Bids Are invited for Repair, Maintenance, And Installation Of Plant/ Systems/Equipments (Version 2) - Commercial; Electrical System Or Installation; As Per Boq - Carriage Of Following Material From Esc Store/Site To Site Of Work Through The Kacha And Pakka Road Including The Work Of Its Loading And Unloading At The Respective Ends In The Area Of Edd-Karhal, Mainpuri Including The Cost Of Arrangement Of Labour, T&P, Carrier Etc. Required For Proper Completion Of Work.(Distance 00-50 Kms.) , 9 /11 Mtr. Long St Poles. , 8.5 Mtr. Long Pcc Poles. , 11 Kv X-Arms,L Conductor, G.I Wire,Disc Insulators, Pin Insulators And Other Required Line Material, If Any. , Replacement Of Damaged 8.5 Mtr. Long Pcc Pole By Digging Of Pit And Dismantling Of All Accessories From The Existing / Damaged Pole And Erection Of Single New Pole Including Fitting All Accessories Including The Cost Of Labour, T&P Etc. Required For Proper Completion Of Work. , Replacement Of Damaged Double Pole Of 8.5 Meter Long Pcc Pole (First Opening Of All Accessories & Then Removing Damaged Poles), Re-Erecting D/P Including Fixing Of Disc Insulators With Fitting And Other 11 Kv Accessories As Per Respo Manual And As Per Direction Of Supervising Engineer, Including The Cost Of Arrangement Of Labour, T&P, Carrier Etc., Required For Proper Completion Of Work. , Replacement Of Damaged 9/11 Mtr. Long Stp By Digging Of Pits And Dismantling Of All Accessories From The Existing / Damaged Pole And Erection Of Single New Pole Including Fitting All Accessories Including The Cost Of Labour, T&P Etc. Required For Proper Completion Of Work. The Pole Shall Be Grouted In Cement Sand, Bricks Blast In Ratio 1:2:4 , Replacement Of Damaged Double Pole Of 9/11 Meter Long Stp Pole (First Opening Of All Accessories & Then Removing Damaged Poles), Re-Erecting D/P Including Fixing Of Disc Insulators With Fitting And Other 11 Kv Accessories As Per Respo Manual And As Per Direction Of Supervising Engineer, Including The Cost Of Arrangement Of Labour, T&P, Carrier Etc., Required For Proper Completion Of Work. , Straightening Of Tilted Single St Pole In The Existing Lines As Per Direction Of Supervising Engineer Including The Cost Of Arrangement Of Labour, T&P Carrier Etc. Required For Proper Completion Of Work. , Replacement Of Following Damaged Accessories In 11 Kv /Lt Line - , 11 Kv X-Arms Including Pin / Disc Insulators Complete. , 11 Kv Pin Insulators With Pin , 11 Kv Disc Insulator With Fitting , Erection And Grouting Of Stays As Per Respo Manual And As Per Direction Of Supervising Engineer Including The Cost Of Arrangement Of Labour, T&P, Carrier Etc. Required For Proper Completion Of Work. Grouting Material I.E. Cement, Sand, Brick Ballast/Stone Ballast Etc. Shall Be Arranged By The Contractor At His Own Cost. , Fixing Of Earthing Rod As Per Respo Manual And As Per Direction Of Supervising Engineer Including The Cost Of Arrangement Of Labour, T&P, Carrier Etc. Required For Proper Completion Of Work. , Replacement Of Following Ht/Lt Old Damaged By New Conductor Including Removal Of Damaged Conductor And Re-Stringing. , Acsr Weasal Conductor , Acsr Dog Conductor , Replacement Of Following 33 Kv Old Damaged Acsr Dog Conductor Including Removal Of Damaged Conductor And Re-Stringing. , Replacement Of Damaged Lt Ab Cable Of Following Sizes By Old & Used Ab Cable. , 11 Kv Ab Cable Of Size 3X50 Sqmm , 11 Kv Ab Cable Of Size 3X95 Sqmm , 11 Kv Ab Cable Of Size 3X120 Sqmm , Supply Of Following Decentralized Material , 11 Kv Cross Arm Cl With Nut And Bolts , Suspension Cl With Respected Material As Required , Dead End With Respected Material As Required , J Hook With Respected Material As Required , Lt Cl With Nut And Bolts , Received Back Of Alluminium Scrap And Other Material From Pit Site To Esc Store Mainpuri. As Per Norms.
BOQ
| Sl. No. | Item Title | Item Description |
| 1 | Carriage of following material from ESC Store/Site to site of work through the Kacha and Pakka road including the work of its loading and unloading at the respective ends in the area of EDD-KARHAL, MAINPURI including the cost of arrangement of labour, T&P, carrier etc. required for proper completion of work.(Distance 00-50 Kms.) | Carriage of following material from ESC Store/Site to site of work through the Kacha and Pakka road including the work of its loading and unloading at the respective ends in the area of EDD-KARHAL, MAINPURI including the cost of arrangement of labour, T&P, carrier etc. required for proper completion of work.(Distance 00-50 Kms.) |
| 2 | 9 /11 mtr. Long ST Poles. | 9 /11 mtr. Long ST Poles. |
| 3 | 8.5 Mtr. long PCC Poles. | 8.5 Mtr. long PCC Poles. |
| 4 | 11 KV X-Arms,l conductor, G.I wire,Disc Insulators, Pin insulators and other required line material, if any. | 11 KV X-Arms,l conductor, G.I wire,Disc Insulators, Pin insulators and other required line material, if any. |
| 5 | Replacement of damaged 8.5 Mtr. long PCC pole by digging of pit and dismantling of all accessories from the existing / damaged pole and erection of single new pole including fitting all accessories including the cost of labour, T&P etc. required for proper completion of work. | Replacement of damaged 8.5 Mtr. long PCC pole by digging of pit and dismantling of all accessories from the existing / damaged pole and erection of single new pole including fitting all accessories including the cost of labour, T&P etc. required for proper completion of work. |
| 6 | Replacement of damaged Double pole of 8.5 meter long PCC Pole (first opening of all accessories & then removing damaged poles), re-erecting D/P including fixing of Disc Insulators with fitting and other 11 KV accessories as per RESPO manual and as per direction of supervising engineer, including the cost of arrangement of labour, T&P, carrier etc., required for proper completion of work. | Replacement of damaged Double pole of 8.5 meter long PCC Pole (first opening of all accessories & then removing damaged poles), re-erecting D/P including fixing of Disc Insulators with fitting and other 11 KV accessories as per RESPO manual and as per direction of supervising engineer, including the cost of arrangement of labour, T&P, carrier etc., required for proper completion of work. |
| 7 | Replacement of damaged 9/11 Mtr. long STP by digging of pits and dismantling of all accessories from the existing / damaged pole and erection of single new pole including fitting all accessories including the cost of labour, T&P etc. required for proper completion of work. The pole shall be grouted in cement sand, bricks blast in ratio 1:2:4 | Replacement of damaged 9/11 Mtr. long STP by digging of pits and dismantling of all accessories from the existing / damaged pole and erection of single new pole including fitting all accessories including the cost of labour, T&P etc. required for proper completion of work. The pole shall be grouted in cement sand, bricks blast in ratio 1:2:4 |
| 8 | Replacement of damaged Double pole of 9/11 meter long STP Pole (first opening of all accessories & then removing damaged poles), re-erecting D/P including fixing of Disc Insulators with fitting and other 11 KV accessories as per RESPO manual and as per direction of supervising engineer, including the cost of arrangement of labour, T&P, carrier etc., required for proper completion of work. | Replacement of damaged Double pole of 9/11 meter long STP Pole (first opening of all accessories & then removing damaged poles), re-erecting D/P including fixing of Disc Insulators with fitting and other 11 KV accessories as per RESPO manual and as per direction of supervising engineer, including the cost of arrangement of labour, T&P, carrier etc., required for proper completion of work. |
| 9 | Straightening of tilted single ST Pole in the existing lines as per direction of supervising engineer including the cost of arrangement of labour, T&P carrier etc. required for proper completion of work. | Straightening of tilted single ST Pole in the existing lines as per direction of supervising engineer including the cost of arrangement of labour, T&P carrier etc. required for proper completion of work. |
| 10 | Replacement of following damaged accessories in 11 KV /LT line - | Replacement of following damaged accessories in 11 KV /LT line - |
| 11 | 11 KV X-Arms including pin / disc insulators complete. | 11 KV X-Arms including pin / disc insulators complete. |
| 12 | 11 KV Pin Insulators with pin | 11 KV Pin Insulators with pin |
| 13 | 11 KV Disc Insulator With Fitting | 11 KV Disc Insulator With Fitting |
| 14 | Erection and grouting of stays as per RESPO manual and as per direction of supervising engineer including the cost of arrangement of labour, T&P, carrier etc. required for proper completion of work. Grouting material i.e. cement, sand, brick ballast/stone ballast etc. shall be arranged by the contractor at his own cost. | Erection and grouting of stays as per RESPO manual and as per direction of supervising engineer including the cost of arrangement of labour, T&P, carrier etc. required for proper completion of work. Grouting material i.e. cement, sand, brick ballast/stone ballast etc. shall be arranged by the contractor at his own cost. |
| 15 | Fixing of earthing rod as per RESPO manual and as per direction of supervising engineer including the cost of arrangement of labour, T&P, carrier etc. required for proper completion of work. | Fixing of earthing rod as per RESPO manual and as per direction of supervising engineer including the cost of arrangement of labour, T&P, carrier etc. required for proper completion of work. |
| 16 | Replacement of following HT/LT old damaged by new conductor including removal of damaged conductor and re-stringing. | Replacement of following HT/LT old damaged by new conductor including removal of damaged conductor and re-stringing. |
| 17 | ACSR Weasal conductor | ACSR Weasal conductor |
| 18 | ACSR Dog conductor | ACSR Dog conductor |
| 19 | Replacement of following 33 KV old damaged ACSR Dog conductor including removal of damaged conductor and re-stringing. | Replacement of following 33 KV old damaged ACSR Dog conductor including removal of damaged conductor and re-stringing. |
| 20 | Replacement of damaged LT AB cable of following sizes by Old & Used AB cable. | Replacement of damaged LT AB cable of following sizes by Old & Used AB cable. |
| 21 | 11 KV AB cable of size 3x50 sqmm | 11 KV AB cable of size 3x50 sqmm |
| 22 | 11 KV AB cable of size 3x95 sqmm | 11 KV AB cable of size 3x95 sqmm |
| 23 | 11 KV AB cable of size 3x120 sqmm | 11 KV AB cable of size 3x120 sqmm |
| 24 | Supply of following Decentralized material | Supply of following Decentralized material |
| 25 | 11 KV Cross Arm Clamp with Nut and Bolts | 11 KV Cross Arm Clamp with Nut and Bolts |
| 26 | Suspension Clamp with respected material as required | Suspension Clamp with respected material as required |
| 27 | Dead End with respected material as required | Dead End with respected material as required |
| 28 | J Hook with respected material as required | J Hook with respected material as required |
| 29 | LT Clamp with Nut and Bolts | LT Clamp with Nut and Bolts |
| 30 | Received back of Alluminium Scrap and Other Material from Pit Site to ESC Store Mainpuri. As per Norms. | Received back of Alluminium Scrap and Other Material from Pit Site to ESC Store Mainpuri. As per Norms. |
AI Tender Summary
Tender Timeline
Tender Published
Tender notice published.
CompletedBid Submission Deadline
Online submission via eProcurement portal.
Upcoming · 9 daysBid Opening Date
Technical bids will be opened and evaluated.
Upcoming · 9 daysTender Documents
Download All (ZIP) ↓We takes all possible care for accurate & authentic tender information. However users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender