Tender For Td-555/26 Construction Of 132 Kv Transmission Lines On Acsr Panther Conductor Approx 90 Route Kms Of Upptcl On Turnkey Basis
Tender Value
Ref. Documents
Estimated cost
Bid Submission
21 Sep 2026
19 days left
EMD
47.67 Lakhs
Bank guarantee accepted
Document Fee
5900
Non-refundable
Tender Type
Online
Tender Overview
Organization
Tender ID
Competition Type
NCB
Bidding Type
Tender
Location / State
Lucknow → Uttar Pradesh
EMD Exemption
Not Available
Quantity
Not Available
Website
Contact Person
Address
Project Description
Tender For Td-555/26 Construction Of 132 Kv Transmission Lines On Acsr Panther Conductor Approx 90 Route Kms Of Upptcl On Turnkey Basis
BOQ
| Sl. No. | Item Description |
| 1 | Schedule-3 Summary Tender Inviting Authority: Superintending Engineer, Electricity Transmission Design Circle, 10th Floor, Shakti Bhawan Extension, 14-Ashok Marg, Lucknow-226001 Name of Work: Design, Engineering, Manufacturing, Testing, Supply, Stringing, Installation, Testing & Commissioning etc. for Construction of various 132 KV line on ACSR Panther conductor (approx. 90.2 route Km) of UPPTCL, on Turn-key basis Tender No: TD-555/26 Bidder Name & Address : SCHEDULE OF QUANTITIES AND PRICES (This BOQ template must not be modified/replaced by the bidder and the same should be uploaded after filling the relevent columns, else the bidder is liable to be rejected for this tender. Bidders are allowed to enter the Bidder Name, Address and Values only ) |
| 2 | Total Price for Supply [Schedule S-1 ] |
| 3 | Total Price for Work [Schedule S-2 ] |
| 4 | Total Price [S-1+S-2] |
| 5 | GST @18% [18% of 3] Total Bid Price including GST [3+4] 0.0 Date: Signature Bidder Name: Designation : Name & Address of Company SCHEDULE S-1 : (SUPPLY OF MATERIAL) Tender Specification No.: TD-555/26 Name of Firm: S N Item Unit Quantity Ex-Work per unit rate (Rs.) Freight(Rs.) P&F(Rs.) INS(Rs.) Unit FOR Destination rate (5+6+7+8)(Rs) Total Amt (Exclusive of GST) (Rs.) |
| 6 | TOWERS a Fabrication, galvanizing, Inspection and supply of DC towers including stubs, extension and stub-setting templates, gantry structures as per drawings & BOM (i) Mild steel MT 2188.175 0.0 0.0 (ii) High Tensile Steel MT 0.0 0.0 0.0 b Hot dip galvanized, Hexagon round hexagon head transmission tower Bolts Nuts and washers for above structures as per BOM MT 92.11699999999999 0.0 0.0 |
| 7 | TOWER ACCESSORIES (a) Number Plate Nos. 362.0 0.0 0.0 (b) Danger Plate Nos. 362.0 0.0 0.0 (c) Phase Plate in sets of red, blue and yellow for Tension towers Nos. 583.0 0.0 0.0 (d) Bird Guard for towers Nos. 1050.0 0.0 0.0 (e) Pipe type earthing material for towers Nos. 558.0 0.0 0.0 (f) Circuit plate (Set of two) SET 297.0 0.0 0.0 (g) Anticlimbing device Nos. 273.0 0.0 0.0 3 (i) Porcelain Disc Insulators (a) 70 KN Nos. 2653.0 0.0 0.0 (b) 120 KN Nos. 12049.0 0.0 0.0 3 (ii) Polymer Insulators/Composite silicon rubber insulator string (a) 70 KN suitable for 132 KV suspension fitting per string 697.0 0.0 0.0 (b) 120 KN suitable for 132 KV tension fitting per string 1980.0 0.0 0.0 |
| 8 | HARDWARES SUITABLE FOR ACSR PANTHER (a) Single suspension fittings Nos. 838.0 0.0 0.0 (b) Single Tension fittings Nos. 2448.0 0.0 0.0 (c) Double suspension fittings Nos. 12.0 0.0 0.0 (d) Double Tension fittings Nos. 282.0 0.0 0.0 |
| 9 | CONDUCTOR ACCESSORIES SUITABLE FOR ACSR PANTHER (a) Vibration Dampers Nos. 5574.0 0.0 0.0 (b) Mid Span compression Joint Nos. 553.0 0.0 0.0 (c) Repair sleeves Nos. 475.0 0.0 0.0 (d) Performed Armour Rod Nos. 651.0 0.0 0.0 6 (i) OPGW (a) 96 Fibre (DWSM) OPGW Fibre Optic Cable route km 24.0 0.0 0.0 (b) Supply & Installation of Hardware set for 96 Fibre (DWSM) OPGW* route km 24.0 0.0 0.0 (c) Joint box (96 Fibre) Nos. 10.0 0.0 0.0 (d) FODP (192 F) Nos. 1.0 0.0 0.0 (g) Fibre Optic Approach Cable for 96 F OPGW route km 1.0 0.0 0.0 (h) Supply & Installation of hardware set for 96 Fibre(DWSM, G.652D) Fibre Optic Approach Cable* route km 1.0 0.0 0.0 6(ii) OPGW (a) 48 Fibre (DWSM) OPGW Fibre Optic Cable route km 77.43 0.0 0.0 (b) Supply & Installation of Hardware set for 48 Fibre (DWSM) OPGW* route km 77.19 0.0 0.0 (c) Joint box (48 Fibre) Nos. 42.0 0.0 0.0 (d) FODP (96 F) Nos. 10.0 0.0 0.0 (g) Fibre Optic Approach Cable for 48 F OPGW route km 6.85 0.0 0.0 (h) Supply & Installation of hardware set for 48Fibre(DWSM, G.652D) Fibre Optic Approach Cable* route km 6.85 0.0 0.0 Total 0.0 GST@18% 0.0 Total with GST 0.0 NOTE: * Tenderer must quote their rates for Ex-Works, Packing and Forwarding, Transportation and Insurance Charges separately in Indian Rupees and upto 02 decimal places only as per Columns of above Price Schedule. * GST shall be paid extra (applicable at the time of supply/work) on total of Ex-Works, Packing and Forwarding, Transportation and Insurance Charges. Present rate of GST on work contract is 18%. Signature Date: Bidder Name: Designation : Name & Address of Company * One set of installation hardware set shall contain all installation hardware fittings& accessories as may be required for 1 km of OPGW/Fibre Optic Approach Cable * Tenderer must quote their rates for Ex-Works, Packing and Forwarding, Freight and Insurance Charges separately in Indian Rupees and upto 02 decimal places only as per Columns of above Price Schedule. * GST shall be paid extra (applicable at the time of supply/work) on total of Ex-Works, Packing and Forwarding, Transportation and Insurance Charges. Present rate of GST on work contract is 18%. Signature Date: Bidder Name: Designation : Name & Address of Company SCHEDULE-S-2 (Erection work) Tender Specification No.: TD-555/26 Name of Bidder(Firm): SN DESCRIPTION UNIT Quantity Unit Rate Amount Ecxclusive of GST (Rs.) |
| 10 | 2.0 1(i) Survey including preparation of schedule of materials, marking of locations (Route length),GPS Survey of line with co-ordinates of each tower(The length of line shall be authenticated by GPS Survey) Km 73.86 0.0 0.0 1(ii) Check survey Km 94.04 0.0 0.0 1(iii) Soil testing Locs. 294.0 0.0 0.0 |
| 11 | Cost of excavation of 132 KV tower foundation pits including all earth work,backfilling, levelling etc. |
| 12 | Setting of stubs including all foundation work but excluding the cost of concerting and excavation (Rate per location) for following towers : i 132 KV DA Nos. 115.0 0.0 0.0 ii 132 KV DB Nos. 83.0 0.0 0.0 iii 132 KV DC/DE Nos. 133.0 0.0 0.0 iv 220 KV MC Nos. 1.0 0.0 0.0 |
| 13 | Cost of concreting for all types of tower foundation including cost of cement,dewatering,shoring and shuttering,forming,curing but excluding cost of reinforcement bars i 1:2:4 concreting Cu .m. 11028.817 0.0 0.0 |
| 14 | Erection of Superstructure of 132KV/220KV Towers and Anchor tower and their extensions wherever required including all work above ground level excluding hoisting of insulators, hardware & accessories, but including fitting of danger number, phase plates, bird guard and fixing & punching for 132/220KV SC/DC lines |
| 15 | Tack welding of all the bolts up to the height of one section of the tower or 5 meter from ground level whichever is higher with three tacks at 1200seperatiion of minimum 10 mm thickness with 10mm/12 mm electrode & application of Zinc rich Aluminium paint on the affected surface including cost of all material including tack welding of River Crossing tower & Anchor towers. |
| 16 | Laying, stringing, tensioning clamping, jointing etc of ACSR ‘Panther’ conductor including hoisting of insulators , fitting of all necessary hardware and accessories i.e. fittings Armour rods, vibration dampers etc.on all Six phases of 132 KV DC lines |
| 17 | Laying, stringing, tensioning, clamping, jointing,including fittings of all necessary Hardware and accessories of OPGW & OFAC,installation of FODP, termaination at S/s, end to end connectivity & testing etc on 132KV & 220 KV lines |
| 18 | (a) Grounding work including earth work etc for pipe type grounding including cost of coke & salt. |
| 19 | (b) Grounding work including earthwork etc for counterpoise grounding materials including cost of all material |
| 20 | Installation of steel reinforcement bars in R.C.C. foundation including cost of steel reinforcement bars with cutting, bending, placing, binding etc. |
| 21 | Dismantling of old existing 132/220kV Tower with all accessories including shifting of all material from site to store. |
| 22 | Dismantiling of old existing earthwire/OPGW with all accessories including re-rolling of dismantled Earthwire/OPGW on empty drums for reuse and shifting of all material from site to store. |
| 23 | Dismantling of earliers foundation which includes excavation , breaking of foundations upto 2 meter depth and removing of stubs and steel reinforcement, backfilling, levelling and making field suitable for agriculture |
| 24 | Dismantling of old existing All 3 Phases of ACSR Moose Conductor with all accessories including re-rolling of dismantled conductor on empty drums for reuse and shifting of all material from site to store. 0.0 Date: |
AI Tender Summary
Tender Timeline
Aug 25, 2026
11:30 IST
Tender Published
Tender notice published.
CompletedSep 21, 2026
17:00 IST
Bid Submission Deadline
Online submission via eProcurement portal.
Upcoming · 19 daysSep 22, 2026
Bid Opening Date
Technical bids will be opened and evaluated.
Upcoming · 20 daysTender Documents
Download All (ZIP) ↓
Disclaimer
We takes all possible care for accurate & authentic tender information. However users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender