Tender For Construction Of 12 Mtr. And 24 Mtr. Wide Internal Roads In Sector - 5, U/E, Sonipat Phase-I. Supplying And Laying Of Earth In Embankment, Preparation Of Sub-Grade, Providing And Laying Of 150 Mm Thick Gsb And Wmm, Priming Coat And 30 Mm Th
Tender Overview
Project Description
Tender for Construction Of 12 Mtr. And 24 Mtr. Wide Internal Roads In Sector - 5, U/E, Sonipat Phase-I. Supplying And Laying Of Earth In Embankment, Preparation Of Sub-Grade, Providing And Laying Of 150 Mm Thick Gsb And Wmm, Priming Coat And 30 Mm Thick Bc And 150 Mm Thick Gsb, 225 Mm Thick Wmm, Priming Coat, 50 Mm Thick Dbm And 30 Mm Thick Bc On 12 Mtr. And 24 Mtr. Wide Roads Respectively And Providing And Fixing Of Kerbs Etc. And All Other Works Contingent Thereto (Including Three-Years Maintenance And Defect Liability Period Free Of Cost)
BOQ
| Sl. No. | Item Description |
| 1 | [10.7]Providing and laying of conglomerate floor 50mm thick cement concrete topping 1:2:4 [Through Rate] |
| 2 | [11.5.1]12 mm cement plaster of mix : 1. 1:2 (1 cement: 2 fine sand) [Through Rate] |
| 3 | [11.52]Cement rendering on plaster 1 mm thick [Through Rate] |
| 4 | [17.15.2]Granular Sub-Base with Coarse Graded Material - Grading-I or II or III (Table:- 400-2) Construction of granular sub-base by providing coarse graded material, spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with Rotavator at OMC, and compacting with vibratory roller to achieve the desired density, complete as per clause 401.of MORTandH specifications 2. Grading II material [Through Rate] |
| 5 | [17.24]Wet Mix Macadam Providing, laying, spreading and compacting graded stone aggregate to wet mix macadam specification including premixing the Material with water at OMC in mechanical mix plant carriage of mixed Material by tipper to site, laying in uniform layers with paver in sub- base / base course on well prepared surface and compacting with vibratory roller to achieve the desired density as per technical clause 406 of MORT&H specifications [Through Rate] |
| 6 | [17.25.1]Prime Coat @ 0.85kg per sqm 1. Prime Coat @ 0.60kg per sqm Providing and applying primer coat with bitumen emulsion on prepared surface of granular Base including clearing of road surface and spraying primer at the rate of 0.60 kg/sqm using mechanical means as per technical clause 503 of MORT&H specifications [Through Rate] |
| 7 | [17.26.1]Tack Coat 1. Providing and applying tack coat with bitumen emulsion using emulsion pressure distributor at the rate of 0.25 kg per sqm on the prepared bituminous/granular surface cleaned with mechanical broom as per technical clause 503 of MORT&H specifications [Through Rate] |
| 8 | [17.26.2]Tack Coat 2. Providing and applying tack coat with penetration grade bitumen VG - 10 using bitumen pressure distributor at the rate of 0.30 kg per sqm on the prepared bituminous/ granular surface cleaned with mechanical broom as per technical clause 503 of MORT&H specifications [Through Rate] |
| 9 | [17.30.2]Dense Graded Bituminous Macadam with Batch Type HMP 2. Dense Graded Bituminous Macadam 50 mm to 75 mm thickness (Grading II) Providing and laying 50mm - 75 mm dense graded bituminous macadam with 100-120 TPH batch type HMP producing an average output of 75 tonnes per hour using crushed aggregates of specified grading, premixed with bituminous binder VG 30 @ 4.5% by weight of total mix and filler, transporting the hot mix to work site, laying with a hydrostatic paver finisher with sensor control to the required grade, level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction complete, as per technical clause No. 505 of MORT&H specifications Note-If bitumen required is more than 4.5% as per job mix formula, no extra payment will be paid. Extra bitumen required will be considered as incidental to work. [Through Rate] |
| 10 | [17.31.2]Bituminous Concrete with Batch type HMP 2. Bituminous Concrete 30 mm to 45 mm thickness (grading II) with 100-120 TPH batch type HMP Providing and laying 30mm - 45 mm bituminous concrete with 100-120 TPH batch type hot mix plant producing an average output of 75 tonnes per hour using crushed aggregates of specified grading, premixed with bituminous binder VG - 30 @ 5.4% per cent of mix and filler, transporting the hot mix to work site, laying with a hydrostatic paver finisher with sensor control to the required grade, level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction complete as per technical clause 507 of per MORTH specifications Note-If bitumen required is more than 5.4% as per job mix formula, no extra payment will be paid. Extra bitumen required will be considered as incidental to work. [Through Rate] |
| 11 | [17.5.3]Compacting Original Ground 3. Compaction of Earthwork Compaction of & preparation of sub grade including loosening, levelling of earth 225 mm thick top layer, rough dressing of soil, final dressing of earth to give level, camber, watering, rolling with road roller, compacting the bed to achieve minimum dry density as given in the Table 3000-2 as per technical clause 305 of MORT&H specifications [Through Rate] |
| 12 | [17.6]Construction of Embankment with Material obtained from Borrow pits NA Construction of Embankment CBR 8% (for new road/ raising/ berms/ etc.) with approved material obtained from borrow pits, including compensation of earth with all lead and lift transporting to site, spreading, grading to required slope and compacting to meet requirement of table 300-2, as per technical clause 305 of MORT&H specifications. [Through Rate] |
| 13 | [4.15.1]Excavation work by mechanical means (Hydraulic excavator)/ manual means in foundation trenches or drains (not exceeding 1.5m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift up to 1.5 m, including getting out the excavated soil and disposal of surplus excavated soils as directed, within a lead of 50 m. 1. Ordinary rock [Through Rate] |
| 14 | [6.1.5]Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work below plinth level and up to Floor IV level: 5. 1:3:6 (1 Cement : 3 coarse sand (zone-III): 6 graded stone aggregate 40 mm nominal size) [Through Rate] |
| 15 | [6.1.6]Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work below plinth level and up to Floor IV level: 6. 1:4:8 (1 Cement : 4 coarse sand (zone-III) : 8 graded stone aggregate 40 mm nominal size) [Through Rate] |
| 16 | [6.14.1]Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level : 1. 1:1.5:3 (1 cement : 1.5 coarse sand (zone-III): 3 graded stone aggregate 20 mm nominal size) [Through Rate] |
| 17 | [6.15.1]Reinforced cement concrete work in walls (any thickness), including attached pilasters, buttresses, plinth and string courses, fillets, columns, pillars, piers, abutments, posts and struts etc. above plinth level up to floor four level, excluding cost of centering, shuttering, finishing and reinforcement : 1. 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) : 3 graded stone aggregate 20 mm nominal size) [Through Rate] |
| 18 | [6.29.2]Centering and shuttering including strutting, propping etc. and removal of form work for : 2. Retaining walls, return walls, walls (any thickness) including attached pilasters, buttresses, plinth and string courses fillets, kerbs and steps etc. [Through Rate] |
| 19 | [6.30.3]Centering and shuttering including strutting, propping etc. and removal of form for 3. Suspended floors, roofs, landings, balconies and access platform [Through Rate] |
| 20 | [6.33.6]Steel reinforcement for R.C.C. work, where not included in the complete rate of RCC, including straightening, cutting, bending, placing in position, binding, wastage, overlaps, welded joints, spacer bars, chairs, stays, hangers and annealed steel wire etc. complete in all respect below plinth level Note: Reinforcement shall be measured in length including hooks, if any, separately for different diameters as actually used in work , excluding overlaps. Wastage, overlaps, couplings, welded joints, spacer bars, chairs, stays, hangers and annealed steel wire or other methods of binding & placing shall not be measured and cost of these items shall be deemed to be included in the rates for reinforcement. 6. Thermo-Mechanically Treated bars of grade Fe-500D or more [Through Rate] |
| 21 | [7.20.1]Brick work with common burnt clay modular bricks of class designation 10.5 in foundation and plinth in: 1. Cement mortar 1:4 (1 cement : 4 coarse sand) [Through Rate] Please Enable Macros to View BoQ information |
AI Tender Summary
Tender Timeline
Tender Published
Tender notice published.
CompletedBid Submission Deadline
Online submission via eProcurement portal.
Upcoming · 5 daysBid Opening Date
Technical bids will be opened and evaluated.
Upcoming · 7 daysTender Documents
Download All (ZIP) ↓We takes all possible care for accurate & authentic tender information. However users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender