Tender For Construction Of The Boundary Wall And Pathway, Painting And Whitewashing, And Installation Of An Open Gym, Benches, Dustbins, And Swings, Along With Horticultural Work, For The Park Located In Ward-03, Mes Colony Phase-01.
Tender Overview
Project Description
Tender for Construction Of The Boundary Wall And Pathway, Painting And Whitewashing, And Installation Of An Open Gym, Benches, Dustbins, And Swings, Along With Horticultural Work, For The Park Located In Ward-03, Mes Colony Phase-01.
BOQ
| Sl. No. | Item Description |
| 1 | Dismantling of old damage BOE C.C. tiles Road work i/c stacking of dismantlled materials as directed by E/I.within a distance of 60.00M |
| 2 | Supply of Earth work in cutting or in embankment in ordinary soil, excavation to be in the regular pits not exceefing 0.5m in depth and earthwork in embankment to be in 20cm layers, including ramming and dressing the surface to required levels & slope & also including 1.50m lift & 30m lead. The earth from cutting to be used in making embankment or to be deposited as spoil banks within 30m. Distance as directed by the Engineer-in-Charge. (Excluding Royalty) S.I. No. 253 |
| 3 | Excavation in foundation in ordinary Soil (Loam, Clay or sand) including, lift upto 1.50 M and lead Upto 30m and including filling watering and ramming of excavated earth into the trenches or into the space between the building and the sides of foundation trenches or into the plinth and removal and disposal of surplus earth as directed by the Engineer-in-charge upto a distance of 30.0m from the foundation trencches. excluding royalty.( S.I. No.251) |
| 4 | Providing and laying cement concrete in 1:6:12 (1 cement : 6 Fine sand : 12 Brick ballast 40 mm gauge) and curing complete, including cost of form work in foundation and floors-completion of the work as per direction of E/ I. (S.I No. 273) |
| 5 | First class brick work in 1:4 cement and fine sand of 1.25 FM. Mortar in foundation and plinth including supply of all materials, labour and T&P etc. required for proper completion of the work. |
| 6 | P/L of 2cm thick DPC with cement and approved coarse sand 1:2 and including water proofing materials as ordered by the E/I in the proportion as specified by the manufactures including supply of all material, labour and T&P etc. required for proper complition of the work and including proper curing and shuttering as necessary. S.I. No. 360 |
| 7 | First class B/w in 1:4 Cement C'sand mortor in S/S including supply of all meterial labour t&P etc required for proper completion of work SI N0. (305+310) |
| 8 | 12 mm thick plaster in 1:5 cement & c'sand mortor over brick work minimume thickness not less then 10 mm including all supply of meterial , Labour T&P etc S.I.No. 584(i) |
| 9 | Providing and laying cement concrete in 4:2:1 of not less than strength of M-150 stone ballast (20 mm nominal size), approved coarse sand and cement, curing complete including of cost of form work in foundation and floors-completion of the work as per direction of the E / I. |
| 10 | RCC 1:2:4 with cement c'sand stone grit of 20 mm gauge in slab of culvert excluding supply of reinforcement with its bending but including its binding & fixing with supply of all meterial labour T&P etc. required for proper completion of the work. SI No. 284 |
| 11 | Mild steel or Iron for plain work such as reinforced concrete brought to proper shape as necessary including its bending with supply of steel with overlaps & wastage also required for proper completion of the work as per E/I SI No. 504 |
| 12 | Fabrication of Mild steel or iron work of grill and stair case railling (When not included in an overall rates) brought to required form including supply of steel and its wastage including cost of bolts, nuts and wastage etc. and there fixing if required for proper completion of work.(S.I.No.502c) |
| 13 | P/Laying 2mm thick plaster of paris putty for proper complition of the work as per Direction of E/I all complete As per D.S.R. No. 13.26 |
| 14 | Finishing walls with Acrylic Smooth exterior paint of required shade New work (Two or more coat applied @ 1.67 ltr/10 sqm over and including priming coat of exterior primer applied @ 2.20 kg/ 10 sqm) as per D.S.R. 13.46.1 |
| 15 | Two coat painting with synthetic enamel paints on new plain surface with primer of approved quality of colour by E/I. |
| 16 | P/L of Granular sub base with coarse graded materials (Table 400-2 ) in granular sub base by providing coare graded materials, spreading in uniform layer with motor grader on preparing surface mixing by mix in place method with rotovator O.M.C. and compacting with power vibratory roller to achieve the desired density complete as per clause 401compected incluing lighting, guarding, barricating and maintance of diversion etc |
| 17 | Supply and Laying of rubber Moulded C.C Interlocking Tiles 80mm thick in road pavement having a compressive strength not lass than 300 kg / cm2 including 40 mm thick bed of fine sand of F/M 1.25 with a specification ratio of coarse material stone grit of size 8 mm to 12 mm in ratio 2:3 and fine material port land cement & coarse sand 1 : 1 -1/2 and mix it coarse material with ratio 3:2 and top sarface of tile at least 5mm thick with mix of cement and marble dust with ratio 1:1 provide the machanical pressure of 380 kg/cm2 at the time of manifacture of tile. In the manifacture of tiles the use of cement 7.5 begs of 50 kg to 8.5 bages per m,3 and labour, including supply of all material, T&P for proper completion of the work, and joint filled with fine sand, also including as per direction of E/I |
| 18 | Supply & fixing of STRAIGHT BENCH (ROUND HANDEL) of 05 feet length ITEM No. SB-03 fixing at above all parks as per Diection of E/I all complete |
| 19 | Supply & fixing of DESIGNER DUST BIN (MONKEY) ITEM NO. DB-03 fixing at above all parks as per Diection of E/I all complete |
| 20 | Supply & fixing of SWING (DOUBLE SEATER) ITEM NO. SW-02 fixing at above all parks as per Diection of E/I all complete |
| 21 | Supply & fixing of WAVE SLIDE (M) Height-06 feet ITEM NO. SD-05 B fixing at above all parks as per Diection of E/I all complete |
| 22 | Deduction cost of brick bats |
| 23 | Deduction cost of bricks Please Enable Macros to View BoQ information |
AI Tender Summary
Tender Timeline
Tender Published
Tender notice published.
CompletedBid Submission Deadline
Online submission via eProcurement portal.
Upcoming · 4 daysBid Opening Date
Technical bids will be opened and evaluated.
Upcoming · 4 daysTender Documents
Download All (ZIP) ↓We takes all possible care for accurate & authentic tender information. However users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender