Tender For Rate Contract For Repair & Maintenance Works (Breakdown / Emergency Works And Planned Works) Pertaining To 400 Kv D/C Baglihar-Kishanpur Transmission Line Including Lilo Line.
Tender Value
Ref. Documents
Estimated cost
Bid Submission
07 Sep 2026
15 days left
EMD
1.60 Lakhs
Bank guarantee accepted
Document Fee
2000
Non-refundable
Tender Type
Online
Tender Overview
Organization
Tender ID
Competition Type
NCB
Bidding Type
Tender
Location / State
Ramban → Jammu and Kashmir
EMD Exemption
Not Available
Quantity
Not Available
Website
Contact Person
Address
Project Description
Tender for Rate Contract For Repair & Maintenance Works (Breakdown / Emergency Works And Planned Works) Pertaining To 400 Kv D/C Baglihar-Kishanpur Transmission Line Including Lilo Line.
BOQ
| Sl. No. | Item Description |
| 1 | Breakdown/Emergency works |
| 2 | Replacement of burnt/ damaged jumpers and tightening of remaining Jumpers on the same tower. |
| 3 | Replacement of damaged disc insulators of Tension string. |
| 4 | Replacement of damaged disc insulators of Suspension string. |
| 5 | Restoration of snapped power conductor. Complete job including mid-span compression joint, laying of conductor, rough sagging, tensioning of conductor dead-end assembly etc upto span of 500 meter tension to tension point. |
| 6 | Restoration of snapped earth wire Complete job including mid-span compression joint, laying of earth wire, rough sagging, tensioning of earth wire dead-end assembly etc up to span of 500 meter tension to tension point. |
| 7 | Removal of trees if dropped on the transmission line in case the fault occurred. |
| 8 | Repairing of damaged moose conductor by using helical sleeve or bolted or by shorting method without lowering the conductor. |
| 9 | Emergency tower top checking in case if the fault not located from ground. |
| 10 | Providing of stay wire to the towers for it strengthening. (Complete Job). |
| 11 | Erection of ERS tower including transportation, head loading, watch/ward of tower material incase of tower collapse of 400 KV D/C Baglihar Kishanpur transmission line (Complete Job). |
| 12 | De-stringing of 400KV D/C line conductor. |
| 13 | Dis-mantling of tower(Either Full or Partial) |
| 14 | ERS Material segregation & transportation including loading & unloading from store to site |
| 15 | Installation of ERS (Erection Including Anchoring Arrangement). |
| 16 | Installation of ERS (Base Plate Foundation as per Attached Drawing. |
| 17 | Backstay arrangement with Deadment (depth 2-2.5 mtr with wooden deadment, eye sling both side- 5-7 mtr, Anchor shackle- 5T). |
| 18 | Stringing of Single CKT with Twin Bundle Conductor including Jumper & Spacer Work. |
| 19 | Security for watch & ward of material at Site (6 security guard with 8 hr shift). (6*833) |
| 20 | Temporary Stay arrangement for Security Staff |
| 21 | Planned Works: |
| 22 | Checking and tightening of jumper including inserting/removal of temporary local earthing. (Complete Job). |
| 23 | Checking and tightening of vibration dampers (12 Nos. per circuit per tower) including inserting/removal of temporary local earthing. (Complete job). |
| 24 | Checking and tightening of corona rings (12 Nos. per circuit per tower) including inserting/removal of temporary local earthing. (Complete Job). |
| 25 | Replacement of damaged disc insulators of Tension string. |
| 26 | Replacement of damaged disc insulators of Suspension string. |
| 27 | Tightening of nuts and bolts of tower superstructures having tower weight from upto 20 tonnes. |
| 28 | Tightening of nuts and bolts of tower superstructures having tower weight more than 20 tonnes. |
| 29 | Replacement of damaged corona ring. |
| 30 | Replacement of Damaged or missing line spacers. |
| 31 | Fixing of anti-climbing device/Bird Guard over tower. |
| 32 | Checking and tightening of tower footing earthing bolt and measuring tower footing resistance. |
| 33 | Fixing of new vibration dampers on earthwire/ACSR moose conductor (including inserting/removal of temporary local earthing). |
| 34 | Replacement of damaged or missing tower members. |
| 35 | Branch cutting: Under the corridor of 400 KV D/C Baglihar Kishanpur transmission line 48 metre wide and under tower structure. Please Enable Macros to View BoQ information |
AI Tender Summary
Tender Timeline
Aug 10, 2026
11:30 IST
Tender Published
Tender notice published.
CompletedSep 07, 2026
17:00 IST
Bid Submission Deadline
Online submission via eProcurement portal.
Upcoming · 15 daysSep 08, 2026
Bid Opening Date
Technical bids will be opened and evaluated.
Upcoming · 16 daysTender Documents
Download All (ZIP) ↓
Disclaimer
We takes all possible care for accurate & authentic tender information. However users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender