Tender For Planning, Design, Engineering, Construction, Fabrication, Supply, Erection, Installation, Trial Run, Testing And Commissioning Of Electrical Drive Unit With Gear Box, Plc-Vfd System With New Drum & Disc Braking And Emergency Backup Supply
Tender Overview
Project Description
Tender for Planning, Design, Engineering, Construction, Fabrication, Supply, Erection, Installation, Trial Run, Testing And Commissioning Of Electrical Drive Unit With Gear Box, Plc-Vfd System With New Drum & Disc Braking And Emergency Backup Supply Along With Camc For 5 Years (Including 1-Year Warrantee Period) By Converting The Existing Steam Winders To Electrical Winders At Various Locations Of Ecl- 08 (Eight) (Nos As Per Details In Scope Of Work)
Corrigendum
| Sr No | Corrigendum Date | Corrigendum | Type | New Submission Date |
|---|---|---|---|---|
| 1 | 12-Aug-2026 | Corrigendum in scope of work | Other | 29-Aug-2026 |
BOQ
| Sl. No. | Item Description |
| 1 | SCHEDULE 1 (Kunustoria Colliery, Pit No.3) |
| 2 | SCHEDULE 2 (Bansra Colliery, Pit No. B) |
| 3 | SCHEDULE 3 (Jambad UG Colliery, Pit No.3) |
| 4 | SCHEDULE 4 (Khas Kajora Colliery, Pit No.5) |
| 5 | SCHEDULE 5 (Kumardihi A colliery, Pit No.4) |
| 6 | SCHEDULE 6 (Pandaveswar Colliery, Pit No.B |
| 7 | SCHEDULE 7 (Ningha Colliery, Pit No.4 & 5) Please Enable Macros to View BoQ information |
| 8 | Supply, Fabrication, and Delivery of a Mine Winder Drum |
| 9 | Supply, Fabrication, and Delivery of Mine Winder Drum with Disc Brake Assembly including Brake Discs, Actuators, and MountingProvisions, as per Technical Specifications |
| 10 | AC Variable Frequency regenerative braking system at unity power factor, 415V, rated capacity of 165KVA - 200KVA. |
| 11 | AC squirrel cage induction motor, 415V, rated capacity: min 100 kW (as per requirement) |
| 12 | Digital motor Encoder |
| 13 | Gearbox with suitable ratio with minimum power transmission capacity as per requirement |
| 14 | PLC with PC-based suitable software |
| 15 | Online UPS |
| 16 | LT Switch Board |
| 17 | Control Desk |
| 18 | Power & Control Cable |
| 19 | Signaling & Communication system |
| 20 | Hydraulic Braking System |
| 21 | Transformers, VCB, NGR |
| 22 | Emergency Power back-up system with 500 KVA, 415V DG Set |
| 23 | Thrustor Brakes, Couplings, Safety devices, Earthing materials, etc. |
| 24 | Civil Works include the foundation of motors, cable trenches, etc. |
| 25 | Design, Engineering, Installation & commissioning |
| 26 | Civil work for Air-conditioned PLC Control Room for keeping VFD Panel, Transformer room, VCB room, LT Switch Room, DG Shed Total Estimated Cost for Design, Civil, Supply, Install & Commissioning (Excluding GST) GST |
| 27 | NPV of 1st year Comprehensive AMC charges after warranty period |
| 28 | NPV of 2nd year Comprehensive AMC charges after warranty period |
| 29 | NPV of 3rd year Comprehensive AMC charges after warranty period |
| 30 | NPV of 4th year Comprehensive AMC charges after warranty period |
| 31 | Supply, Fabrication, and Delivery of a Mine Winder Drum |
| 32 | Supply, Fabrication, and Delivery of Mine Winder Drum with Disc Brake Assembly including Brake Discs, Actuators, and MountingProvisions, as per Technical Specifications |
| 33 | AC Variable Frequency regenerative braking system at unity power factor, 415V, rated capacity of 165KVA - 200KVA. |
| 34 | AC squirrel cage induction motor, 415V, rated capacity: min 100 kW (as per requirement) |
| 35 | Digital motor Encoder |
| 36 | Gearbox with suitable ratio with minimum power transmission capacity as per requirement |
| 37 | PLC with PC-based suitable software |
| 38 | Online UPS |
| 39 | LT Switch Board |
| 40 | Control Desk |
| 41 | Power & Control Cable |
| 42 | Signaling & Communication system |
| 43 | Hydraulic Braking System |
| 44 | Transformers, VCB, NGR |
| 45 | Emergency Power back-up system with 500 KVA, 415V DG Set |
| 46 | Thrustor Brakes, Couplings, Safety devices, Earthing materials, etc. |
| 47 | Civil Works include the foundation of motors, cable trenches, etc. |
| 48 | Design, Engineering, Installation & commissioning |
| 49 | Civil work for Air-conditioned PLC Control Room for keeping VFD Panel, Transformer room, VCB room, LT Switch Room, DG Shed Total Estimated Cost for Design, Civil, Supply, Install & Commissioning (Excluding GST) GST |
| 50 | NPV of 1st year Comprehensive AMC charges after warranty period |
| 51 | NPV of 2nd year Comprehensive AMC charges afetr warranty period |
| 52 | NPV of 3rd year Comprehensive AMC charges after warranty period |
| 53 | NPV of 4th year Comprehensive AMC charges after warranty period |
| 54 | Supply, Fabrication, and Delivery of a Mine Winder Drum |
| 55 | Supply, Fabrication, and Delivery of Mine Winder Drum with Disc Brake Assembly including Brake Discs, Actuators, and MountingProvisions, as per Technical Specifications |
| 56 | AC Variable Frequency regenerative braking system at unity power factor, 415V, rated capacity of 165KVA - 200KVA. |
| 57 | AC squirrel cage induction motor, 415V, rated capacity: min 100 kW (as per requirement) |
| 58 | Digital motor Encoder |
| 59 | Gearbox with suitable ratio with minimum power transmission capacity as per requirement |
| 60 | PLC with PC-based suitable software |
| 61 | Online UPS |
| 62 | LT Switch Board |
| 63 | Control Desk |
| 64 | Power & Control Cable |
| 65 | Signaling & Communication system |
| 66 | Hydraulic Braking System |
| 67 | Transformers, VCB, NGR |
| 68 | Emergency Power back-up system with 500 KVA, 415V DG Set |
| 69 | Thrustor Brakes, Couplings, Safety devices, Earthing materials, etc. |
| 70 | Civil Works include the foundation of motors, cable trenches, etc. |
| 71 | Design, Engineering, Installation & commissioning |
| 72 | Civil work for Air-conditioned PLC Control Room for keeping VFD Panel, Transformer room, VCB room, LT Switch Room, DG Shed Total Estimated Cost for Design, Civil, Supply, Install & Commissioning (Excluding GST) GST |
| 73 | NPV of 1st year Comprehensive AMC charges after warranty period |
| 74 | NPV of 2nd year Comprehensive AMC charges after warranty period |
| 75 | NPV of 3rd year Comprehensive AMC charges after warranty period |
| 76 | NPV of 4th year Comprehensive AMC charges after warranty period |
| 77 | Supply, Fabrication, and Delivery of a Mine Winder Drum |
| 78 | Supply, Fabrication, and Delivery of Mine Winder Drum with Disc Brake Assembly including Brake Discs, Actuators, and MountingProvisions, as per Technical Specifications |
| 79 | AC Variable Frequency regenerative braking system at unity power factor, 415V, rated capacity of 165KVA - 200KVA. |
| 80 | AC squirrel cage induction motor, 415V, rated capacity: min 100 kW (as per requirement) |
| 81 | Digital motor Encoder |
| 82 | Gearbox with suitable ratio with minimum power transmission capacity as per requirement |
| 83 | PLC with PC-based suitable software |
| 84 | Online UPS |
| 85 | LT Switch Board |
| 86 | Control Desk |
| 87 | Power & Control Cable |
| 88 | Signaling & Communication system |
| 89 | Hydraulic Braking System |
| 90 | Transformers, VCB, NGR |
| 91 | Emergency Power back-up system with 500 KVA, 415V DG Set |
| 92 | Thrustor Brakes, Couplings, Safety devices, Earthing materials, etc. |
| 93 | Civil Works include the foundation of motors, cable trenches, etc. |
| 94 | Design, Engineering, Installation & commissioning |
| 95 | Civil work for Air-conditioned PLC Control Room for keeping VFD Panel, Transformer room, VCB room, LT Switch Room, DG Shed Total Estimated Cost for Design, Civil, Supply, Install & Commissioning (Excluding GST) GST |
| 96 | NPV of 1st year Comprehensive AMC charges after warranty period |
| 97 | NPV of 2nd year Comprehensive AMC charges after warranty period |
| 98 | NPV of 3rd year Comprehensive AMC charges after warranty period |
| 99 | NPV of 4th year Comprehensive AMC charges after warranty period |
| 100 | Supply, Fabrication, and Delivery of a Mine Winder Drum |
| 101 | Supply, Fabrication, and Delivery of Mine Winder Drum with Disc Brake Assembly including Brake Discs, Actuators, and MountingProvisions, as per Technical Specifications |
| 102 | AC Variable Frequency regenerative braking system at unity power factor, 415V, rated capacity of 165KVA - 200KVA. |
| 103 | AC squirrel cage induction motor, 415V, rated capacity: min 100 kW (as per requirement) |
| 104 | Digital motor Encoder |
| 105 | Gearbox with suitable ratio with minimum power transmission capacity as per requirement |
| 106 | PLC with PC-based suitable software |
| 107 | Online UPS |
| 108 | LT Switch Board |
| 109 | Control Desk |
| 110 | Power & Control Cable |
| 111 | Signaling & Communication system |
| 112 | Hydraulic Braking System |
| 113 | Transformers, VCB, NGR |
| 114 | Emergency Power back-up system with 500 KVA, 415V DG Set |
| 115 | Thrustor Brakes, Couplings, Safety devices, Earthing materials, etc. |
| 116 | Civil Works include the foundation of motors, cable trenches, etc. |
| 117 | Design, Engineering, Installation & commissioning |
| 118 | Civil work for Air-conditioned PLC Control Room for keeping VFD Panel, Transformer room, VCB room, LT Switch Room, DG Shed Total Estimated Cost for Design, Civil, Supply, Install & Commissioning (Excluding GST) GST |
| 119 | NPV of 1st year Comprehensive AMC charges after warranty period |
| 120 | NPV of 2nd year Comprehensive AMC charges after warranty period |
| 121 | NPV of 3rd year Comprehensive AMC charges after warranty period |
| 122 | NPV of 4th year Comprehensive AMC charges after warranty period |
| 123 | Supply, Fabrication, and Delivery of a Mine Winder Drum |
| 124 | Supply, Fabrication, and Delivery of Mine Winder Drum with Disc Brake Assembly including Brake Discs, Actuators, and MountingProvisions, as per Technical Specifications |
| 125 | AC Variable Frequency regenerative braking system at unity power factor, 415V, rated capacity of 165KVA - 200KVA. |
| 126 | AC squirrel cage induction motor, 415V, rated capacity: min 100 kW (as per requirement) |
| 127 | Digital motor Encoder |
| 128 | Gearbox with suitable ratio with minimum power transmission capacity as per requirement |
| 129 | PLC with PC-based suitable software |
| 130 | Online UPS |
| 131 | LT Switch Board |
| 132 | Control Desk |
| 133 | Power & Control Cable |
| 134 | Signaling & Communication system |
| 135 | Hydraulic Braking System |
| 136 | Transformers, VCB, NGR |
| 137 | Emergency Power back-up system with 500 KVA, 415V DG Set |
| 138 | Thrustor Brakes, Couplings, Safety devices, Earthing materials, etc. |
| 139 | Civil Works include the foundation of motors, cable trenches, etc. |
| 140 | Design, Engineering, Installation & commissioning |
| 141 | Civil work for Air-conditioned PLC Control Room for keeping VFD Panel, Transformer room, VCB room, LT Switch Room, DG Shed Total Estimated Cost for Design, Civil, Supply, Install & Commissioning (Excluding GST) GST |
| 142 | NPV of 1st year Comprehensive AMC charges after warranty period |
| 143 | NPV of 2nd year Comprehensive AMC charges after warranty period |
| 144 | NPV of 3rd year Comprehensive AMC charges after warranty period |
| 145 | NPV of 4th year Comprehensive AMC charges after warranty period |
| 146 | Supply, Fabrication, and Delivery of a Mine Winder Drum |
| 147 | Supply, Fabrication, and Delivery of Mine Winder Drum with Disc Brake Assembly including Brake Discs, Actuators, and MountingProvisions, as per Technical Specifications |
| 148 | AC Variable Frequency regenerative braking system at unity power factor, 415V, rated capacity of 165KVA - 200KVA. |
| 149 | AC squirrel cage induction motor, 415V, rated capacity: min 100 kW (as per requirement) |
| 150 | Digital motor Encoder |
| 151 | Gearbox with suitable ratio with minimum power transmission capacity as per requirement |
| 152 | PLC with PC-based suitable software |
| 153 | Online UPS |
| 154 | LT Switch Board |
| 155 | Control Desk |
| 156 | Power & Control Cable |
| 157 | Signaling & Communication system |
| 158 | Hydraulic Braking System |
| 159 | Transformers, VCB, NGR |
| 160 | Emergency Power back-up system with 500 KVA, 415V DG Set |
| 161 | Thrustor Brakes, Couplings, Safety devices, Earthing materials, etc. |
| 162 | Civil Works include the foundation of motors, cable trenches, etc. |
| 163 | Design, Engineering, Installation & commissioning |
| 164 | Civil work for Air-conditioned PLC Control Room for keeping VFD Panel, Transformer room, VCB room, LT Switch Room, DG Shed Total Estimated Cost for Design, Civil, Supply, Install & Commissioning (Excluding GST) GST |
| 165 | NPV of 1st year Comprehensive AMC charges after warranty period |
| 166 | NPV of 2nd year Comprehensive AMC charges after warranty period |
| 167 | NPV of 3rd year Comprehensive AMC charges after warranty period |
| 168 | NPV of 4th year Comprehensive AMC charges after warranty period |
| 169 | Kunustoria Colliery, Pit no. 3 (Schedule 1) |
| 170 | 1st year Comprehensive AMC charges after warranty period |
| 171 | 2nd year Comprehensive AMC charges after warranty period |
| 172 | 3rd year Comprehensive AMC charges after warranty period |
| 173 | 4th year Comprehensive AMC charges after warranty period |
| 174 | Bansra Colliery, Pit no. B (Schedule 2) |
| 175 | 1st year Comprehensive AMC charges after warranty period |
| 176 | 2nd year Comprehensive AMC charges after warranty period |
| 177 | 3rd year Comprehensive AMC charges after warranty period |
| 178 | 4th year Comprehensive AMC charges after warranty period |
| 179 | Jambad UG Colliery, Pit no. 3 (Schedule 3) |
| 180 | 1st year Comprehensive AMC charges after warranty period |
| 181 | 2nd year Comprehensive AMC charges after warranty period |
| 182 | 3rd year Comprehensive AMC charges after warranty period |
| 183 | 4th year Comprehensive AMC charges after warranty period |
| 184 | Khas Kajora Colliery, Pit no. 5 (Schedule 4) |
| 185 | 1st year Comprehensive AMC charges after warranty period |
| 186 | 2nd year Comprehensive AMC charges after warranty period |
| 187 | 3rd year Comprehensive AMC charges after warranty period |
| 188 | 4th year Comprehensive AMC charges after warranty period |
| 189 | Kumardihi A Colliery,Pit no. 4 (Schedule 5) |
| 190 | 1st year Comprehensive AMC charges after warranty period |
| 191 | 2nd year Comprehensive AMC charges after warranty period |
| 192 | 3rd year Comprehensive AMC charges after warranty period |
| 193 | 4th year Comprehensive AMC charges after warranty period |
| 194 | Pandaveswar Colliery Pit No.B (Schedule 6) |
| 195 | 1st year Comprehensive AMC charges after warranty period |
| 196 | 2nd year Comprehensive AMC charges after warranty period |
| 197 | 3rd year Comprehensive AMC charges after warranty period |
| 198 | 4th year Comprehensive AMC charges after warranty period |
| 199 | Ningha Colliery, Pit no.4 & 5 (Schedule 7) |
| 200 | 1st year Comprehensive AMC charges after warranty period (for both pit no 4 & 5) |
| 201 | 2nd year Comprehensive AMC charges after warranty period (for both pit no 4 & 5) |
| 202 | 3rd year Comprehensive AMC charges after warranty period (for both pit no 4 & 5) |
| 203 | 4th year Comprehensive AMC charges after warranty period (for both pit no 4 & 5) |
AI Tender Summary
Tender Timeline
Tender Published
Tender notice published.
CompletedCorrigendum-1 Issued
Clarifications on tender conditions and amendments issued.
Upcoming · 5 daysBid Submission Deadline
Online submission via eProcurement portal.
Upcoming · 5 daysTender Documents
Download All (ZIP) ↓We takes all possible care for accurate & authentic tender information. However users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender