Tender For Augmentation/Segregation Of 11 Kv Feeders To Overcome Lcp Constraints For Various Divisions Of Kpdcl Falling Under The Jurisdiction Of P&Ao, Kpdcl Sopore.(Augmentation Of Bsf Feeder {Phase 1, From Rs Ajar To Evergreen Heath Centre})
Tender Overview
Project Description
Tender for Augmentation/Segregation Of 11 Kv Feeders To Overcome Lcp Constraints For Various Divisions Of Kpdcl Falling Under The Jurisdiction Of P&Ao, Kpdcl Sopore.(Augmentation Of Bsf Feeder {Phase 1, From Rs Ajar To Evergreen Heath Centre})
BOQ
| Sl. No. | Item Description |
| 1 | SITC/ITC of below mentioned items |
| 2 | 13 Mtr. Long Pole (ST-410 SP 69) |
| 3 | GI V cross-arm / side cross arm with top Bracket including clamp including back clamps(For 33kV and 11kV as per site requirement) |
| 4 | Shifting of 150 mm² ACSR Conductor from existing 33kV line poles to new poles(Existing 33kv Line) |
| 5 | Dismantling and reerection (Shifting) of Existing 30/50/100 mm² ACSR Conductor from existing poles/feeder to new poles(Town II, Muslimabad & Arin Feeder) |
| 6 | 50 mm² ACSR Conductor |
| 7 | PG Clamps for 50/150 mm² ACSR Conductor |
| 8 | 33kV Polymeric composite Pin Insulator 36kV, 10kN, Lighting Impulse 170kV Positive and 180kV Negative, creepage distance 900mm |
| 9 | 33 kV Polymeric composite Disc Insulator as per standard |
| 10 | 11kV Polymeric composite Pin Insulator 12kV, 5kN, Lighting Impulse 75kV Positive and 80kV Negative, creepage distance 320mm |
| 11 | 11kV Polymeric composite Disc Insulator 12kV,min failing load 45kN, Lighting Impulse 75kV Positive and 80kV Negative, creepage distance 320mm |
| 12 | Galvanized Nuts and Bolts |
| 13 | Danger Plates with Clamps |
| 14 | Anti-Climbing Device with Clamps |
| 15 | Earthing Complete by GI Pipe 40 mm 3 mtr long/ 25mm through GI Strip 25x3 mm |
| 16 | Painting of Poles with Red Oxide and Aluminium Paint |
| 17 | Cement bottoming 1:2:4 mix as per Standards |
| 18 | 11 kV Isolator, Double Break,3-pole, 630Amp, horizontal mounting Type, with Earth Switch. |
| 19 | Dismantling of Existing poles along with accessories and their transportation to Divisional Stores at Ajar/STD Sub Stores Ajar (for 33kV poles/accessories) |
| 20 | Dismantling of Existing ACSR and its transportation to Divisional Stores at ajar |
| 21 | Dismantling and re-erection (Shifting) of SMDBs and metres from existing poles to new poles |
| 22 | Dismantling and re-erection (Shifting) of LT AB Cable along with accessories from existing poles to new poles |
| 23 | Sundry items like Aluminium lugs, Jumpers, Binding Tape,metre/smdb clamps, insulating piercing connectors etc |
| 24 | 70 mm² AB Cable (3x70+1x16+1x50) mm² XLPE (1.1kV, 3+1 C, Al) |
| 25 | Bidders Note 1: Bidders are advised to acquaint themselves thoroughly with the site and its surroundings prior to submitting their bids. This includes careful assessment of the terrain, location, accessibility, connectivity, availability of local resources, and prevailing environmental or climatic conditions. It shall be deemed that bidders have inspected the site and obtained all necessary information relevant to the execution of the work. Any failure to do so will not relieve them of their responsibility, and no claim on account of lack of knowledge or misapprehension of site conditions shall be entertained. |
| 26 | Bidders Note 2:The work is to be executed within a highly congested electrical network comprising one 33 kV line and four 11 kV feeders. Execution of the work shall require shutdowns of the feeders, which can be availed only once a week. Bidders shall plan their resources and execution schedule accordingly. No claim on account of delay due to non-availability of additional shutdowns shall be entertained. |
| 27 | Bidders Note 3: The work is to be executed along the busy Bandipora–Gurez Road. As closure of the road is not permissible, the contractor shall execute the work during lean traffic hours, preferably in the early morning, while ensuring adequate traffic management and public safety. |
| 28 | Bidders Note 4: The dismantling of the existing 11 kV/LT AB Cable and erection of the new 11 kV/LT AB Cable shall be carried out in a synchronized manner to minimize disruption to the power supply and ensure public safety. |
| 29 | Bidders Note 5: Considering the congested nature of the work site and limited working space, the contractor may be required to deploy a suitable crane or other lifting equipment for safe and efficient erection of poles. Please Enable Macros to View BoQ information |
AI Tender Summary
Tender Timeline
Tender Published
Tender notice published.
CompletedBid Submission Deadline
Online submission via eProcurement portal.
Upcoming · 19 daysBid Opening Date
Technical bids will be opened and evaluated.
Upcoming · 19 daysTender Documents
Download All (ZIP) ↓We takes all possible care for accurate & authentic tender information. However users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender