand and bricks balast) including fixing of all accessories alongwith stone pad as per RESPO norms Labour, T &P and carrier, grouting material etc. required for proper completion of work shall be done by the contractor at his own cost.Erection and grouting of Double Pole 8.5 Mtr. long PCC Pole in 1:2:4 ratio (cement, sand and bricks balast) including fixing of all accessories alongwith stone pad as per RESPO norms Labour, T &P and carrier, grouting material etc. required for proper completion of work shall be done by the contractor at his own cost.
44Erection and grouting of 11 Mtr. long PCC Pole in 1:2:4 ratio (cement, sand and bricks balast) including fixing of all accessories alongwith stone pad as per RESPO norms Labour, T &P and carrier, grouting material etc. required for proper completion of work shall be done by the contractor at his own cost.Erection and grouting of 11 Mtr. long PCC Pole in 1:2:4 ratio (cement, sand and bricks balast) including fixing of all accessories alongwith stone pad as per RESPO norms Labour, T &P and carrier, grouting material etc. required for proper completion of work shall be done by the contractor at his own cost.
45Erection and grouting of ST Pole 11/13 Mtr. long Single in 1:2:4 ratio (cement, sand and bricks balast) including fixing of all accessories alongwith stone pad as per RESPO norms.Labour, T &P and carrier, grouting material etc. required for proper completion of work shall be done by the contractor at his own cost.Erection and grouting of ST Pole 11/13 Mtr. long Single in 1:2:4 ratio (cement, sand and bricks balast) including fixing of all accessories alongwith stone pad as per RESPO norms.Labour, T &P and carrier, grouting material etc. required for proper completion of work shall be done by the contractor at his own cost.
46Construction of plinth for 250 KVA Transformer of size 6’x6’x3.6’ above the ground lable and 1 feet below the ground. At the bottom there shall be CC pad of brick ballast of size 5x5’x3” thick in ratio 1:3:6 [Cement, sand and brick ballast]. The first class brick wall work shall be 9” thick in ratio 1:4 [Cement and sand]. The hollow portion among the wall shall be filled up with the brick ballast. On the top of the wall of plint there shall be RCC work in ratio 1:3:6 [Cement, Sand and grit stone] by using 12 mm dai MS bar at distance of 9’’. There shall be plastering all over the plinth 12 mm thick in ratio 1:4 [Cement and sand] above the ground level. Proper watering and curing of the plinth shall be carried out as per direction of supervising engineer.Construction of plinth for 250 KVA Transformer of size 6’x6’x3.6’ above the ground lable and 1 feet below the ground. At the bottom there shall be CC pad of brick ballast of size 5x5’x3” thick in ratio 1:3:6 [Cement, sand and brick ballast]. The first class brick wall work shall be 9” thick in ratio 1:4 [Cement and sand]. The hollow portion among the wall shall be filled up with the brick ballast. On the top of the wall of plint there shall be RCC work in ratio 1:3:6 [Cement, Sand and grit stone] by using 12 mm dai MS bar at distance of 9’’. There shall be plastering all over the plinth 12 mm thick in ratio 1:4 [Cement and sand] above the ground level. Proper watering and curing of the plinth shall be carried out as per direction of supervising engineer.
47Fencing of 250 KVA T/Fs as per following specification -Fabrication of 50x50x6 mm size MS Angle frame of size 3000x2400mm with 450 mm long angle for grouting the frame and fixing of 2\\"x1.5\\", 10 SWG welded wire mesh with MS strip of 24x5mm size all round the frame and drilling 9 mm holes insides of frames at as distance of 300mm for jointing of frame with the help of boslts and nuts including cost of material. The width of panal may vary as per site conditions, Grouting and fixing of angle iron frames in ratio 1:2:4 (cement, coarse sand and stone ballast ) in the pocket of 150x150x150mm all round the plinth and bolting of frames with 25x8 mm size bolts and nuts, Making main gate in front of the plinth of size 3000x2400 mm by making two leaves of size 3000x1200mm size and grouting the same in ratio and method mentioned at item (b) above fixing with hinges with dandlas for locking system & Painting of entire wire mesh angle iron etc. with Bus Green super enamelled pain in two coats on the primer two coats of Red oxide.Fencing of 250 KVA T/Fs as per following specification -Fabrication of 50x50x6 mm size MS Angle frame of size 3000x2400mm with 450 mm long angle for grouting the frame and fixing of 2\\"x1.5\\", 10 SWG welded wire mesh with MS strip of 24x5mm size all round the frame and drilling 9 mm holes insides of frames at as distance of 300mm for jointing of frame with the help of boslts and nuts including cost of material. The width of panal may vary as per site conditions, Grouting and fixing of angle iron frames in ratio 1:2:4 (cement, coarse sand and stone ballast ) in the pocket of 150x150x150mm all round the plinth and bolting of frames with 25x8 mm size bolts and nuts, Making main gate in front of the plinth of size 3000x2400 mm by making two leaves of size 3000x1200mm size and grouting the same in ratio and method mentioned at item (b) above fixing with hinges with dandlas for locking system & Painting of entire wire mesh angle iron etc. with Bus Green super enamelled pain in two coats on the primer two coats of Red oxide.
48Earthing with strip of 250 KVA distribution transformer by maintenance free Earthing Electrods (Chemical) by digging pits 6\\" dia 3mtr. deep including inserting pipe in pipe technology concept involve two mild steel pipes one inserted inside the other of size ;- 1. Inner pip dia meter 50 Mm. 2. outer pipe dia meter 100 mm. length of the both pipe shall be 3000 mm. The M.S.pipe shall be ISI mark of class B as per IS 1239. Thickness of the pipe shall be 12 swg. The empty space in the pipe shall be filled with the specially developed crystalline material conductiv mixture such as copper and aluminimum powder.conductive carbon and bonding material etc. mixed in diffrent proportions. Conductive mixture contents shall be 70 % carbon powder & 30% metal powder preferably pure copper or aluminum material along with the required quantity of bonding materials. Granule size of the carbon & metal powder shall be 100 mesh. The mixture if forced (pressurized) inside the earth electrode in empty space of inner pipe & in empty space between the inner & outer pipe of the earth electrode, in paste form and after soldification of the same the bottom end cap as well as top end cap is provided. The mixture shall be pressed by machine in the pipe. Precaution shall be taken has to have no air gap inside the pipe while pressing. The back fill compound (earth enhancment material ) shall be superior conductive material that improves earthing effectiveness especially in areas of poor conductivity such as rocky ground, sandy soil & areas of moisture varation. It may contain conductive cement (20%) graphite carbon powder(50%), hydrous aluminum siliacate (10%), Sodium montmorillonite (20%) etc. it shall be placed around earth electrode in the earth pit to improve the conductive of earth electrode & ground contact area. Mild steel electro galavanized Flat 50x6 mm shall welded to earth electrode pips & connected with Trasnformer neutral and body as below with the hlep of steel nut & bolt or through welding as per requirment of site, to GI pipe and filling of chemical mixutre around the GI pipe upto 3 mtr. including making of chamber & connecting the top of the inserted pipe with transformer body & neutral through M.S.flat 50x6mm with the help of nut & bolt or through welding and making a main hole of size 2'×2' and covering the same by a stone pad for the purpose of poring water for moisture.Earthing with strip of 250 KVA distribution transformer by maintenance free Earthing Electrods (Chemical) by digging pits 6\\" dia 3mtr. deep including inserting pipe in pipe technology concept involve two mild steel pipes one inserted inside the other of size ;- 1. Inner pip dia meter 50 Mm. 2. outer pipe dia meter 100 mm. length of the both pipe shall be 3000 mm. The M.S.pipe shall be ISI mark of class B as per IS 1239. Thickness of the pipe shall be 12 swg. The empty space in the pipe shall be filled with the specially developed crystalline material conductiv mixture such as copper and aluminimum powder.conductive carbon and bonding material etc. mixed in diffrent proportions. Conductive mixture contents shall be 70 % carbon powder & 30% metal powder preferably pure copper or aluminum material along with the required quantity of bonding materials. Granule size of the carbon & metal powder shall be 100 mesh. The mixture if forced (pressurized) inside the earth electrode in empty space of inner pipe & in empty space between the inner & outer pipe of the earth electrode, in paste form and after soldification of the same the bottom end cap as well as top end cap is provided. The mixture shall be pressed by machine in the pipe. Precaution shall be taken has to have no air gap inside the pipe while pressing. The back fill compound (earth enhancment material ) shall be superior conductive material that improves earthing effectiveness especially in areas of poor conductivity such as rocky ground, sandy soil & areas of moisture varation. It may contain conductive cement (20%) graphite carbon powder(50%), hydrous aluminum siliacate (10%), Sodium montmorillonite (20%) etc. it shall be placed around earth electrode in the earth pit to improve the conductive of earth electrode & ground contact area. Mild steel electro galavanized Flat 50x6 mm shall welded to earth electrode pips & connected with Trasnformer neutral and body as below with the hlep of steel nut & bolt or through welding as per requirment of site, to GI pipe and filling of chemical mixutre around the GI pipe upto 3 mtr. including making of chamber & connecting the top of the inserted pipe with transformer body & neutral through M.S.flat 50x6mm with the help of nut & bolt or through welding and making a main hole of size 2'×2' and covering the same by a stone pad for the purpose of poring water for moisture.
49Installation for 250 KVA T/F on Plinth in proper alignment direction & making HT/LT connection all Cost of labour and T&P which required for completion of work.Installation for 250 KVA T/F on Plinth in proper alignment direction & making HT/LT connection all Cost of labour and T&P which required for completion of work.
50Mounting & Installation of 63 KVA T/F on Plinth in proper alignment direction & making HT/LT connection all Cost of labour and T&P which required for completion of work.Mounting & Installation of 63 KVA T/F on Plinth in proper alignment direction & making HT/LT connection all Cost of labour and T&P which required for completion of work.
51Laying of LT XLPE LT XLPE CABLE 3.5 core 250/400/630SQMM,LT XLPE Single core Cable 250/400/630SQMM as per RESPO Norms and direction by superivising Engineer.Laying of LT XLPE LT XLPE CABLE 3.5 core 250/400/630SQMM,LT XLPE Single core Cable 250/400/630SQMM as per RESPO Norms and direction by superivising Engineer.
52Fixing of DISTRIBUTION BOX with Clamp on Errected pole for giving supply to consumer by connecting consumer cables.Fixing of DISTRIBUTION BOX with Clamp on Errected pole for giving supply to consumer by connecting consumer cables.
53Fixing of pole earthing Complete as per RESPO norms including the cost of arrangement of labour, T&P, carrier etc. required for proper completion of work.Fixing of pole earthing Complete as per RESPO norms including the cost of arrangement of labour, T&P, carrier etc. required for proper completion of work.
54Laying, sagging, stringing, binding and jumpering of ACSR Weasal conductor/ Dog Conductor/ Rabbit Conductor in 33/11kv line as per RESPO manual and as per direction of supervising engineer. It includes the cost of labour, T & P, carrier etc reauired for proper completion of work.Laying, sagging, stringing, binding and jumpering of ACSR Weasal conductor/ Dog Conductor/ Rabbit Conductor in 33/11kv line as per RESPO manual and as per direction of supervising engineer. It includes the cost of labour, T & P, carrier etc reauired for proper completion of work.
55Laying sagging stringing and binding and jumpering of conductor in LT line as per RESPO manual and as per direction of supervising engineer. It includes the cost of labour, T & P, carrier etc reauired for proper completion of work. ABC 3X50/120SQMMLaying sagging stringing and binding and jumpering of conductor in LT line as per RESPO manual and as per direction of supervising engineer. It includes the cost of labour, T & P, carrier etc reauired for proper completion of work. ABC 3X50/120SQMM
56Laying of 33/11 KV XLPE cable 3x300 sqmm Through H.D.P.E.pipe by drill machine/H.D.D. Machine including the cost of arrangment of labour, T&P & Drill machine/H.D.D. machine at a depth as per Railway Norms. Below the Railway Crossing.Laying of 33/11 KV XLPE cable 3x300 sqmm Through H.D.P.E.pipe by drill machine/H.D.D. Machine including the cost of arrangment of labour, T&P & Drill machine/H.D.D. machine at a depth as per Railway Norms. Below the Railway Crossing.
57Laying of LT XLPE Cable 3.5x70 sqmm overhead with making loop as per RESPO Norms and direction by superivising Engineer.Laying of LT XLPE Cable 3.5x70 sqmm overhead with making loop as per RESPO Norms and direction by superivising Engineer.
58Concreting of Stay erection complete in all respect as direction by supervising Engineer. All required Material Provided by Contractor at his own costConcreting of Stay erection complete in all respect as direction by supervising Engineer. All required Material Provided by Contractor at his own cost
59Laying of 33 KV XLPE Cable 3x300 sqmm through GI Pipe and Mounting on Double Pole as per RESPO Norms and direction by superivising Engineer.Laying of 33 KV XLPE Cable 3x300 sqmm through GI Pipe and Mounting on Double Pole as per RESPO Norms and direction by superivising Engineer.
60Laying of 11 KV XLPE cable 3x185 sqmm/3x300sqmm Through H.D.P.E.pipe by drill machine/H.D.D. Machine including the cost of arrangment of labour, T&P & Drill machine/H.D.D. machine at a depth as per Railway Norms. Below the Railway Crossing.Laying of 11 KV XLPE cable 3x185 sqmm/3x300sqmm Through H.D.P.E.pipe by drill machine/H.D.D. Machine including the cost of arrangment of labour, T&P & Drill machine/H.D.D. machine at a depth as per Railway Norms. Below the Railway Crossing.
61Filling of 11 KV Jointing Kit 3x300/ 3x185/ 3.5x70 sqmm OD/ID and making connection as per direction by supervising engineer.Filling of 11 KV Jointing Kit 3x300/ 3x185/ 3.5x70 sqmm OD/ID and making connection as per direction by supervising engineer.
62Filling of 33 KV Jointing Kit 3x300 sqmm OD/ID and making connection as per direction by supervising engineer.Filling of 33 KV Jointing Kit 3x300 sqmm OD/ID and making connection as per direction by supervising engineer.
63Installation of 11kv DO fuse set Complete as direction by supervising Engineer.Installation of 11kv DO fuse set Complete as direction by supervising Engineer.
64Installation of Stay set Complete as direction by supervising Engineer.Installation of Stay set Complete as direction by supervising Engineer.
65Erection of Gaurding below 33/11kv overhead line using 6 SWG GI wire complete with Gaurding Engle clamps nut & Bolt binding and all necessary complete in all respects as per RESPO normsErection of Gaurding below 33/11kv overhead line using 6 SWG GI wire complete with Gaurding Engle clamps nut & Bolt binding and all necessary complete in all respects as per RESPO norms
66Dismentling & Removal of 100 KVA T/F and Recived back to ele. Store Center Taj AgraDismentling & Removal of 100 KVA T/F and Recived back to ele. Store Center Taj Agra
67Dismentling, Removal of Old & used Scrap Material and received back to ele. Store center Taj Agra including Loading, unloading both ends (0-50km)Dismentling, Removal of Old & used Scrap Material and received back to ele. Store center Taj Agra including Loading, unloading both ends (0-50km)

AI Tender Summary

OUR REF NO 57230049
AUTHORITY Government Departments
TENDER VALUE 84.21 Lakhs
LAST DATE 10-09-2026
Authority
Authority Name Uttar Pradesh Power Corporation Limited
Work Description Bids Are invited for Operation And Maintenance Of Electrical Systems/Electrical Installations - Increasing Capacity Of 100Kva To 250Kva Dt And Erection Of 33 11 Kv Line Strengthening Work On Semi Turnkey Basis In Business Plan 2026 Under The Area Of Edd Fatehabad Agra - (Part-A) Supply & Erection Providing & Fixing Of 11Kv X Arm Cl , Providing & Fixing Of 33Kv X Arm Cl , Providing & Fixing Of Stone Pad , Providing & Fixing Of Cl With Nut & Bolt , Providing & Fixing Of 33Kv F Bracket , Providing & Fixing Of 11Kv F Bracket , Providing & Fixing Of F Cl , Providing & Fixing Of Ms Angle , Providing & Fixing Of Hdpe Pipe , Providing & Fixing Of I Hook , Providing & Fixing Of Suspencion Cl With Eye Hook , Providing & Fixing Of 33Kv Pvc Pipe , Providing & Fixing Of Dropper Channel , Providing & Fixing Of Pg Cl , Providing & Fixing Of 11 Kv Top Channel , Providing & Fixing Of 33 Kv Top Channel , Providing & Fixing Of Shakel Insulator , Providing & Fixing Of T Off Channel , Providing & Fixing Of T- Off Channel With Cl , Providing & Fixing Of Lt Cl For Pcc , Providing & Fixing Of Number Plate , Providing & Fixing Of Gaurding Cl , Providing & Fixing Of Danger Bourd With Nut Bolt , Providing & Fixing Of Gaurding Angle Holding Cl , Providing & Fixing Of Nut & Bolt , Providing & Fixing Of Piercing Connector , Providing & Fixing Of Db Cl , Providing & Fixing Of Dead & Cl , Providing & Fixing Of Holding Cl For Fuse Set , Providing & Fixing Of Lt Lug 250/400/630 Etc , Providing & Installation Of Henley Type Tailless Unit Protection Cubical Panel 500 A 650 V For 250 Kva Dt , Providing & Fixing Of Ms Channel , Providing & Fixing Of Boot &Sleve , Providing & Fixing Of Gaurding Angle , (Part-B) Carriage & Erection Carriage Of Pcc Pole 8.5 Mtr. Long. From Electricity Store Centretajganj Agra To Work Of Site Through Kacha And Pakka Road Including The Work Of Its Loading And Unloading At The Respective Ends Including The Cost Of Arrangement Of Labour, T&P, Carrier Etc. Required For Proper Completion Of Work..(Distance 00-50Kms.) , Carriage Of Pcc Pole 11 Mtr. Long. From Electricity Store Centretajganj Agra To Work Of Site Through Kacha And Pakka Road Including The Work Of Its Loading And Unloading At The Respective Ends Including The Cost Of Arrangement Of Labour, T&P, Carrier Etc. Required For Proper Completion Of Work..(Distance 00-50Kms.) , Carriage Of St Pole 11/13 Mtr. Long. From Electricity Store Centretajganj Agra To Work Of Site Through Kacha And Pakka Road Including The Work Of Its Loading And Unloading At The Respective Ends Including The Cost Of Arrangement Of Labour, T&P, Carrier Etc. Required For Proper Completion Of Work..(Distance 00-50Kms.) , Carriage Of 250 Kva T/F Fromelectricity Store Centretajganj Agra To Work Of Site Through Kacha And Pakka Road Including The Work Of Its Loading And Unloading At The Respective Ends Including The Cost Of Arrangement Of Labour, T&P, Carrier Etc. Required For Proper Completion Of Work..(Distance 00-50Kms.) , Carriage Of 63 Kva T/F Fromelectricity Store Centretajganj Agra To Work Of Site Through Kacha And Pakka Road Including The Work Of Its Loading And Unloading At The Respective Ends Including The Cost Of Arrangement Of Labour, T&P, Carrier Etc. Required For Proper Completion Of Work..(Distance 00-50Kms.) , Cartiage Of 33Kv /11Kv Xlpe Cable 3*300 Sqmm , 11Kv Xlpe Cable 3X185sqmm , Lt Xlpe Cable 3.5*70Sqmm, Lt Xlpe Cable 3.5 Core 250/400/630Sqmm (1070Mtr) Lt Xlpe Single Core Cable 250/400/630Sqmm (744Mtr) From Electricity Store Centretajganj Agra To Work Of Site Through Kacha And Pakka Road Including The Work Of Its Loading And Unloading At The Respective Ends Including The Cost Of Arrangement Of Labour, T&P, Carrier Etc. Required For Proper Completion Of Work.(Distance 00-50Kms.) , Carriage Of Following Material From Electricity Store Centretajganj Agra To Dump Site Through The Kacha And Pakka Road Including The Work Of Its Loading And Unloading At The Respective Ends Including The Cost Of Arrangement Of Labour, T&P, Carrier Etc. Required For Proper Completion Of Work.(Distance 00-50 Kms.) Abc 3*50/120Sqmm (5305Mtr) 33/11 Kv X Arm V Type (1011 Nos), 33/11Kv Disc Insulator With Fitting (394 Nos) 11Kv Pin Insulator (3019 Nos), Stay Set (251 Nos ) Earthing Complete (1107 Nos), Weasal Conductor (31932 Mtr) Rabbit Conductor (3100 Mtr) Gaurding Wire (2154 Kg), Jointing Kit 3*185 Indoor/Outdoor (6 Nos), Jointing Kit 3.5*70 (4 Nos), 33/11Kv Jointing Kit 3*300 (6 Nos), 11Kv Do Fuse Set (25 Nos), Distribution Box (141Nos) Barbed Wire Gi (30Kg) , Cable Box 3*300 Incoming/Outgoing/ Straight Through (4 Nos), And Other Meterials As Per Package , Erection And Grouting Of Single Pole 8.5 Mtr. Long Pcc Poles In 1:2:4 Ratio (Cement, Sand And Bricks Balast) Including Fixing Of All Accessories Alongwith Stone Pad As Per Respo Norms Labour, T &P And Carrier, Grouting Material Etc. Required For Proper Completion Of Work Shall Be Done By The Contractor At His Own Cost. , Erection And Grouting Of Double Pole 8.5 Mtr. Long Pcc Pole In 1:2:4 Ratio (Cement, Sand And Bricks Balast) Including Fixing Of All Accessories Alongwith Stone Pad As Per Respo Norms Labour, T &P And Carrier, Grouting Material Etc. Required For Proper Completion Of Work Shall Be Done By The Contractor At His Own Cost. , Erection And Grouting Of 11 Mtr. Long Pcc Pole In 1:2:4 Ratio (Cement, Sand And Bricks Balast) Including Fixing Of All Accessories Alongwith Stone Pad As Per Respo Norms Labour, T &P And Carrier, Grouting Material Etc. Required For Proper Completion Of Work Shall Be Done By The Contractor At His Own Cost. , Erection And Grouting Of St Pole 11/13 Mtr. Long Single In 1:2:4 Ratio (Cement, Sand And Bricks Balast) Including Fixing Of All Accessories Alongwith Stone Pad As Per Respo Norms.Labour, T &P And Carrier, Grouting Material Etc. Required For Proper Completion Of Work Shall Be Done By The Contractor At His Own Cost. , Construction Of Plinth For 250 Kva Transformer Of Size 6X6x3.6 Above The Ground Lable And 1 Feet Below The Ground. At The Bottom There Shall Be Cc Pad Of Brick Ballast Of Size 5X5x3 Thick In Ratio 1:3:6 [Cement, Sand And Brick Ballast]. The First Class Brick Wall Work Shall Be 9 Thick In Ratio 1:4 [Cement And Sand]. The Hollow Portion Among The Wall Shall Be Filled Up With The Brick Ballast. On The Top Of The Wall Of Plint There Shall Be Rcc Work In Ratio 1:3:6 [Cement, Sand And Grit Stone] By Using 12 Mm Dai Ms Bar At Distance Of 9. There Shall Be Plastering All Over The Plinth 12 Mm Thick In Ratio 1:4 [Cement And Sand] Above The Ground Level. Proper Watering And Curing Of The Plinth Shall Be Carried Out As Per Direction Of Supervising Engineer. , Fencing Of 250 Kva T/Fs As Per Following Specification -Fabrication Of 50X50x6 Mm Size Ms Angle Frame Of Size 3000X2400mm With 450 Mm Long Angle For Grouting The Frame And Fixing Of 2X1.5, 10 Swg Welded Wire Mesh With Ms Strip Of 24X5mm Size All Round The Frame And Drilling 9 Mm Holes Insides Of Frames At As Distance Of 300Mm For Jointing Of Frame With The Help Of Boslts And Nuts Including Cost Of Material. The Width Of Panal May Vary As Per Site Conditions, Grouting And Fixing Of Angle Iron Frames In Ratio 1:2:4 (Cement, Coarse Sand And Stone Ballast ) In The Pocket Of 150X150x150mm All Round The Plinth And Bolting Of Frames With 25X8 Mm Size Bolts And Nuts, Making Main Gate In Front Of The Plinth Of Size 3000X2400 Mm By Making Two Leaves Of Size 3000X1200mm Size And Grouting The Same In Ratio And Method Mentioned At Item (B) Above Fixing With Hinges With Dandlas For Locking System & Painting Of Entire Wire Mesh Angle Iron Etc. With Bus Green Super Enamelled Pain In Two Coats On The Primer Two Coats Of Red Oxide. , Earthing With Strip Of 250 Kva Distribution Transformer By Maintenance Free Earthing Electrods (Chemical) By Digging Pits 6 Dia 3Mtr. Deep Including Inserting Pipe In Pipe Technology Concept Involve Two Mild Steel Pipes One Inserted Inside The Other Of Size ;- 1. Inner Pip Dia Meter 50 Mm. 2. Outer Pipe Dia Meter 100 Mm. Length Of The Both Pipe Shall Be 3000 Mm. The M.S.Pipe Shall Be Isi Mark Of Class B As Per Is 1239. Thickness Of The Pipe Shall Be 12 Swg. The Empty Space In The Pipe Shall Be Filled With The Specially Developed Crystalline Material Conductiv Mixture Such As Copper And Aluminimum Powder.Conductive Carbon And Bonding Material Etc. Mixed In Diffrent Proportions. Conductive Mixture Contents Shall Be 70 % Carbon Powder & 30% Metal Powder Preferably Pure Copper Or Aluminum Material Along With The Required Quantity Of Bonding Materials. Granule Size Of The Carbon & Metal Powder Shall Be 100 Mesh. The Mixture If Forced (Pressurized) Inside The Earth Electrode In Empty Space Of Inner Pipe & In Empty Space Between The Inner & Outer Pipe Of The Earth Electrode, In Paste Form And After Soldification Of The Same The Bottom End Cap As Well As Top End Cap Is Provided. The Mixture Shall Be Pressed By Machine In The Pipe. Precaution Shall Be Taken Has To Have No Air Gap Inside The Pipe While Pressing. The Back Fill Compound (Earth Enhancment Material ) Shall Be Superior Conductive Material That Improves Earthing Effectiveness Especially In Areas Of Poor Conductivity Such As Rocky Ground, Sandy Soil & Areas Of Moisture Varation. It May Contain Conductive Cement (20%) Graphite Carbon Powder(50%), Hydrous Aluminum Siliacate (10%), Sodium Montmorillonite (20%) Etc. It Shall Be Placed Around Earth Electrode In The Earth Pit To Improve The Conductive Of Earth Electrode & Ground Contact Area. Mild Steel Electro Galavanized Flat 50X6 Mm Shall Welded To Earth Electrode Pips & Connected With Trasnformer Neutral And Body As Below With The Hlep Of Steel Nut & Bolt Or Through Welding As Per Requirment Of Site, To Gi Pipe And Filling Of Chemical Mixutre Around The Gi Pipe Upto 3 Mtr. Including Making Of Chamber & Connecting The Top Of The Inserted Pipe With Transformer Body & Neutral Through M.S.Flat 50X6mm With The Help Of Nut & Bolt Or Through Welding And Making A Main Hole Of Size 2×2 And Covering The Same By A Stone Pad For The Purpose Of Poring Water For Moisture. , Installation For 250 Kva T/F On Plinth In Proper Alignment Direction & Making Ht/Lt Connection All Cost Of Labour And T&P Which Required For Completion Of Work. , Mounting & Installation Of 63 Kva T/F On Plinth In Proper Alignment Direction & Making Ht/Lt Connection All Cost Of Labour And T&P Which Required For Completion Of Work. , Laying Of Lt Xlpe Lt Xlpe Cable 3.5 Core 250/400/630Sqmm,Lt Xlpe Single Core Cable 250/400/630Sqmm As Per Respo Norms And Direction By Superivising Engineer. , Fixing Of Distribution Box With Cl On Errected Pole For Giving Supply To Consumer By Connecting Consumer Cables. , Fixing Of Pole Earthing Complete As Per Respo Norms Including The Cost Of Arrangement Of Labour, T&P, Carrier Etc. Required For Proper Completion Of Work. , Laying, Sagging, Stringing, Binding And Jumpering Of Acsr Weasal Conductor/ Dog Conductor/ Rabbit Conductor In 33/11Kv Line As Per Respo Manual And As Per Direction Of Supervising Engineer. It Includes The Cost Of Labour, T & P, Carrier Etc Reauired For Proper Completion Of Work. , Laying Sagging Stringing And Binding And Jumpering Of Conductor In Lt Line As Per Respo Manual And As Per Direction Of Supervising Engineer. It Includes The Cost Of Labour, T & P, Carrier Etc Reauired For Proper Completion Of Work. Abc 3X50/120Sqmm , Laying Of 33/11 Kv Xlpe Cable 3X300 Sqmm Through H.D.P.E.Pipe By Drill Machine/H.D.D. Machine Including The Cost Of Arrangment Of Labour, T&P & Drill Machine/H.D.D. Machine At A Depth As Per Railway Norms. Below The Railway Crossing. , Laying Of Lt Xlpe Cable 3.5X70 Sqmm Overhead With Making Loop As Per Respo Norms And Direction By Superivising Engineer. , Concreting Of Stay Erection Complete In All Respect As Direction By Supervising Engineer. All Required Material Provided By Contractor At His Own Cost , Laying Of 33 Kv Xlpe Cable 3X300 Sqmm Through Gi Pipe And Mounting On Double Pole As Per Respo Norms And Direction By Superivising Engineer. , Laying Of 11 Kv Xlpe Cable 3X185 Sqmm/3X300sqmm Through H.D.P.E.Pipe By Drill Machine/H.D.D. Machine Including The Cost Of Arrangment Of Labour, T&P & Drill Machine/H.D.D. Machine At A Depth As Per Railway Norms. Below The Railway Crossing. , Filling Of 11 Kv Jointing Kit 3X300/ 3X185/ 3.5X70 Sqmm Od/Id And Making Connection As Per Direction By Supervising Engineer. , Filling Of 33 Kv Jointing Kit 3X300 Sqmm Od/Id And Making Connection As Per Direction By Supervising Engineer. , Installation Of 11Kv Do Fuse Set Complete As Direction By Supervising Engineer. , Installation Of Stay Set Complete As Direction By Supervising Engineer. , Erection Of Gaurding Below 33/11Kv Overhead Line Using 6 Swg Gi Wire Complete With Gaurding Engle Cl S Nut & Bolt Binding And All Necessary Complete In All Respects As Per Respo Norms , Dismentling & Removal Of 100 Kva T/F And Recived Back To Ele. Store Center Taj Agra , Dismentling, Removal Of Old & Used Scrap Material And Received Back To Ele. Store Center Taj Agra Including Loading, Unloading Both Ends (0-50Km)
Basic Detail
Tender No GEM/2026/B/7969724
Bidding Type Tender
Location
City Agra
State Uttar Pradesh
Key Dates
Publish Date 07 Sep 2026
Submission Date 10 Sep 2026
Open Date 11 Sep 2026
Finance
Tender Value 84.21 Lakhs
Tender Fee Ref. Documents
EMD 84300
Exemption Not Available
Document List
3a6a4374-c057-4118-a16f-297d4eaa32b8.pdf
1787850258.xlsx
1787850370.pdf
1787850389.pdf
1787850399.pdf
1787850428.pdf
ATCftd_e73fef76-9e7e-4e67-a1ed1787851213733_EDC2FATEHABADBUYER.pdf

Unlock Full AI Tender Summary

Get instant access to the complete AI-generated analysis — scope, eligibility, timeline & more.

Instant Access Secure Free
Your details are secure and used only for document delivery.

Tender Timeline

Sep 07, 2026
11:30 IST

Tender Published

Tender notice published.

Completed
Sep 10, 2026
18:00 IST

Corrigendum-1 Issued

Clarifications on tender conditions and amendments issued.

Today
Sep 10, 2026
17:00 IST

Bid Submission Deadline

Online submission via eProcurement portal.

Today
Sep 11, 2026

Bid Opening Date

Technical bids will be opened and evaluated.

Upcoming · 1 day

Tender Documents

Download All (ZIP) ↓
pdf

3a6a4374-c057-4118-a16f-297d4eaa32b8.pdf

xlsx

1787850258.xlsx

pdf

1787850370.pdf

pdf

1787850389.pdf

pdf

1787850399.pdf

pdf

1787850428.pdf

pdf

ATCftd_e73fef76-9e7e-4e67-a1ed1787851213733_EDC2FATEHABADBUYER.pdf

Disclaimer

We takes all possible care for accurate & authentic tender information. However users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender

TenderDetail
Loading tenders