Tender For Compound Wall Heightening, Plaster, Colour, Repair Of Gate, Repair Of W.B. Room, Electrification & Repair Of Office Building (Old), Construction Of Fire Hydrant Sump, Security Room, Construction Of Qc Room And Construction Of Labour Shed A
Tender Overview
Project Description
Tender for Compound Wall Heightening, Plaster, Colour, Repair Of Gate, Repair Of W.B. Room, Electrification & Repair Of Office Building (Old), Construction Of Fire Hydrant Sump, Security Room, Construction Of Qc Room And Construction Of Labour Shed At Swc Dumerpani.
BOQ
| Sl. No. | Item Description |
| 1 | Earth work in ordinary soil within 50 m.intial lead and 1.5 m.intial lift including rough dressing breaking clods to maximum 5cm.to 7cm.and laying in layers not exceeding 0.3m.depth and as per the direction of Engineer-in - charge. |
| 2 | Filling sand in foundation and plinth well watered and rammed including cost, conveyance, royalty all labour charges etc. complete. |
| 3 | Cement concrete (1:3:6) using 40 mm size B.H.G. Metal of approved quality and from approved quarry including hoisting lowering laying compacting,watering ,curring, cost , conveyance and royalty of all materials, cost of all labour and T&P.required for the work etc.complete. |
| 4 | R.C.C.Work M-20 using 20mm and down grade b.h.grnite chips approved quality and from approved quarry COLUMN BASE ,COLUMN IN S/S AND BEAM including hoisting lowering laying and compacting the concrete including providing smooth centering and shuttering with watering curring cost, conveyance,royalties and taxes of all materials cost of all labour and T&P required for the work etc. complete |
| 5 | COLUMN BASE & PLINTH BAND |
| 6 | COLUMN |
| 7 | PLINTH BAND |
| 8 | Lintel |
| 9 | Chajja/sunshade/Shelve |
| 10 | Brick work using Fly ash B.bricks having crushing strength not less tan 75kg/cm2 in C.M (1:6) using bricks of approved quality of size 10\\"x 5\\"x 3\\" having diamensional tolerance ± 10% after immersing the bricks 6 hours in water before use including hoisting, lowering, laying, cutting, moulding, corbelling, champering, watering, curring in Foundation & Plinth with cost conveyance taxes royalties of all materials cost of all labour and T&P required for the work etc. complete. |
| 11 | Cement concrete (1:2:4) using 12 mm size black hard granite chips of approved quality and from approved quarry including hoisting lowering laying and compacting with watering ,curring ,cost,conveyance, royalties and taxes of all materials ,cost of all labour and T&P required for the work etc, complete |
| 12 | 12 mm thick Cement Plaster(1:6) over rough surface of Brick massonry including racking out joints including watering , curring, cost , conveyance, royalties and taxes of all materials,cost of all labour and T&P required for the work etc. complete . |
| 13 | Weather Painting two coats over a coat of primer over the wall surface with approved quality paint including cost,conveyance and royalty of all materials and all labour charges etc. complete. |
| 14 | Priming 1 coat with any approved primer including cost per (Plastered surface) |
| 15 | supplying fitting & fixing well febricated M.S. tublar gate using outer frames and mid struts of 56O.D. and inner struts of 26O.D. to be febricated in100mm C/C having gate size of 5.00mtr × 1.50mtr (double leaf) providing 250mm long angular W.I. clamp well hinged and providing 'V' shape hook febricated with 40mm × 6mm M.S.flat with effective depth of 200mm , 450mm long × 20mmΦ m.s. plane rod and 380mm long × 20mm Φ m.s. plane rod etc fixing the gate to proper allignment to be embeded rigidly with R.C.C. piller including cost conveyance, taxes of all materials, cost of all labour and T&P required for the work etc complete as directed by the E.I.C.. |
| 16 | Painting 2 coats over a coat of red oxide over M.S.Door over a coats primar etc,complete. |
| 17 | Scraping old paint with scrapers, sand papering and washinh with soap water or soda including scaffolding charges including all cost et complete. |
| 18 | Distempering two coat to walls with distemper of approved shade on new work to give an even shade including cost. |
| 19 | Removing old grading plaster from roof slab and cleaning the surface including removing the debris within 50m lead etc. |
| 20 | 2.5mm thick Cement concrete 1:2:2 for grading concrete over roof slab with 6 mm C.B.H.G. chips |
| 21 | Supplying fitting & Fixing Vertfied Tile in floors of size 600mm x 600mm of approved make conforming to ISI:13755 laid on 20mm thick cement mortar(1:4)(1 cement:1 course sand) and filling joints with white cement of approved quality including cost of all material,labour T&P etc.required for the work all complete as per direction of Engineer-in-charge. |
| 22 | Dismanteling & removing cement concrete including stacking the useful materials for reuse and removing the debris away from the working area i.e. with in 50.00mtr. Lead., including cost of all labour and T&P required for the work etc. complete. |
| 23 | Supplying, fitting and placing uncoated HYSD bar reinforcement complete as per drawing and technical specification etc.including cost,conveyance of MS Rod and binding wires of 18mm to 20mm gauge complete as per directed by the Engineer-in-Charge. |
| 24 | provision for Electrfication with supply fitting with all cost complete. |
| 25 | Cement Punning for ground floor. |
| 26 | providing manhole set including cost,convtax,lab,etc,complete |
| 27 | 12mm. Thick cememnt plaster (1:6) for brick work |
| 28 | 16mm. Thick cement plaster (1:6) for 22.5 cm. to 25cm. Wall and over brick or stone masonry |
| 29 | Priming 1 coat with any approved primer including cost for new wood work/ Iron work. |
| 30 | Supplying fitting fixing of M.S door and window ,grill in window including all lab,tax,conv,etc complete. |
| 31 | Earthwork Excavation of Foundation in hard Soil within 50M Initial Lead and 1.5M Initial Lift…............etc with all cost complete. |
| 32 | Filling in F&P with excavated materials including cost of labour….........etc with all cost complete. |
| 33 | Fly Ash Brick Masonry in Superstructure in (1:6) CM…................. etc with all cost complete. |
| 34 | Supplying Fitting and Fixing of Double Leaved MS Doors and Windows ….........etc with all cost complete. |
| 35 | Supplying, Fitting and Fixing of Vitrified Tiles in Dados, Skirtings and Risers in (1:3) C.P ………etc with all cost complete. |
| 36 | Supplying, fitting & fixing of MS/GI doors & windows, Trusses, Purlins etc…….. With all cost complete. |
| 37 | 12 mm thick C.P in C.M (1:4) with neat punning……….etc with all cost complete. |
| 38 | Suppling and fixing of 0.45mm thick Galvalume Sheet in Roofing……..etc with all cost complete. |
| 39 | Cost of Supplying, Fitting and Fixing of pre-cast concrete ventilators of size 0.38 x 0.25 m |
| 40 | Provision for Sanitary and water supply fittings ….etc with all cost complete. Please Enable Macros to View BoQ information |
AI Tender Summary
Tender Timeline
Tender Published
Tender notice published.
CompletedBid Submission Deadline
Online submission via eProcurement portal.
Upcoming · 9 daysBid Opening Date
Technical bids will be opened and evaluated.
Upcoming · 10 daysTender Documents
Download All (ZIP) ↓We takes all possible care for accurate & authentic tender information. However users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender