Tender For special Repair To Roof Treatment Of Bldg No. P-1 (Main Hospital Bldg), P-14 ( Opd Complex), P-39 (Poly Clinic) And P-1, 2, 3 & 4 ( A To D Block Mns Mess) At Mh Jalandhar Cantt (Tender Id: 2026_Mes_782273_1)
Tender Overview
Project Description
Tender for special Repair To Roof Treatment Of Bldg No. P-1 (Main Hospital Bldg), P-14 ( Opd Complex), P-39 (Poly Clinic) And P-1, 2, 3 & 4 ( A To D Block Mns Mess) At Mh Jalandhar Cantt (Tender Id: 2026_Mes_782273_1)
Corrigendum
| Sr No | Corrigendum Date | Corrigendum | Type | New Submission Date |
|---|---|---|---|---|
| 1 | 28-Aug-2026 | CorrigendumNo02dated28Aug2026 | Date | 15-Sep-2026 |
| 2 | 15-Sep-2026 | Bid Auto Extn Corrigendum | Bid Auto Extn Corrigendum | 22-Sep-2026 |
| 3 | 17-Aug-2026 | CORRIGENDUM01DT17AUG2026 | Date | 08-Sep-2026 |
BOQ
| Sl. No. | Item Description |
| 1 | Note: Please refer Schedule 'A' Notes given on serial page No. 21 to 23 of tender documents. |
| 2 | Dismantling of brick tiles single layer as in roof covering complete all as specified and directed. |
| 3 | Demolition of mud phuska in roofs any thickness all as specified. Note:- The contractor will arrange the cables alignment on the roof while working, at his own cost and arrangement. |
| 4 | Preparing the surfaces with Wire brushing and cleaning top surface of cement concrete, including flashing and juction of parapets etc complete all as specified and directed. |
| 5 | Supply and applying polyurethane waterproofing coating on prepared concrete surface (top of prepared padding surface) of roof slab and upto 300 mm of parapets and crumple joint including junction of roof and parapet complete all as specified and directed. Comprissing of item are as under:- (i) Surface preparation of substrate including cleaning, crack filling and priming with FORSOC / Nitoproof WB primer and Equivalent.(ii) Application of FORSOC/Nitoproof 650 PU waterproofing membrane in two coats(iii) Application of FORSOC / Nitofoam 45 thermal insulation (80mm avg thickness 40 kg/mtr cub density) to maintain slop 1:40 in plan area.(iv) PUF insulation layer sealer coat (compatible with PU membrane)(v) Laying of 150-200 GSM geotextile layer with 150mm overlaps(vi) Laying of 25mm thick M-20 cement screed with slope 1:40 in plan area.(vii) Supply & Fixing of 300x300x8mm Endura-Johnson (or equivalent) cool roof tiles (SRI > 78) using Nitolite adhesive in plan area.Note:- All measurements for payment shall be only plan area. |
| 6 | Removal of mud/soil and retrieved material to a distance exc 5KM and thereof depositing where directed at a level not exc 1.5 mtr above the starting point complete all as specified and directed. Note:- The contractor will arrange disposal at his own cost and arrangement. |
| 7 | Taking down old GI tubing and connection including fittings 15mm bore pipe complete all as specified and directed. |
| 8 | Taking down old GI tubing and connection including fittings 20mm bore pipe complete all as specified and directed. |
| 9 | Taking down old GI tubing and connection including fittings 25mm bore pipe complete all as specified and directed. |
| 10 | Refixing old steel tubing 20 mm dia and connections in new or old position (Walls, ceiling, floors, etc) complete all as specified and directed. |
| 11 | Refixing old steel tubing 25 mm dia and connections in new or old position (Walls, ceiling, floors, etc.), complete all as specified and directed. |
| 12 | Supply and laying 20mm unplasticised PVC pipe of pressure rating 10 kgf/cm square laid in trenches and wall complete all as specified. |
| 13 | Supply and laying 25mm unplasticised PVC pipe of pressure rating 10 kgf/cm square laid in trenches and wall complete all as specified and directed. |
| 14 | Dismantling of water tanks any type of capacity exc 250 ltrs n exc 500 ltrs and removing to store complete all as specified and directed. |
| 15 | Dismantling of water tanks any type of capacity exc 500 ltrs n exc 1000 ltrs and removing to store complete all as specified and directed. |
| 16 | S&F 500 litre rotational moulded polyethylene water storage tank (cylindrical vertical with closed top) hoisted and fixed in position any description including necessary fittings complete all as specified and directed. |
| 17 | S&F 1000 Litre rotational moulded polyethylene water storage tank (cylindrical vertical with closed top) hoisted and fixed in position any description including necessary fittings complete all as specified and directed. |
| 18 | Supply and fixing 20mm gun metal globe or gate valve, with iron wheel head screwed both ends for iron pipe and fixed in repairs complete all as specified and directed. |
| 19 | S&F 20mm bore brass ball valve high pressure with epoxy coated aluminium rod & high density polythene float ball and fly nut screwed for iron pipe complete all as specified and directed. |
| 20 | Demolition of brick work built in cement mortar including all quoins, arches, pillars etc complete all as specified and directed. |
| 21 | M&L for Brick work with sub class ‘B’ brick, straight or curved on plan exc 6 m mean radius built in CM 1:6 complete all as specified and directed. |
| 22 | Taking down cement plaster on brick/stone masonary including raking out joints, hacking for scrubbing down with water etc complete all as specified and directed. |
| 23 | M&L for 15mm thick ready mix plaster with chicken wire mesh on brick work or concrete surfaces finished even and fair without using extra cement, height of the building upto fourth storey complete all specified and directed. |
| 24 | M&L for Preparation of new plastered surfaces of walls and applying two coats of cement base paint over priming complete all as specified and directed. |
| 25 | Taking down eaves gutters and rainwater pipes (any size or pattern), including all fittings,heads,shoes,bends,swan necks etc. including cleaning or refixing or removal to store complete all as specified and directed. |
| 26 | S&F 110 mm dia PVC (SWR) pipes Single socketed in any length with rubber rings joints fixed to walls, height of the bldg upto fourth storey complete all as specified and directed. |
| 27 | S&F 110 mm dia PVC (SWR) bends any radius complete all as specified and directed. |
| 28 | E/M WORKS |
| 29 | Demolition of Plain/Reinforced cement concrete of any description & in any position not otherwise specifically provided for complete all as specified and directed. |
| 30 | Dismantling of air termination single pointed aluminium rod 12mm dia, 300mm long without damage and kept in safe custody of MES Yard for re-use after roof treatment at same location complete all as specified and directed.. |
| 31 | Taking down aluminium strip 25x3.15mm from roof upto test point complete with saddles,screws and wooden rectangular block and kept in safe custody of MES Yard for re-use/demolition after roof treatment at same location complete all as specified and directed. |
| 32 | Re-fixing of air termination single pointed aluminium rod 12mm dia, 300mm long from MES Yard complete all as specified and directed. |
| 33 | Supplying and fixing in replacement of air termination single pointed aluminium rod 12mm dia, 300mm long complete all as specified and directed. |
| 34 | Re-fixing of aluminium strip 25x3.15mm complete with saddles,screws and wooden rectangular block of size 25x25x40mm for fixing as loop conductor etc complete all as specified and directed. |
| 35 | Supplying and fixing in replacement of aluminium strip 25x3.15mm complete with saddles,screws and wooden rectangular block of size 25x25x40mm for fixing as loop conductor etc complete all as specified and directed. |
| 36 | Material & Labour for PCC work (1:4:8) type D-2 using 40 mm graded stone aggregate of size 30cmx30cmx45cm including necessary form work and fair finish to exposed surfaces without using extra cement etc. complete all as specified and directed. |
| 37 | Material and labour for fixing of GI pipe light grade of 20mm dia complete all as specified and directed.Note : Civil work for fixing will be measured and paid in relevent item of schedule. |
| 38 | Taking down outdoor unit of Split Air conditioner from the roof of building along with all fixing accessories and re-fixing the same during removal of old brick and old mud phuska work within two hour for each unit along with all necessary electrical connection complete all as specified and directed. |
| 39 | Taking down outdoor unit of Split Air conditioner from the roof of building along with all fixing accessories and re-fixing the same during roof treatment after PCC work on roof and before roof treatment within two hour for each unit along with all necessary electrical connection complete all as specified and directed. Please Enable Macros to View BoQ information |
| 40 | Taking down outdoor unit of Split Air conditioner from the roof of building along with all fixing accessories and re-fixing the same during roof treatment after PCC work on roof and before roof treatment within two hour for each unit along with all necessary electrical connection complete all as specified and directed. Please Enable Macros to View BoQ information |
AI Tender Summary
Tender Timeline
Tender Published
Tender notice published.
CompletedCorrigendum-1 Issued
Clarifications on tender conditions and amendments issued.
CompletedCorrigendum-2 Issued
Clarifications on tender conditions and amendments issued.
Upcoming · 4 daysCorrigendum-3 Issued
Clarifications on tender conditions and amendments issued.
CompletedBid Submission Deadline
Online submission via eProcurement portal.
Upcoming · 4 daysBid Opening Date
Technical bids will be opened and evaluated.
Upcoming · 11 daysTender Documents