Tender For Construction Of Bowli Nho Sh Sham Lal & Others (Rs. 0.94 Lac) & Repair Of Khul Sidhi Nallaha To Thakur Mohalla Nho Sh Ramesh Singh & Others At W. No. 01 Pyt Pathwar, Block Khoon (Rs. 1.00 Lac) District Udh Ur Under:- Pri Capex For The Year
Tender Overview
Project Description
Tender for Construction Of Bowli Nho Sh Sham Lal & Others (Rs. 0.94 Lac) & Repair Of Khul Sidhi Nallaha To Thakur Mohalla Nho Sh Ramesh Singh & Others At W. No. 01 Pyt Pathwar, Block Khoon (Rs. 1.00 Lac) District Udh Ur Under:- Pri Capex For The Year 2026-27.
BOQ
| Sl. No. | Item Description |
| 1 | Percentage BoQ BoQ_Ver3.0 Percentage Normal INR Only INR Select, At Par, Excess (+), Less (-) IOCL Tender Inviting Authority: EXECUTIVE ENGINEER REW DIVISION Udhampur Name of Work:- Const. of bowli NHO Sh Sham Lal & others (Rs. 0.94 Lac) & repair of Khul Sidhi Nallaha to Thakur mohalla NHO Sh Ramesh Singh & others at W. No. 01 Pyt Pathwar, Block Khoon (Rs. 1.00 Lac) District Udhampur Under:- PRI CAPEX FOR THE YEAR 2026-27. Contract No: (Tender amount =1.88 lacs, Time for compeltion = 30 Days) r Name of the Bidder/ Bidding Firm / Company : PRICE SCHEDULE(This BOQ template must not be modified/replaced by the bidder and the same should be uploaded after filling the relevent columns, else the bidder is liable to be rejected for this tender. Bidders are allowed to enter the Bidder Name and Values only ) NUMBER # TEXT # TEXT # NUMBER # TEXT # NUMBER NUMBER TEXT TEXT # NUMBER # TEXT# TEXT # NUMBER # NUMBER NUMBER NUMBER NUMBER TEXT TEXT NUMBER NUMBER NUMBER NUMBER TEXT TEXT NUMBER NUMBER NUMBER NUMBER TEXT TEXT NUMBER NUMBER NUMBER NUMBER TEXT TEXT NUMBER NUMBER NUMBER NUMBER TEXT TEXT NUMBER NUMBER NUMBER # NUMBER # TEXT TEXT NUMBER # NUMBER # DATE NUMBER # NUMBER # TEXT # Sl.No. items Item Code / Make Quantity Units Estimated Rate inRs. P Addition / Deduction Addition / Deduction Values Currency Convertion against each Item Quoted Currency in INR / Other Currency BASIC RATE In Figures To be entered by the Bidder Rs. P Excise Duty VAT Freight Charges ( Unloading & Stacking) Any Other Taxes/Duties/Levies Other Taxes 2 IIIrd Party i.e DGS&D / RITES etc Inspection Charges @0.34%+Service Tax Less for Cenvat Credit,if any respect of Supplies Under full Excise Duty Category TOTAL AMOUNT inRs. P TOTAL AMOUNT With Taxes TOTAL AMOUNT In Words |
| 2 | PART 1 Earh Work in Excavation by manual labour in foundation trenches including dressing of sides and ramming of bottoms, lift upto 1.5m, including getting out the excavated soil and disposal of surplus excavated soil. 1m from cutting edge.100% in All kinds of soil . |
| 3 | Reinforced cement concrete work in beams, suspended floors, roofs excluding cost of centring, shuttering, finishing and reinforcement.1 cement: 1.5 coarse sand :3 graded stone aggregates 20mm nominal size. |
| 4 | Reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete . |
| 5 | Cetring and shuttering including strutting, propping etc and removal of the formwork. |
| 6 | Cetring and shuttering including strutting, propping etc and removal of the formwork. |
| 7 | R.R stone masonary with hard stone from nallah of approved quality in 1:6 mix |
| 8 | 12mm thick cement plaster of 1 cement: 6 fine sand mix |
| 9 | Structural steel work in built up sections, trusses and framed work,including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer all complete welded |
| 10 | Carriage of construction material sand |
| 11 | Carriage of construction material aggregate |
| 12 | Carriage of construction material stone |
| 13 | PART 2 Earh Work in Excavation by manual labour in foundation trenches including dressing of sides and ramming of bottoms, lift upto 1.5m, including getting out the excavated soil and disposal of surplus excavated soil. 1m from cutting edge.100% in All kinds of soil. |
| 14 | Providing and lying in position dry crushed stone aggregates 40mm size.excludingthe cost of centring and shuttering all work upto plinth Level. |
| 15 | Providing and laying in position cement concrete of specified grade including curing but excluding the cost of centring and shuttering. All work upto plinth level with 1:3:6 MIX. |
| 16 | Cetring and shuttering including strutting, propping etc and removal of the formwork. |
| 17 | P/L 50mm thick DPC of 1:2:4 mix with curing complete. |
| 18 | Add provision for Sign Board (to be paid as per actual) |
| 19 | Carriage of construction material(sand) |
| 20 | Carriage of construction material(aggregate) Total in Figures 188420.58 96736.25 INR Ninety Six Thousand Seven Hundred & Thirty Six and Paise Twenty Five Only 4.0 Construction of chamber for 100mm sluice plates item5 10.0 Nos Quoted Rate in Figures Select 0.0 0.0 INR Zero Only Quoted Rate in Words INR Zero Only Please Enable Macros to View BoQ information |
AI Tender Summary
Tender Timeline
Tender Published
Tender notice published.
CompletedBid Submission Deadline
Online submission via eProcurement portal.
Upcoming · 13 daysBid Opening Date
Technical bids will be opened and evaluated.
Upcoming · 14 daysTender Documents
Download All (ZIP) ↓We takes all possible care for accurate & authentic tender information. However users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender