Work Related To Providing Electricity Connections And Electrification Under The Mla Fund Within The Electricity Distribution Division, Robertsganj, On A Year-Round Basis Via A Running Tender. (Semi-Turnkey)
Tender Overview
Project Description
Work Related To Providing Electricity Connections And Electrification Under The Mla Fund Within The Electricity Distribution Division, Robertsganj, On A Year-Round Basis Via A Running Tender. (Semi-Turnkey)- 1 Centralized Materials,Loading Unloading & Safe Cartage And Errection Of New Stp/Pcc Poles And Other Materials From Electricity Store Center, Robertsganj To The Work Place And Proper Stocking. (Distance Up To 50 Km.) 2 Pcc Pole 8.5 Mtr 3 11 Kv V-Type X-Arm 4 Top Channel Ms 100X50X2240 Mm. Long 5 Acsr Weasel Conductor 6 Stay Complete 7 10 Kva T/F 8 25 Kva T/F 9 63 Kva T/F 10 Dropper Channel Ms 100X50X2000 Mm 11 Lt Ab Cable 1X25+1X16 Sq Mm 12 11 Kv T-Off Channel 13 S/S Base Angle 14 Earthing Complete 15 De-Centralized Materials, Provided Contractor 16 11 Kv Polymeric Pin Insulator With Pin 17 11 Kv Polymeric Disc Insulator With Fitting 18 Top, T-Off Dropper Clamp With Nut Bolt 19 Cross Arm Holding Clamp 20 Pg Clamp 21 Lt Shackle Insulator 22 Lt Shackle Insulator For Clamp Nut & Bolt 23 I Hook With Dead End Clamp 24 I Hook With Suspenstion Clamp 25 F- Clamp 26 Nut & Bolt Washear 27 Stone Pad 28 Clamp For T/F 29 Clamp With Nut & Bolt 30 Work Of Following Materials As Per Resspo/Puvvnl Norms At The Work Site. 31 Erection Of Single Support St/Pcc Pole For Construction Of 11 Kv Line Including Digging Of Pit, Fitting Of All Accessories, Back Filling Of Earth & Others Required Work. 32 Grouting Of Pole With 1:4:8 Ratio Of Cement Sand & Brick Ballast As Per Resspo Norms. (Cement Sand & Brick Ballast Wil Be Supplied By The Constractor On His Own His Own Cost) 33 Grouting Of Stay With 1:4:8 Ratio Of Cement Sand & Brick Ballast As Per Resspo Norms. (Cement Sand & Brick Ballast Wil Be Supplied By The Constractor On His Own His Own Cost) 34 Earthing Complete 35 Stringing & Sagging Of 3 Phase 11 Kv Line Upto Proper Sag Including Laying Of Weasel Al Conductor, Binding With Insulators & Jumpering.
BOQ
| Sl. No. | Item Description |
| 1 | CENTRALIZED MATERIALS,Loading unloading & safe cartage and errection of new STP/PCC Poles and other materials from Electricity store center, Robertsganj to the work place and proper stocking. (Distance up to 50 Km.) |
| 2 | PCC Pole 8.5 Mtr |
| 3 | 11 KV V-type X-Arm |
| 4 | Top Channel MS 100x50x2240 MM. Long |
| 5 | ACSR Weasel Conductor |
| 6 | Stay Complete |
| 7 | 10 KVA T/F |
| 8 | 25 KVA T/F |
| 9 | 63 KVA T/F |
| 10 | Dropper Channel MS 100x50x2000 MM |
| 11 | LT AB Cable 1x25+1x16 SQ MM |
| 12 | 11 KV T-off Channel |
| 13 | S/S Base Angle |
| 14 | Earthing Complete |
| 15 | DE-CENTRALIZED MATERIALS, Provided Contractor |
| 16 | 11 KV Polymeric Pin Insulator with Pin |
| 17 | 11 KV Polymeric Disc Insulator with Fitting |
| 18 | Top, T-off Dropper Clamp with Nut Bolt |
| 19 | Cross Arm Holding Clamp |
| 20 | PG Clamp |
| 21 | LT Shackle Insulator |
| 22 | LT Shackle Insulator for Clamp Nut & Bolt |
| 23 | I Hook With Dead End Clamp |
| 24 | I Hook With Suspenstion Clamp |
| 25 | F- Clamp |
| 26 | Nut & Bolt Washear |
| 27 | Stone Pad |
| 28 | Clamp for T/F |
| 29 | Clamp with Nut & Bolt |
| 30 | Work of following materials as Per RESSPO/PuVVNL norms at the work site. |
| 31 | Erection of single support ST/PCC pole for construction of 11 KV line including digging of pit, fitting of all accessories, back filling of earth & others required work. |
| 32 | Grouting of pole with 1:4:8 ratio of cement sand & brick ballast as per RESSPO norms. (cement sand & brick ballast wil be supplied by the constractor on his own his own cost) |
| 33 | Grouting of stay with 1:4:8 ratio of cement sand & brick ballast as per RESSPO norms. (cement sand & brick ballast wil be supplied by the constractor on his own his own cost) |
| 34 | Earthing Complete |
| 35 | Stringing & sagging of 3 phase 11 KV line upto proper sag including laying of WEASEL AL Conductor, binding with insulators & jumpering. |
| 36 | 10 KVA T/F |
| 37 | 25 KVA T/F |
| 38 | 63 KVA T/F |
| 39 | LT AB Cable 1x25+1x16 SQ MM Please Enable Macros to View BoQ information |
AI Tender Summary
Tender Timeline
Tender Published
Tender notice published.
CompletedBid Submission Deadline
Online submission via eProcurement portal.
Upcoming · 8 daysBid Opening Date
Technical bids will be opened and evaluated.
Upcoming · 9 daysTender Documents
Download All (ZIP) ↓We takes all possible care for accurate & authentic tender information. However users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender