Tender For 1296 - Providing And Laying Dwc Pipe From Chawla Colony To Drain No. 6 Mc Sonipat
Tender Value
3.17 Lakhs
Estimated cost
Bid Submission
03 Aug 2026
2 days left
EMD
6350
Bank guarantee accepted
Document Fee
1000
Non-refundable
Tender Type
Online
Tender Overview
Organization
Tender ID
Competition Type
NCB
Bidding Type
Tender
Location / State
Sonipat → Haryana
EMD Exemption
Available
Quantity
Not Available
Website
Contact Person
Address
Project Description
Tender for 1296 - Providing And Laying Dwc Pipe From Chawla Colony To Drain No. 6 Mc Sonipat
BOQ
| Sl. No. | Item Description |
| 1 | [11.13.1]Cement plaster 1:3 (1 cement: 3 coarse sand) finished with a floating coat of neat cement. 1. 12 mm cement plaster [Through Rate] |
| 2 | [11.5.3]12 mm cement plaster of mix : 3. 1:4 (1 cement: 4 fine sand) [Through Rate] |
| 3 | [17.15.1]Granular Sub-Base with Coarse Graded Material - Grading-I or II or III (Table:- 400-2) Construction of granular sub-base by providing coarse graded material, spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with Rotavator at OMC, and compacting with vibratory roller to achieve the desired density, complete as per clause 401.of MORTandH specifications 1. Grading I material [Through Rate] |
| 4 | [21.93.1]Providing and fixing SFRC MANHOLE COVERS AND FRAMES MARKED WITH IS: 12592 including setting the same to correct lines and levels in 1:3 cement sand mortar over manhole including carriage loading unloading stacking handling re-handling etc. complete in all respects to the satisfaction to the Engineer-in-charge. 1. Type:- Extra Heavy Duty Set (EHD-35) 560MM Clear Opening [Through Rate] |
| 5 | [22.198.1]Providing M.S. foot rests including fixing in manholes with 20x20x10 cm cement concrete blocks 1:3:6 (1 cement : 3 coarse sand : 6 graded stone aggregate 20 mm nominal size) as per standard design : 1. With 20x20 mm square bar [Through Rate] |
| 6 | [22.218.2]Providing and Supplying of class SN 8 structured wall Polyethylene Piping system (Pipe with online/ offline coupler and elastomeric sealing ring) with non smooth external annular corrugated and smooth internal surface (double wall) for non-pressure underground sewerage and drainage application as confirm to IS 16098 (part II):2013 including transportation, frieght charges, inspection charges, loading, unloading, complete as specified and directed by Engineer In-Charge. 2. 300 mm Internal Diameter [Through Rate] |
| 7 | [22.219.2]Lowering, Laying and jointing of class SN 8 structured wall (External Annular Corrugated and Smooth Internal Surface Polyethylene Piping and fitting with the help of coupler(online/ offline) attached with one end of pipes, sliding over the elastomeric sealing rubber ring placed on the specified valley of the corrugation at the spigot end, lowering the same into the trench, laying on the lower bedding (constructed at bottom of trenches) at prescribed gradient, depth and alignment, testing the water tightness of the joints, ensuring the continuity tests of specified pipe segment etc. complete as per drawing, specification and detailed engineering, including cartage of pipes and fitting etc. as per direction of Engineer-in-charge. 2. 300 mm Internal Diameter [Through Rate] |
| 8 | [4.14.1]Earth work in excavation by mechanical means (Hydraulic excavator) / manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift up to 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m. 1. All kinds of soil. [Through Rate] |
| 9 | [4.16.1.2]Excavating trenches of required width and depth for pipes, cables, etc including excavation for sockets, and dressing of sides, ramming of bottoms, including getting out the excavated soil, and then returning the soil as required, in layers not exceeding 20 cm in depth, including consolidating each deposited layer by ramming, watering, etc. and disposing of surplus excavated soil as directed, within a lead of 50 m. 1.2. All kind of soil Pipes, cables etc, exceeding 80 mm dia but not exceeding 300 mm dia. [Through Rate] |
| 10 | [4.17]Extra for excavating trenches for pipes, cables etc. in all kinds of soil for depth exceeding 1.5 m, but not exceeding 3 m. (Rate is over corresponding basic item for depth up to 1.5 metre). [Through Rate] |
| 11 | [4.31.1]Extra for every additional lift of 1.5 m or part thereof in excavation / banking excavated or stacked materials. 1. All kinds of soil [Through Rate] |
| 12 | [4.32]Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundations etc. in layers not exceeding 20cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift up to 1.5 m. [Through Rate] |
| 13 | [6.1.1]Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work below plinth level and up to Floor IV level: 1. 1:1½:3 (1 Cement: 1½ coarse sand (zone-III) : 3 graded stone aggregate 20 mm nominal size) [Through Rate] |
| 14 | [6.1.7]Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work below plinth level and up to Floor IV level: 7. 1:5:10 (1 cement : 5 coarse sand (zone-III): 10 graded stone aggregate 40 mm nominal size) [Through Rate] |
| 15 | [6.34.6]Steel reinforcement for R.C.C. work, where not included in the complete rate of RCC, including straightening, cutting, bending, placing in position, binding, wastage, overlaps, welded joints, spacer bars, chairs, stays, hangers and annealed steel wire etc. complete in all respect above plinth level Note:- Reinforcement shall be measured in length including hooks, if any, separately for different diameters as actually used in work , excluding overlaps. Wastage, overlaps, couplings, welded joints, spacer bars, chairs, stays, hangers and annealed steel wire or other methods of binding & placing shall not be measured and cost of these items shall be deemed to be included in the rates for reinforcement. 6. Thermo-Mechanically Treated bars of grade Fe-500D or more. [Through Rate] |
| 16 | [7.20.1]Brick work with common burnt clay modular bricks of class designation 10.5 in foundation and plinth in: 1. Cement mortar 1:4 (1 cement : 4 coarse sand) [Through Rate] Please Enable Macros to View BoQ information |
AI Tender Summary
Tender Timeline
Jul 27, 2026
11:30 IST
Tender Published
Tender notice published.
CompletedAug 03, 2026
17:00 IST
Bid Submission Deadline
Online submission via eProcurement portal.
Upcoming · 2 daysAug 03, 2026
Bid Opening Date
Technical bids will be opened and evaluated.
Upcoming · 2 daysTender Documents
Download All (ZIP) ↓
Disclaimer
We takes all possible care for accurate & authentic tender information. However users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender