Tender For Shifting Of 250 Kva Sub-Station Along With Ht Network For Irrigation Department At Hamdania Colony, Bemina (Lis Bemina) Falling Under The Jurisdiction Of Esd Watalkadal, Ed-3Rd (Turnkey Basis)
Tender Overview
Project Description
Tender for Shifting Of 250 Kva Sub-Station Along With Ht Network For Irrigation Department At Hamdania Colony, Bemina (Lis Bemina) Falling Under The Jurisdiction Of Esd Watalkadal, Ed-3Rd (Turnkey Basis)
Corrigendum
| Sr No | Corrigendum Date | Corrigendum | Type | New Submission Date |
|---|---|---|---|---|
| 1 | 22-Aug-2026 | Extension Notice 1 | Date | 29-Aug-2026 |
BOQ
| Sl. No. | Item Description |
| 1 | Shifting of 250 KVA Sub-Station along with HT Network for Irrigation Department at Hamdania Colony, Bemina (LIS Bemina) |
| 2 | Supply, installation, testing and commissioning of S.T. poles 11.0 Meter long swaged Type conforming to ST 410 SP-56, IS: 2713 amended up-to date well finished and coated with black bituminous paint upto plant depth and Red-Oxide coated above ground level with earthing arrangement through bolt welded on pole, provided at height of 300mm above the planting depth which should be 1.5 mtr (SP 56). Top plate 3mm thick fully welded & bottom plate 35cm*35cm, 5mm thick fully welded. |
| 3 | Supply, installation, testing and commissioning of S.T. poles 9.0 Meter long swaged Type conforming to ST 410 SP-33, IS: 2713 amended up-to date well finished and coated with black bituminous paint upto plant depth and Red-Oxide coated above ground level with earthing arrangement through bolt welded on pole, provided at height of 300mm above the planting depth which should be 1.5 mtr (SP 33). Top plate 3mm thick fully welded & bottom plate 35cm*35cm, 5mm thick fully welded. |
| 4 | Supply, installation, testing and commissioning of Gapless Surge Arrestor, 9 KV, 10 KA, Lighting Arrestor Set Heavy duty with Polymer Housing, Station type conforming to IEC-99-4 Capable of withstanding Maximum continuous operating voltages (M.C.O.V) |
| 5 | Supply, installation, testing and commissioning of 11 KV Horn, Gap (fuse 3-phase 200A) as per Relevant IS. |
| 6 | Supply, installation, testing and commissioning of 11kV GO, AB Switch 3-Phase, 3-Pole, 200 Amp, Vertical Type conforming: IS-2544, IS: 5340 (Part-III) and SS: 9921 (Part-I -V) |
| 7 | Supply, fabrication, installation, testing and commissioning of G.I Channel X/V crossarm Iron / Angle Iron /Flat of sizes including Top Bracket, clamps and collars. (As per KPDCL approved drawing) |
| 8 | Supply, laying, installation, testing and commissioning of 300 mm² Single Core Cable,1.1kV Grade, Un-armoured, XLPE Insulated Stranded Conductor FRLS type including lugs/thimbles/clamps/cable ties. |
| 9 | Supply, Laying, installation, testing and commissioning of 30 mm² ACSR |
| 10 | Supply, Fixing, Testing and commissioning of 11kV Polymeric composite Disc Insulator 12kV,min failing load 45kN, Lighting Impulse 75kV Positive and 80kV Negative, creepage distance 320mm |
| 11 | Supply, Fixing, Testing and commissioning of 11kV Polymeric composite Pin Insulator 12kV, 5kN, Lighting Impulse 75kV Positive and 80kV Negative, creepage distance 320mm |
| 12 | Design, Fabrication, Supply, installation, testing and commissioning of LT Distribution Box for 250 kVA DTR with 02 no. 400 Amp MCCB 3P 36 KA (one MCCB for circuit & 1 no. Spare) |
| 13 | Providing and laying Earthing of substation --Excavation of earth pit of dia 650 mm & depth 3000 mm, installation of Earthing pipe of 40 mm Nominal bore & 4mm wall thickness & length 2.5 mtr long as Per IS 1239.GI Strip for neutral earthing of size 25 mm x 3 mm for connection of transformer body along with baby insulators, nuts/bolts, G.O Set & lighting arrestor as per IS 2629/85, GI nuts &bolts,refilled with earth enhancement materials and earth Chamber made of brick masonary with RCC slab cover. |
| 14 | Providing & Laying of Pole Earthing Complete by GI Pipe 40 mm 3 mtr longthrough GI Strip 25x3 mm |
| 15 | Supply & Fixing of Galvanized Nuts and Bolts |
| 16 | Supply & Fixing of Danger Plates with Clamps |
| 17 | Supply & FIxing of Anti-Climbing Device with Clamps |
| 18 | Providing and painting of poles with single coat of red oxide an two coats of Aluminum Paint |
| 19 | Supply & Fixing of PG Clamps/ Wedge connectors |
| 20 | Supply, installation, testing and commissioning of PVC Copper wire flexible multi-strand of required size for secondary connections for CT wiring the minimum wire size shall be 4 mm2 (RYB) and for PT wiring minimum wire size shall be 2.5 mm2 (RYB). |
| 21 | Supply and fixing of Copper Lugs preferably ring type duly crimped for termination of wires and tapes |
| 22 | Providing and fixing of Grounding bus of minimum 40mm copper, 25cm long fixed to the unit in HV chamber. The CTs, PT meter and 11 KV Cable sheath shall be grounded to the bus through grounding wire (green) of min size 10mm2. |
| 23 | Supply and fixing of Pedestal made out of G.I Channel of size 75 x 40 mm or angle iron of size (65 x 65 x 5) mm, duly painted as per site requirement for mounting of metering panel including concrete foundation wherever required including cost of nuts and bolts. |
| 24 | Supply and fixing of Independent flexible PVC pipes for CT wiring and PT wiring of appropriate size from HTcompartment to meter compartment |
| 25 | Supply, installation, testing and commissioning of 3 Core 11 kV Aluminium cable XLPE armoured 35 mm2 including cost of clamp for its fixing where ever required. |
| 26 | Supply, installation, testing and commissioning of Cable termination kits suitable for 3 x 35 mm2 XLPE Cable(indoor/outdoor) |
| 27 | Providing and laying of Earthing by way of 40 mm GI Pipe earthing for HT metering. Job includes , excavation, enhancement material and man Hole Chamber (500x450x600)mm with frame and cover. |
| 28 | Dismantling of 250 KVA Transformer from old site and re-erection of same at new place including transportation, carriage, loading, unloading & integration with system. |
| 29 | Dismantling of old ST Poles along with allied Material and shifting of same to divisional Stores including transportation, carriage, loading & unloading.Substation structure - 2 poles along with material |
| 30 | Dismantling & Re-erection of HT Meter along with allied Accessories (11 KV Pilfer resistant metering cubicle, Current Transformer, Potential Transformer, Busbars etc) including transportation, carriage, loading, unloading & integration with system. |
| 31 | Supply of material & Laying of Cement bottoming of poles (1:2:4 Mix as per REC Standards 0.66 M3 per Pole) |
| 32 | Supply of material & Laying of Cement bottoming of poles (1:2:4 Mix as per REC Standards 0.48 M3 per Pole) Please Enable Macros to View BoQ information |
AI Tender Summary
Tender Timeline
Tender Published
Tender notice published.
CompletedCorrigendum-1 Issued
Clarifications on tender conditions and amendments issued.
CompletedBid Submission Deadline
Online submission via eProcurement portal.
CompletedBid Opening Date
Technical bids will be opened and evaluated.
Upcoming · 1 dayTender Documents
Download All (ZIP) ↓We takes all possible care for accurate & authentic tender information. However users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender