Tender For Construction Of 11 Kv Dedicated Feeder From Nimakhandi Pss To Idco Barapalli Msme Park Under Lochhapada Electrical Section , Berh Ur.
Tender Value
2.22 Crore
Estimated cost
Bid Submission
06 Aug 2026
4 days left
EMD
2.22 Lakhs
Bank guarantee accepted
Document Fee
11800
Non-refundable
Tender Type
Online
Tender Overview
Organization
Tender ID
Competition Type
NCB
Bidding Type
Tender
Location / State
Ganjam → Odisha
EMD Exemption
Available
Quantity
Not Available
Website
Contact Person
Address
Project Description
Tender for Construction Of 11 Kv Dedicated Feeder From Nimakhandi Pss To Idco Barapalli Msme Park Under Lochhapada Electrical Section , Berh Ur.
BOQ
| Sl. No. | Item Description |
| 1 | Cost of Matterial for Construction of 11 KV line with 3C X 300 Sqmm XLPE U.G cable - a) 35 Mtr from Nimakhandi D.P to Proposed RMU in the existing PSS trench b) 15 Mtr from proposed RMU to existing Borigoan D.P in the existing PSS trench c) 25 Mtr from proposed RMU to proposed D.P. of IDCO with new trench construction d) 0.5 Km with spare in HDD method as per drawing. |
| 2 | SITC of 3C x 300 sqmm 11 KV XLPE cable (Armoured),A2XWaY-FRLSH. complete as required & as per approved technical specification & direction of EIC. |
| 3 | SITC of HDPE pipe, 8'' (Spec PE80-PN8,160mm dia). complete as required & as per approved technical specification & direction of EIC. |
| 4 | SITC of Heat Shrinkable jointing kit for 3Cx300 mm sq. 11KV XLPE Cable (Outdoor type). complete as required & as per approved technical specification & direction of EIC. |
| 5 | SITC of Heat shrinkable jointing kit for 3Cx300 Sq mm 11 KV XLPE Cable(indoor type). complete as required & as per approved technical specification & direction of EIC. |
| 6 | SITC of Heat shrinkable jointing kit for 3Cx300 Sq mm 11 KV XLPE Cable(straight type). complete as required & as per approved technical specification & direction of EIC. |
| 7 | Supply & installation of Clamp for pipe. complete as required & as per approved technical specification & direction of EIC. |
| 8 | SITC of Lightning Arrester(12KV,10KA) Station Class. complete as required & as per approved technical specification & direction of EIC. |
| 9 | Supply (of all reqd. Materials ) ,Erection, testing & commissioning of pipe earth electrode made out of 40 mm dia class-B G.I Pipe of 2.5 mtr. Long (02 nos for LA,04 nos for UG cable) with arrangements for fitting and termination of G.I Flat (25x6) mm 1.2 kg/Mtr including cost for Provide necessary civil material for construction of Earthing chamber, excavation & installation of earthingpipe dia up to 100mm dia for length of 3Mtr.Scope also includes necessary nutbolt, 25 Kg Bentonide Power, connection & welding with incoming earth flat. The work to be executed as per standard drawing & design. complete as per approved technical specification and direction of E.I.C. |
| 10 | Supply & fixing of G.I Nut, Bolt & Washers of assorted size. complete in all respect as per approved technical specification and direction of E.I.C. |
| 11 | Sundries complete as required & as per direction of EIC. |
| 12 | Cost of Civil work |
| 13 | Excavation of cable trench length (3 mtr W X 3 mtr D) by providing all necessary tool, Manpower, pump etc suitable for HT & LT Cable laying. Scope also includes supply of neccessry barricades at the excavation site.complete as per direction of EIC. |
| 14 | Provide all necessary Manpowet, Tool, Tackles, Barricades, Dewatering pump, Gunny bags,Compressor for excavation (3 mtr W X 3 mtr D in Hard Surface.complete as per direction of EIC. |
| 15 | Back fill the cable excvation site with same earth (3 mtr W X 3 mtr D). Scope also includes provide of necessary Tools, Machinery & Manpower for the activity. complete as per direction of EIC. |
| 16 | Supply all materials required for backfilling and has to carry out the job of backfilling with sand, as per DISCOM Standards.complete as per direction of EIC. |
| 17 | Supply & Laying/ Mounting and fixing of HDPE Pipe -160mm Dia (PN-8,Grade PE- 80)and sealing of the same for LT / HT Cables. Scope also includes providing and laying all required consumable etc. for collar fixing and sealing of Pipe. (Excavation is excluded).complete as per direction of EIC. |
| 18 | Supply & Laying of PIPE HDPE 160 MM DIA PN8 , PE 80 through HDD method Scope of work also includes making Trenchless ducts with 160 mm Dia HDPE pipe casing using HDD machine including supply of HDPE pipe as per 1S 4984, (Providing parabolic graph included in the scope). complete as per direction of EIC. |
| 19 | PCC (1:3:6(M-10 Grade)) below trench (Length 2100 mm, width 1000mm, thickness 75mmn throughout). complete as per direction of EIC. |
| 20 | Brick work Both Sides(2.1 mtr. L X 0.19 mtr W X 0.5 mtr D) with F.P.S. bricks of class designation 75mm in Cement mortar 1:4 (1 Cement : 4 Coarse sand) as per standard specifcation, Scope includes supply of all material. complete as per direction of EIC. |
| 21 | 15 mm cement plaster, All Sides (2.13+0.21 mtr. L X 0.5 mtr W) on the rough side of single brick wall of mix -1:4 (1 Cement:4 Fine sand (50 % fine :50% coarse)) as per standard specification. Scope includes supply of all materia. complete as per direction of EIC. |
| 22 | Supply end erection of material for RCC partition slab 800mrnX250mmX75mmn (M-25 grade)- 9 Nos. with supply of all civil material (Cement, Sand & 10 to 12mm stone aggregate). with 8mm dia R/f cutting & bending etc.complete as per direction of EIC. |
| 23 | PCC (1:3:6(M-10 Grade)) below trench (Length 2800 mm, width 2800mm, thickness 75mm throughout).complete as per direction of EIC. |
| 24 | Brick work Both Sides(2.8 mtr, L X 0.19 mtr W X 0.5 mtr D) with F.P.S, bricks of class designation 75mm in Cement mortar 1:4 (1Cement:4 Coarse sand) as per standard specifcation. Scope includes supply of all material.complete as per direction of EIC. |
| 25 | 15 mm cement plaster, All Sides (2.83+0.21 mtr, L X 0.5 mtr W) on the rough side of single brick wall of mix -1:4 (1 Cement : 4 Fine sand (50 % fine : 50% coarse)) as per standard specification. Scope includes supply of all material.complete as per direction of EIC. |
| 26 | Supply and erection of material for RCC partition slab 800mmX250mmX75mm (M-25 grade)- 12 Nos, with supply of all civil material (Cement, Sand & 10 to 12mm stone aggregate), with 8mm dia R/f cutting & bending etc.complete as per direction of EIC. |
| 27 | Supply and Installation of cable Route marker including transportation from site/ tent, excavation, refilling, disposing of malba, flooding with waler, ramming/compacting of foundation as per standard specifications and drawing. complete as per direction of EIC. |
| 28 | Survey of incremental/ delta network and asset changes of 11KV network and updation in GESW databas.complete as per direction of EIC. |
| 29 | Cost of Material for Construction of New 11KV line(with 100mm2 AAAC)using 11Mtr WPB pole=4.0 ckm,cut point =15nos(04 nos 90 degr.and 11 nos 180 degr.) New 11KV line(with 100mm2 cover conductor)using 13Mtr WPB pole =2.11 ckm,cantilever arrangement for 55nos of pole (Near Borigam and Jagannathpur village), Line crossing Guarding-10,cut point=20nos(05 nos degr.and 15 nos 180 degr.) |
| 30 | Supply ( of all reqd. Materials ), Erection, testing & commissioning of 11mtrs long WPB (160 x 152mm) (30.44 KG/Mtr) Pole with base plate 300x300x12 and Excavation of pole pit in all kind of soil and rock up to a depth of 1.8 mtr from ground level & installation with mass Concreting of poles in ratio 1:1.5:3 (500mmX500mm X1500mm) = 0.375Cu.mtr & couping of poles in ratio 1:1.5:3 (500X500X450)= 0.1125 Cu mtr with necessary curing.complete in all respect as per approved technical specification & direction of EIC. |
| 31 | Supply ( of all reqd. Materials ), Erection, testing & commissioning of 13mtrs long WPB (160 x 152mm) (30.44 KG/Mtr) Pole with base plate 300x300x12 (Including 11 nos of line crossing) and Excavation of pole pit in all kind of soil and rock up to a depth of 1/6 th mtr of hight of the pole from ground level & installation with mass Concreting of poles in ratio 1:1.5:3 (500mmX500mm X2000mm) = 0.5Cu.mtr & couping of poles in ratio 1:1.5:3 (500X500X450)= 0.1125 Cu mtr with necessary curing.complete in all respect as per approved technical specification & direction of EIC. |
| 32 | Supply, fabrication, Erection, testing & commissioning of GI structural Members : a)-100x50x6 mm GI channel for straight Cross arm 1.2 mtr each 2 nos & 0.2 mtr long 2 Nos for 1 Nos cut Point .b)- 100x50x6 mm GI channel for straight Cross arm 1.2 mtr (9.2 KG/mtr) for pin point.c)-100x50x6 mm GI channel for straight Cross arm 1,5 mtr @ (9.2 KG/mt) for cut point.d)-Angle for supporting (50X50X6) mm 2mtr (45 Kg:/Mtr.) for pin point.e)- Angle for supporting (50X50X6) mm 2mtr (4.5 Kg./Mtr.) cut point . f)- Fish Plate 50x6mm, 2.36Kg/ Mtr, each 0.280Mtr Length Complete in all respect as per approved technical specification & direction of EIC. |
| 33 | Supply & installation of 11KV GI V-Cross arm(10.2KG each) with G.I Back Clamp for V cross arm(0.85 KG each). complete as required & as per approved technical specification & direction of EIC. |
| 34 | Supply & installation of 11KV GI F-Clamp(2.9KG). complete as required & as per approved technical specification & direction of EIC. |
| 35 | Supply & Stringing of 100 mm² AAAC conductor. complete as required & as per approved technical specification & direction of EIC. |
| 36 | Supply & installation of PG Clamp for 100 mm2 conductor. complete as required & as per approved technical specification & direction of EIC |
| 37 | Supply & Stringing of 11KV XLPE COVERED CONDUCTOR 100 SQMM,AAA. complete as required & as per approved technical specification & direction of EIC |
| 38 | Supply & installation of Ties for 11KV (For covered conductor). complete as required & as per approved technical specification & direction of EIC |
| 39 | Supply & installation of IPC for 100 sq.mm AAA conductor (For covered conductor). complete as required & as per approved technical specification & direction of EIC |
| 40 | Supply & installation of Tension Assembly Wedge Type with Anchoring Clamp for 11 kV covered conductor. complete as required & as per approved technical specification & direction of EIC |
| 41 | Supply & installation of Jointing Kit End Termination for 11KV 100 Sqmm AAA Covered Conductor. complete as required & as per approved technical specification & direction of EIC |
| 42 | Supply & installation of Bird Cap Guarding. complete as required & as per approved technical specification & direction of EIC |
| 43 | Supply & installation of 11KV Pin Insulator(POLYMER). complete as required & as per approved technical specification & direction of EIC. |
| 44 | Supply & installation of 11 KV Disc Insulator B & S Type 45 KN POLYMER. complete as required & as per approved technical specification & direction of EIC. |
| 45 | Supply & installation of 11 KV hard ware fitting B & S Type 45KN. complete as required & as per approved technical specification & direction of EIC. |
| 46 | Supply & fixing of G.I Nut, Bolt & Washers of assorted size. complete in all respect as per approved technical specification and direction of E.I.C. |
| 47 | Supply & installation of Earthing of support (coil type). complete as required & as per approved technical specification & direction of EIC. |
| 48 | Supply & installation of No-8 GI wire (Dia 4.6mm) 0.131 KG/ Mtr. complete as required & as per approved technical specification & direction of EIC. |
| 49 | SITC of Anticlimbing Device using GI barbed wire (3kg per support) with Back Clamp (25X3 mm GI flat, 0.59Kg/Mtr. Flat of 0.510mtr length 4 no's = (4x0.59x0.510)). complete in all respect as per approved technical specification and direction of E.I.C. |
| 50 | Supply and installation of Danger Board using GI Back clamp (Pole-clamp) made of 25x3 mm flat flat, 0.59Kg/Mtr. Flat of 0.510mtr length 2 no's = (2x0.59x0.510). complete in all respect as per approved technical specification and direction of E.I.C. |
| 51 | Supply & installation of 100X50X6mm. GI Channel for straight cross arm (1.8 m X 4 pcs) for Guarding. complete as required & as per approved technical specification & direction of EIC. |
| 52 | Supply & installation of EYE hook for Guarding. complete as required & as per approved technical specification & direction of EIC. |
| 53 | Supply (of all reqd. Materials ) ,Erection, testing & commissioning of pipe earth electrode made out of 40 mm dia G.I Pipe of 3 mtr. Long with arrangements at both end of guarding for fitting and termination of G.I Flat (25x6) mm 1.2 kg/Mtr (Two point Nut Bolts joints should be provided for earth flat with overlap of 450mm) including cost of excavation of earth pit in all kind of soil & rock, filling with burnt wood charcoal, salt / Bentonite powder & soft soil and making brick masonry chamber with removable RCC cover complete as per approved technical specification and direction of E.I.C. |
| 54 | Supply & installation of No-6 GI wire for guarding. complete as required & as per approved technical specification & direction of EIC. |
| 55 | Supply & installation of No-8 G I wire for guarding. complete as required & as per approved technical specification & direction of EIC. |
| 56 | Supply & installation of Alumunium Blnding wire. complete as required & as per approved technical specification & direction of EIC. |
| 57 | Supply (of all reqd. Materials ) ,Erection, testing & commissioning of HT Stay Set complete including excavation of stay pit in all kind of soil and rock as required with GI HT Stay Set, Stay Clamp , Stay Insulator & 7/8 GI stay Wire Grade-2 & Concreting (1:2:4) of Stay Anchor plate of size (0.5x0.5x0.8)=0.2 Cu. Mtr. complete with curing as required & as per approved technical specification & direction of EIC. |
| 58 | Supply and painting of Black paint(GIS Numbering & Zebra Stripping) as required and direction of EIC. |
| 59 | Supply and painting of Yellow colour paint for back ground as required and direction of EIC. |
| 60 | Sundries . complete as required & as per direction of EIC.. |
| 61 | Cost of material for Four pole structure ( using 13 mtr WPB pole) with 630A Isolator 02 nos = 1 no. |
| 62 | Supply ( of all reqd. Materials ), Erection, testing & commissioning of 13mtrs long WPB (160 x 152mm) (30.44 KG/Mtr) Pole with base plate 300x300x12 (Including 11 nos of line crossing) and Excavation of pole pit in all kind of soil and rock up to a depth of 1/6 th mtr of hight of the pole from ground level & installation with mass Concreting of poles in ratio 1:1.5:3 (500mmX500mm X2000mm) = 0.5Cu.mtr & couping of poles in ratio 1:1.5:3 (500X500X450)= 0.1125 Cu mtr with necessary curing.complete in all respect as per approved technical specification & direction of EIC. |
| 63 | Supply, fabrication, Erection, testing & commissioning of GI structural Members for Four Pole Structure: a)-Top Pressure Channel (100x50x6) 3.5 mtr long 2 Nos (9.2kg/mtr) .b)- Busbar Channel & lsolator mounting Channel 100x50x6 mm 3.5 mtr long (9.2 kg/mtr).c)-75x40x6 mm GI Channel for bottom Bracing 4.5 mtr Long 2 Nos @6.8 KG/ Mt.d)-50x50x6 mm M5 angle 4.5 mtr long 2 Nos for providing cross bracing.e)- Isolator Operating Down Pipe Support Channel 75x40x6mm.,of length 0.8 mtr. f)- Down Pipe Diagonal Support Angle 50x50x6mm, each angle length 0.388mtr. g)- Down Pipe Base Support Angle 50x50x6mm, each angle length 0.34mtr h)-Isolator Support Side Channel 100x50x6mm, each channel length 0.5 mtr. i)- Fish Plate 50X8 mm, 3.14kg/Mtr. each 0.280 mtr, Length Complete in all respect as per approved technical specification & direction of EIC. |
| 64 | Supply and installation of Danger Plate using GI Back clamp (Pole-clamp) made of 25x3 mm flat flat, 0.59Kg/Mtr. Flat of 0.510mtr length 1 no's. complete in all respect as per approved technical specification and direction of E.I.C. |
| 65 | SITC of Anticlimbing Device using GI barbed wire (3kg per support) with Back Clamp (25X3 mm GI flat, 0.59Kg/Mtr. Flat of 0.510mtr length 4 no's = (4x0.59x0.510)). complete in all respect as per approved technical specification and direction of E.I.C. |
| 66 | Supply & installation of Earthing of support (coil type). complete as required & as per approved technical specification & direction of EIC. |
| 67 | Supply & installation of 11 KV Disc Insulator B & S Type 45 KN POLYMER. complete as required & as per approved technical specification & direction of EIC. |
| 68 | Supply & installation of 11 KV hard ware fitting B & S Type 45KN. complete as required & as per approved technical specification & direction of EIC. |
| 69 | SITC of 11KV 630A ISOLATOR Double Break Centre Post Rotating Gang Operated WITH E/S GI Box,25KA for 3sec (Porcelain). complete as required & as per approved technical specification & direction of EIC. |
| 70 | SITC of Lightning Arrester(12KV,10KA) Station Class. complete as required & as per approved technical specification & direction of EIC. |
| 71 | Supply & installation of No-8 GI wire (Dia 4.6mm) 0.131 KG/ Mtr.- 2 Mtr. For connecting pole with Coil earthing. complete as required & as per approved technical specification & direction of EIC. |
| 72 | Supply & fixing of G.I Nut, Bolt & Washers of assorted size. complete in all respect as per approved technical specification and direction of E.I.C. |
| 73 | Supply (of all reqd. Materials ) ,Erection, testing & commissioning of HT Stay Set complete including excavation of stay pit in all kind of soil and rock as required with GI HT Stay Set, Stay Clamp , Stay Insulator & 7/8 GI stay Wire Grade-2 & Concreting (1:2:4) of Stay Anchor plate of size (0.5x0.5x0.8)=0.2 Cu. Mtr. complete with curing as required & as per approved technical specification & direction of EIC. |
| 74 | Supply (of all reqd. Materials ) ,Erection, testing & commissioning of pipe earth electrode made out of 40 mm dia G.I Pipe of 3 mtr. Long with arrangements at both end of guarding for fitting and termination of G.I Flat (25x6) mm 1.2 kg/Mtr (Two point Nut Bolts joints should be provided for earth flat with overlap of 450mm) including cost of excavation of earth pit in all kind of soil & rock, filling with burnt wood charcoal, salt / Bentonite powder & soft soil and making brick masonry chamber with removable RCC cover complete as per approved technical specification and direction of E.I.C. |
| 75 | Supply and painting of Black paint(GIS Numbering & Zebra Stripping) as required and direction of EIC. |
| 76 | Supply and painting of Yellow colour paint for back ground as required and direction of EIC. |
| 77 | Sundries . complete as required & as per direction of EIC. |
| 78 | Cost of material for 3.11 KV Line DP (using 11 mtr WPB pole) with 630A Isolator = 03 nos. |
| 79 | Supply ( of all reqd. Materials ), Erection, testing & commissioning of 11mtrs long WPB (160 x 152mm) (30.44 KG/Mtr) Pole with base plate 300x300x12 and Excavation of pole pit in all kind of soil and rock up to a depth of 1.8 mtr from ground level & installation with mass concreting of poles in ratio 1:1.5:3 (500mmX500mm X1500mm) = 0.375Cu.mtr & couping of poles in ratio 1:1.5:3 (500X500X450)= 0.1125 Cu mtr with necessary curing.complete in all respect as per approved technical specification & direction of EIC. |
| 80 | Supply, fabrication, Erection, testing & commissioning of GI structural Members for DP Structure: a)-Top Pressure GI Channel (100x50x6) 2.8 mtr long 2 Nos (9.2kg/mtr) .b)- 75x40x6 mm GI Channel 2.8 mtr long 2 Nos for Isolator mounting (6.8kg/mtr).c)-75x40x6 mm G1 Channel 2.8 mtr long 2 Nos Supporting Cross Bracing at bottomn of DP.d)-50x50x6 mm GI Angle 3.5mtr long 2 Nos for providing cross bracing at bottom of [email protected] Kg/mtr.e)- Isolator Operating Down Pipe Support Channel 75x40x6mm of length 0.8 mtr. f)- Down Pipe Diagonal Support Angle 50x50x6mm, each angle length 0.388mtr. g)- Down Pipe Base Support Angle 50x50x6mm, each angle length 0.34mtr h)-Isolator Support Side Channel 100x50x6mm, each channel length 0.5 mtr. i)- Fish Plate 50X8 mm, 3.14kg/Mtr. each 0.280 mtr, Length Complete in all respect as per approved technical specification & direction of EIC. |
| 81 | SITC of 11KV 630A ISOLATOR Double Break Centre Post Rotating Gang Operated Without E/S GI Box,25KA for 3sec (Porcelain). complete as required & as per approved technical specification & direction of EIC. |
| 82 | SITC of Lightning Arrester(12KV,10KA) Station Class. complete as required & as per approved technical specification & direction of EIC. |
| 83 | Supply & installation of 11 KV Disc Insulator B & S Type 45 KN POLYMER. complete as required & as per approved technical specification & direction of EIC. |
| 84 | Supply & installation of 11 KV hard ware fitting B & S Type 45KN. complete as required & as per approved technical specification & direction of EIC. |
| 85 | Supply & installation of Earthing of support (coil type). complete as required & as per approved technical specification & direction of EIC. |
| 86 | Supply & installation of No-8 GI wire (Dia 4.6mm) 0.131 KG/ Mtr.- 2 Mtr. complete as required & as per approved technical specification & direction of EIC. |
| 87 | Supply (of all reqd. Materials ) ,Erection, testing & commissioning of pipe earth electrode made out of 40 mm dia G.I Pipe of 3 mtr. Long with arrangements at both end of guarding for fitting and termination of G.I Flat (25x6) mm 1.2 kg/Mtr (Two point Nut Bolts joints should be provided for earth flat with overlap of 450mm) including cost of excavation of earth pit in all kind of soil & rock, filling with burnt wood charcoal, salt / Bentonite powder & soft soil and making brick masonry chamber with removable RCC cover complete as per approved technical specification and direction of E.I.C. |
| 88 | Supply (of all reqd. Materials ) ,Erection, testing & commissioning of HT Stay Set complete including excavation of stay pit in all kind of soil and rock as required with GI HT Stay Set, Stay Clamp , Stay Insulator & 7/8 GI stay Wire Grade-2 & Concreting (1:2:4) of Stay Anchor plate of size (0.5x0.5x0.8)=0.2 Cu. Mtr. complete with curing as required & as per approved technical specification & direction of EIC. |
| 89 | Supply & fixing of G.I Nut, Bolt & Washers of assorted size. complete in all respect as per approved technical specification and direction of E.I.C. |
| 90 | SITC of Anticlimbing Device using GI barbed wire (3kg per support) with Back Clamp (25X3 mm GI flat, 0.59Kg/Mtr. Flat of 0.510mtr length 4 no's = (4x0.59x0.510)). complete in all respect as per approved technical specification and direction of E.I.C. |
| 91 | Supply and installation of Danger Board using GI Back clamp (Pole-clamp) made of 25x3 mm flat flat, 0.59Kg/Mtr. Flat of 0.510mtr length 2 no's = (2x0.59x0.510). complete in all respect as per approved technical specification and direction of E.I.C. |
| 92 | Supply and painting of Black paint(GIS Numbering & Zebra Stripping) as required and direction of EIC. |
| 93 | Supply and painting of Yellow colour paint for back ground as required and direction of EIC. |
| 94 | Sundries . complete as required & as per direction of EIC. |
| 95 | Cost of material for 4.11 KV Line DP (using 11 mtr WPB pole) with 630A Isolator and Earth Switch 01 no . |
| 96 | Supply ( of all reqd. Materials ), Erection, testing & commissioning of 11mtrs long WPB (160 x 152mm) (30.44 KG/Mtr) Pole with base plate 300x300x12 and Excavation of pole pit in all kind of soil and rock up to a depth of 1.8 mtr from ground level & installation with mass Concreting of poles in ratio 1:1.5:3 (500mmX500mm X1500mm) = 0.375Cu.mtr & couping of poles in ratio 1:1.5:3 (500X500X450)= 0.1125 Cu mtr with necessary curing.complete in all respect as per approved technical specification & direction of EIC. |
| 97 | Supply, fabrication, Erection, testing & commissioning of GI structural Members for DP Structure: a)-Top Pressure GI Channel (100x50x6) 2.8 mtr long 2 Nos (9.2kg/mtr) .b)- 75x40x6 mm GI Channel 2.8 mtr long 2 Nos for Isolator mounting (6.8kg/mtr).c)-75x40x6 mm GI Channel 2.8 mtr long 6 Nos Supporting Cross Bracing at bottomn of DP.d)-50x50x6 mm GI Angle 3.5mtr long 4 Nos for providing double cross bracing at bottom of [email protected] Kg/mtr.e)- Fish Plate 50X8 mm, 3.14kg/Mtr. each 0.280 mtr, Length Complete in all respect as per approved technical specification & direction of EIC. |
| 98 | Supply & installation of 11 KV Pin Insulator (Polymer). complete as required & as per approved technical specification & direction of EIC. |
| 99 | Supply & installation of Earthing of support (coil type). complete as required & as per approved technical specification & direction of EIC. |
| 100 | Supply & installation of No-8 GI wire (Dia 4.6mm) 0.131 KG/ Mtr.- 2 Mtr for connecting pole with coil earthing. complete as required & as per approved technical specification & direction of EIC. |
| 101 | SITC of Lightning Arrester(12KV,10KA) Station Class. complete as required & as per approved technical specification & direction of EIC. |
| 102 | SITC of 11KV 630A ISOLATOR Double Break Centre Post Rotating Gang Operated With E/S GI Box,25KA for 3sec (Porcelain). complete as required & as per approved technical specification & direction of EIC. |
| 103 | Supply (of all reqd. Materials ) ,Erection, testing & commissioning of pipe earth electrode made out of 40 mm dia G.I Pipe of 3 mtr. Long with arrangements at both end of guarding for fitting and termination of G.I Flat (25x6) mm 1.2 kg/Mtr (Two point Nut Bolts joints should be provided for earth flat with overlap of 450mm) including cost of excavation of earth pit in all kind of soil & rock, filling with burnt wood charcoal, salt / Bentonite powder & soft soil and making brick masonry chamber with removable RCC cover complete as per approved technical specification and direction of E.I.C. |
| 104 | Supply (of all reqd. Materials ) ,Erection, testing & commissioning of HT Stay Set complete including excavation of stay pit in all kind of soil and rock as required with GI HT Stay Set, Stay Clamp , Stay Insulator & 7/8 GI stay Wire Grade-2 & Concreting (1:2:4) of Stay Anchor plate of size (0.5x0.5x0.8)=0.2 Cu. Mtr. complete with curing as required & as per approved technical specification & direction of EIC. |
| 105 | Supply & fixing of G.I Nut, Bolt & Washers of assorted size. complete in all respect as per approved technical specification and direction of E.I.C. |
| 106 | SITC of Anticlimbing Device using GI barbed wire (3kg per support) with Back Clamp (25X3 mm GI flat, 0.59Kg/Mtr. Flat of 0.510mtr length 8 no's = (8x0.59x0.510)). complete in all respect as per approved technical specification and direction of E.I.C. |
| 107 | Supply and installation of Danger Board using GI Back clamp (Pole-clamp) made of 25x3 mm flat flat, 0.59Kg/Mtr. Flat of 0.510mtr length 2 no's = (2x0.59x0.510). complete in all respect as per approved technical specification and direction of E.I.C. |
| 108 | Supply and painting of Black paint(GIS Numbering & Zebra Stripping) as required and direction of EIC. |
| 109 | Supply and painting of Yellow colour paint for back ground as required and direction of EIC. |
| 110 | Sundries . complete as required & as per direction of EIC.. |
| 111 | Cost for Survey |
| 112 | Survey of incremental/ delta network and asset changes of 11KV network and updation in GESW database.complete as per direction of EIC. |
| 113 | Cost of material for 11 KV 4-Way Ring Main Unit - 1 Nos |
| 114 | SITC of 11KV , 4 WAY,Motorized, 630A, 21kA/3 sec, Outdoor Type LLVV (2 ISO + 2 BKR) + AUX PT + FRTU. complete in all respect as per approved technical specification and direction of E.I.C. |
| 115 | Supply of 11kV AL 3CX400 Sqmm XLPE Cable armoured-FRLSH.complete in all respect as per approved technical specification and direction of E.I.C. |
| 116 | SITC of Heat shrinkable jointing kit for 3Cx400 mm2 11KV XLPE Cable(outdoor type). complete in all respect as per approved technical specification and direction of E.I.C. |
| 117 | SITC of Jointing Kit 11KV I/D 3CX400SQMM SCREEN TYPE TOUCH PROF. complete in all respect as per approved technical specification and direction of E.I.C. |
| 118 | Supply (of all reqd. Materials ) , Erection, testing & commissioning of pipe earth electrode made out of 40 mm dia G.I Pipe of 3 mtr. Long with arrangements at both end of guarding for fitting and termination of G.I Flat (25x6) mm 1.18 kg/Mtr including cost of Construction of Earthing Chamber (Size: 2'X2') and RCC Slab cover as per specification. complete as per approved technical specification and direction of E.I.C. |
| 119 | Construction of RMU foundation O/D as per TPSODL drawing. complete in all respect as per direction of E.I.C. |
| 120 | Laying of 11kV AL 3CX400 Sqmm XLPE Cable armoured-FRLSH in the existing Trench/ Pipe. complete in all respect as per direction of E.I.C. |
| 121 | Construction of FRP fencing. complete in all respect as per direction of E.I.C. |
| 122 | GIS coordinate mapping drawing preparation and submission of the same for DTR,ABS,ARC,Sectionalizer ,RMU etc.complete in all respect as per direction of E.I.C. |
| 123 | N.B: The bidders are required to Quote theire rates excluding of Goods & Service Tax (GST). GST as applicable will be paid extra. The existing rule of Govt. and any amendment made in future will be followed. Please Enable Macros to View BoQ information |
AI Tender Summary
Tender Timeline
Jul 17, 2026
11:30 IST
Tender Published
Tender notice published.
CompletedAug 06, 2026
17:00 IST
Bid Submission Deadline
Online submission via eProcurement portal.
Upcoming · 4 daysAug 07, 2026
Bid Opening Date
Technical bids will be opened and evaluated.
Upcoming · 5 daysTender Documents
Download All (ZIP) ↓
Disclaimer
We takes all possible care for accurate & authentic tender information. However users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender