Tender For Extension Of 132 And 33 Kv Main/Transfer Busbar, Erection And Commissioning Of 63 Mva T/F And Its Bays With Other Associated Work At 132 Kv S/S Shahganj Under Etd-Ii Jaunpur.
Tender Value
15 Lakhs
Estimated cost
Bid Submission
24 Jul 2026
7 days left
EMD
15000
Bank guarantee accepted
Document Fee
590
Non-refundable
Tender Type
Online
Tender Overview
Organization
Tender ID
Competition Type
NCB
Bidding Type
Tender
Location / State
Jaunpur → Uttar Pradesh
EMD Exemption
Not Available
Quantity
Not Available
Website
Contact Person
Address
Project Description
Tender for Extension Of 132 And 33 Kv Main/Transfer Busbar, Erection And Commissioning Of 63 Mva T/F And Its Bays With Other Associated Work At 132 Kv S/S Shahganj Under Etd-Ii Jaunpur.
BOQ
| Sl. No. | Item Description |
| 1 | Item Rate BoQ BoQ_Ver3.0 Item Rate Normal INR Only INR Select, Excess (+), Less (-) Less (-) Tender Inviting Authority: Superintending Engineer, Electricity Transmission Circle-II, U.P. Power Transmission Corporation Ltd. 400 KV S/S Campus Sarnath Varanasi. Name of Work: EXTENSION OF 132 AND 33 KV MAIN/TRANSFER BUSBAR, ERECTION AND COMMISSIONING OF 63 MVA T/F AND ITS BAYS WITH OTHER ASSOCIATED WORK AT 132 KV S/S SHAHGANJ UNDER ETD-II JAUNPUR. Contract No: E-tender No-02-ETC-II(VNS)/2026-2027 Name of the Bidder/ Bidding Firm / Company : PRICE SCHEDULE(This BOQ template must not be modified/replaced by the bidder and the same should be uploaded after filling the relevent columns, else the bidder is liable to be rejected for this tender. Bidders are allowed to enter the Bidder Name and Values only ) NUMBER # TEXT # TEXT # NUMBER # TEXT # NUMBER NUMBER TEXT TEXT # NUMBER # TEXT# TEXT # NUMBER # NUMBER NUMBER NUMBER NUMBER TEXT TEXT NUMBER NUMBER NUMBER NUMBER TEXT TEXT NUMBER NUMBER NUMBER NUMBER TEXT TEXT NUMBER NUMBER NUMBER NUMBER TEXT TEXT NUMBER NUMBER NUMBER NUMBER TEXT TEXT NUMBER NUMBER NUMBER # NUMBER # TEXT TEXT NUMBER # NUMBER # DATE NUMBER # NUMBER # TEXT # Sl.No. Description Item Code / Make Quantity Units Estimated Rate inRs. P Addition / Deduction Addition / Deduction Values Currency Convertion against each Item Quoted Currency in INR / Other Currency BASIC RATE In Figures To be entered by the Bidder Rs. P Excise Duty VAT Freight Charges ( Unloading & Stacking) Any Other Taxes/Duties/Levies Other Taxes 2 IIIrd Party i.e DGS&D / RITES etc Inspection Charges @0.34%+Service Tax Less for Cenvat Credit,if any respect of Supplies Under full Excise Duty Category TOTAL AMOUNT Without Taxes inRs. P TOTAL AMOUNT With Taxes TOTAL AMOUNT In Words |
| 2 | Carriage of main and auxilary structure |
| 3 | Shifting , Counting and loading of S/S main & auxiliary Structure at EFU, Naini Prayagraj (AKR-02, BKR-02,DKR-2, ALP-20, BCT-15, BBL-07, ABL-05, CCR-02, CCM-04, ABL-05, CGM-02, CGR-01 set) |
| 4 | Transporation of S/S main & auxliary structure from EFU Naini Prayagraj to 132 KV S/S Shahganj distanc approx 140 Km. |
| 5 | Unloading and Stacking of S/S main & auxiliary Structure at 132 KV S/S Shahganj (AKR-02, BKR-02,DKR-2, ALP-20, BCT-15, BBL-07, ABL-05, CCR-02, CCM-04, ABL-05, CGM-02, CGR-01 set) |
| 6 | Laying of eartmat in the extended switchyard 132/33 kV of the substation along with connecting the newly earthmat with existing earthmat as per detail below |
| 7 | Fabrication of 3 mtr long electrode with 40mm dia MS Round bar having 150mm long conical shape by due cutting straighting etc. and then piercing it vertically inside the ground with top 700mm below the ground level including shifting of MS round bar from the storage place at substation to switchyard. |
| 8 | Laying of 40mm dia MS round bar, 700mm below the ground level by due cutting, straighting, welding, painting. Excavation of trenches, backfilling of trench after laying of earthmat include shifting of MS round bar from storage palce to switchyard. |
| 9 | Making of 150mm long lap joint of above laid 40mm dia round bar to connect with existing earth mat of substaion by due cutting straighting welding etc. |
| 10 | Making of cross joint of above laid 40mm dia MS round bar 700mm below the ground level by due welding at all four cormers including providing and welding rod suitable size 4 no. of MS angle pieces on opposite corner of cross joint. |
| 11 | Erection of S/S main and auxliary Structure (AKR-02, BKR-02,DKR-2, ALP-20, BCT-15, BBL-07, ABL-05, CCR-02, CCM-04, ABL-05, CGM-02, CGR-01 set) for installation of equipment e.g. 145 kV C.B, CT, PT, BSI, 33 KV CB, Isolator, CT etc. The work included shifting of all materials from storage places to works site, Proper erection of structure as per drawing and all associated work. |
| 12 | Cutting straightening bending laying of 50x6mm M.S flat for earthing of main and auxilary structure, equipment structure, equipments etc. including welding with main earthmat below 500-700 mm below ground level with object to earth excavation of trenches its back filling painting with synthetic enamel green color above ground and all associated work to complete the job satisfactory including cost of M.S flat. |
| 13 | Stringing of 132 kv main and transfer bus and 33 kV Bus Bar |
| 14 | Stringing of 3-phase 132 kV main and transfer twin moose bus bar 36 Mtr. Approx at the height of 11 Mtr approx with proper sagging of bus including fixing of spacer at required distance. The work includes cutting & bending of conductor, fixing of double bolted type tension fitting/Suspension hoisting of disc insulator & shifting of material from store site to erection site and all other associate work to complete satidsfactorily as per drawing and technical specfication In 132 kV live switchyard (3x2x2=12) |
| 15 | Connecting jumper of Twin Moose bus section to bus section at the gantry at the height of 11mtr. (aprox) by Twin moose conductor with clamp & specers In 132 kV live switchyard. |
| 16 | Laying and strringing of 132 kV 3 phase ACSR Moose conductor Jack bus bar for 132 kV Transfer Bus Bay (approx 18 mtr.) includning hoisting of disc insulator, suspention and tension fitting etc. along with shifting of the conductor/ material place at that substation to the erection site. |
| 17 | Jumpering of various equipment with ACSR Panther conductor in Transfer Bay between 132 kV main bus and transfer bus by cutting and bwnding of conducor and fixing tightening etc of all the conductor/clamps/spacer etc. (1 job per all three phases) |
| 18 | Laying and strringing of 33 kV 3 phase double ACSR Moose conductor bus bar (approx 18 mtr.) includning hoisting of disc insulator, suspention and tension fitting etc. along with shifting of the conductor/ material place at that substation to the erection site. |
| 19 | Shifting of 132 kV Siddiquuepr-Shahganj Line Bay |
| 20 | Dismantling of all the three phase panther conductor including de-hoisting of conductor and disc insulator between dead end tower to gantry of 132 kv SC Siddiquepur-Shahganj Line |
| 21 | Dismantling of earthwire and de-hoisting of earthwire between dead end tower to gantry of 132 kv SC Siddiquepur-Shahganj Line |
| 22 | Stringing of all three phase ACSR Panther Conductor from dead end tower to gantry (new position) of 132 kv SC Siddiquepur-Shahganj Line including laying , stringing, tensioning, clapmping etc. along with necessary shifting of all material from store to line site. |
| 23 | Stringing of 3.25mm earthwire from dead end tower to gantry (new position) of 132 kv SC Siddiquepur-Shahganj Line including laying , stringing, tensioning, clapmping etc. along with necessary shifting of all material from store to line site. |
| 24 | Erection of following equipment as per instruction manual of various equipment and technical specification including shifting of equipment from store to site and all other associated work to complete the job satisfactorily. |
| 25 | 145 KV CB with structure |
| 26 | 145kv Bus Isolator |
| 27 | 145 KV CT |
| 28 | Junction Box for 145 kV CT |
| 29 | 145 kV PT |
| 30 | Junction Box for 145 kV PT |
| 31 | Junction Box for 145 kV Isolators |
| 32 | 145 KV PI |
| 33 | 132 kv Buscoupler Panel |
| 34 | Energy metre .2 accu. Class ( ABT) |
| 35 | T/F Control relay panel |
| 36 | 120 kV LA |
| 37 | 36 kV VCB |
| 38 | 36 kV CT |
| 39 | 33 kV CT Junctio Box |
| 40 | 30 kV LA |
| 41 | Erection of 132/33 kV 63MVA T/F |
| 42 | Shifting of main tank 63 MVA T/F from unloading point to plinth up to a 20 meter distance, including turning of tank if required, including all T&P and work required to Complete the job satisfactorily. |
| 43 | Additional shifting of 40 meter @ 5meter/job |
| 44 | Complete Erection of 63 MVA T/F by erection of radiators, conservator tank, all bushing with their turrets, connecting oil pipes, cooling fans, motor drive mechanism, tape changer, RTCC panel, and associated oil pipe line, etc. to complete the job, including first filling of oil and topping up of T/F oil in tank, radiator lines, conservator tank, etc. and attending oil leakage, if any, and all other work required for satisfactory completion of work along with arrangement of labor T&P to complete the job in all respects. (Hydra, crane, special tools, will be provided by the contractor) |
| 45 | Erection of 63 MVA Transformer RTCC panel including grouting, earthing after shifting from storage place to relay room as per instruction of site engineer. |
| 46 | Earthing of erected 63 MVA T/F main tank, neutral bushing, marshaling box, OLTC, RTCC, panel, etc. at two points using 75x10/50x6 mm electrodes. (MS flat provided by the contractor. The work also includes painting of earthing strip with one coat of red oxide primer and two coats of bus green synthetic enamel paint. |
| 47 | Raising the height of 3 Nos. ALP structure for 30KV LA after dismantling of LA and structure and re-erecting it, replacing all the Panther conductor, jumpering of 33KV side of 63 MVA, 132/33KV T/F from 33KV Buthing to 33KV But Bar with ACSR Moose conductor, fixing of all the insulator clamps, CB clamps, LA clamps, CT clamps suitable for the proper size of Moose conductor and jumpering of all the 132/33KV side equipment |
| 48 | Delta earthing for L.A consisting of fabrican of 3 Nos 3 metre long electrodes, its piercing inside ground and connection of all three nos. electrodes with 75x10mm M.S flat and connection of same with above LA including cost of M.S flat but excluding cost of bar which shall be supplied by the department. |
| 49 | Making of 02 no. additional delta of 63 MVA T/F HV/LV netural bushing with fabrication of 3 no. 3 meter long electrodes of 36mm/40mm dia MS round bar, piercing it inside ground at equal distance of 1 meter up to depth of 700mm, by digging of earth and connecting all the 3 no. electrodes with 75mmx10mm size MS flats and connecting with existing earth mat and taking out riser by due cutting, bending welding etc. as per technical specfication (MS bar will be provided by department) above work also include painting of earthing strips with one coat of red oxide primer and two coats of bus green synthetic enameled paint 1 job for each delta earthing. |
| 50 | Jumpering of various equipment with ACSR Panther conductor in T/F HV bay between 132 kV Main bus to HV side bushing of T/F and LAs by due cutting and bending of conductor and fixing & tightning etc of the conductor /clamp/connectors/spacers (1 job for all 3 Phases) |
| 51 | Jumpering of various equipment with ACSR Twin Moose conductor in T/F LV bay between 33 kV Main bus to LV side bushing of T/F including isolators, CB, CTs, LAs by due cutting and bending of conductor and fixing & tightning of the conductor /clamp/conductors/spacers (1 job for all 3 Phases) |
| 52 | Laying of following size control cable in the cable trench from control relay/ RTCC panel to Transformer marshalling/ Drive Mechanism as per cable schedule, its Saddling as every 75 mm distance with MS saddles of size of size 25x3mm , including carriage of cable drums from store to laying site and all other associated work to complete the job satisfactory. |
| 53 | 2C x 2.5 sq.mm |
| 54 | 4C x 2.5 sq.mm |
| 55 | 6C x 2.5 sq.mm |
| 56 | 10C x 2.5 sq.mm |
| 57 | Termination of following size of cable as laid above as per cable schedule including making necessary holes in glands, plate or box where ever required. Supply and fixing of cable gland of appropriate size, supply and fixing ferruls for each core as required and termination with proper size of lug and all other associated work to complete the job satisfactory as per technical specification. |
| 58 | 2Cx2.5mm2 |
| 59 | 4Cx2.5mm2 |
| 60 | 6Cx2.5mm2 |
| 61 | 10Cx2.5mm2 |
| 62 | Connection of cables as per cable schedule of new 63 MVA Transformer & its RTCC panel al both ends cooling fans marshalling box etc, using existing cables connection of all control cables at RTCC & Transformer end as per technical specfications. |
| 63 | Centrifuging of complete 63 MVA T/F oil in T/F & Tank by connecting centrifuging pipes, circulating the T/F oil through a centrifuge machine to be provided by the contractor, and taking the BDV value of the oil periodically until the required value is achieved as per the direction of the supervising engineer. All T&P, labor, and centrifuge machine shall be provided by the contractor. |
| 64 | Testing of transformer oil, including BDV, PPM, and DGA, of 63 MVA T/F at NABL certified Lab |
| 65 | SFRA Testing of 63MVA T/F & WRM Testing of 63MVA T/F |
| 66 | Dismantalling work of 33 kv Capacitor Bank |
| 67 | Dismantalling of 33 kV capacitor bank which include complete dismantalling of main Structure beam and colum with isolator, breaker, capacitor cell Series reactor Netural current transformer and associated ausxilary structure from the base. Then stacking and arranging of dismantalled old structure from site to store location as per isntruction of engineer with the help of hydra and manual labour. |
| 68 | Dismantalling and decommissioning of 33 kV capacitor bank protection panel which include tracing the cables from control panel to switchyard then removing it from trench after making proper cable termination schedule by skilled Technician such that during the dismantalling work no other cable or protection system of control room or switchyard gets damaged . Work shall be complted properly and very delicately and then de commissioned panel will be transfered to JE store as per instruction of engineer. |
| 69 | Work of re-erection of dismantled 33 kV capacitor bank include following. |
| 70 | Carriage of main gantry and column structure of 33 kV capacitor bank from dismantlled/store to erection site with the help of hydra and then erecion of column and gantry completely on the plinth. |
| 71 | Hosting and stringing of 3 phase main bus bar single ACSR panher conductor with asociated hardware accessories which include disc ,gun fitting to completet the job sataisfacory. |
| 72 | Erection of 33kv breaker , isolator ,cell with auxillary structure , series reactor ,NCT main CT, PT ,capacitor bank, protection and control panel from old place to new place in proper alignment with complete adjustment in switchyard on the erected structure as per manufacture drawing or as per direction of supervising engineer after levelling includeing shifting the equipment from store to working site etc. along with their junction box. control cubical and accesssories including the latest cost of labour T&P cranes for proper completion of work. |
| 73 | Shifting and stacking of old and used stock item laying in open store yard with the help of hydra at new storege place (approx 70Mtr.distance) for space required 132kv main and transfer bus bar extension. |
| 74 | Supply and fixing of outdoor high beam flood light with power 120 watt (LED) as light source and versitlie pressure Die-cast aluminium body with poly carbonate fitting suitable for 220 AC input supply of IS make of standard make including laying of cable & termination of connection LE in switchyard with the help of clamps. |
| 75 | Installation and fixing of Window type Air Conditioners (2 Ton each) in 11×9 meter Control Room of 132kV Substation Badlapur including supply and fixing of 63A power board with 63A 2-pole MCB for each AC, wiring with 2.5 sq.mm copper wire through PVC conduit from ACDB, necessary accessories and labour charges for electrical connection and mechanical fixing (excluding cost of AC units), complete in all respects Total in Figures 0.0 0.0 INR Zero Only 4.0 Construction of chamber for 100mm sluice plates item5 10.0 Nos Quoted Rate in Figures Select 0.0 0.0 Zero Only Quoted Rate in Words INR Zero Only Please Enable Macros to View BoQ information |
AI Tender Summary
Tender Timeline
Jul 16, 2026
11:30 IST
Tender Published
Tender notice published.
CompletedJul 24, 2026
17:00 IST
Bid Submission Deadline
Online submission via eProcurement portal.
Upcoming · 7 daysJul 25, 2026
Bid Opening Date
Technical bids will be opened and evaluated.
Upcoming · 8 daysTender Documents
Download All (ZIP) ↓
Disclaimer
We takes all possible care for accurate & authentic tender information. However users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender