Tender For Short Refit (Sr 27) Of Installation Sudarshini (O/L)
Tender Value
Ref. Documents
Estimated cost
Bid Submission
18 Aug 2026
34 days left
EMD
1.40 Crore
Bank guarantee accepted
Document Fee
Ref. Documents
Non-refundable
Tender Type
Online
Tender Overview
Organization
Tender ID
Competition Type
NCB
Bidding Type
Tender
Location / State
Ernakulam → Kerala
EMD Exemption
Available
Quantity
Not Available
Website
Contact Person
Address
Project Description
Tender For Short Refit (Sr 27) Of Installation Sudarshini (O/L)
BOQ
| Sl. No. | Item Description |
| 1 | SUMMARY OF QUOTATION |
| 2 | ServicesTotal Cost of Dry Dock Hire Charges and other Admin & General Services quoted in the BoQ |
| 3 | Cost of repair part :-(a) Total cost of Hull & Rigging Work Package |
| 4 | (b) Total cost of Engineering Work Package |
| 5 | (c) Total cost of Electrical Work Package |
| 6 | GST on serial 1.01 to 1.04 |
| 7 | Total Budgeary Cost of Spares |
| 8 | GST applicable for 1.06 |
| 9 | Any other Taxes & Duties |
| 10 | Miscellaneous (not included in any of the serial above) |
| 11 | GST if any on serial 1.09 |
| 12 | HULL - PART I |
| 13 | SHIPYARD TO UNDERTAKE STEEL RENEWAL/BUILD UP AS INDICATED BY NSRY(KOC) TO REPAIR CORROSSION / UNDULATION / PITTING ETC AT ALL LOCATIONS INCLUDING TANKS / SEA TUBE / SEA CHEST / HULL PLATES/RUDDER / BRIDGE TOP SOFT PATCH / MACHINERY FOUNDATION PLATES/HAWSE PIPE / FIAR LEAD / BOLLARD ETC SHIPYARD TO QUOTE FOR NECESSARY DE-GUTTING / RE-GUTTING INCLUDING COST OF SPARES LIKE LAGGING ETC. COATING / PAINTING TO BE RESOTRED POST STEEL RENEWAL. PAYMENT BASED ON THE ACTUAL QUANTITY OF SOW UNDERTAKEN AS PER WCC ON NOT EXCEEDING BASIS. APPROX 20 TONS OF STEEL RENEWAL ENVISAGED. ALL HOT WORK ARE TO BE UNDERTAKEN INCLUDING ALL SAFETY REQUIRMENT INCLUDING HOT WORK SENTRIES |
| 14 | SR 4 - ALL TANKS, COFFERDAMS AND SEA TUBES WHICH ARE REPAIRED BY BUILD-UP/RENEWAL ARE TO BE AIR PRESSURE TESTED IAW PARA 47 OF NO 01/15. THE PRESSURE TESTING IS TO BE CARRIED OUT BY REFITTING AUTHORITIES IN THE PRESENCE OF SHIP STAFF AND QUALITY CONTROL INSPECTORS OF THE REFITTING AUTHORITY. UNDER NO CIRCUMSTANCE, THE PROCEDURE OF RUNNING PRESSURE TEST IS TO BE USED TO CONFIRM THE STRUCTURAL INTEGRITY OF THESE SPACES. |
| 15 | SR 2 - SURVEY THE FOLLOWING STRUCTURE IN ACCORDANCE WITH NO 01/15 AND IHQ MOD (N)/ DNA LETTER NC/7631 DATED 01 NOV 22 AS MENTIONED BELOW :-EXTERNAL UW HULL1. CARRY OUT 100% ROBOTIC SURVEY OF EXTERNAL UW HULL INCLUDING BOOT TOP AND USG IN WAY OF MACHINERY COMPARTMENT (SURVEY TO BE UNDERTAKEN BY SHIPYARD)NOTE:- EYE HOOKS IF USED FOR PROPELLER OR SHAFT REMOVAL/ FITMENT ARE TO BE REMOVED BEFORE UNDOCKING AND GROUND FLUSHED. PAD PIECES WITH FAIR EDGES MAY BE RETAINED EXCEPT THOSE WITH WATERJETS AND SURFACE DRIVES. |
| 16 | SR2 - INTERNAL UW HULL STRUCTURE & ABOVE WATER STRUCTURENOTES: -1. PAINT SCHEME IS TO BE RESTORED POST SURVEY/ RENEWAL IAW NO 53/16/ NCDS/ POLICY DIRECTIVES.2. FOR THE AREAS WHEREIN SAMPLE USG IS TO BE UNDERTAKEN, IT IS ESSENTIAL THAT THE SAMPLE AREA BE CHOSEN SUCH THAT IT TRULY REPRESENTS THE SUSPECT AREAS UNDER CHECK. SUCH AREA TO BE IDENTIFIED JOINTLY BY THE SHIP STAFF AND REFITTING AUTHORITY. |
| 17 | SR 3 CARRY OUT SURVEY AND INSPECTION OF ALL BOLLARDS/FAIRLEADS/ CLEATS/ DECK EYES/ STAGHORN AND OTHER DECK FITTINGS STRUCTURE INCLUDING STIFFENING MEMBERS IN THE VICINITY WITH NON-DESTRUCTIVE TECHNIQUES, IF REQUIRED AND INCLUDE IN THE SURVEY REPORT. FOR TOWING AND CABLE CLENCH, CHECK THE EFFICACY OF THE ATTACHMENT USING NON-DESTRUCTIVE TESTING. |
| 18 | SR 1 -REMOVE MARINE FOULING FROM ENTIRE UW EXTERNAL HULL AREA USING WOODEN SCRAPPER OR HYDRO JETTING WITH MAXIMUM PRESSURE NOT EXCEEDING 3000 PSI. |
| 19 | SR2 - SCRAPE AND CLEAN UNDER WATER AND BOOT TOPPING AREA (INCLUDING WIND AND WATER AREAS) TO REMOVE ALL LOOSE PAINT FILM, RUST ETC. PAINT SCHEME REPAIR/ RENEWAL IS TO BE UNDERTAKEN IAW IHQ, MOD POLICY LETTER NC/0528/LLPS DATED 20 JUL 11 AND NCD 1491 ISSUE 1 OF MAY 11 AND SURFACE PREPARATION TO BE UNDERTAKEN IAW WITH NO 53/16.NOTE :- WIND AND WATER AREAS TO BE CONSIDERED UP TO 500MM ABOVE BOOT TOP. |
| 20 | SR 3- SURVEY THE FOLLOWING STRUCTURE IN ACCORDANCE WITH NO 01/15 AND IHQ MOD (N)/ DNA LETTER NC/7631 DATED 01 NOV 22 AND REPAIR AS PER SURVEY REPORT AS MENTIONED BELOW :-EXTERNAL UW HULL (A) 100% VISUAL SURVEY OF COMPLETE UNDERWATER HULL ANDBOOT TOP INCLUDING WIND AND WATER AREAS I.E. AREA UP TO500MM ABOVE BOOT TOP AREA (FOR GROUP A, B, C SHIPS) |
| 21 | SR5 - APPLICATION OF ONE COAT OF A/F PAINT ON UNDER WATER HULL AND BOOT TOP AREA TO BE CARRIED OUT POST ADEQUATE SURFACE PREPARATION BASED ON THE FINDINGS OF JOINT INSPECTION WITH OEM. PAINT TOUCH UP/ MAINTENANCE PAINTING TO BE CARRIED OUT IAW NO 53/16/ POLICIES/ NCD IN VOGUE. PAYMENT AS PER ACTUALS. |
| 22 | SR2 - EXAMINE RUDDER STRUCTURE IN ACCORDANCE WITH NO 01/15, PAYING PARTICULAR ATTENTION TO HULL PLATING IN THE VICINITY OF RUDDER(S) AND FITTINGS UP TO THE RUDDER HEAD, FOR ANY SIGNS OF CORROSION AND ANY OTHER DEFECTS/ DAMAGE. |
| 23 | SR3 - EXAMINE AND CHECK CLEARANCES OF LOWER AND UPPER BEARINGS OR BUSHES, WHICHEVER IS FITTED, OF RUDDER. RENEW/ REPACK RUDDER BEARINGS/ GLAND BUSHES, IF REQUIRED (BR 3000 ART. 2811 & BR 3001 ART. 2805 REFERS) . SS TO RECORD IN EMAP. |
| 24 | SR4 - EXAMINE RUDDER PINTLE BEARINGS TO ENSURE THAT THEY ARE FULLY LUBRICATED BEFORE UNDOCKING. |
| 25 | SR 1 CARRY OUT ABRASIVE BLASTING/SCRAPING TO BARE METAL OF AREAS OF CORROSION/ PAINT DAMAGE. RESTORE THE PAINT SCHEME AS PER SHIPS UW PAINT SCHEME IN ACCORDANCE WITH NO 53/16. |
| 26 | SR 1 INSPECT SACRIFICIAL ANODES FITTED TO UNDERWATER HULL, RUDDERS,ROPE GAURD, SHAFT TUNNEL, STERN TUBES, INLETS AND OUTLETS, SEATUBES, BILGES AND COFFER DAMS. RENEW THOSE CONSUMED 50%OR MORE.NOTE:- FOR SACRIFICIAL ANODES, A MINIMUM OF 4 MM GAPBETWEEN THE HULL AND THE ANODE IS TO BE MAINTAINED. OLDANODE LEGS/ WELD METAL IS TO BE FLUSH GROUND, POST REMOVALAND RESTORED WITH THESR 2 CLEAN REMAINING SACRIFICIAL ANODES WITH STEEL WIRE BRUSH.NOTE:- ENSURE SACRIFICIAL ANODES ARE NOT PAINTED. ANY PAINTOR COATING OVER THE ANODES IS TO BE SCRAPPED CLEAN BEFOREUN-DOCKING. |
| 27 | SR1 - REMOVE, CLEAN AND EXAMINE GRATING OF ALL UNDER WATER INLETS AND DISCHARGES. EXAMINE ALL PLATING, COATING AND ZINCS OF INLETS AND DIACHARGES AND AREAS ADJASCENT TO THEM. REPLACE GRATING POST COMPLETION OF REPAIR AND RECOAT WORK ON INLETS DISCHARGES GRATINGS. NOTE: - VAVES ARE REQUIRED TO BE OPENED BY SS/YARD(>100MM) |
| 28 | SR2 - CARRY OUT 100% VISUAL SURVEY AND ENDOSCOPY OF ALL SEA CHEST/SEA TUBE/ UW INLETS/ OUTLETS AND OBD FOR INTERNAL CORROSSION, PITTING AND CRACKS ETC. SEA TUBE GRADED CRITICAL DURING THE PRECEEDING REFITS ARE TO BE ULTRASINICALLY SURVEYED AND REPAIRED AS PER INSTRUCTION CONTAINED IN THE NAVY ORDER 01/15. UNDERTAKE AIR PRESSURE TEST OF ALL REPAIRED/ RENEWED SEA TUBES/ SEA CHEST OF OBD POST STRUCTURAL REPAIR/ RENEWAL. NOTE - 1. ALL SEATUBES ARE TO BE SURVEYED IRRESPECTIVE OF THEIR MATERIAL. DURING SURVEY OF SEATUBE, SPECIFIC ATTENTION IS TO BE PAID TO TNE NECK REGION. ALL BRANCH PIPE/ FLUSH THROUGH LIiNE WELDED TO SEACHEST/ SEATUBE ARE TO BE SURVEYED AS PART OF SEATUBE.2. CONDITIONAL ASSESSMENT OF BIMETALIC JOINT IS TO BE CARRIED OUT WHILST UNDERTAKING SURVEY OF THE SEA TUBE. 100%ENDOSCOPY OF SEATUBES IS TO BE CARRIED OUT POST REPAIRS AND APPLICATION OF COATING PRIOR TO UNDOCKING OF THE SHIP 3. SEA TUBE NOT ACCESSIBLE FOR SURVEY AND PAINTING ARE TO BE RENEWED. |
| 29 | SR3 - ALL SEA CHEST/ SEA TUBE AND OBDS WHICH ARE REPAIRED BY BUILD-UP/ RENEWAL ARE TO BE AIR PRESSURE TESTED IAW PARA 47 OF NO 01/15. PRESSURE TESTING ARE TO BE CARRIED OUT BY REFITTING AUTHORITES IN PRESENCE OF SHIP'S STAFF AND QUALITY CONTROL INSPECTORS OF THE REFITTING AUTHORITY. UNDER NO CIRCUMSTANCE, THE PROCEDURE OF RUNNING PRESSURE TEST IS TO BE USED TO CONFIRM THE STRUCTURAL INTEGRITY OF THEASE SPACES. |
| 30 | SR4 -RESTORE/RENEW PAINT SCHEME OF ALL UNDERWATER SEA CHEST/SEA TUBES/OBDS WITH APPORIATE PAINT SCHEME POST COMPLETION OF SURVEY AND REPAIR AS PER NO 53/16 AND POLICY DIRECTIVES ISSUED BY IHQ/DNA TIME TO TIME SEA TUBES REMOVED FOR REPAIR TO BE ABRASIVE BLASTED AND COATED WITH PAINT SCHEME PRIOR TO FITMENT. PLATE LAPS,WELDS ETC TO BE FAIRED WITH EPOXY PUTTY BEFORE APPLICATION OF PAINT. |
| 31 | SR3 - APPLY A MIXTURE OF LINSEED OIL AND PARAFFIN (1:4 OR 5) TO THE ENTIRE DECK |
| 32 | 3M2: CHECK FOR CRACKS/ LOSS OF INTEGRITY IN BOWSPIRIT USING VISUAL TECHNIQUES. |
| 33 | A1: INSPECT HALYARDS FOR ANY DEFECT/ DAMAGE AND REPLACE DEFECTIVE COMPONENTS |
| 34 | A2: INSPECT STANDING RIGGING, CLEVIS PINS BY SLACKING THE RIGGING AND PULLING THE PINS FOR WEAR AND DISTORSION. UPON REINSERTION TURN THE PINS 180 DEGREES. IN CASE OF ANY WEAR AND TEAR, REPLACE AS NECESSARY. |
| 35 | A3: INSPECT SLINGS, NETS BASKETS, CHAINS, LINKS, RINGS, SHACKELS EYE PLATES, BOTTLE SCREWSLIP, BLOCKS AND ALL OTHER RIGGING ACCESSORIES IN CASE OF ANY WEAR AND TEAR, RENEW/ REPLACE AS NECESSARY. |
| 36 | 24M1: CARRY OUT LOAD TESTING OF EYE PLATES, BOTTLE SCREWS AND OTHER RIGGING ACCESSORIES AS PER INBR 1552. IN CASE OF ANY REPAIRS CARRIED OUT ON ANY LOAD BEARING MEMBER, THE APPLIANCE IS TO BE LOAD TESTED IRRESPECTIVE OF WHETHER THE LOAD TESTING IS DUE. |
| 37 | SR1 - EXAMINE ALL RUNNING RIGGING AND RENEW AS PER RUNNING RIGGING SCHEDULE SERIALS ( EXCEPT YARDS, GAFFS, BOOMS AND ASSOCIATED FITTINGS) |
| 38 | SR2 - UNDERTAKE INSPECTION OF BOWSPRIT, RUNNING, RIGGING,YARDARMS, STANDING RIGGING AND ASSOCIATED ACCESSORIES THROUGH OEM. NOTE: - OEM INSPECTION TO INCLUDE INSPECTION OF MAST AND MAST STEP (WITHOUT REMOVAL) IN PRECEDING SHORT REFIT TOWARDS UNDERTAKING WORK AS PER MR1 ROUTINE IN FORTHCOMING MEDIUM REFIT. |
| 39 | SR7 - UNDERTAKE IN-SITU VISUAL SURVEY AND EXAMINATION OF LIFTING AND ASSOCIATED CONNECTING HOOK/ FASTENING INCLUDING DIMENSIONAL CHECKS.NOTE:- LIMITS FOR WEAR DOWN TO BE RESTRICTED IAW 2.13 OF INBR 1552. |
| 40 | SR6 - EXAMINE ASSOCIATED EYE PLATES AND STRUCTURE TO WHICH THEY ARE ATTACHED AND RENEW EYE PLATES IF DEFECTIVE.NOTE:-1. EXAMINE DAVIT FOR DEFECT BEFORE AND AFTER HANDLING THEIR NORMAL LOAD. WHEN DAVITS ARE USED FOR HANDLING AMMUNITION, EXAMINE ALSO AT INTERVALS DURING OPERATION.2. IF ANY PART EFFECTING THE STRENGTH OF LIFTING AND HANDLING EQUIPMENT BECOMES DEFECTIVE AND IS REPAIRED OR RENEWED, SHIP STAFF INSPECT BEFORE FURTHER USE AND ARRANGE FOR FURTHER STANDARD TEST AT FIRST OPPORTUNITY.3. INSPECT THE BRAKE LININGS, PINS, BUSHES, AND GEARS FOR WEAR AND TEAR. |
| 41 | SR1 - ENSURE ANCHOR WINDLASS FOUNDATION BOLTS FOR TIGHTNESS. EXAMINE CONDITION OF HULL STRUCTURE AT WINDLASS MOUNTING AND ENSURE WATERTIGHT INTEGRITY. |
| 42 | SR2- REMOVE, EXAMINE AND REASSEMBLE THE FOLLOWING AS PER INSTRUCTION AND MAINTENANCE MANUAL:(A) CLUTCH SHIFTING ARRANGEMENT.(B) SPOOLING GEAR ASSEMBLY. |
| 43 | SR3 - OPEN UP GEAR BOX AND EXAMINE GEAR TEETH AND BEARINGS FOR DAMAGE/WEAR. RENEW AS NECESSARY. |
| 44 | SR1 - SURFACE PREPARATION BY HYDRO BLASTING OF THE ANCHOR, CHAIN CABLE AND ASSOCIATED ACCESSORIES IS TO BE CARRIED OUT PRIOR UNDERTAKING VISUAL SURVEY. QTY 16 SHACKLES AND 02 ANCHOR AND 02 SWIWEL PIECE |
| 45 | SR5 UNSCREW BOTTLE SLIP/COMPRESSOR WHEREAS FITTED TO ITS FULLEST EXTENT AND THOROUGHLY CLEAN AND GREASE THREADS BEFORE ASSEMBLY. |
| 46 | SR6 - UNDERTAKE SURVEY OF ADAPTER PIECE FOR CRECKS OR WEAR AND UNDERTAKE REPAIR AS PER NO 02/21. |
| 47 | SURVEY ALL DECK FITTINGS ASSOCIATED WITH ANCHOR CHAIN CABLEARRANGEMENT IE DECK EYES/ EYE PLATES INCLUDING GULLETINE/GULLETINE ROLLER, COMPRESSOR WITH COMPLETE STRUCTURE WHEREASFITTED PAYING PARTICULAR ATTENTION EYE PLATES/ EYE BOLTS ETC FORWEAR, CORROSION/ DETERIORATION AND OVALITY OF HOLE. UNDERTAKEREPAIR/ RENEWAL IAW NO 02/21. |
| 48 | SR9 - SURVEY ANCHOR, CHAIN CABLE SWIVEL ADAPTER, SHACKLES AND ALL ASSOCIATED FITTINGS. BREAK, CLEAN AND GREASE ALL JOINING SHACKLES. (AN EXPERIENCED DOCKYARD BLACKSMITH IS TO ASSIST THE SURVEY). QTY - 18 SHACKLESBREAK, CLEAN AND GREASE ALL JOINING SHACKLES. UNDERTAKE REPAIR/ RENEWAL AS APPLICABLE IAW NO 02/21. FORWARD A REPORT ON IN 305/ NSO 269(B) TO AUTHORITIES AS MENTIONED IN PARA 15 OF NO 02/21. |
| 49 | SR12 - UNDERTAKE PRESERVATION OF THE ANCHORS, CHAIN CABLES AND ACCESSORIES HELD ONBOARD AS PER NO 53/16. QTY - 18 SHACKLES |
| 50 | UNDERTAKE AIR PRESSURE TESTING OF ALL SLUDGE AND BILGE TANKS WHICH ARE REPAIRED BY BUILD-UP/RENEWAL IAW PARA 47 OF NO 01/15.NOTE: - THE PRESSURE TESTING IS TO BE CARRIED OUT BY REFITTING AUTHORITIES IN THE PRESENCE OF SHIP STAFF AND QC INSPECTORS OF THE REFITTING AUTHORITY. UNDER NO CIRCUMSTANCE, THE PROCEDURE OF RUNNING PRESSURE TEST IS TO BE USED TO CONFIRM THE STRUCTURAL INTEGRITY OF THESE SPACES. |
| 51 | SR1 - WEIGH THE RIB AND COMPARE WITH IDEAL WEIGHT. RECORD THE SAME IN BOAT LOG BOOK. UNDUE INCREASE OF WEIGHT, IF ANY BE REPORTED FOR DETAILED EXAMINATION.(NOTE: - FOR AFLOAT UNITS DURING EVERY REFITS.) |
| 52 | SR3 - EXAMINE DOOR SURFACES, SEALING WEDGE AND BLOCKING CONES ETC FOR DAMAGE AND CARRY OUT REPAIRS AS NECESSARY. |
| 53 | SR6 REPLACE/RENEW DEFECTIVE/ BROKEN/ CORRODED EARTHING CONNECTIONS AS PROJECTED BY SS. |
| 54 | SR1 BROWS ARE TO BE EXAMINED, REPAIRED AS NECESSARY. DOCKYARD TESTING NOT MORE THAN 16 MONTHS.NOTE: BROWS ARE TO BE TESTED AT THE FIRST OPPORTUNITY AFTER ANY REPAIRS CARRIED OUT BY SHIPS STAFF. |
| 55 | RIGGING |
| 56 | UNDERTAKE THOROUGH CHECK OF THE STRUCTURESR1 EXAMINE MAST STRUCTURE, WHIP AERIAL PLATFORMS AND THESURROUNDING STRUCTURE ON DECK, EYE PLATES, LOAD CARRYINGMEMBERS FOR SIGNS OF CORROSION. EXAMINE BOLTED, RIVETED ANDINTERMITTENT WELDED STRUCTURE CONNECTIONS FOR SIGNS OFFRACTURE. PORTABLE AND SEMI PORTABLE FITTINGS TO BE REMOVEDFOR CLOSER EXAMINATION OF STRUCTURE UNDERNEATH. ANY KNOWNDEFECTS TO BE RAISED TO DOCKYARD FOR RECTIFICATION.SR2 CARRY OUT LOAD TESTING OF EYE PLATES, BOTTLE SCREWS ETC IF DUE(NOT TO EXCEED 27 MONTHS). |
| 57 | RENEW COMPLETE THE FOLLOWING RUNNING RIGGING. |
| 58 | FORE MASTHEAD JIB HALLIARD |
| 59 | FORE MASTHEAD JIB DOWNHAUL |
| 60 | FORE MASTHEAD JIB TACK PURCHASE |
| 61 | FORE MASTHEAD JIB SHEETS |
| 62 | FORE TOPGALLANT OUTER JIB HALLIARD |
| 63 | FORE TOPGALLANT OUTER JIB DOWNHAUL |
| 64 | FORE TOPGALLANT OUTER JIB TACK PURCHASE |
| 65 | FORE TOPGALLANT OUTER JIB SHEETS |
| 66 | FORE TOPGALLANT INNER JIB HALLIARD |
| 67 | FORE TOPGALLANT INNER JIB DOWNHAUL |
| 68 | FORE TOPGALLANT INNER JIB TACK PURCHASE |
| 69 | FORE TOPGALLANT INNER JIB SHEETS |
| 70 | FORE STAYSAIL HALLIARD |
| 71 | FORE STAYSAIL DOWNHAUL |
| 72 | FORE STAYSAIL TACK PURCHASE |
| 73 | FORE STAYSAIL SHEETS |
| 74 | MAIN STAYSAIL HALLIARD, PURCHASE & TACK PENDANT |
| 75 | MAIN STAYSAIL DOWNHAUL |
| 76 | MAIN STAYSAIL SHEETS |
| 77 | MAIN TOPMAST STAYSAIL HALLIARD |
| 78 | MAIN TOPMAST STAYSAIL DOWNHAUL |
| 79 | MAIN TOPMAST STAYSAIL SHEETS |
| 80 | MIZZEN STAYSAIL HALLIARD & TACK PURCHASE |
| 81 | MIZZEN STAYSAIL DOWNHAUL |
| 82 | MIZZEN STAYSAIL SHEETS |
| 83 | MIZZEN TOPMAST STAYSAIL HALLIARD, PURCHASE & TACK PENDANT |
| 84 | MIZZEN TOPMAST STAYSAIL DOWNHAUL |
| 85 | MIZZEN TOPMAST STAYSAIL SHEETS |
| 86 | LOWER SPANKER PEAK HALLIARD |
| 87 | LOWER SPANKER THROAT HALLIARD |
| 88 | LOWER SPANKER GAFF VANGS |
| 89 | SPANKER TOPPING LIFT |
| 90 | LOWER SPANKER HEAD INHAUL & OUTHAUL |
| 91 | LOWER SPANKER BRAILS |
| 92 | LOWER SPANKER FOOT INHAUL |
| 93 | LOWER SPANKER FOOT OUTHAUL |
| 94 | SPANKER SHEETS |
| 95 | MIZZEN BOOM PREVENTER |
| 96 | UPPER SPANKER TOPPING LIFT |
| 97 | UPPER SPANKER THROAT HALLIARD |
| 98 | UPPER SPANKER GAFF VANGS |
| 99 | UPPER SPANKER HEAD OUTHAUL |
| 100 | UPPER SPANKER HEAD INHAUL |
| 101 | UPPER SPANKER BRAILS |
| 102 | UPPER SPANKER FOOT OUTHAUL |
| 103 | UPPER SPANKER FOOT INHAUL |
| 104 | SPANKER TOPSAIL HALLIARD |
| 105 | SPANKER TOPSAIL OUTHAUL |
| 106 | SPANKER TOPSAIL DOWNHAUL |
| 107 | TRISAIL HALLIARD |
| 108 | TRISAIL TACK PURCHASE |
| 109 | TRISAIL SHEET |
| 110 | FORE COURSE LIFTS |
| 111 | FORE COURSE BRACES |
| 112 | FORE COURSE SHEETS |
| 113 | FORE COURSE TACKS AND BOWLINES |
| 114 | FORE COURSE BUNTLINES |
| 115 | FORE COURSE CLEW LINES |
| 116 | FORE COURSE REEF PURCHASES |
| 117 | FORE TOPSAIL HALLIARD |
| 118 | FORE TOPSAIL LIFTS |
| 119 | FORE TOPSAIL BRACES |
| 120 | FORE TOPSAIL SHEETS |
| 121 | FORE TOPSAIL BUNTLINES |
| 122 | FORE TOPSAIL CLEWLINES |
| 123 | FORE TOPSAIL REEF PURCHASES |
| 124 | FORE TOPGALLANT HALLIARD |
| 125 | FORE TOPSAIL LIFTS |
| 126 | FORE TOPGALLANT BRACES |
| 127 | FORE TOPGALLANT SHEETS |
| 128 | FORE TOPGALLANT BUNTLINES |
| 129 | FORE TOPGALLANT CLEWLINES |
| 130 | FORE ROYAL HALLIARD |
| 131 | FORE ROYAL LIFTS |
| 132 | FORE ROYAL BRACES |
| 133 | FORE ROYAL SHEETS |
| 134 | FORE ROYAL BUNTLINES |
| 135 | FORE ROYAL CLEWLINES |
| 136 | MAIN COURSE LIFTS |
| 137 | MAIN COURSE BRACES |
| 138 | MAIN COURSE SHEETS |
| 139 | MAIN COURSE TACKS AND BOWLINES |
| 140 | MAIN COURSE BUNTLINES |
| 141 | MAIN COURSE CLEW LINES |
| 142 | MAIN COURSE REEF PURCHASES |
| 143 | MAIN TOPSAIL HALLIARD |
| 144 | MAN TOPSAIL LIFTS |
| 145 | MAIN TOPSAIL BRACES |
| 146 | MAIN TOPSAIL SHEETS |
| 147 | MAIN TOPSAIL BUNTLINES |
| 148 | MAIN TOPSAIL CLEWLINES |
| 149 | MAIN TOPSAIL REEF PURCHASES |
| 150 | MAIN TOPGALLANT HALLIARD |
| 151 | MAIN TOPSAIL LIFTS |
| 152 | MAIN TOPGALLANT BRACES |
| 153 | MAIN TOPGALLANT SHEETS |
| 154 | MAIN TOPGALLANT BUNTLINES |
| 155 | FORE TOPGALLANT CLEWLINES |
| 156 | MAIN ROYAL HALLIARD |
| 157 | MAIN ROYAL LIFTS |
| 158 | MAIN ROYAL BRACES |
| 159 | MAIN ROYAL SHEETS |
| 160 | MAIN ROYAL BUNTLINES |
| 161 | FORE ROYAL CLEWLINES |
| 162 | FORE, MAIN AND MIZZEN GANTLINES |
| 163 | HANDY BILLIES |
| 164 | ENSIGN HALLIARD |
| 165 | COURTESY FLAG HALLIARDS |
| 166 | BOAT DAVIT MIDSHIP TACKLES |
| 167 | BOAT DAVIT VEERING TACKLES |
| 168 | FOOTROPES |
| 169 | FLEMISH HORSES |
| 170 | STURRUPS |
| 171 | GASKETS |
| 172 | CLEW LASHINGS |
| 173 | FOREMAST CANELINES |
| 174 | MAINMAST CRANELINES |
| 175 | MIZZEN CRANELINES |
| 176 | SAFETY LINE ON ALL YARDS |
| 177 | SAFETY LINE ON BOWSPRIT |
| 178 | SAFETY LINE ON ALL TOPS |
| 179 | DETAILED INSPECTION OF MASTS, YARDS, GAFFS, BOOM AND ASSOCIATED FITTINGS INSITU |
| 180 | REMOVAL AND REFITMENT OF YARD CHAIN SLINGS |
| 181 | SUPPLY OF ONE FULL SETS OF SAILS AND FITEMNT ON BOARD. SAILS TO BE SUPPLIED THROUGH OEM NORTH SAILS |
| 182 | SUPPLY OF FULL SET OF SAIL COVERS AND SAIL BAGS AS PER SPECIFICATION RECEIVED FROM INDIAN NAVY |
| 183 | SUPPLY OF SQUARE SAIL GASKETS |
| 184 | PAINTING OF MASTS, YARDS, GAFFS, BOOM AS PER ORIGINAL PAINT SPECIFICATION. M/S AKZO NOBEL MAKE AWLGRIP YACHT PAINT SCHEME TO BE USED. PAINT AND SERVICES FOR APPLICATION OF MAST PAINT TO BE SOURCED THROUGH M/S WEST COAST MARINE YACHT SERVICES AUTHORISED REP OF M/S AKZO NOBEL |
| 185 | INSPECTION AND REPAIRS / REPLACEMENT OF DOLPHIN STRIKER |
| 186 | MANUFACTURE AND FITMENT OF NEW SAFETY NET UNDER BOWSPRIT |
| 187 | INSPECTION AND REPAIRS TO ALL METAL LUGS, DECK CLENCHES, EYES, CLEATS AND PLATES WHERE STANDING AND RUNNING RIGGING SYSTENS ARE FITTED |
| 188 | REPLACEMENT OF WOODEN RATLINE BARS ALONG WITH SUPPORTING ALUMINIUM ANGLES, SS 316 NUTS BOLTS ETC |
| 189 | BOSUN CHAIRS TO BE RENEWED AS PER SAMPLE, QTY - 05 NOS. |
| 190 | WOODEN LADDER TO BE REMOVED/ RENEWED AND REFITTED POST VARNISHED, QTY - 05, MAT - TEAK WOOD. |
| 191 | 50 IN NOS BELAY PINS DAMAGED AT VARIOUS LOCATIONS. SAME TO BE MANUFACTURED AS PER SAMPLE, MAT - SS, QTY - 50 NOS. |
| 192 | RA FOR SERVICEABILITY CHECKS/ LOAD TEST OF SHROUDS BASE PLATE. QTY -15. |
| 193 | RENEWAL OF ALL CRANE LINE OF CROSS TREE (TYPE - 3-STRAND, SIZE- 10MM, MAT - UV PROTECTIVE POLYESTER, COLOUR- BEIGE), QTY -100 RMT |
| 194 | REMOVE FIFE RAILS FROM DECK. REPAIR/ RENEW AND REFIT. CHECK CONDITIONS OF DECK PLATES. SS, TEAK WOOD. AS PER SAMPLE POST FITMENT OF MAST. QTY - 03, MAT - SS, TEAK WOOD, BRASS CAP FOR BELAY PIN PROVIDED BY THE SHIPYARD. |
| 195 | REMOVAL OF BOWSPRIT. INSPECTION AND RECOMMENDATIONS ON REPAIRS OF BOWSPRIT |
| 196 | SUPPLY OF 2 FULL SETS OF SAILS AND FITEMNT ON BOARD. SAILS TO BE SUPPLIED THROUGH OEM NORTH SAILS |
| 197 | SUPPLY OF FULL SET OF SAIL COVERS AND SAIL BAGS AS PER SPECIFICATION RECEIVED FROM INDIAN NAVY |
| 198 | SUPPLY OF SQUARE SAIL GASKETS |
| 199 | SUPPLY OF RIGGING HARNESS |
| 200 | MANUFACTURE AND FITMENT OF NEW SAFETY NET UNDER BOWSPRIT |
| 201 | REPLACEMENT OF WOODEN RATLINE BARS ALONG WITH SUPPORTING ALUMINIUM ANGLES, SS 316 NUTS BOLTS ETC |
| 202 | MAINTENANCE OF ALL POWERED WINCHES ON UPPER DECK (THESE ARE REQUIRED BY RIGGEERS TO GO ALOFT) |
| 203 | 150 IN NOS BELAY PINS DAMAGED AT VARIOUS LOCATIONS. SAME TO BE MANUFACTURED AS PER SAMPLE, MAT - SS, QTY - 150 NOS. |
| 204 | RA FOR SERVICEABILITY CHECKS/ LOAD TEST OF SHROUDS BASE PLATE. QTY -15. |
| 205 | RENEWAL OF ALL CRANE LINE OF CROSS TREE (TYPE - 3-STRAND, SIZE- 10MM, MAT - UV PROTECTIVE POLYESTER, COLOUR- BEIGE), QTY -100 RMT |
| 206 | HULL - PART III |
| 207 | ABER REPLACEMENT OF ANCHOR WINDLASS IS TO BE UNDERTAKEN VIEW PERFORMANCE WINDLASS IS SUBOPTIMAL. QTY - 01. SOW IS AS FOLLOWS: - (I) REMOVAL OF EXISTING ANCHOR WINDLASS INCLUDING FITTINGS. (II) REMOCAL OF OLD FOUNDATION. (III) FITMENT OF NEW FOUNDATION.(IV) FITMENT OF NEW ANCHOR WINDLASS. (IV) FUNCTIONAL TRIALS AND LOAD TESTING OF THE WINDLASS IS TO BE PROOVED POST COMPLETION OF REPLACEMENT. APPROVAL FOR ABER REPLACEMENT IS UNDER PROCESS. (ALL JOB RELATED TO FITMENT OF ANCHOR WINDLASS INCLUDING DEGUTTING, REGUTTING, TO BE UNDERTAKEN BY YARD) |
| 208 | HULL - PART II |
| 209 | WATER LEAKAGE OBSERVED FROM FOLLOWING LOCATION IN WEATHER DECK: - (I) FORE MAST AND FIFRAIL. (II) MAIN MAST AND FIFRAIL. (III) PORT AND STBD FIFRAIL ON FOXLE. (IV) MIZZEN MAST AND FIFRAIL. (V) 14 NUMBERS SKYLIGHTS, (VI) SOFT PATCHES ON BRIDGE DECK. RA FOR REPAIR OF THE SAME. JOB INVOLVE: - REMOVAL OF WOODEN DECK, SEALING OF ALL DECK PENETRATING NUTS, BOLTS AND FITTINGS USING SEALING COMPOUND AND RESTORING OF WOODEN DECK. APPROX AREA FOR WOOD REMOVAL 40 SQMT. |
| 210 | ALL THE HULL STRUCTURE BENEATH STANDING RIGGING LIKE SHROUDS BASE PLATE, MASTS ETC TO BE SURVEYED AND RENEWED AS PER SURVEY REPORT. |
| 211 | RUST MARK OBSERVED AT INDICATED LOCATION IN THE FOLLOWING COMPARTMENT. PAINT TOUCH-UP TO BE UNDERTAKEN AT RUSTED AREA AS PER PAINT SCHEME: -(I) STP COMPARTMENT(II) REF COMPARTMENT(III) ELECTRICAL STORE(IV) AFT PUMP ROOM(V) CABLE LOCKERS PORT AND STBD(VI) BOSUN STORE(VII) ENG. STORE(VIII) ENGINE ROOM(IX) STEERING BILGE. NOTE: - PAINT TO BE PROVIDED BY YARD |
| 212 | PAINTING OF ABOVE WATER SHIPSIDE AND SUPERSTRUCTURE DETERIORATED/PLEED OFF AT SCATTERED LOCATION. PAINT TOUCH UP OF THE SAME TO BE CARRIED OUT, QTY- 250 SQMT. PAINT TO BE PROVIDED BY YARD. |
| 213 | ADVANCE INTERNAL FINISH COATING OF INTERNAL COMPARTMENT'S EXPOSED DECKS, BULKHEADS AND DECKHEAD TO BE CARRIED OUT AS PER IHQ MoD(N) LETTER PP-144/2021/MB/NC/PAINT-NCD 1485 DATED 18 OCT 21 VIEW PAINT DETERIORATED, PLEED OFF. QTY - 400 SQMT. PAINT TO BE PROVIDED BY THE YARD. |
| 214 | CLEANING OF THE FOLLOWING TANKS TO BE UNDERTAKEN FOLLOWED BY CONDITION BASED TOUCH UP PAINTING: - (I) FRESH WATER TANKS , QTY - 06, (II) GREY WATER TANKS - QTY - 04, (III) DIRTY OIL TANK AND (IV) LUB OIL TANKS. APPROX AREA - 1200 SQMT |
| 215 | DEGUTTING AND RE-GUTTING OF LAGGING OF HOT WORK AFFECTED AREA TO BE UNDERTAKEN, QTY 300 SQMT. NOTE:- FAT INSULATION LAGGING TO BE USED DURING REGUTTING OF LAGGING. |
| 216 | TWO IN NUMBERS MARLIN SPIKES DEFORMED/ DAMAGED. SAME TO BE MANUFACTURED AS PER SAMPLE, QTY - 02. LENTGH - 6 INCH, DIA- ONE INCH. |
| 217 | 02 IN NUMBERS SWIVEL PIECE JAMMED TO BE EASE OUT. HEATING ASSISTANCE REQUIRED FOR 02 SWIVEL PIECE, 02 IN NUMBER ANCHOR RING (02+02) |
| 218 | TWO IN NUMBER CHAIN HOOKS DAMAGED TO BE RENEWED AS PER SAMPLE, QTY - 02 , MAT - MS ,SIZE- 20MMX60MM |
| 219 | TWO IN NUMBERS GUILLOTINE HEAVILY CORRODED. SAME TO BE RENEWED ALONG WITH SECURING PINS. MAT - MS SIZE- 2X2X7 INCH |
| 220 | ANCHOR STROP (P & S) DETERIORATED. TO BE MANUFACTURED AS PER SAMPLE. QTY - 02, MAT- 10 MM SWR WITH THIMBLE EYE. LENGTH - 830MM |
| 221 | COMPLETE OVERHAULING OF ANCHOR WINDLASS IS TO BE UNDERTAKEN VIEW OBNORMAL NOISE OBSERVED FROM ANCHOR WINDLASS. SOW IS AS FOLLOWS: - (I) OPENING OF GEAR BOX AND OVERHAULING. (II) OPENING OF GIPSSY/ CABLE HOLDER AND OVERHAULING. (III) REPLACEMENT OF MECHANICAL BRAKE SHOE LINBER (IV) TEST AND TRIALS TO BE PROOVED POST OVERHAULING. |
| 222 | BOAT DAVIT ( P & S) ROLLER DETERIORATED TO BE RENEWED. QTY - 02 MAT - PVC. DIA - 40MM, LENGTH- 60MM |
| 223 | BOAT DAVIT (P & S) STRUCTURE AND FOUNDATION CORRODED AND PITTED. RA FOR SURVEY AND REPAIR AS PER SURVEY REPORT. DIA - 1 FEET, LENGTH- 6 MTR |
| 224 | ABNORMAL NOISE OBSERVED FROM BOAT DAVITS ( P & S). OVERHAULING OF BOTH BOAT DAVIT TO BE CARRIED OUT . JOB INVOLVE DISMANTLING OF BOAT DAVITS, OVERHAULING OF DAVITS AND FITMENT OF THE SAME. NEW SS BOLTS TO BE USED WHILE FITMENT. QTY - 02. |
| 225 | TOP COAT OF EPOXY DECK COVERING PERISHED. THE SAME TO BE RENEWED, AREA - 70 SQMT. |
| 226 | FRESHWATER PIPE DEFECTIVE IN 05 WC. RA FOR REPAIR/ RENEWAL OF THE SAME. MAT - CU-NI, QTY 10 RMT. DIA - 1/2 INCH |
| 227 | WATER LEAKAGE OBSERVED IN HOT WATER LINE IN SENIOR SAILOR BATHROOM AND OFFICER'S BATHROOM. THE SAME TO BE RENEWED WITH END FITTING. REMOVAL AND FITMENT OF PANELING TO BE UNDERTAKEN PRE AND POST COMPLETION OF WORK RESPECTIVELY. MAT- CU-NI, DIA - 1/2 INCH. |
| 228 | WATER LEAKAGE OBSERVED IN FRESH WATER LINE IN JUNIOR SAILOR BATH, SS BATH AND OFFICER'S BATHROOM, QTY 70 RMT, MAT - CU-NI, DIA - 1/2 INCH. THE SAME TO BE RENEWED ALONG WITH END FITTINGS. JOB INVOLVE: - (I) REMOVAL OF OLD LINES AND FITMENT OF NEW LINES. (II)REMOVAL AND FITMENT OF ASSOCIATED PANELING. |
| 229 | 12 IN NUMBERS HEALTH FAUCET DAMAGED TO BE RENEWED ALONG WITH STAND. MAKE - JAGUAR |
| 230 | 20 IN NUMBERS GUARDRAILS DAMAGED. SAME TO BE RENEWED ALONG WITH END FITTING, QTY - 100 MTR MAT - PVC |
| 231 | FIXED GUARD ON CHART-HOUSE TOP DETERIORATED. RA FOR RENEWAL OF THE SAME, QTY - 20 RMT |
| 232 | 15 IN NUMBERS GUARDRAILS STANCHION DETERIORATED TO BE RENEWED WITH IT'S SHOE. MAT - AL |
| 233 | LOAD TESTING OF FOLLOWING TO BE CARRIED OUT.(A) DECK EYE PORT FOR BOTTLE SCREW SLIP-01 |
| 234 | (B) DECK EYE STBD FOR BOTTLE SCREW SLIP-01 |
| 235 | (C) BOTTLE SCREW SLIP PORT (FOXLE) - 01 |
| 236 | (D) BOTTLE SCREW SLIP STBD (FOXLE) - 01 |
| 237 | (E) ANCHOR STROP - 02 |
| 238 | (F) CABLE CLENCH PORT - 01 |
| 239 | (G) CABLE CLENCH STBD - 01 |
| 240 | (H) BOAT DAVIT PORT - 01 |
| 241 | (J) BOAT DAVIT STBD - 01 |
| 242 | (K) FOOD SERVICE LIFT - 01 |
| 243 | (L) BOLLARDS - 20 |
| 244 | (M) FAIR LEADS - 10 |
| 245 | (N) MOORING WINCHES - 04 |
| 246 | (P) SHIPS BROW - 02 |
| 247 | (Q) BOAT FALLS - 02 |
| 248 | (R) BOAT SLINGS - 02 |
| 249 | (S) AFT ANCHOR WITH WIRE ROPE - 01 |
| 250 | (T) CATTING DAVITS (P&S)- 02 |
| 251 | (U) SAFETY PREVENTER (P&S) – 02 |
| 252 | (V) BOAT ARH – 02 NOS |
| 253 | (W) DECK EYE FOR ANCHOR STROP (P&S) – 4 NOS |
| 254 | (X) GUARDRAILS – 30 NOS |
| 255 | CARRY OUT CLEANING / SURVEY OF V1 AND V2 TANKS AND REPAIR AS NECESSARY. INSPECT THE INTERNAL AND EXTERNAL PAINT COATING AND RECOAT WITH APPROPRIATE PAINT SCHEME AFTER COMPLETION OF REPAIRS AND SURFACE PREPARATION. |
| 256 | CHECK FUNCTION OF CONTROL PANEL AND CARRYOUT OUT CALIBRATION OF LEVEL SWITCHES OF V1 AND V2 TANKS. REPLACE IF NECESSARY. |
| 257 | OVERHAUL / REPAIR THE FOLLOWING :(A) OVERBOARD PUMP(B) DISCHARGE PUMP(C) MACERATOR PUMP(D) IMO PUMP (IF FITTED)(E) ROTARY AIR COMPRESSOR |
| 258 | INSPECT FREENESS OF VENT LINE OF V1 AND V2 TANKS BY BLOWING THROUGH WITH AIR. |
| 259 | OVERHAULING OF TWO IN NOS GREY WATER DISCHARGE VALVE TO BE CARRIED OUT VIEW VALVE NOT HOLDING. QTY - 02. DIA - 65 MM |
| 260 | 04 IN NUMBERS GREY WATER TANK CONNECTING VALVE JAMMED. OVERHAULING OF THE SAME TO BE CARRIED OUT. DIA - 65 MM |
| 261 | THREE IN NUMBER DECK DRAIN SHIP'S GALLEY CHOCKED. TO BE RENEWED. QTY - 18 RMT , MAT- CU-NI, DIA - 50MM, SOW INVOLVE: - (I)DEGUTTING OF DECK COVERING APPROX AREA - 05 SQMT. (II) REMOVAL OF OLD DRAIN LINES AND FITMENT OF NEW DRAIN LINES. (III) EPOXY DECK COVERING IS TO BE RESTORED POST COMPLETION OF WORK. |
| 262 | UNDERTAKE CHEMICAL CLEANING OF ALL SYSTEM/SEWAGE PIPELINE VIEW CLOGGED AND REPAIR/RENEWAL AS NECESSARY, QTY- 80 RMT, DIA - 50MM. |
| 263 | GREY WATER PIPE LINE DETERIORATED AT FWD AND AFT PUMP ROOM TO BE RENEWED. QTY - 15 RMT, MAT - CU-NI, DIA - 50MM |
| 264 | THREE IN NUMBER DRAIN LINE CHOCKED IN SENIOR SAILOR'S BATHROOM, TO BE RENEWED. SOW INVOLVE : - (I) DEGUTTING OF DECK COVERING AND DECK , APPROX AREA 4 SQMT, (II) REMOVAL OF OLD DRAIN LINE AND FITMENT OF NEW DRAIN LINES, QTY - 20 RMT, MAT - CU-NI, DIA 50MM (III) EPOXY DECK COVERING AND DECK PLATE ARE TO BE RESTORED POST COMPLETION OF WORK. |
| 265 | SIX IN NUMBER DRAIN LINES CHOCKED IN JUNIOR SAILOR'S BATHROOM AND CADET'S BATHROOM. SAME TO BE RENEWED. MAT - MS. SOW INVOLVE: - (I) DEGUTTING OF DECKCOVERING , APPROX AREA 5 SQMT, (II) REMOVAL OF OLD DRAIN LINES AND FITMENT OF NEW DRAIN LINES, QTY - 20 RMT, MAT - CU-NI, DIA 50MM. (III) EPOXY DECK COVERING AND DECK PLATE IS TO BE RESTORED POST COMPLETION OF WORK. |
| 266 | WATER LEAKAGE OBSERVED FROM 20 IN NUMBERS SHIP SIDE SCUTTLES. ALL SIDE SCUTTLE TO BE REPLACED. WATER HOSE TEST IS TO BE CARRIED OUT POST REPAIR/ RENEWAL. |
| 267 | RETAINING HOOK OF OFFICER'S BATHROOM AFT SIDE SCUTTLE DETERIORATED TO BE REPAIRED IN SITU. |
| 268 | RUBBER BEADING OF 20 IN NUMBERS SIDE SCUTTLES DETERIORATED TO BE REPLACED. |
| 269 | 10 IN NUMBERS TUMBLER BOLTS JAMMED/ DEFECTIVE. SAME TO BE RENEWED. |
| 270 | OIL LEAKAGE OBSERVED FROM 10 IN NOS 4/2 PILOT VALVES. RA FOR REPLACEMENT OF THE SAME. QTY - 10. DIA - 12MM |
| 271 | LEAKAGE OBSERVED FROM HYDRAULIC HAND PUMP AND PIPE CONNECTIONS. REQUEST ASSISTANCE FOR REPAIR. QTY-05 |
| 272 | 10 IN NUMBER HYDRAULIC DOOR OPENING LEVER CORRODED/ BROKEN. TO BE RENEWED AS PER SAMPLE. MAT - MS/ GI PIPE. DIA- 3/4 INCH APPROX |
| 273 | OVERHAULING OF 10 IN NUMBER HYDRAULIC HAND PUMPS JAMMED/ NOT WORKING PROPERLY. REPLACE DEFECTIVE |
| 274 | RUBBER BEADING OF 10 IN NUMBER HYDRAULIC SLIDING DOOR DETERIORATED. RA FOR RENEWAL OF THE SAME. MAT- SILICON RUBBER. DIA 12MM |
| 275 | 10 IN NUMBER HYDRAULIC SLIDING DOORS NOT CLOSING PROPERLY VIEW MISALIGNMENT. RA FOR OVERHAULING AND PROVING OF FEELER GAUGE TEST. |
| 276 | OIL LEAKAGE OBSERVED FROM HYDRAULIC CYLINDERS OF SLIDING DOORS. RA FOR OVERHAULING OF THE SAME, QTY - 5 |
| 277 | RUBBER BEADING OF 10 IN NUMBER WT DOOR AND 03 IN NUMBER HATCHES DETERIORATED/ PERISHED TO BE RENEWED AND ULD TEST TO BE PROVED. MAT- SILICONE RUBBER BEADING. QTY - 80RMT, SIZE - 30X20MM APPROX |
| 278 | 10 IN NUMBERS WT DOORS OPENING/CLOSING MECHANISM NOT WORKING SATISFACTORY. OVERHAULING OF DOORS TO BE CARRIED OUT AND CHALK TEST/ ULD TEST TO BE PROVED. |
| 279 | HINGES OF THREE IN NUMBER WT DOORS CRACKED/ DAMAGED. SAME TO BE RENEWED. JOB INVOLVE DEGUTTING OF LAGGING/ PANELING, REPAIR RENEWAL RENEWAL OF HINGES. POST REPAIR LAGGING/PANELING AND ASSOCIATED FITTINGS ARE TO BE RESTORED. QTY - 06 HINGES, MAT -SS |
| 280 | DOOR RETAINING HOOK/CLIP OF TEN IN NUMBER WT DOOR BROKEN. RA FOR RENEWAL OF THE SAME. MAT - MS/ AL |
| 281 | ULTRASONIC LEAK DETECTION TEST OF 15 DOOR AND 2 HATCHES FAILED. ULD TEST IS TP BE PROOVED FOR THE SAME |
| 282 | WIRE MESH OF VENT OF ENGINE ROOM EXHAUST DETERIORATED TO BE RENEWED, QTY - 04 SQMTR. MAT - SS |
| 283 | WIRE MESH OF 12 IN NUMBER MUSHROOM HEAD ON UPPER CORRODED AND BROKEN TO BE RENEWED, MAT - SS, QTY - 12 SQMT |
| 284 | HATCH COAMING AND HINGES OF FWD AND AFT HATCH CORRODED THINNED TO BE RENEWED. QTY - 02, MAT - MS, HATCH SIZE- 600X900 APPROX |
| 285 | HATCHES SUPPORTING HYDRAULIC CYLINDERS NOT WORKING. RA FOR RENEWAL/ REPLACEMENT OF THE SAME, QTY - 4 |
| 286 | FWD AND AFT HATCH MUSHROOM HEAD COVER CORRODED THINNED AND HOLED. TO BE RENEWED IN SITU, QTY - 02 MAT - MS DIA - 8 INCH, LENGTH - 01 FEET |
| 287 | RUBBER BEADING OF 03 HATCHES DEDERIORATED TO BE REPLACED. QTY - 12 QMT, MAT- SILICON RUBBER |
| 288 | MANUAL RUDDER LEVER DETERIORATED. TO BE REPAIRED IN SITU, QTY 02. |
| 289 | CARRY OUT CLEANING AND APPLICATION OF OM 750 IN FUEL TANKS FOR PRESERVATION. QTY- 100 SQMT |
| 290 | 6 IN NUMBER NWT DOORS DAMAGED/ DEFECTIVE. SAME TO BE REPAIRED. SIZE - 177X 47 CM . (A) PO'S MESS (B) HOD'S MESS (C ) REF COMPT LOBBY (D) ENGINE ROOM, (F) CLASSROOM-01 (G) CADET'S MESS, |
| 291 | 20 IN NUMBERS MORTISE LOCKS OF NWT DOORS DEFECTIVE. THE SAME TO BE REPLACED. MAT - SS |
| 292 | 20 IN NUMBERS HYDRAULIC DOOR CLOSER DEFECTIVE TO BE REPAIRED/REPLACED. MAT SS |
| 293 | OPERATING HANDLE OF RIGGING LOCKER AND AMMUNITION LOCKER DOOR DETERIORATED. RA FOR REPAIR OF THE SAME. QTY - 02. MAT - MS |
| 294 | 04 IN NUMBERS BOAT SLING DAMAGED. NEW BOAT SLINGS TO BE MANUFACTURED AS PER SAMPLE. MAT - POLISTER |
| 295 | LIFTING HANDLE OF BOTH RIB BROKEN. SAME TO BE REPAIRED/ RENEWED. QTY -08, MAT - POLISTER |
| 296 | 4 IN NUMBERS BOAT HOOK DAMAGED. SAME TO BE RENEWED, MAT - SS |
| 297 | WOODEN DECK OF STERN PLATFORM PERISHED/ DETERIORATED TO BE RENEWED. APPROX AREA - 16 SQMTR, MAT - TEAK WOOD |
| 298 | SEALING/CAULKING COMPOUND BETWEEN WOOD ON UPPER AND LOWER DECKS COMPARTMENTS DETERIORATED TO BE REPAIRED IN SITU, QTY - 100 RMT |
| 299 | POLISHING AND VARNISHING OF WOODEN FLOORING OF WEATHER DECKS TO BE CARRIED OUT VIEW POLISHING DETERIORATED .JOB INVOLVE SCRUBBING OF DECK, REMOVAL OF DIRT/ OIL/ GREASE / PAINT FROM DECK WITH BUFFING MACHINE AND APPLICATION OF VARNISH IN FOLLOWING STEPS; _ (I) APPLY TWO COAT OF SEALER, (II) TWO COAT OF COLOUR, (III) ONE COAT OF VARNISH. TOTAL AREA - 400 SQMT |
| 300 | POLISHING AND VARNISHING OF WOODEN DECK OF FOLLOWING COMPARTMENT TO BE CARRIED OUT VIEW DETERIORATED: - (A) CAPTAIN'S CABIN (B) EXO'S CABIN (C ) WARDROOM (D) OFFICER'S CABIN (E) WARDROOM LOBBY (F) PO'S MESSSQMT, (G) DINING HALL (H) HOD MESS (J) GUNWALE (K) PO MESS LOBBY (L) PIN RAIL (M) WOODEN GRATINGS (N) COCK PIT STORE (P) CHART HOUSE (Q) SHIP'S OFFICE, (R) BOW SPRIT SQMT, (S) SICKBAY (T) CADET'S MESS . JOB INVOLVE SCRUBBING OF DECK, REMOVAL OF DIRT/ OIL/ GREASE / PAINT FROM DECK WITH BUFFING MACHINE AND APPLICATION OF VARNISH IN FOLLOWING STEPS; _ (I) APPLY TWO COAT OF SEALER, (II) TWO COAT OF COLOUR, (III) ONE COAT OF VARNISH. TOTAL AREA - 200 SQMT. |
| 301 | BULKHEAD PANELING IN SHIP'S GALLEY DAMAGED TO BE REPAIRED AND RE-FITTED INSITU, QTY - 40 SQMT. MAT SS |
| 302 | PERPLEX SHEET IN BRIDGE BROKEN/ DAMAGED. TO BE RENEWED INSITU. OPENING CLOSING ARRANGEMENT TO BE PROVIDED. APPROX AREA - 20 SQMT. |
| 303 | CARRYOUT WELDING OF BONDING STRAPS ON DOORS, HATCHES, STANCHION AND FLAPS VIEW UPROOTED. QTY - 70 |
| 304 | THREE IN NUMBER PILOT LADDER STEPS BROKEN/ DAMAGE TO BE RENEWED. QTY - 15 STEPS, SIZE 600MMX100MM, MAT - TEAK WOOD |
| 305 | 15 IN NUMBER WOODEN GRATING DAMAGED TO BE RENEWED AS PER SAMPLE. SIZE 4X3X1/4 FEET FOLLOWED BY VARNISHING |
| 306 | PIPE SECURING CLAMPS DAMAGED BROKEN AT VARIOUS LOCATIONS. SAME TO BE RENEWED QTY - 14, MAT- MS. DIA 50MM |
| 307 | 30 IN NUMBERS BUTTERFLY NUTS OF WTC CORRODED. TO BE RENEWED AS PER SAMPLE, MAT - SS, SIZE- M8 |
| 308 | RA FOR MANUFACTURING OF FOXLE AWNING AS PER SAMPLE, QTY - 2, MAT CANVAS, SIZE 8X6 MTR APPROX. |
| 309 | BUNK LEGS AND SHOE CORRODED/BROKEN IN CADET'S MESS, JUNIOR SAILOR MESS, SENIOR MESS AND PO MESS. TO BE RENEWED QTY 24. MAT - GI PIPE WITH MS BRACKET. POST COMPLETION OF WORK DEGUTTED AREA TO BE RESTORED. |
| 310 | EOT COVER IN BRIDGE DETERIORATED. SAME TO BE REPLACED. QTY -01. SIZE 2X2 FEET, MAT - PERSPECT SHEET. |
| 311 | WOODEN LOCKERS OF FLAG HEAVILY DAMAGED TO BE MANUFACTURED AS PER SAMPLE , QTY - 02. SIZE- 3X2X2 FEET APPROX |
| 312 | RA FOR REPAIR/RENEWAL OF PANELING QTY- 150 SQM MAT- CRCA |
| 313 | MANUFACTURING AND FITMENT OF SECURING CLAMPS OF OXYGEN CYLINDERS VIEW DETERIOTRATED. QTY - 4, MAT - MS, DIA - 200 MM |
| 314 | 15 IN NUMBERS SHOE LOCKERS BROKEN. TO BE REPAIRED INCLUDING LOCKS. MAT - CRCA, SIZE 2X2X1/2 FEET. |
| 315 | LOCKS OF STORAGE LOCKERS IN CLASSROOM DAMAGED TO BE REPLACED. QTY - 17, MAT - SS |
| 316 | 02 IN NUMBER LOCKERS IN SICKBAY DETERIORATED/ DAMAGED TO BE REPLACED. MAT CRCA, SIZE 2.5X1.5X3 FEET APPROX |
| 317 | WARD ROOM TABLE AND DRAWER SECURING ARRANGEMENT BROKEN . SAME TO BE REPAIRED. MAT - WOOD. SIZE - 6X4 FEET APPROX |
| 318 | RA FOR MANUFACTURING AND FITMENT OF 300 METALLIC TALLIES VIEW DAMAGED/DETERIORATED. LIST OF TALLIES WILL BE PROVIDED BY SS. SIZE- 15X50MM MAT - SS |
| 319 | BILGE PLATE IN ENGINE ROOM DETERIORATED. RA FOR RENEWAL OF THE SAME, QTY 20 SQMT, MAT - AL. |
| 320 | 15 IN NUMBERS WOODEN CLEATS DAMAGED TO BE RENEWED INSITU. DIA- 25MM, LENGTH - 200MM |
| 321 | RUBBER BEADING AND HINGES OF FF AND DC LOCKERS DAMAGED. SAME TO BE RENEWED. QTY - 6RMT, SIZE 25MMX20MM |
| 322 | GUNWALE AND PINWALE DAMAGED AT VARIOUS LOCATIONS TO BE RENEWED. QTY - 20 RMT, MAT - TEAK WOOD |
| 323 | BILGE PLATES IN REF AND STP COMPARTMENT DETERIORATED/DAMAGED. RA FOR RENEWAL OF THE SAME , QTY - 20 SQMT, MAT - AL |
| 324 | QUARTER MASTER CHAIR IN BRIDGE DETERIORATED TO BE REPLACED. QTY - 01 |
| 325 | SUDARSHINI TAIL BOARD CRACKED/ DAMAGED. TO BE REPAIRED RENEWED AND PAINTED. QTY - 02. MAT - TEAK WOOD. SIZE - 8X2.5 FEET |
| 326 | SUDARSHINI TAIL BOARD SUPPORTING BRACKETS BROKEN AT SHIP SIDE (PORT AND STBD) TO BE WELDED. Mat - MS. JOB INVOLVE (I) REMOVAL OF SUDARSHINI TAIL BOARD QTY - 02. (II) REMOVAL OF WOODEN FIRNITURE AND PANELLING FROM CAPTAIN'S AND EXO'S CABIN AND FITMENT OF THE SAME POST WELDING. (III) WELDING OF BRACKETS. (IV) FITMENT OF TARANGNI TAIL BOARD. BRACKET SIZE - 2X3 INCH X 5MM |
| 327 | SECURING BRACKET ON 02 IN NUMBER CO2 EXTINGUISHER BROKEN. TO BE RENEWED. MAT - MS DIA - 100MM APPROX |
| 328 | RENEWAL OF 40 IN NUMBER SECURING BELTS OF ELSA STOWAGE BOXES TO BE CARRIED OUT. MAT - POLOSTER BELT WITH LOCKING ARRANGEMENT. QTY- 35 MTR |
| 329 | RUBBER SEAL OF SPLINTER BOX AROUND ITS EDGE DAMAGED TO BE RENEWED. QTY - 02 SIZE- 5X15X600 MM |
| 330 | 20 IN NUMBER BUNK LEE-RAILS IN MESSES BROKEN TO BE REPLACED AS PER SAMPLE. MAT - CRCA, SIZE - 1/2X2 FEET APPROX |
| 331 | SLIDING RAIL OF BUNK CURTAINS IN LIVING SPACES DAMAGED TO BE RENEWED , QTY 35., MAT - CRCA, SIZE - 10X10X2000MM |
| 332 | CAM LOCK OF LOCKERS IN LIVING SPACES DEFECTIVE TO BE RENEWED , QTY - 45, DIA- 15MM, MAT - SS |
| 333 | CABLE GLANDS OF SPLIT AC PIPES AT WEATHER DECKS DETERIORATED DAMAGED TO BE RENEWED, QTY - 20 , MAT - MS PIPE. JOB INVOLVE REMOVAL AND FITMENT OF WOODEN DECK. DEGUTTING OF OLD PIPES AND FITMENT OF NEW PIPE. DIA -25MM, LENGTH - 1 FEET. |
| 334 | HINGES OF FILE/ BOOKS WOODEN LOCKERS DOOR UPROOTED. RA FOR REPAIRING OF THE SAME. QTY - 15 |
| 335 | 20 IN NUMBERS COMMODE COVERS DEFECTIVE. SAME TO BE RENEWED AS PER SAMPLE. |
| 336 | 8 IN NUMBERS SHOWER MIXER DEFECTIVE/ DAMAGED IN BATHROOMS TO BE REPLACED . MAKE - JAGUAR. |
| 337 | 15 IN NUMBERS WATER MIXING TAP OF WASH BASIN DEFECTIVE TO BE RENEWED . MAKE - JAGUAR |
| 338 | WASH BASIN AND HYGIENE LOCKER NEAR MAIN MAST DETERIORATED TO BE REPLACED. QTY - 01 MAT - SS SIZE- 2X2X3 FEET. |
| 339 | WOODEN DECK OF COCKPIT STORE PERISHED/ DETERIORATED. TO BE RENEWED. POLISHING TO DONE POST RENEWAL. AREA APPROX - 20 SQMTR, MAT-TEAK WOOD |
| 340 | SEEPAGE OF WATER OBSERVED FROM ANGLE SKY LIGHT BELOW THE DECK TO BE REPAIR/RENEWED Qty -15 |
| 341 | BOWSPRIT MAJOR WEATHERING CRACKS AT SCATTERED LOCATIONS TO BE REPAIRED. SCOPE OF WORK AS FOLLOWS : -(I) BUFFING OF THE AREA.(II) REPAIRS TO BE CARRIED OUT USING MARINE EPOXY RESIN. |
| 342 | VARNISH OF BOWSPRIT IS TO BE UNDERTAKEN WITH SATURATED COATS OF DECK OLJE D1 SATURATING WOOD OIL WITH CLEAR MATT FINISH AND SIX COATS OF DECK OLJE D2 FLEXIBLE HIGH GLOSS OIL VARNISH. QTY - 20 SQMT. |
| 343 | BOW SPRIT BASE BOLTS TO BE RENEWED VIEW NUT & BOLTS DETERIORATED( SIZE- M20 , MAT - SS), QTY - 30 NOS |
| 344 | BOWSPRIT HANDRAIL REPAIRS AT SCATTERED LOCATIONS( TYPE - TEAK WOOD, MAT AND DIMENSION- AS PER SAMPLE).SCOPE OF WORK AS FOLLOWS : -(I) CUTTING OF HANDRAIL OF DESIGNATED AREA AND RENEWAL OF THE SAME AS PER THE PIECE CUT. QTY - 04 |
| 345 | BOW SPRIT BASE DETERIORATED. BOW SPRIT BASE TO BE REMOVED/ RENEWED AND REFITTED, QTY - 01 NOS, MAT - MS, TEAK WOOD. |
| 346 | BOW SPRIT FOUND TO BE DETERIORATED. RENEWAL OF BOW SPRIT TO BE UNDERTAKEN. THE SoW INCLUDES THE FOLLOWING: - (a) REMOVAL OF EXISTING BOW SPIRIT (TO BE UNDERTAKEN BY SHIPYARD)(b) FITMENT OF NEW BOW SPIRIT (TO BE UNDERTAKEN BY SHIPYARD) (QTY - 01 NOS, MAT-DOUGLAS FIR. (BOW SPIRIT WILL BE SUPPLIED BY IN ) |
| 347 | NUTS AND BOLTS OF VARIOUS SIZE TO BEREPLACED,AS PER SAMPLE. QTY - 100 |
| 348 | CLEAN AND WASH DOWN ALL GREY WATER TANKS INCLUDING SOUNDING LINE TO BE REMOVE ALL DIRT/SLUDGE AND PREPARE FOR SURVEY. ALL MANHOLES TO BE REMOVED, RENEWED, REFITTED AND RENEW RUBBER PACKING MATERIAL. ALL STUDS AND NUT TO BE RENEWED WITH SS FOR WATERTIGHT INTEGRITY. QTY – 04 NOS, |
| 349 | ENGINEERING - PART I |
| 350 | CARRY OUT 6000 HRLY ROUTINES.SPARES :- SPARES TO BE SUPPLIED BY SHIPYARD. HARBOUR AND SEA TRIALS TO BE OFFERED TO NAVAL TRIAL AGENCY. DEFECTS OBSERVED BY NAVAL TRIAL AGENCY TO BE LIQUIDATED BY SHIPYARD AND RE OFFERED FOR TRIALS. |
| 351 | 6000H2-FUEL SYSTEM:1. CLEAN AND CALIBRATE INJECTORS AND RECORD TEST PRESSURES IN SERVICE LOG. ALSO CHANGE INJECTOR INLET SCREEN (Qty - 6).2. REPLACE ROCKER COVER GASKETS (Qty -3).3. ADJUST VALVE TAPPET CLEARANCES WITHIN LIMITS AND RECORD IN SERVICE LOG (Qty -12).4. REPLACE FUEL PUMP FILTER (SCREEN AND MAGNET) (Qty -1)5. CALIBRATE PT FUEL PUMP AND RECORD IN SERVICE LOG.(Qty -1)6. ADJUST INJECTOR TRAVEL AND TORQUE (Qty -1) |
| 352 | 6000H3 -AIR SYSTEM1. OVERHAULING TURBOCHARGERS OF BOTH BANKS WITH NEW REPAIR KIT. Qty -12. CHECK TURBO CHARGER RADIAL/END BEARING CLEARANCE IN-SITU. RENEW 'O' RING AND TEFLON GASKET WHEN TURBOCHERGER IS OPENED FOR CHECKING CLEARANCES. Qty -13. TORQUE MANIFOLD NUTS OR CAP SCREWS AS PER SPECIFICATIONS. Qty -1 |
| 353 | 6000H4- CHARGE AIR COOLER & FRESH WATER COOLER: Qty - 21. CLEAN THE INTERNAL PASSAGES OF CHARGE AIR COOLER AND FRESH WATER COOLER COOLANT SIDE USING RADIWASH PLUS Qty - 22. RENEW COOLANT IN THE SYSTEM Qty - 13. INSPECT CHARGE AIR COOLER AIR SIDE AND IF REQUIRED CLEAN USING HOT WATER AND PRESSURE TEST UP TO 2KG/CM2. Qty - 1 |
| 354 | 6000H6- CHECK THICKNESS OF VIBRATION DAMPER AT 0, 90, 180 AND 270 DEGREE POSITIONS. REPLACE DAMPER IF VARIATION OF THE 4 READINGS EXCEEDS 0.010 INCH (0.25MM) OR EXCEEDS MAX ALLOWABLE THICKNESS. CHECKS TO BE UNDERTAKEN IN COUPLED CONDITION. |
| 355 | 6000H8- CHECK CRANK END CLEARANCES WITH A DIAL INDICATOR, ATTACHINGAGAINST DAMPER MIN- 0.13 MM, MAX-0.51 MM.CHECK CRANK END CLEARANCES WITH A DIAL INDICATOR, ATTACHINGAGAINST DAMPER MIN- 0.13 MM, MAX-0.51 MM. |
| 356 | 6000H10- ALIGNMENT CHECKS:UNDERTAKE ALIGNMENT CHECKS BETWEEN THE GENERATOR AND ENGINE AND RESTORE RADIAL/AXIAL INITIAL ALIGNMENT TO 25% OF THEMAX LIMIT. |
| 357 | 6000H13- INSPECT HOLSET/VULCAN/CENTAMAX FLEXIBLE COUPLING AND TORQUE TIGHTEN INNER/OUTER MEMBERS. CHECK RUBBER BLOCKS/DISC FORDETERIORATION. RENEW IF BEYOND PERMISSIBLE LIMIT. |
| 358 | 6000H14- CHECK FOR CRACKS ON RUBBER AND IF WEAR MARK DOES NOT EXCEED LIMITS. CHECK TIGHTNESS OF ADAPTOR PLATE BOLTS (COUPLING BOLTS). |
| 359 | 6000H15- CHECK THICKNESS OF VIBRATION DAMPER AT 0, 90, 180 AND 270 DEGREE POSITIONS. REPLACE DAMPER IF VARIATION OF THE 4 READINGS EXCEEDS 0.010 INCH (0.25MM) OR EXCEEDS MAX ALLOWABLE THICKNESS. CHECKS TO BE UNDERTAKEN IN COUPLED CONDITION. |
| 360 | 6000H16- CHECK TURBO CHARGER RADIAL/END BEARING CLEARANCE IN-SITU ON REMOVAL OF INLET/EXHAUST PIPES. NOTE: RENEW ‘O’ RING AND TEFLON GASKET WHENEVER T/C ISOPENED FOR CHECKING CLEARANCES. |
| 361 | 6000H18- CLEAN THE LCP BACK UP BATTERY TERMINALS AND REPLACE CABLES AND LUGS. |
| 362 | CARRY OUT 6000 HRLY ROUTINES.SPARES :- SPARES TO BE SUPPLIED BY SHIPYARD. HARBOUR AND SEA TRIALS TO BE OFFERED TO NAVAL TRIAL AGENCY. DEFECTS OBSERVED BY NAVAL TRIAL AGENCY TO BE LIQUIDATED AND RE OFFERED FOR TRIALS. |
| 363 | 6000H2-FUEL SYSTEM:1. CLEAN AND CALIBRATE INJECTORS AND RECORD TEST PRESSURES IN SERVICE LOG. ALSO CHANGE INJECTOR INLET SCREEN (Qty - 6).2. REPLACE ROCKER COVER GASKETS (Qty -3).3. ADJUST VALVE TAPPET CLEARANCES WITHIN LIMITS AND RECORD IN SERVICE LOG (Qty -12).4. REPLACE FUEL PUMP FILTER (SCREEN AND MAGNET) (Qty -1)5. CALIBRATE PT FUEL PUMP AND RECORD IN SERVICE LOG.(Qty -1)6. ADJUST INJECTOR TRAVEL AND TORQUE (Qty -1) |
| 364 | 6000H3 -AIR SYSTEM1. OVERHAULING TURBOCHARGERS OF BOTH BANKS WITH NEW REPAIR KIT. Qty -12. CHECK TURBO CHARGER RADIAL/END BEARING CLEARANCE IN-SITU. RENEW 'O' RING AND TEFLON GASKET WHEN TURBOCHERGER IS OPENED FOR CHECKING CLEARANCES. Qty -13. TORQUE MANIFOLD NUTS OR CAP SCREWS AS PER SPECIFICATIONS. Qty -1 |
| 365 | 6000H4- CHARGE AIR COOLER & FRESH WATER COOLER: Qty - 21. CLEAN THE INTERNAL PASSAGES OF CHARGE AIR COOLER AND FRESH WATER COOLER COOLANT SIDE USING RADIWASH PLUS Qty - 22. RENEW COOLANT IN THE SYSTEM Qty - 13. INSPECT CHARGE AIR COOLER AIR SIDE AND IF REQUIRED CLEAN USING HOT WATER AND PRESSURE TEST UP TO 2KG/CM2. Qty - 1 |
| 366 | 6000H6- CHECK THICKNESS OF VIBRATION DAMPER AT 0, 90, 180 AND 270 DEGREE POSITIONS. REPLACE DAMPER IF VARIATION OF THE 4 READINGS EXCEEDS 0.010 INCH (0.25MM) OR EXCEEDS MAX ALLOWABLE THICKNESS. CHECKS TO BE UNDERTAKEN IN COUPLED CONDITION. |
| 367 | 6000H8- CHECK CRANK END CLEARANCES WITH A DIAL INDICATOR, ATTACHINGAGAINST DAMPER MIN- 0.13 MM, MAX-0.51 MM.CHECK CRANK END CLEARANCES WITH A DIAL INDICATOR, ATTACHINGAGAINST DAMPER MIN- 0.13 MM, MAX-0.51 MM. |
| 368 | 6000H10- ALIGNMENT CHECKS:UNDERTAKE ALIGNMENT CHECKS BETWEEN THE GENERATOR AND ENGINE AND RESTORE RADIAL/AXIAL INITIAL ALIGNMENT TO 25% OF THEMAX LIMIT. |
| 369 | 6000H13- INSPECT HOLSET/VULCAN/CENTAMAX FLEXIBLE COUPLING AND TORQUE TIGHTEN INNER/OUTER MEMBERS. CHECK RUBBER BLOCKS/DISC FORDETERIORATION. RENEW IF NECESSARY. |
| 370 | 6000H14- CHECK FOR CRACKS ON RUBBER AND IF WEAR MARK DOES NOT EXCEED LIMITS. CHECK TIGHTNESS OF ADAPTOR PLATE BOLTS (COUPLING BOLTS). |
| 371 | 6000H15- CHECK THICKNESS OF VIBRATION DAMPER AT 0, 90, 180 AND 270 DEGREE POSITIONS. REPLACE DAMPER IF VARIATION OF THE 4 READINGS EXCEEDS 0.010 INCH (0.25MM) OR EXCEEDS MAX ALLOWABLE THICKNESS. CHECKS TO BE UNDERTAKEN IN COUPLED CONDITION. |
| 372 | 6000H16- CHECK TURBO CHARGER RADIAL/END BEARING CLEARANCE IN-SITU ON REMOVAL OF INLET/EXHAUST PIPES. NOTE: RENEW ‘O’ RING AND TEFLON GASKET WHENEVER T/C ISOPENED FOR CHECKING CLEARANCES. |
| 373 | 6000H18- CLEAN THE LCP BACK UP BATTERY TERMINALS AND REPLACE CABLES AND LUGS. |
| 374 | CARRY OUT SR ROUTINES.SPARES :- SPARES TO BE SUPPLIED BY SHIPYARD. HARBOUR AND SEA TRIALS TO BE OFFERED TO NAVAL TRIAL AGENCY. DEFECTS OBSERVED BY NAVAL TRIAL AGENCY TO BE LIQUIDATED AND RE OFFERED FOR TRIALS. |
| 375 | SR1- UNDERTAKE SAMPLE INSPECTION OF PLUMMER BEARINGS ON EACH SHAFT LINE FOR SCORING/CORROSION. IN CASE ANY ABNORMALITY IS OBSERVED, |
| 376 | SPARES :- SPARES TO BE SUPPLIED BY SHIPYARD. HARBOUR AND SEA TRIALS TO BE OFFERED TO NAVAL TRIAL AGENCY. DEFECTS OBSERVED BY NAVAL TRIAL AGENCY TO BE LIQUIDATED AND RE OFFERED FOR TRIALS.4000H1-OVERHAUL GEAR BOX. REPLACE ALL OIL SEALS, GASKETS, LOCK PLATES, PISTON RINGS,'O' RINGS AND ALL PARTS SHOWING SIGNS OF WEAR FATIGUE ETC. |
| 377 | A1- CALIBRATE ALL RELIEF VALVES. |
| 378 | SR1- CHECK WIRING/CONTACTS OF THE PANEL FOR WEAR/DETERIORATION. REPLACE IF NECESSARY. |
| 379 | SPARES :- SPARES TO BE SUPPLIED BY SHIPYARD. HARBOUR AND SEA TRIALS TO BE OFFERED TO NAVAL TRIAL AGENCY. DEFECTS OBSERVED BY NAVAL TRIAL AGENCY TO BE LIQUIDATED AND RE OFFERED FOR TRIALS.4000H1-OVERHAUL GEAR BOX. REPLACE ALL OIL SEALS, GASKETS, LOCK PLATES, PISTON RINGS,'O' RINGS AND ALL PARTS SHOWING SIGNS OF WEAR FATIGUE ETC. |
| 380 | A1- CALIBRATE ALL RELIEF VALVES. |
| 381 | SR1- CHECK WIRING/CONTACTS OF THE PANEL FOR WEAR/DETERIORATION. REPLACE IF NECESSARY. |
| 382 | CARRY OUT 6000 HRLY ROUTINES.SPARES :- SPARES TO BE SUPPLIED BY SHIPYARD. HARBOUR AND SEA TRIALS TO BE OFFERED TO NAVAL TRIAL AGENCY. DEFECTS OBSERVED BY NAVAL TRIAL AGENCY TO BE LIQUIDATED AND RE OFFERED FOR TRIALS. |
| 383 | 6000H1- REMOVE INTAKE MANIFOLD. CLEAN & PRESSURE TEST. |
| 384 | 6000H2- REMOVE EXHAUST MANIFOLD. CLEAN & PRESSURE TEST. |
| 385 | 6000H3- REMOVE TURBOCHARGER. CLEAN, INSPECT & REPAIR WITH NEW SPARES. |
| 386 | 6000H4- REMOVE FUEL INJECTION PUMP. CLEAN, INSPECT, CALIBRATE & REPAIR WITH NEW SPARES PARTS. |
| 387 | 6000H5- REMOVE ROCKER LEVER & SHAFT. CLEAN, INSPECT & REPAIR WITH NEW SPARES. |
| 388 | 6000H6- REMOVE INJECTORS, CLEAN, INSPECT, REPAIR & CALIBRATE WITH NEW SPARES. |
| 389 | 6000H7- REMOVE FUEL CONNECTIONS (HIGH PRESSURE PIPE LINES). CLEAN, INSPECT & REPAIR WITH NEW SPARES. |
| 390 | 6000H8- REMOVE PUSH RODS. CLEAN, INSPECT. REPLACE IF REQUIRED. |
| 391 | 6000H9- DISMANTLE CYLINDER HEAD.CLEAN, INSPECT & REPAIR WITH NEW SPARES. |
| 392 | 6000H10- DISMANTLE ONE PISTON & ONE CON ROD ASSEMBLY. REPLACE IF REQUIRED. BASED ON INSPECTION, UNDERTAKE INSPECTION OF BALANCE PISTON/ CONNECTING RODS ACCORDINGLY. |
| 393 | 6000H11- DISMANTLE ONE LINER FOR INSPECTION OF LINER OUTER SURFACE PITTING. REPLACE IF REQUIRED. |
| 394 | 6000H12- REMOVE & REPLACE WATER PUMP. |
| 395 | 6000H13- REMOVE BELT TENSIONER. CLEAN, INSPECT & REPAIR WITH NEW SPARE PARTS. |
| 396 | 6000H14- REMOVE & REPLACE FUEL FEED PUMP. |
| 397 | 6000H15- CHECK VIBRATION DAMPER. |
| 398 | 6000H16-REMOVE SEA WATER PUMP. CLEAN, INSPECT & REPAIR WITH NEW SPARE PARTS. |
| 399 | 6000H17- REMOVE STARTER MOTOR. CLEAN, INSPECT & REPAIR WITH NEW SPARE PARTS. |
| 400 | 6000H21- CLEAN ALL DISMANTELED PARTS AND CYLINDER BLOCKS TOP POSITION. ASSEMBLE ENGINE WITH ALL NEW GASKETS 'O' RINGS, SEALS AND ABOVE DISMANTLE SUB- ASSEMBLIES. |
| 401 | 6000H22- CARRY OUT TAPPET SETTINGS. VALVE SETTING INTAKE VALVE CLEARANCE IS 0.012\\" & EXHAUST VALVE CLEARANCE IS 0.024\\" |
| 402 | 6000H23- POST COMPLETION OF ROUTINES, START THE ENGINE AND CHECK ALL GAUGES, REPLACE IF REQUIRED, CHECK FOR ANY OIL/WATER LEAKAGE, STOP THE ENGINE AND RECHECK ENGINE OIL LEVEL, TOP UP IF REQUIRE. RUN UNDER SHIPS LOAD FOR TWO HOURS AND OBSERVE PARAMETERS. |
| 403 | 6000H24- UNDERTAKE INSPECTION AND CLEANING OF CHARGE AIR COOLER FOLLOWED BY PRESSURE TESTING. |
| 404 | CARRY OUT 6000 HRLY ROUTINES.SPARES :- SPARES TO BE SUPPLIED BY SHIPYARD. HARBOUR AND SEA TRIALS TO BE OFFERED TO NAVAL TRIAL AGENCY. DEFECTS OBSERVED BY NAVAL TRIAL AGENCY TO BE LIQUIDATED AND RE OFFERED FOR TRIALS. |
| 405 | 6000H1- REMOVE INTAKE MANIFOLD. CLEAN & PRESSURE TEST. |
| 406 | 6000H2- REMOVE EXHAUST MANIFOLD. CLEAN & PRESSURE TEST. |
| 407 | 6000H3- REMOVE TURBOCHARGER. CLEAN, INSPECT & REPAIR WITH NEW SPARES. |
| 408 | 6000H4- REMOVE FUEL INJECTION PUMP. CLEAN, INSPECT, CALIBRATE & REPAIR WITH NEW SPARES PARTS. |
| 409 | 6000H5- REMOVE ROCKER LEVER & SHAFT. CLEAN, INSPECT & REPAIR WITH NEW SPARES. |
| 410 | 6000H6- REMOVE INJECTORS, CLEAN, INSPECT, REPAIR & CALIBRATEWITH NEW SPARES. |
| 411 | 6000H7- REMOVE FUEL CONNECTIONS ( HIGH PRESSURE PIPE LINES). CLEAN, INSPECT & REPAIR WITH NEW SPARES. |
| 412 | 6000H8- REMOVE PUSH RODS. CLEAN, INSPECT. REPLACE IF REQUIRED. |
| 413 | 6000H9- DISMANTLE CYLINDER HEAD.CLEAN, INSPECT & REPAIR WITH NEW SPARES. |
| 414 | 6000H10- DISMANTLE ONE PISTON & ONE CON ROD ASSEMBLY. REPLACE IF REQUIRED. BASED ON INSPECTION, UNDERTAKE INSPECTION OF BALANCE PISTON/ CONNECTING RODS ACCORDINGLY. |
| 415 | 6000H11- DISMANTLE ONE LINER FOR INSPECTION OF LINER OUTER SURFACE PITTING. REPLACE IF REQUIRED. |
| 416 | 6000H12- REMOVE & REPLACE WATER PUMP. |
| 417 | 6000H13- REMOVE BELT TENSIONER. CLEAN, INSPECT & REPAIR WITH NEW SPARE PARTS. |
| 418 | 6000H14- REMOVE & REPLACE FUEL FEED PUMP. |
| 419 | 6000H15- CHECK VIBRATION DAMPER. |
| 420 | 6000H16- REMOVE SEA WATER PUMP. CLEAN, INSPECT & REPAIR WITH NEW SPARE PARTS. |
| 421 | 6000H17- REMOVE STARTER MOTOR. CLEAN, INSPECT & REPAIR WITH NEW SPARE PARTS. |
| 422 | 6000H21- CLEAN ALL DISMANTELED PARTS AND CYLINDER BLOCKS TOP POSITION. ASSEMBLE ENGINE WITH ALL NEW GASKETS 'O' RINGS, SEALS AND ABOVE DISMANTLE SUB- ASSEMBLIES. |
| 423 | 6000H22- CARRY OUT TAPPET SETTINGS. VALVE SETTING INTAKE VALVE CLEARANCE IS 0.012\\" & EXHAUST VALVE CLEARANCE IS 0.024\\" |
| 424 | 6000H23- POST COMPLETION OF ROUTINES, START THE ENGINE AND CHECK ALL GAUGES, REPLACE IF REQUIRED, CHECK FOR ANY OIL/WATER LEAKAGE, STOP THE ENGINE AND RECHECK ENGINE OIL LEVEL, TOP UP IF REQUIRE. RUN UNDER SHIPS LOAD FOR TWO HOURS AND OBSERVE PARAMETERS. |
| 425 | 6000H24- UNDERTAKE INSPECTION AND CLEANING OF CHARGE AIR COOLER FOLLOWED BY PRESSURE TESTING. |
| 426 | CARRY OUT SR AND BIENNIAL ROUTINES.SPARES :- SPARES TO BE SUPPLIED BY SHIPYARD. HARBOUR AND SEA TRIALS TO BE OFFERED TO NAVAL TRIAL AGENCY. DEFECTS OBSERVED BY NAVAL TRIAL AGENCY TO BE LIQUIDATED AND RE OFFERED FOR TRIALS. |
| 427 | SR1-EXAMINE SHAFT BRACKET BUSHES (RUBBER BEARING) CLEARANCE. |
| 428 | SR2 - EXAMINE THE LINING BETWEEN THE SHAFT BEARING FOR ANY DAMAGE AND REPAIR, IF WATER GETS TO THE STEEL SHAFT TO FORM RUST. (REFER BR 3000 ART 0802, PARA 2 & 3 WHICH EVER IS APPLICABLE. |
| 429 | SR3-EXAMINE THE PROPELLER FOR ANY DAMAGE, REPAIR AS NECESSARY. |
| 430 | SR5-EXAMINE CATHODIC PROTECTION/ZINC PROTECTION CAP , RENEW IF CONSIDERED NECESSARY. |
| 431 | SR6-EXAMINE THE STERN TUBE SEAL FOR WEAR. REPAIR/RENEW AS NECESSARY. |
| 432 | SR7- INSPECT SHAFT BRAKE PADS FOR SERVICEABILITY IF FOUND WORN OUT, RENEW IT. |
| 433 | SR8- CHECK TIGHTNESS OF PROPELLER LOCK NUT. |
| 434 | SR9- CARRY OUT CALIBRATION OF TORSION METER. |
| 435 | 2A1- INSPECTED BULKHEAD SEAL ND TYPE. INSPECTION WILL BE CARRIED OUT WITH THE SHAFT SURVEY. CLEAN AND REFIT. RENEW 'O' CORD WHILE SEAL IS DISMANTLED |
| 436 | 2A2- CARRY OUT PERFORMANCE CHECKS OF HYDRAULIC BREAKS AND REPAIR AS NECESSARY. |
| 437 | CARRY OUT ANNUAL, BIENNIAL AND SR ROUTINES.SPARES :- SPARES TO BE SUPPLIED BY SHIPYARD. HARBOUR AND SEA TRIALS TO BE OFFERED TO NAVAL TRIAL AGENCY. DEFECTS OBSERVED BY NAVAL TRIAL AGENCY TO BE LIQUIDATED AND RE OFFERED FOR TRIALS. |
| 438 | A5-CARRYOUT TOP OVERHAUL OF HP PUMP PP 60. REPLACE ALL LP AND HP MANIFOLD SEALS, O RINGS AND BACK UP TEFLON WASHERS.CHECK SUCTION/ DELIVERY VALVES AND MANIFOLD FOR SEALING AREA. IF CORRODED REPLACE AS NECESSARY.(REFER JIC : 42902/A5 ANDCHAPTER 5&7 OF OEM MANUAL). |
| 439 | A7-CALIBRATE ALL GAUGES, PANEL MODULES AND ALARM /TRIP CUTOUTS |
| 440 | A8- CHECK WIRING/ CONTACTS OF THE PANEL FOR WEAR/ DETERIROTATION. |
| 441 | A9- CLEAN AND CALIBRATE CONDUCTIVITY METER PROBE. |
| 442 | A13- REPLACE ALL VICTAULIC COUPLERS. CHECK COUPLING AND REPLACE AS NECESSARY. |
| 443 | A14- RENEW DA FILTERS MEDIA. |
| 444 | A15- REPLACE PULSATION DAMPER CHARGING PLUG SEAL RING. RECHARGE WITH NITROGEN TO 39 BAR. |
| 445 | A16- CHECK CONTROL PANEL FITTINGS/ FUSE FOR PROPER FUNCTIONING. |
| 446 | A17- CHECK CONTROL EQUIPMENTS - SERVO MOTOR VALVE/ PRESSURE TRANSMITTER/ SOLENOID VALVES/ FLOW AND LEVEL SWITCHES AND PLC FOR OPERATION. REPAIR/ REPLACE AS NECESSARY. |
| 447 | A18- CHECK HP RELIEF VALVE FOR OPERATION. CALIBRATE/ REPAIR AS REQUIRED. |
| 448 | A19- CHECK ANTI VIBRATION MOUNTS OF THE HP PUMP MOUNTING PLATE FOR BULGING/ DETERIORATION. REPLACE AS REQUIRED. |
| 449 | A20- CHECK AIR REGULATOR FOR OPERATION. CALIBRATE/ REPAIR AS NECESSARY. |
| 450 | A21- CHECK NON RETURN VALVES OF SAND FILTER BACK WASH AND MODULE PERMEATE LINE. |
| 451 | A22- CALIBRATE TORQUE WRENCH USED FOR TIGHTENING OF DT MODULE END NUT. |
| 452 | A23- CALIBRATE HAND CONDUCTIVITY METER AND PANEL MOUNTED CONDUCTIVITY METER. REPLACE IF DEFECTIVE. |
| 453 | A24- REMOVE CIS-80 (CONDUCTIVITY ELECTRODE) TIP. CLEAN AND CALIBRATE WITH ANOTHER CONDUCTIVITY METER. |
| 454 | 2A1- INSPECT FRICTION PADS FITTED ON THE MOTOR OF 'SERVO MOTORCONTROL VALVE' FOR CONDITION OF WORKING SURFACE (CLEARANCESHOULD NOT BE MORE THAN 2 MM). |
| 455 | SR1-CALIBRATION THROUGH CIT FOR ALL OLR/ MPU MECHANISM INSTALLED IN THE SYSTEM. |
| 456 | SR2-OVERHAULING OF CONTROL PANEL AND STARTERS FOR INDIVIDUAL MOTORS. |
| 457 | CARRY OUT ANNUAL, BIENNIAL AND SR ROUTINES. TRIALS TO BE OFFERED TO NAVAL TRIAL AGENCY. DEFECTS OBSERVED BY NAVAL TRIAL AGENCY TO BE LIQUIDATED AND RE OFFERED FOR TRIALS.SPARES : SPARES TO BE PROVIDED BY SHIPYARD |
| 458 | SR1- EXAMINE SEA WATER SIDE OF CONDENSER FOR CORROSION AND FOULING.SIGHT TUBES AND CARRY OUT MECHANICAL CLEANING AND WATER ETS AS NECESSARY.RENEW CORROSION PLUGS AND CARRY OUT PRESSURE TESTING OF THE ASSEMBLED CONDENSER |
| 459 | SR2- REFIT ALL ISOLATING VALVES ON GAS SYSTEM AND COOLING WATER SYSTEM |
| 460 | SR5- CHECK FUNCTION OF PRESSURE RELIEF VALVE. REPAIR/ REPLACE IF DEFECTIVE. |
| 461 | TRIALS TO BE OFFERED TO NAVAL TRIAL AGENCY. DEFECTS OBSERVED BY NAVAL TRIAL AGENCY TO BE LIQUIDATED AND RE OFFERED FOR TRIALS.SPARES : SPARES TO BE PROVIDED BY SHIPYARD. SR1-OPERATE ALL SYSTEM VALVES AND PHYSICALLY VERIFY THE STATE OF THE SYSTEM. IF ANY DEFECTS, TO BE LIQUIDATED. |
| 462 | CARRY OUT ANNUAL AND THREE ANNUAL ROUTINES.SPARES : SPARES TO BE PROVIDED BY SHIPYARD. TRIALS TO BE OFFERED TO NAVAL TRIAL AGENCY. DEFECTS OBSERVED BY NAVAL TRIAL AGENCY TO BE LIQUIDATED AND RE OFFERED FOR TRIALS. |
| 463 | A1- CHECK THREADS OF INLET PIPE AND OIL PAIRING DISC FOR DAMAGE AND WEAR. |
| 464 | A2- INLET DEVICE: 1. CHECK THE FLOW INDICATOR IF CLOGGED. CLEAN THE SIGHT GLASS.2. CHECK THE REDUCING VALVE CONE FOR SCRATCHES AND PLAY.3. CHECK THE NON RETURN VALVE CONE FOR SCRATCHES AND PLAY. |
| 465 | A3- DISMANTEL AND EXAMINE SEPERATOR BOWL ASSEMBLY THROUGHLY. CLEAN ALL COMPONENTS AND CHECK FOLLOWING:-1. CHECK DISC STACK PRESSURE.2. CHECK FOR CORROSION, EROSION AND CRACKS3. GALLING OF GUIDE SURFACE |
| 466 | A4- RENEW OIL IN GEAR HOUSING. CHECK THE TEETH OF WORM WHEEL AND WORM FOR WEAR. |
| 467 | 3A1- RENEW FRAME FEET RUBBER CUSHIONS/ VIBRATION DAMPERS. |
| 468 | 3A2-CHECK HEIGHT POSITION FOR PAIRING DISC FOR MAB 103 TYPESEPARATORS |
| 469 | 3A3-HORIZONTAL DRIVE1. CHECK AXIAL PLAY OF COUPLING DISC.2. RENEW BEARINGS OF WORM WHEEL SHAFT. |
| 470 | 3A4-VERTICAL DRIVE1. CLEAN AND CHECK BOWL SPINDLE AND NAVE FOR IMPACT MARKS.2. CHECK RADIAL WOBBLE OF BOWL SPINDLE.3. CLEAN AND CHECK BUFFER AND BALL BEARING HOUSING. RENEW IFREQUIRED.4. RENEW BALL BEARINGS AND TOP BEARING SPRINGS. |
| 471 | 3A5-CLEAN AND CHECK SPRING AND BRAKE SHOE. RENEW FRICTIONPAD/BRAKE PLUG. |
| 472 | 3A6-CLEAN AND CHECK FRICTION COUPLING. RENEW FRICTION PADS ANDLIPSEAL RING. |
| 473 | 3A7-DISMANTLE PUMP ASSEMBLY. CLEAN AND CHECK BUSHINGS, WEARGASKETS, FLEXIBLE COUPLING, RELIEF/SAFETY VALVE AND IMPELLERSHAFT. RENEW LIPSEAL RING. |
| 474 | A1- WEIGH THE CO2 CYLINDER USING BEAM SCALE/ ULTRASONIC LEVEL DETECTOR. IF THE WEIGHT FALLSBELOW 10% OF INITIAL WEIGHT, RECHARGE THE CYLINDERS.MAINTAIN RECORD IN LOG BOOK.NOTE:- ALTERNATELY USE OF APPROVED PORTABLE ULTRASONIC LEVELDETECTORS IS PERMITTED FOR UNDERTAKING THIS ROUTINE. (IHQ MOD(N) LETTER EG/4726/04/NBCD DATED 30 JAN 09 REGARDING USEOF \\"PORTABLE ULTRASONIC LIQUID LEVEL INDICATOR\\" RELEVANT) |
| 475 | A4 - CARRY OUT CALIBRATION OF CO2 CONCENTRATION SENSORS |
| 476 | CARRY OUT SR ROUTINES.SPARES : SPARES TO BE PROVIDED BY SHIPYARD. TRIALS TO BE OFFERED TO NAVAL TRIAL AGENCY. DEFECTS OBSERVED BY NAVAL TRIAL AGENCY TO BE LIQUIDATED AND RE OFFERED FOR TRIALS. |
| 477 | SR1-DISMANTLE PUMP AND EXAMINE PARTS FOR WEAR. RENEW WORN PARTS AS NECESSARY. |
| 478 | SR2-GAUGE CLEARANCE BETWEEN BUSH AND SHAFT. RENEW BUSH IFCLEARANCE EXEEDS 0.4 MM. |
| 479 | SR3-CARRY OUT PERFORMANCE TRIALS ON COMPLETION OF OVERHAUL. |
| 480 | CARRY OUT SR ROUTINES.SPARES : SPARES TO BE PROVIDED BY SHIPYARD. TRIALS TO BE OFFERED TO NAVAL TRIAL AGENCY. DEFECTS OBSERVED BY NAVAL TRIAL AGENCY TO BE LIQUIDATED AND RE OFFERED FOR TRIALS. |
| 481 | 2Y1- AIR RECEIVER: CHEMICALLY CLEAN INSIDE OF AIR RECEIVER. |
| 482 | 2Y2- HYDRAULICALLY TEST RECEIVER FOR SPECIFIED PRESSURE. |
| 483 | CARRY OUT SR ROUTINES.SPARES : SPARES TO BE PROVIDED BY SHIPYARD. TRIALS TO BE OFFERED TO NAVAL TRIAL AGENCY. DEFECTS OBSERVED BY NAVAL TRIAL AGENCY TO BE LIQUIDATED AND RE OFFERED FOR TRIALS. |
| 484 | SR1- EXAMINE AIR RESERVIOR EXTERNALLY FOR CORROSION. |
| 485 | SR2- STRIPE AND EXAMINE ALL REDUCING VALVES AND RELIEF VALVES. |
| 486 | SR3- CALIBRATE ALL PRESSURE GAUGE. |
| 487 | SR4- REFIT ALL AIR STOP VALVES. |
| 488 | CARRY OUT ANNUAL AND SR ROUTINES.SPARES : SPARES TO BE PROVIDED BY SHIPYARD. TRIALS TO BE OFFERED TO NAVAL TRIAL AGENCY. DEFECTS OBSERVED BY NAVAL TRIAL AGENCY TO BE LIQUIDATED AND RE OFFERED FOR TRIALS. |
| 489 | A2- CHECK LEVEL AND CONDITION OF OIL IN SEAL PACKAGE. RENEW SEAL PACKAGE IF OIL IS EMULSIFIED. |
| 490 | SR1- THE LUBRICANT MIGHT GET CONTAMINATED WITH FOREIGN MATERIAL OR GET BLACKENED DUE TO OVERHEATING. IN SUCH CASES, OIL CHAMBER SHOULD BE FLUSHED AND FILLED WITH FRESH OIL. BEFORE FILLING, HEAT THE OIL TO 140 DEGREES C AND COOL IT TO 60 DEGREES C FOR REMOVAL OF MOISTURE IN OIL |
| 491 | CARRY OUT SR ROUTINES.SPARES : SPARES TO BE PROVIDED BY SHIPYARD. TRIALS TO BE OFFERED TO NAVAL TRIAL AGENCY. DEFECTS OBSERVED BY NAVAL TRIAL AGENCY TO BE LIQUIDATED AND RE OFFERED FOR TRIALS. |
| 492 | SR1-SURVEY AND RENEWAL OF UNDERWATER EXHAUST PIPES WELDED TO THE HULL ( WHERE APPLICABLE) |
| 493 | SR2- CHECK NON METALLIC PARTS, PIPES, MUFFLER AND EXHAUST LINE FOR CRACKS AND DISTORTION. |
| 494 | SR3- CHECK ALIGNMENT OF COMPENSATOR. ADJUST AS NECESSARY ( DURING FITMENT) |
| 495 | SR6- CHECK AND GREASE ALL SUPPORTING HANGERS OF AIR INDUCTION AND EXHAUST SYSTEM. |
| 496 | SR7- CALIBRATE THERMO COUPLES AND TEMP INDICATORS |
| 497 | SR8- INSPECT FOR CONDITION AND OVERHAUL COCKS/ FITTINGS FOR MEASUREMENT OF AIR INTAKE DEPRESSION AND EXHAUST BACK PRESSURE MEASUREMENT IN EXHAUST TRUNKINGS AT APPROPIATE LOCATION. |
| 498 | SR9- APPLICATION AND RESTORATION OF RECOMMENDED PAINT SCHEME ON ALL COMPONENTS OF THE AIR INTAKE SYSTEM. |
| 499 | SR10- INSPECT AND CLEAN ALL COMPONENTS OF AIR INDUCTION SYSTEM FROM WEATHER DECK OPENING TO TC RUBBER BELLOW. |
| 500 | CARRY OUT ANNUAL AND SR ROUTINES.SPARES :- SPARES TO BE SUPPLIED BY SHIPYARD. HARBOUR AND SEA TRIALS TO BE OFFERED TO NAVAL TRIAL AGENCY. DEFECTS OBSERVED BY NAVAL TRIAL AGENCY TO BE LIQUIDATED BY SHIPYARD AND RE OFFERED FOR TRIALS. |
| 501 | A1- CALIBRATE ALL RELIEF VALVES. |
| 502 | A2- CALIBRATE ALL GAUGES, PANEL MODULES AND ALARMS /TRIPS CUTOUTS. |
| 503 | SR3- CHECK SAFETY VALVES AND VALVE CEST DK-200 FOR CORRECT FUNCTIONING.REFIT AND RESET IF NECESSARY |
| 504 | SR4- CALIBRATE ALL PRESSURE GAUGE. |
| 505 | SR5- RENEW RUDDER STOCK GLAND PACKINGS. |
| 506 | SR6- REPACK RUDDER GLANDS WITH HEMP PACKING AND GREASE THE GLANDS. |
| 507 | SR9- CHECK RUDDER STUFFING BOX MOUNTING PLATE AND SECURING STUDS FOR CORROSION AND LOOSENING. RENEW /REPLACE IF NECESSARY. |
| 508 | SR10- COMPLETELY REMOVE FAIRING EPOXY COMPUND TO INSPECT THE STATE OF FASTENERS ON THE RUDDER. RENEW THE FASTERNERS IF DETERIORATED. RE-APPLY FAIRING EPOXY COMPOUND POST INSPECTION/DR. |
| 509 | SR12- RENEW COMPLETE LOCAL WIRING IN CASE OF ANY MAJOR ROUTINES FALLING DUE ON STEERING GEAR SYSTEM. |
| 510 | SPARES : SPARES TO BE PROVIDED BY SHIPYARD. TRIALS TO BE OFFERED TO NAVAL TRIAL AGENCY. DEFECTS OBSERVED BY NAVAL TRIAL AGENCY TO BE LIQUIDATED AND RE OFFERED FOR TRIALS. SR2- EXAMINE PROPELLER FOR DAMAGE AND DETERMINE FITNESS FOR FURTHER USE. REPLACE/ REPAIR AS NECESSARY. |
| 511 | CARRY OUT SR ROUTINES.SPARES : SPARES TO BE PROVIDED BY SHIPYARD. TRIALS TO BE OFFERED TO NAVAL TRIAL AGENCY. DEFECTS OBSERVED BY NAVAL TRIAL AGENCY TO BE LIQUIDATED AND RE OFFERED FOR TRIALS. |
| 512 | SR1-SURVEY ALL UNDER WATER APPENDAGES/ FITTINGS FOR PITTING, CORROSION OR ANY DAMAGE PAYING PARTICULAR ATTENTION TO PAINTFAILURE/ DAMAGE AREA TO STERN SHAFT BRACKET, ROPEGUARD, EDDY PLATES, EDDY CONES, STERN TUBE, SKEG, BILGE KEEL PLATE,STABILIZERS FIN ETC. IAW NO 01/15. UNDERTAKE REPAIR AS NECESSARY. |
| 513 | SR2-CLEAN TO BARE METAL ALL CORRODED AREA AND AREA OF PAINT FAILURE OF U/W APPENDAGES AND PRESERVED IN ACCORDANCE WITH NO 53/16 AND POLICY DIRECTIVES ISSUED BY NHQ/IHQ TIMETO TIME. |
| 514 | SR3-CHECK DRAUGHT MARKS ARE IN POSITION AND INTACT WITH SHIP STRUCTURE. (NES-164/DEFSTAN 02-164 & BR 3001 CHAPTER 28 ARTICLE 2811). UNDERTAKE PAINTING OF DRAFT MARKS AS PERNO 53/16 AND POLICY DIRECTIVES ISSUED BY IHQ/DNA FROM TIME TO TIME. |
| 515 | SR4-EXAMINE FAIRING OF UNDERWATER APPENDAGES FOR ROUGHNESSAND UNFAIRNESS OR ANY DAMAGE PAYING PARTICULAR ATTENTION TOTHE SHAFT BRACKETS, ROPEGUARDS AND EDDY PLATES ETC.RENEW/REPAIR THE UNFAIRED/DAMAGED FAIRING FOR THEIRSMOOTHNESS. |
| 516 | SR7-RECOAT SHAFT BRACKETS IN ACCORDANCE WITH NO 53/16. |
| 517 | CARRY OUT SR ROUTINES.SPARES : SPARES TO BE PROVIDED BY SHIPYARD. TRIALS TO BE OFFERED TO NAVAL TRIAL AGENCY. DEFECTS OBSERVED BY NAVAL TRIAL AGENCY TO BE LIQUIDATED AND RE OFFERED FOR TRIALS. |
| 518 | SR1-CARRY OUT PERFORMANCE TRIAL OF THE PUMP INCLUDING PARAMETER CHECKS (SUCTION/ DISCHARGE PRESSURE), VIBRATION TRIALS, INSULATION/ SPM CHECKS ON MOTOR, MOTOR STARTING/RUNNING CURRENT CHECKS ETC. ASSESS FOR SATISFACTORY PERFORMANCE AND DEFECTS, IT ANY. OVERHAUL PUMP IF PERFORMANCE IS SUBOPTIMAL. |
| 519 | SR2-INSPECT CONDITION OF SUCTION/ DISCHARGE COMPENSATORS.RENEW AS NECESSARY. |
| 520 | SR3-CALIBRATE ALL INSTRUMENTATION. |
| 521 | SR4-CARRY OUT FUNCTIONAL TEST OF RELIEF VALVE. RESET TO SPECIFIED LIFTING PRESSURE. |
| 522 | SR5-INSPECT THE SUCTION STRAINER. RENEW IF REQUIRED. |
| 523 | SR7-REFIT SUCTION AND DISCHARGE VALVES. |
| 524 | SR8-CHECK CONDITION OF COUPLING GUARDS. REPAIR/ REPLACE IF REQUIRED. |
| 525 | CARRY OUT SR ROUTINES.SPARES : SPARES TO BE PROVIDED BY SHIPYARD. TRIALS TO BE OFFERED TO NAVAL TRIAL AGENCY. DEFECTS OBSERVED BY NAVAL TRIAL AGENCY TO BE LIQUIDATED AND RE OFFERED FOR TRIALS. |
| 526 | SR6-CHECK AND CALIBRATE ALL INSTRUMENTATION IN THE SYSTEM. |
| 527 | SR7-CHECK OPERATION OF HAND PUMPS IN THE SYSTEM AND OVERHAUL ,IF REQUIRED. |
| 528 | ENGINEERING - PART III |
| 529 | ABER CAT-II- ABER REPLACEMENT OF FIREMAIN PUMP OF MAKE BE PUMPS PVT LTD WITH MAKE- SPX FLOW (KGEC 16-6) AS PER APPROVED BPS. ENVISAGED SCOPE OF WORK INCLUDES: 1. REMOVAL/DEGUTTING OF OLD EQUIPMENT AND SUB-EQUIPMENT. 2. REMOVAL OF EXISTING CABLE AND STARTING PANEL. 3. MODIFICATION ON FOUNDATION FRAMES. 4. FITMENT OF NEW EQUIPMENT. 5. MANUFACTURING OF BRASS TALLIES FOR ALL SUB UNIT AND EQUIPMENT PANEL. 6. POWERING UP, STW, TESTING, COMMISSIONING, TRAINING OF CREW AND TRIALS. QTY- 02 |
| 530 | ABER CAT-II- ABER REPLACEMENT OF BILGE PUMP OF MAKE BE PUMPS PVT LTD WITH MAKE- SPX FLOW (KGEC 16-6) AS PER APPROVED BPS. ENVISAGED SCOPE OF WORK INCLUDES: 1. REMOVAL/DEGUTTING OF OLD EQUIPMENT AND SUB-EQUIPMENT. 2. REMOVAL OF EXISTING CABLE AND STARTING PANEL. 3. MODIFICATION ON FOUNDATION FRAMES. 4. FITMENT OF NEW EQUIPMENT. 5. MANUFACTURING OF BRASS TALLIES FOR ALL SUB UNIT AND EQUIPMENT PANEL. 6. POWERING UP, STW, TESTING, COMMISSIONING, TRAINING OF CREW AND TRIALS. QTY- 02 |
| 531 | ABER CAT-II- ABER REPLACEMENT OF HOT WATER CIRCULATING PUMP WITH MAKE- SPX FLOW (KGEC 11-3) AS PER APPROVED BPS. ENVISAGED SCOPE OF WORK INCLUDES: 1. REMOVAL/DEGUTTING OF OLD EQUIPMENT AND SUB-EQUIPMENT. 2. REMOVAL OF EXISTING CABLE AND STARTING PANEL. 3. MODIFICATION ON FOUNDATION FRAMES. 4. FITMENT OF NEW EQUIPMENT. 5. MANUFACTURING OF BRASS TALLIES FOR ALL SUB UNIT AND EQUIPMENT PANEL. 6. POWERING UP, STW, TESTING, COMMISSIONING, TRAINING OF CREW AND TRIALS. QTY- 01 |
| 532 | ABER CAT I- REPLACEMENT OF DIESEL ALTERNATOR, MAKE- M/S CUMMINS, 6CTA 8.3D(M), . ENVISAGED SCOPE OF WORK INCLUDES: 1. REMOVAL/DEGUTTING OF OLD EQUIPMENT AND SUB-EQUIPMENT. 2. REMOVAL OF EXISTING CABLE AND STARTING PANEL. 3. MODIFICATION ON FOUNDATION FRAMES. 4. FITMENT OF NEW EQUIPMENT. 5. MANUFACTURING OF BRASS TALLIES FOR ALL SUB UNIT AND EQUIPMENT PANEL. 6. POWERING UP, STW, TESTING, COMMISSIONING, TRAINING OF CREW AND TRIALS. QTY- 02 |
| 533 | MAJOR A’S & A’S- FITMENT OF MARINE ACs IN LIEU OF SPLIT AC MAKE- AEROEQUIP 2 TONS AS PER APPROVED BPS . MAJOR SCOPE OF WORK INCLUDES: 1. REMOVAL/DEGUTTING OF OLD EQUIPMENT AND SUB-EQUIPMENT. 2. REMOVAL OF EXISTING CABLE AND STARTING PANEL.3. FITMENT OF TRUNKING WITH BLOWERS.4. FITMENT OF SEA WATER PIPELINES WITH VALVES. 5. MODIFICATION ON FOUNDATION FRAMES. 6. FITMENT OF NEW EQUIPMENT. 7. MANUFACTURING OF BRASS TALLIES FOR ALL SUB UNIT AND EQUIPMENT PANEL. 8. POWERING UP, STW, TESTING, COMMISSIONING, TRAINING OF CREW AND TRIALS. QTY- 01 |
| 534 | MANUFACTURING AND FITMENT OF EDA EXHAUST LINE FROM COCKPIT STORE TO CATWALK. LENGTH - 10 MTRS |
| 535 | ENGINEERING - PART II |
| 536 | SAFETY DEVICE CHECKS OF BOTH MAIN ENGINES TO BE CARRIED OUT IN COLD AS WELL AS HOT CONDITION POST 06K ROUTINES. CERTIFICATE TO BE ISSUED POST COMPLETION. |
| 537 | CALIBRATION OF MAIN ENGINE LOCAL AND REMOTE STARTING PANEL TO BE UNDERTAKEN VIEW MALFUNCTIONING. REPLACEMENT OF ALL CONTRACTORS AND LAMPS. STARTING OF ENGINE TO BE PROVED FROM LOCAL AND REMOTE POSITIONS. QTY-02 |
| 538 | REPLACEMENT OF DEFECTIVE GAUGES OF BOTH MAIN ENGINES AT LOCAL AND REMOTE PANEL TO BE CARRIED OUT VIEW MALFUNCTIONING, CALIBRATION TO BE UNDERTAKEN AND CERTIFICATE TO BE ISSUED:- 1. LUB OIL PRESSURE GAUGE- 02 2. LUB OIL TEMP GAUGES- 023. FRESH WATER TEMP GAUGES- 024. SEA WATER PRESSURE GAUGE- 02 5. FRESH WATER PRESSURE GAUGE- 02 . CERTIFICATE TO BE ISSUED POST COMPLETION. |
| 539 | SAFETY DEVICE CHECKS OF BOTH GEAR BOXES TO BE CARRIED OUT. DEFECT TO BE RECTIFIED (IF NOT SATISFACTORY). CERTIFICATE TO BE ISSUED POST COMPLETION |
| 540 | CALIBRATION OF 06 IN NO. PRESSURE GAUGES OF BOTH GEAR BOXES TO BE CARRIED OUT. DEFECTIVE GAUGES TO BE REPLACED. |
| 541 | SAFETY DEVICE CHECKS OF BOTH DIESEL ALTERNATORS TO BE CARRIED OUT IN COLD AS WELL AS HOT CONDITION POST 6000 HRLY ROUTINES. DEFECT TO BE RECTIFIED (IF NOT SATISFACTORY). CERTIFICATE TO BE ISSUED POST COMPLETION |
| 542 | CALIBRATION OF LOCAL ANALOG GAUGES OF BOTH DA'S AT LOCAL POSITION TO BE CARRIED OUT VIEW MALFUNCTIONING:- 1. LUB OIL PRESSURE GAUGE- 01 2. LUB OIL TEMP GAUGES- 013. FRESH WATER TEMP GAUGES- 01 4. EXHAUST TEMP GAUGES- 01 . CERTIFICATE TO BE ISSUED POST COMPLETION. |
| 543 | SAFETY DEVICE CHECKS OF BOTH REF PLANTS TO BE CARRIED OUT POST SR ROUTINES. DEFECT TO BE RECTIFIED, IF NOT SATISFACTORY. CERTIFICATE TO BE ISSUED POST COMPLETION. |
| 544 | SAFETY DEVICE CHECKS OF RO PLANTS TO BE CARRIED OUT POST SR ROUTINES. DEFECT TO BE RECTIFIED, IF NOT SATISFACTORY. CERTIFICATE TO BE ISSUED POST COMPLETION. |
| 545 | CALIBRATION OF GOVERNOR CARDS TO BE UNDERTAKEN VIEW MALFUNCTIONING. QTY- 02. RENEW IF FOUND DEFECTIVE. |
| 546 | DA ONLOAD INDICATION NOT WORKING ON BOTH DA. DEFECT TO BE RECTIFIED. QTY-02 |
| 547 | INSPECTION, PERFORMANCE CHECKS AND LOAD TRIALS TO BE CARRIED OUT. RECTIFY DEFECTS OBSERVED DURING TRIALS. |
| 548 | REPLACE FUEL FILTER, OIL FILTER, LUB OIL AND CLEAN AIR FILTER. |
| 549 | CALIBRATION OF GAUGES OF LP AIR COMPRESSOR. QTY - 02. RENEW IF FOUND DEFECTIVE. CERTIFICATE TO BE ISSUED POST COMPLETION. |
| 550 | OVERHAULING OF 5 VALVES OUT OF 25 AIR SYSTEM VALVES TO BE UNDERTAKEN VIEW VALVE NOT HOLDING. AND PRESSURE TESTING UP TO 09 BAR. PAINTING TO BE UNDERTAKEN. DIA- 20 NB, MAT- MS TYPE GLOBE, QTY-5. RENEW IF FOUND DEFECTIVE. |
| 551 | 30 MTRS OUT OF 250 MTRS RENEWAL OF LP AIR SYSTEM PIPE LINES AND PRESSURE TESTING UP TO 07 BAR VIEW CRACKED/ PERISHED. PAINTING OF PIPES TO BE UNDERTAKEN, PRIMER AND TWO COAT WHITE PAINT. MAT- MS, LENGTH-10 MTR , DIA-15MM |
| 552 | OVERHAULING OF 10 OVERBOARD VALVES OUT OF 22 VALVES TO BE UNDERTAKEN VIEW VALVE NOT HOLDING AND PRESSURE TESTING UP TO 05 BAR VIEW LEAKAGE. DIA - VARIOUS(32,55,65 MM), MAT- GUNMETAL, TYPE - NRV, QTY-10 |
| 553 | SECURING CLAMPS/ FRAMES TO BE MANUFACTURED VIEW RUSTED AND BROKEN FOR VARIOUS SYSTEM PIPELINES AS PER REQUIREMENTS.QTY-10 MAT-MS |
| 554 | CALIBRATION OF ACTUATOR OF DA VIEW MALFUNCTIONING. QTY - 02. |
| 555 | CHEMICAL CLEANING AND PRESSURE TESTING OF SEA WATER PIPELINES TO BE UNDERTAKEN. PRESSURE TESTING UPTO 07 BAR. PAINTING iaw PAINTING SCHEME TO BE UNDERTAKEN POST PRESSURE TESTING. LENGTH - 50M, MAT-CUNI DIA- 32,55,65,75 MM |
| 556 | CALIBRATION OF TORQUE WRENCH TO BE CARRIED OUT AND CERTIFICATE TO BE ISSUED. QTY-01 |
| 557 | SERVICING OF SPILT ACS TO BE UNDERTAKEN. QTY - 19. |
| 558 | CHECK FOR LEAKAGE OF REFRIGERANT BY APPLYING SOAP SOLUTION ON PIPE JOINTS AND RUNNING LENGTH. RENEW IF FOUND DEFECTIVE AND RECHARGE REF IF FOUND LOW. |
| 559 | SEA TUBE CHEMICAL CLEANING VIEW CLOGGED AND PRESSURE TESTING UP TO 5 BAR. QTY-02 |
| 560 | MANUFACTURING/ RENEWAL OF SPRINKLING SYSTEM PIPE LINE AND PRESSURE TESTING UP TO 05 BAR IN VIEW OF CRACKED/ PERISHED. . PAINTING OF PIPELINES TO BE UNDERTAKEN. PRIMER, TWO COAT RED PAINT. LENGTH-10 MTR MAT- CUNI, DIA-32MM |
| 561 | DEFECTIVE QUARTZ BULB NOZZLES TO BE REPLACED |
| 562 | OVERHAULING OF REF SEA WATER PUMP VIEW LOW DISCHARGE PRESSURE. CAPACITY - 20TPH, MAKE- JOHNSON QTY-02 |
| 563 | OVERHAULING OF OUT BOARD MOTOR VIEW NOT GETTING STARTED. QTY-02 |
| 564 | OVERHAULING OF TWO SEA CHEST VALVE VIEW LEAKAGE FROM GLAND. PRESSURE TESTING UPTO 07 BAR AND PAINTING TO BE UNDERTAKEN. DIA- 125 MM, MAT- GUNMETAL, TYPE- GLOBE, QTY-02 |
| 565 | OVERHAULING OF TWO SEA CHEST VALVE VIEW LEAKAGE FROM GLAND. PRESSURE TESTING UPTO 07 BAR AND PAINTING TO BE UNDERTAKEN. DIA- 80 MM, MAT- GUNMETAL, TYPE- GLOBE, QTY-02 |
| 566 | 75 MTR OUT OF 300 MTR REPAIR OF SEA WATER LINE AND PRESSURE TESTING UP TO 07 BAR VIEW PERISHED AND CRACKED. PAINTING OF PIPES TO BE UNDERTAKEN, PRIMER AND TWO COAT WHITE PAINT. MAT- CUNI, LENGTH-35 MTR ,DIA-50 MM |
| 567 | OVERHAULING OF 07 VALVES OUT OF OF 28 SEA WATER SYSTEM VALVES TO BE UNDERTAKEN. PRESSURE TESTING UP TO 07 BAR VIEW NOT HOLDING AND PAINTING TO BE UNDERTAKEN. DIA- 65 MM, MAT- GUN METAL, TYPE- GLOBE/GATE, QTY-07 |
| 568 | OVERHAULING OF 07 HYDRANT VALVES AND PRESSURE TESTING UP TO 07 BAR VIEW LEAKAGE FROM GLAND. DIA - 65NB, MAT- GUNMETAL, TYPE - HYDRANT VALVE QTY-07 |
| 569 | OVERHAULING OF TWO BILGE PUMP VIEW LOW DISCHARGE PRESSURE. CAPACITY - 25TPH, MAKE- JOHNSON QTY-02 |
| 570 | OVERHAULING OF 5 VALVES OUT OF 25 BILGE WATER SYSTEM VALVES TO BE UNDERTAKEN VIEW VALVE NOT HOLDING. PRESSURE TESTING UP TO 07 BAR VIEW AND PAINTING TO BE UNDERTAKEN. DIA- 50 MM, MAT- GUN METAL, TYPE- GLOBE, QTY-5 |
| 571 | MANUFACTURING AND FITMENT OF 70 MTR BILGE WATER PIPE LINE AND PRESSURE TESTING UP TO 07 BAR VIEW CRACKED/ PERISHED. PAINTING OF PIPES TO BE UNDERTAKEN, PRIMER AND TWO COAT WHITE PAINT. MAT- CUNI, LENGTH-20 MTR ,DIA-50 MM |
| 572 | OVERHAULING OF TWO FIRE PUMP VIEW LOW DISCHARGE PRESSURE. CAPACITY - 25TPH, MAKE- BE PUMPS QTY-02 |
| 573 | MANUFACTURING AND FITMENT OF 60 MTR OUT OF 250 MTRS FIREMAIN SYSTEM SEA WATER PIPE LINE AND PRESSURE TESTING UP TO 07 BAR VIEW CRACKED/ PERISHED. PAINTING OF PIPES TO BE UNDERTAKEN, PRIMER AND TWO COAT WHITE PAINT. MAT- CUNI, LENGTH-30 MTR ,DIA-65 MM |
| 574 | 60 MTRS OUT OF 250 MTRS REPAIR OF SEA WATER PIPE LINES AND PRESSURE TESTING UP TO 07 BAR VIEW CRACKED/ PERISHED. PAINTING OF PIPES TO BE UNDERTAKEN, PRIMER AND TWO COAT WHITE PAINT. MAT- CUNI, LENGTH-60 MTR ,DIA-65 MM |
| 575 | REPLACEMENT OF 5 VALVES OF 25 FIREMAIN SEA WATER SYSTEM VALVES TO BE UNDERTAKEN VIEW NOT HOLDING. PRESSURE TESTING UP TO 07 BAR AND PAINTING TO BE UNDERTAKEN. DIA- 50 MM, MAT- GUN METAL, TYPE- GLOBE, QTY-5 |
| 576 | FLOW RATE CHECKS TO BE UNDERTAKEN VIEW LOW RATE. CERTIFICATE TO BE ISSUED. QTY-01, CAPACITY- 37 TPH |
| 577 | PNEUMATIC VALVES MALFUNCTIONING.OVERHAULING OF PNEUMATIC VALVES TO BE UNDERTAKEN VIEW NOT HOLDING. QTY-03 |
| 578 | REPLACEMENT OF HEATER TO BE UNDERTAKEN VIEW NOT WORKING. QTY - 01 |
| 579 | REPLACEMENT OF DEFECTIVE DRY PROTECTION UNIT VIEW MALFUNCTIONING. QTY-01 |
| 580 | MANUFACTURING AND PAINTING OF MACHINERY GUARD AS PER SAMPLE. QTY-05, MAT- MS |
| 581 | OVERHAULING OF TWO GRAY WATER PUMP VIEW LOW DISCHARGE PRESSURE. CAPACITY - 25TPH, QTY-02 |
| 582 | OVERHAULING OF 7 VALVES OUT OF 30 FRESH WATER SYSTEM VALVES TO BE UNDERTAKEN VIEW VALVE NOT HOLDING. PRESSURE TESTING UP TO 07 BAR AND PAINTING TO BE UNDERTAKEN. DIA-32MM MAT- GUNMETAL, TYPE- GLOBE, QTY-7 |
| 583 | OVERHAULING OF TWO FRESH WATER PUMP VIEW LOW DISCHARGE PRESSURE. CAPACITY - 2.5TPH, MAKE- JOHNSON QTY-02 |
| 584 | REPLACEMENT OF 7 VALVES OUT OF 30 FRESH WATER SYSTEM VALVES TO BE UNDERTAKEN VIEW VALVE NOT HOLDING. DIA- 32 MM, MAT- GUNMETAL, QTY-7 |
| 585 | 60 MTRS OUT OF 250 MTRS REPAIR/ RENEWAL OF FRESHWATER SYSTEM PIPE LINES AND PRESSURE TESTING UP TO 07 BAR VIEW CRACKED/ PERISHED. PAINTING OF PIPES TO BE UNDERTAKEN, PRIMER AND TWO COAT WHITE PAINT. MAT- MS, LENGTH-25 MTR ,DIA-25,50MM |
| 586 | CALIBRATION OF FOLLOWING EQUIPMENT OF HYDROPHORE TANK VIEW MALFUNCTIONING:-1. PRESSURE GAUGE-012. CUTIN/ CUT OUT SWITCH-01CERTIFICATE TO BE ISSUED POST COMPLETION. |
| 587 | CLEANING AND PRESSURE TESTING OF HYDROPHORE TANK TO BE CARRIED OUT VIEW CLOGGED. CERTIFICATE TO BE ISSUED POST COMPLETION. |
| 588 | PNEUMATIC VALVES MALFUNCTIONING.OVERHAULING OF PNEUMATIC VALVES TO BE UNDERTAKEN VIEW NOT HOLDING. QTY-02. RENEW IF FOUND DEFECTIVE. |
| 589 | OVERHAULING OF HOT WATER CIRCULATING PUMP VIEW LOW DISCHARGE PRESSURE.CAPACITY-2.5 TPH MAKE- JOHNSON QTY-01 |
| 590 | OVERHAULING OF 7 VALVES OUT OF 30 HOT WATER SYSTEM VALVES TO BE UNDERTAKEN VIEW VALVE NOT HOLDING. PRESSURE TESTING UP TO 07 BAR AND PAINTING TO BE UNDERTAKEN. DIA-32MM MAT- GUNMETAL, TYPE- GLOBE, QTY-7 |
| 591 | 50 MTRS OUT OF 250 MTRS REPAIR/ RENEWAL OF HOTWATER SYSTEM PIPE LINES AND PRESSURE TESTING UP TO 07 BAR VIEW CRACKED/ PERISHED. PAINTING OF PIPES TO BE UNDERTAKEN, PRIMER AND TWO COAT WHITE PAINT. MAT- MS, LENGTH-30 MTR ,DIA-25MM |
| 592 | OVERHAULING 5 OUT OF 20 FUEL SYSTEM VALVES TO BE UNDERTAKEN AND PRESSURE TESTING UP TO 05 BAR. PAINTING TO BE UNDERTAKEN VIEW VALVE NOT HOLDING. DIA- 20 NB, MAT- MS TYPE GLOBE, QTY-05 |
| 593 | OVERHAULING OF QUICK SHUT OFF VALVE TO BE UNDERTAKEN VIEW VALVE NOT HOLDING. QTY-03 |
| 594 | 50 MTRS OUT OF 250 MTRS REPAIR OF FUEL SYSTEM PIPE LINES AND PRESSURE TESTING UP TO 07 BAR VIEW CRACKED/ PERISHED. PAINTING OF PIPES TO BE UNDERTAKEN, PRIMER AND TWO COAT WHITE PAINT. MAT- MS, LENGTH-20 MTR ,DIA-25,50 MM |
| 595 | OVERHAULING OF FUEL SUCTION VALVES FROM STORAGE TANKS TO RU TANKS TO BE UNDERTAKEN AND PRESSURE TESTING UP TO 05 BAR VIEW NOT HOLDING. PAINTING TO BE UNDERTAKEN. JOB INVOLVED DE-GUTTING AND RE-FITMENT OF FRAMES AND PIPELINES IN VICINITY. DIA- 60 NB, MAT- MS TYPE GLOBE, QTY-06 |
| 596 | TESTING AND TUNING OF THROTTLE LEVER MECHANISM FOR SMOOTH OPERATION VIEW MALFUNCTIONING. QTY-02. WIRE TO BE RENEWED IF FOUND DEFECTIVE. |
| 597 | 50 MTRS OUT OF 300 MTRS COPPER TUBE REPLACEMENT OF SYSTEM GAUGE LINE AT VARIOUS LOCATIONS VIEW PERSHIED AND CRACKED. QTY-50 MTR |
| 598 | BOTH ENGINES AND BOTH DA MIXING UNIT CHEMICAL CLEANING AND PRESSURE TESTING UP TO 4 BAR VIEW CLOGGED. QTY-04 |
| 599 | RENEWAL OF COLD LAGGING OF REF PLANT GAS LINES TO BE UNDERTAKEN VIEW PERISHED . QTY-50 MTR |
| 600 | CHEMICAL CLEANING OF REF PLANT CONDENSER TO BE UNDERTAKEN VIEW CLOGGED. POST CLEANING, PRESSURE TESTING UP TO 03 BAR. Qty - 02. |
| 601 | SERVICEABILITY CHECKS OF SAFETY DEVICE CHECKS OF BOTH REF PLANT TO BE CARRIED OUT. PROVE SYSTEM OPERATION TO TRIAL TEAMS. CERTIFICATE TO BE ISSUED POST COMPLETION. QTY-02 |
| 602 | OVERHAUL STEERING PUMPS AND MOTORS TO BE UNDERTAKEN VIEW SUB OPTIMAL PERFORMANCE. CHECK ALIGNMENT BETWEEN PUMP AND MOTOR AFTER FITMENT. |
| 603 | OVERHAULING OF REMOTE STARTING PANELS IN CHART HOUSE TO BE UNDERTAKEN VIEW MALFUNCTIONING. |
| 604 | OVERHAUL FEEDBACK UNIT AND REPLACE DEFECTIVE POTENTIOMETER VIEW MALFUNCTIONING. |
| 605 | REPLACE DEFECTIVE RAI AND ROI |
| 606 | CALIBRATION OF FOLLOWING EQUIPMENT OF CO2 MAJOR FIRE FIGHTING SYSTEM TO BE UNDERTAKEN AND CERTIFICATE TO BE ISSUED:- BOURDAN PRESSURE GAUGE-05, MANUAL RELIEF VALVE-05 SAFETY RELIEF VALVE-05 |
| 607 | REPLACEMENT OF 15 MTR CO2 MAJOR FIRE FIGHTING SYSTEM PIPELINES WITH ADAPTER/ UNION AND SYSTEM PRESSURE TESTING UP TO 100 BAR VIEW PERISHED AND CRACKED. LENGTH-15 MTR MAT-SS |
| 608 | WEIGHING AND INSPECTION OF N2 PILOT CYLINDER TO BE UNDERTAKEN AND CHARGE IF REQUIRED. QTY-02 |
| 609 | MANUFACTURING, FITMENT AND PRESSURE TESTING UP TO 150 BAR CO2 MAJOR FIRE FIGHTING SYSTEM N2 BOTTLE PIPE LINE VIEW CRACKED. LENGTH-15 MTR, MAT-CUNI |
| 610 | OVERHAULING OF FOLLOWING PUMPS TO BE CARRIED OUT VIEW NOT TAKING SUCTION. 1. MAIN ENGINE AND DA LUB OIL HAND PRIMING PUMP - 04 2. DIRTY LUB OIL PUMP - 01 3. LUB OIL HAND PUMP - 01 4. HAND BILGE PUMP - 015. FUEL TRANSFER HAND PUMP - 01 |
| 611 | MANUFACTURING OF DD PUMP SUCTION STRAINER AND SEA CHEST AND SEA TUBE STRAINER VIEW RUSTED AS PER SAMPLE. QTY-10(2+4+4) MAT - BRASS, DIA-30MM |
| 612 | BOTH SEA CHEST AND SEA TUBE STRAINER TO BE MANUFACTURED AS PER SAMPLE. QTY-04, MAT- BRASS, DIA-40MM |
| 613 | PAINTING OF VARIOUS SYSTEM PIPE LINES TO BE UNDERTAKEN AS PER COLOUR CODING. ONE COAT WHITE PAINT TO BE APPLIED. QTY-150 MTR |
| 614 | PAINTING OF TANK MANHOLES TO BE UNDERTAKEN AS PER COLOUR CODING. QTY - 16 |
| 615 | MANUFACTURING OF CONICAL NUTS OF TANK MAHOLES TO BE UNDERTAKEN AS PER SAMPLE. QTY - 300. |
| 616 | RENEWAL OF ALL FLEXIBLE METALLIC CABLE CONDUIT OF DA AND MAIN ENGINE CONTROL WIRING VIEW PERISHED AND BROKEN. QTY-50 MTR |
| 617 | REPLACEMENT OF RUBBER COMING OF ENGINE ROOM, AFT PUMP ROOM, STP COMPARTMENT BILGE PLATE. PROPER SECURING OF BILGE PLATES TO BE UNDERTAKEN BY APPLICATION OF RUBBER BEADING AND FASTENERS. LENGTH - 150 SQ MTR |
| 618 | SPRAY PAINTING OF BOTH ENGINE AND BOTH DA TO BE UNDERTAKEN WITH FIRE RETARDANT MACHINERY PAINT VIEW PAINT DETERIORATED. QTY-04 |
| 619 | MANUFACTURING OF SOUNDING CAP AS PER SAMPLE. QTY-15, MAT- BRASS |
| 620 | REPAIRS TO BE UNDERTAKEN OF SOUNDING POINTS. MAT- BRASS, QTY - 05 |
| 621 | MANUFACTURING OF 200 IN NO. NAME TALLIES TO BE CARRIED OUT. (MAT - BRASS, SIZE - 100 MM X 25 MM, QTY - 190 ; SIZE - 180 MM X 120 MM, QTY - 10). |
| 622 | PIPE BLANKS TO BE MADE AS PER SAMPLE. DIA-50MM QTY-05,DIA-65MM QTY-05, DIA-80MM QTY-05,DIA-125MM QTY-10.MAT-MS. |
| 623 | MANUFACTURING OF MACHINERY GUARD AS PER SAMPLE. QTY - 08, MAT- MS |
| 624 | HYDROPHORE TANK GAUGE GLASS SAFETY SHIELD TO BE MANUFACTURED AS PER SAMPLE VIEW BROKEN. MAT - BRASS |
| 625 | CALIBRATION OF RELIEF VALVE OF RO PLANT TO BE UNDERTAKEN |
| 626 | CALIBRATION OF RELIEF VALVE OF BOTH REF PLANT TO BE UNDERTAKEN |
| 627 | FUEL RU TANK OVERFLOW SIGHT GLASS TO BE RENEWED AS APER SAMPLE |
| 628 | DIRTY LUB OIL TANK GAUGE GLASS SAFETY SHIELD TO BE MANUFACTURED AS PER SAMPLE VIEW DAMGED. MAT - BRASS |
| 629 | MANUFACTURING OF RUBBER BELLOW OF MAIN ENGINE AND REF SEA WATER SYSTEM AS PER SAMPLE. QTY - 15 |
| 630 | CALORIFIER LEVEL SIGHT GLASS TO BE RENEWED AS PER SAMPLE. QTY - 01. |
| 631 | RENEWAL OF PORTABLE SUCTION PIPES OF BILGE SYSTEM. MAT - PVC, LENGTH 25 |
| 632 | RENEWAL OF HOT LAGGING OF MAIN ENGINE AND HOT WATER SYSTEM TO BE UNDERTAKEN VIEW PERISHED . QTY-100 MTR |
| 633 | PROPELLER COATING TO BE UNDERTAKEN AS PER HQSNC DIRECTIVE EG/3000/NHQ DT 22 JAN 24. QTY - 02 NOS |
| 634 | ELECTRICAL - PART I |
| 635 | SR 1 - REPLACEMENT OF METERS/INSTRUMENTS.CALIBRATION CERTIFICATES TO BE PROVIDED. |
| 636 | SR 3 - SERVICIBILITY CHECKS AND CALIBRATION OF BREAKERS OF DIFFERENT RATINGS, GSK RELAY AND OTHER PROTECTION CIRCUITS. REPLACE DEFECTIVE. |
| 637 | SR 5 - CARRY OUT FOLLOWING ROUTINES ON SWITCHBOARD AND BUSBARS:-(A) INSPECT LUGS/ CONNECTORS/ CT/ PT AND OTHER COMPONENTSAND UNDERTAKE REPAIR DETERIORATION/ DAMAGE OF MSB CABLES/WIRING AS NECESSARY.(B) REPLACE BUSBARS INSULATORS - QTY - 03(C) CLEAN AND DECARBONIZE THE BUSBARS. - QTY - 02(D) CARRYOUT FUNCTIONAL CHECKS OF MSB AND PARALLELING TRIALSWITH ALL COMBINATIONS OF GENERATOR SUPPLY. |
| 638 | SR 1 -OVERHAUL NAVIGATIONAL LIGHTS, CONTROL PANELS. (A) REPLACE DEFECTIVE ROTARY SWITCHES QTY - 04 (B) REPLACE DEFECTIVE INDICATION LAMPS. QTY- 06 (C ) REPLACE 11 PIN RELAY - 04 (D) CONTROL CARD - 04 |
| 639 | SR 2 - CHECK THE SUPPLY CABLES OF SIGNALLING PROJECTORS, RENEW/REWIRE 2 CORE POWER CABLE LENGTH 15 MTR |
| 640 | SR 3 - CHECK BELL CIRCUITS AND CHECK ALL THE LIGHT FOR CORRECT BRILLIANCY. REPLACE LAMPS QTY - 05 |
| 641 | OVERHAUL THE RECTIFIER AS NECESSARY.LOAD TRIALS OF RECTIFIER TO BE CARRIED OUT. |
| 642 | LAND THE BATTERIES TO THE BATTERY SHOP FOR MAINTENANCE AND CAPACITY TEST AND REPAIR AS NECESSARY |
| 643 | CALIBRATE ALL INSTRUMENTS. REPLACE THE FOLLOWING :- REPLACE THE FOLLOWING :- (A) HEATING ELEMENT - 01 (B) CONTACTOR - 02 (C ) MCB - 02 |
| 644 | SR 1 - CARRY OUT ADJUSTMENT OF FUNDAMENTAL FREQUENCY AS PER PAGE 3 OF EQUIPMENT MANUAL (FUNDAMENTAL FREQUENCY = 305 HZ +/- 03%), BY ADJUSTING THE POTENTIOMETER R12. |
| 645 | SR 1 - CARRYOUT OVERHAULING OF MAGNETIC COMPASS AND RENEW SUPPORITNG LIQUID. |
| 646 | SR 2 - CARROUT SWING CHECK AND CALIBRATE THE COMPASS. |
| 647 | SR 1 - CARRYOUT THE PRINTER AND SPEED CONTROL CHECKS. |
| 648 | SR 3 - CARRY OUT VISUAL EXAMINATION OF PCBs. CARRY OUT SYSTEM HEALTH CHECKS AS PER RESPECTIVE MANUALS. CARRY OUT FOLLOWING CHECKS: - 1. SWITCH OFF THE EQUIPMENT AND CHECK THAT ALL CABLE CONNECTORS ARE INTACT AND CONNECTED PROPERLY. 2. TIGHTEN ALL SCREWS LOOSENED DUE TO VIBRATION. 3. CLEAN THE TRANSDUCER OF ECHOSOUNDER WHEN IN DRY DOCK. EXAMIN THE TRANSDUCER AND CASINGS. PRESERVE THE TRANSDUCER SURFACE DURING DRY DOCKING. CARRY OUT VISUAL EXAMINATION OF TRANSDUCER CABLES, CHECK CONTINUITY AND INSULATION. 4. CARRY OUT TRIALS ON COMPLETION OF ROUTINES/REPAIRS. |
| 649 | RENEWAL OF TRANSDUCER PCB - QTY - 04 |
| 650 | SR 1 - CARRYOUT PERFORMANCE CHECKS OF THE TRANS-RECEIVER AS PER TECH. MANUAL. |
| 651 | SR 2 - IN CASE PERFORMANCE PARAMETERS DO NOT MEASURE UP TO THE FACTORY TEST SHEET PARAMETERS, CARRY OUT ADJUSTMENT OF THE SET. |
| 652 | SR 1 - CARRY OUT PHYSICAL INSPECTION OF ALL THE RACKS/ CABINETS FOR DAMAGE AND REPAIR IF REQUIRED. |
| 653 | SR 2 - CARRY OUT VISUAL INSPECTION OF ALL THE SWITCHES/ METERS/ HANDSETS/ CABLES FOR DEFECT AND REPLACE/ REPAIR IF REQUIRED. |
| 654 | SR 1 - REMOVE AND EXAMINE SEA-WATER SIDE OF ALTERNATOR AIR COOLER (WHERE FITTED) FOR CORROSION, EROSION AND FOULING. CLEAN TUBE PLATE AND TUBES WITH WATER JET. CARRY OUT CHEMICAL CLEANING AND PRESSURE TEST ON COMPLETION. |
| 655 | SR 5 - CHECK AVR FOR SERVICEABILITY. CARRY OUT CALIBRATION AS NEECSSARY. IN CASE OF ANY TUNING/ CALIBRATION UNDERTAKEN ON AVR, THE VOLTAGE CONTROL TEST AND PARALLELING TRIALS TO BE UNDERTAKEN. |
| 656 | SR 9 - CHECK SECURING ARRANGEMENTS OF POWER AND CONTROL CABLES TO BUS BAR/ AVR. ALL LOOSE SCREWS TO BE TIGHTENED. DEFECTIVE SCREWS TO BE REPLACED. |
| 657 | SR 11 - CARRY OUT SPM CHECKS, PHASE BALANCING, INSULATION MEASUREMENT. OVERHAUL GENERATOR AND REPLACE NEARINGS. CARRY OUT LOAD TRIALS AND RECORD RESULTS IN LOG BOOK. REPLACE BEARINGS IF FOUND IN RED ZONE. |
| 658 | SR1 CARRYOUT SERVICEABILITY CHECKS OF ALL UNITS AND OVERALL CHECK UP OF THE SYSTEM INCLUDING PCBS,MANUAL CALL POINTS,DETECTORS AND HOOTERS.UNDERTAKE REPLACEMENT OF DEFECTIVE PART. |
| 659 | OVERHAUL THE EQUIPMENT COPMPLETELY AND UNDERTAKE THE FOLLOWING:- 1. CHANGE THE ELEMENT IF DEFECTIVE 2. RENEW THE INTERNAL WIRING IF PERISHED 3. CHECK THE ROTARY SWITCHES,CHANGE WITH NEW ONE IF REQUIRED |
| 660 | CARRYOUT PARAMETER CHECKS OF THE RADAR |
| 661 | SR 4 - CLEAN AND APPLY RF PAINT ON THE ANTENNA.. |
| 662 | SR 5 - INSPECT THE SHOCK MOUNTS AND CHECK THAT FASTENING UNITS ARE PROPERLY TIGHTENED. RE-COAT WITH NECOL LACQUER |
| 663 | SR 6 - CHANGE THE OIL IN COMBINED ANTENNA PEDESTAL. CHECK THE SYSTEM FOR PROPER OPERATION. |
| 664 | SR 7 - CARRY OUT VSWR, SENSITIVITY AND POWER OUTPUT CHECKS. |
| 665 | SR 10 - MEASURE CHARACTERISTIC IMPEDANCE OF THE ANTENNA FEEDER. |
| 666 | SR 11 - CARRY OUT COMPLETE OVERHAULING OF THE EQUIPMENT AND TEST FOR OPTIMUM PERFORMANCE. |
| 667 | SR 2 CARRY OUT SERVICEABILITY CHECKS OF UPS,PCBS IN INTERFACE UNIT AND PROCESSOR.REPAIR/REPLACE IF ANY. |
| 668 | RENEW SUPPORTING LIQUID,DISTILLED WATER AND CARRY OUT THE FOLLOWING CHECKS:-1. SWITCH ON GYRO COMPASS AND CHECK ITS PERFORMANCE.2. CHECK FOLLOW UP SYSTEM WITH GYRO COMPASS.3. CHECK SENSITIVITY OF FOLLOW UP SYSTEM, IT SHOULD NOT BE LESS THAN 70 DEGREES/ SECOND |
| 669 | SR 1 - CARRY OUT SERVICEABILITY CHECKS OF ALL UNITS AND OVERALL CHECK UP OF SYSTEM INCLUDING ACOS, PCBs, MANUAL CALL POINTS, DETECTORS & HOOTERS (WHERE APPLICABLE). UNDERTAKE REPLACEMENT OFFOLLOWING :- (A) SENSORS - 10 NOS (B) MANUAL CALL POINT - 01 NOS |
| 670 | SR 1 - CHECK LIMIT SWITCH FOR PROPER OPERATION. RENEW DEFECTIVE LIMIT SWITCHES. |
| 671 | SR 1 - OVERHAUL THE MOTOR AND STARTERS. RENEW BEARINGS SUBJECT TO QC CHECKS. |
| 672 | SR 2 - CALIBRATE OVER-LOAD MECHANISM OF THE STARTER. |
| 673 | SR 1 - LUBRICATE/ REPLACE BEARING. (DE: 6205, NDE: 6205) |
| 674 | SR 2 - CARRY OUT CALIBRATION OF OVERLOAD RELAY (OLR)/THERMAL PROTECTION (TP) OF STATER. |
| 675 | SR 1 - OVERHAUL THE MOTOR (1.5KW-03, 3.7KW-02) AND STARTER. RENEW BEARINGS. |
| 676 | SR 2 - CALIBRATE OVER-LOAD MECHANISM OF THE STARTER. |
| 677 | SR2 CARRY OUT INTERNAL CLEANING AND CHECK FEEDER CABLE CONNECTORS |
| 678 | SR 3 - CHECK ALL PCBs AND THEIR COMPONENTS FITTED IN THE ANTENNA. REPAIR IF REQUIRED. |
| 679 | SR 5 - CHECK ALL PCBs, PRINTING HEAD AND OTHER COMPONENTS FOR DAMAGE/ DEFECT. |
| 680 | SR 6 - CARRYOUT NECESSARY CHECKS AND ADJUSTMENTS AFTER REPAIR AS PER PARA 3.3 OF TECHNICAL MANUAL. |
| 681 | SR 7 - CARRYOUT INTERNAL CLEANING OF THE EQUIPMENT. |
| 682 | SR 1 - INSPECT THE SET FOR ANY MECHANICAL DAMAGE/ DEFECT. CARRYOUT REPAIR/ REPLACEMENT IF REQUIRED. |
| 683 | SR 1 - CARRYOUT SENSITIVITY AND SELECTIVITY CHECKS AS PER INSTRUCTIONAL MANUAL. |
| 684 | SR 2 - CHECK COMPLETE OPERATION IN ALL OPTIONS FOR ANY DEFECT AND CARRYOUT REPAIRS IF ANY. |
| 685 | SR 1 - CHECK SENSOR FOR CONTAMINATION DUE TO EXHAUST GASES, WASH IT WITH FRESH WATER AND MILD SOAP SOLUTION AS NECESSARY. |
| 686 | SR 2 - CHECK THE SHOCK/ VIBRATION MOUNTS, RENEW IF NECESSARY. |
| 687 | SR 1 - OVERHAUL THE MOTOR & STARTERS. REPLACE BEARING |
| 688 | SR-2 CALIBRATE OVER-LOADING MECHANISM OF FIRE MAIN STARTER |
| 689 | SR 1 - OVERHAUL THE MOTOR & STARTERS. REPLACE BEARING |
| 690 | SR-2 CALIBRATE OVER-LOADING MECHANISM OF BILGE PUMP STARTER |
| 691 | SR 1 - OVERHAUL THE MOTOR & STARTERS. REPLACE BEARING |
| 692 | SR-2 CALIBRATE OVER-LOADING MECHANISM OF GREY WATER PUMP STARTER |
| 693 | SR 4 - CLEAN AND APPLY RF PAINT ON THE ANTENNA.. |
| 694 | SR 5 - INSPECT THE SHOCK MOUNTS AND CHECK THAT FASTENING UNITS ARE PROPERLY TIGHTENED. RE-COAT WITH NECOL LACQUER |
| 695 | SR 6 - CHANGE THE OIL IN COMBINED ANTENNA PEDESTAL. CHECK THE SYSTEM FOR PROPER OPERTION. |
| 696 | SR 7 - CARRY OUT VSWR, SENSITIVITY AND POWER OUTPUT CHECKS. |
| 697 | SR 10 - MEASURE CHARACTERISTIC IMPEDANCE OF THE ANTENNA FEEDER. |
| 698 | SR 12 - CARRY OUT COMPLETE OVERHAULING OF THE EQUIPMENT AND TEST FOR OPTIMUM PERFORMANCE. |
| 699 | MAJOR AS AND AS INSTALLATION OF DMR 16A AS PER APPROVED BPS. MAJOR WORK ENVISAGED:-1. MANUFACTURING OF REQUIRED BRACKET/ FRAME FOR INSTALLATION OF DMR 16A AND UPS 2. FITMENT OF DEVICES AT DESIGNATED PLACE. 3. LAYING OF POWER SUPPLY CABLE 4. FITMENT OF AMPLIFIERS AND ONE MIC 5. LAYING OF POWER CABLES AND CO-AXIAL CABLE 6. OPENING OF RESPECTIVE GLAND AND SEALING POST CABLE LAYING. 7. GROUNDING OF ALL DEVICES TO AVOID EMI/EMC 8. CONNECTORISATION OF VARIOUS CABLES AND INTERCONNECTION OF DEVICES AS REQUIRED 9. INSTALLATION OF COMPLETE SYSTEM, STW/TT. 10. HATs/SATs |
| 700 | ABER REPLACEMENT OF RAYMARINE RADAR WITH VISION MASTER RADAR. INSTALLATION OF NAV RADAR ENVISAGED FOLLOWING SOW:-1. REMOVAL OF EXISTING RAYMARINE ANTENNA UNIT ALONG WITH FOUNDATION AND DISPLAY UNIT.2. SHIFITING OF ANTENNA SUPPORTING MAST 3. FABRICATION FOR BASE PLATES AND NECESSARY FOUNDATIONS FOR INSTALLATION OF NEW RADAR UNITS IN CHART HOUSE AND POOP DECK 4. SHIFTING OF LRAD TO POOP DECK AND MANUFACTURING A NEW FOUNDATION 5.INSTALLATION OF FOLLOWING UNITS :-5.1. DISPLAY UNI, UPS AND PROCESSOR 5.2. ANTENNA UNIT WITH UPMAST 5.3. INTER-SWITCH 6. OPENING OF EXISTING VABLE GLANDS 6. LAYING OF ALL INTER-SYTEM CABLES AS PER CABLE SCHEDULE 7. LAYING OF ALL POWER SUPPLY CABLES FROM DB TO ANTENNA, DISPLAY UNITS AND SUB UNITS 8. SEALING OF CABLE GLANDS POST CABLING 9. FABRICATION AND FITMENT OF CABLE TALLIES 10. COMMISSIONING, STW AND TT OF EQUIPMENT 11. HATs/ SATs/SEA OP CHECKS OF EQUIPMENT 12.OPENING/CLOSING OF CABLE GLANDS. ULD TEST TO BE CARRIED OUT POST CLOSING OF GLANDS 13. COVERING OF ALL UPPER DECK COVERINGS WITH METALLIC CONDUITS 14. SECUING OF ALL THE CABLES THROUGHOUT THE LENGTH OF THE SHIP/ PASSING THROUGH VARIOUS COMPARTMENTS WITH METTALLIC CABLE-TIES. |
| 701 | ABER CAT I REPLACEMENT 1. REMOVAL AND REPLACEMENT OF FOLLOWING GALLEY EQUIPMENT VIEW VINAGE AND SUB OBTIMAL PERFORMANCE. RENEW CABLE AS PER REQUIREMENT :- 1.1. 15KW COOKING RANGE 1.2. COOKING STOVE |
| 702 | ABER CAT II REPLACEMENT OF EXISTING FITTED EM LOG OF MAKE LILLEY AND GILLEY WITH EM LOG OF MAKE KELTRON AS PER APPROVED BPS. ENVISAGED SOW INCLUDES:-1. REMOVAL/DEGUTTING OF OLD EQUIPMENT AND SUB-EQUIPMENT. 2. REMOVAL OF EXISTING CABLE AND STARTING PANEL. 3. MODIFICATION ON FOUNDATION FRAMES. 4. FITMENT OF NEW EQUIPMENT. 5. MANUFACTURING OF BRASS TALLIES FOR ALL SUB UNIT AND EQUIPMENT PANEL. 6. POWERING UP, STW, TESTING, COMMISSIONING, TRAINING OF CREW AND TRIALS.7. IIS/HATS/SATS QTY- 02 |
| 703 | ABER CAT II REPLACEMENT OF EXISTING FBB 500 OF MAKE FURUNO WITH FBB 500 OF MAKE SAILOR AS PER APPROVED BPS. ENVISAGED SOW INCLUDES:-1. REMOVAL/DEGUTTING OF OLD EQUIPMENT AND SUB-EQUIPMENT. 2. REMOVAL OF EXISTING CABLE AND STARTING PANEL.3. CABLING FOR NEW EQUIPMENT AND STARTER PANEL. 3. MODIFICATION ON FOUNDATION FRAMES. 4. FITMENT OF NEW EQUIPMENT. 5. MANUFACTURING OF BRASS TALLIES FOR ALL SUB UNIT AND EQUIPMENT PANEL. 6. POWERING UP, STW, TESTING, COMMISSIONING, TRAINING OF CREW AND TRIALS.7. COMPLETE OP CHECKSQTY- 01 |
| 704 | ELECTRICAL - PART II |
| 705 | RENEWAL OF 2 CORE CABLE FROM HCOS TO STARTING MOTORS OF BOTH DA |
| 706 | RENEWAL OF 2 CORE CABLE FROM HCOS TO STARTING MOTORS OF BOTH ENGINES |
| 707 | CARRY OUT OVERHAULING OF COMPLETE SET AND CHECK IT FOR COMPLETE OPERATION WITH ALL OPTIONS.REPLACE THE FOLLOWING :- (A) PUSH BUTTONS-02 (B) CONTACTOR - 01 (C ) BELL - 01 (D) INDICATION LAMP - 01 |
| 708 | CARRY OUT INSPECTION OF ALL UNITS FOR PROPER EARTHING AND BONDING,RENEW IF DEFECTIVE |
| 709 | UNDERTAKE INSPECTION OF ALL ASSEMBLIES AND RENEW DEFECTIVE PARTS |
| 710 | REPLACEMENT OF CONTROL PANEL OF ALDIS LANTERN IN BRIDGE VIEW CORROSION |
| 711 | REPLACEMENT OF RELAYS OF MAIN ENGINE |
| 712 | SERVICEABILITY CHECKS OF PCBs OF STEERING CONTROL SYSTEM |
| 713 | REPLACEMENT OF RELAYS OF STEERING CONTROL SYSTEM |
| 714 | REPLACEMENT OF CONTACTORS OF WINCHES |
| 715 | INTERNAL CABLING REPLACEMENT OF GALLEY RANGE EQUIPMENT |
| 716 | OVERHAULING OF QTY - 08 NOS (3.5 Kw) VENTILATION MOTORS |
| 717 | CABLING FROM DA CONTROL PANEL TO BATTERY TERMINAL OF BOTH DAS PERISHED TO BE RENEWED. (CABLE SPECIFICATION: 2*1.5 SQ. MM). QTY - 30 MTR |
| 718 | STBD DA PERCENTAGE PEAK FREQUQNCY VARIATION UNSAT AT 75-100% (LOAD). STBD DA CLEARED FOR EXPLOITATION UPTO 75% LOAD VIDE HQSNC LETTER EE/3090/100 DATED 23 JAN 25. DEFECT TO BE RECTIFIED AND TRIALS TO BE UNDERTAKEN. |
| 719 | NAV AIDS NOT GETTING CONTINUOUS SUPPLY FROM EDA. EDA ONLOAD BREAKER GETTING TRIP INTERMITTENTLY. DI/DR TO BE UNDERTAKEN. QTY - 01. REPLACE DEFECTIVE PARTS. |
| 720 | OVERHAULING OF EDA ALTERNATOR VIEW BEARING DEFECTIVE |
| 721 | REPLACE ALL BROKEN LOCKS OF SWITCHBOARD COVER. |
| 722 | REPLACEMENT OF DEFECTIVE BREAKERS OF DIFFERENT RATINGS, GSK RELAY AND OTHER PROTECTION CIRCUITS. REPLACE DEFECTIVE. |
| 723 | FOLLOWING METERS ARE SHOWING ERRATIC READING. CARRY OUT CALIBRATION OF THE SAME. REPLACE DEFECTIVE METERS. CALIBRATION CERTIFICATE TO BE PROVIDED. 1. DOUBLE VOLTMETER - 012. DOUBLE FREQUENCY METER - 013. VOLTMETER - 024. POWER FACTOR METER - 02 |
| 724 | RUBBER BEADING OF SWITCHBOARD COVERS TO BE REPLACED VIEW PERISHED. QTY - 20 MTR |
| 725 | CALIBRATION OF FOLLOWING MCBs OF SWITCHBOARDTO BE CARRIED OUT. REPLACE DEFECTIVE MCBS.1. SIEMENS SIRIUS 3 POLE 63 AMPS - 022. SIEMENS SIRIUS 3 POLE 32 AMPS - 023. SIEMENS SIRIUS 3 POLE 25 AMPS - 034. SIEMENS SIRIUS 3 POLE 16 AMPS - 035. SIEMENS SIRIUS 3 POLE 10 AMPS - 02 |
| 726 | REPLACEMENT OF FOLLOWING DFECTIVE MCBs OF SWITCHBOARD TO BE CARRIED OUT1. SIEMENS SIRIUS 3 POLE 63 AMPS - 012. SIEMENS SIRIUS 3 POLE 32 AMPS - 013. SIEMENS SIRIUS 3 POLE 25 AMPS - 014. SIEMENS SIRIUS 3 POLE 16 AMPS - 015. SIEMENS SIRIUS 3 POLE 10 AMPS - 01 |
| 727 | REPLACEMENT OF ALL OLD DEFECTIVE DOUBLE POLE SWITCHES AND SOCKETS (230 V SOCKETS) QTY - 100 NOS |
| 728 | COMPLETE CALIBRATION AND SERVICEABILITY CHECKS OF PARALLELING AND PROTECTION UNIT ( PPU-3) AND CALIBRATION CERTIFICATE IS TO BE ISSUED AFTER COMPLETION. RENEW IF DEFECTIVE. QTY - 02 |
| 729 | PAINTING OF MSB TO BE CARRIED OUT WITH MACHINERY COLOR SPRAY PAINT VIEW PAINT DETERIORATED. ALL THE SWITCHBOARD TALLIES TO BE PASTED POST PAINTING. COLOR CODING OF BREAKERS TO BE DONE WITH FLUORESCENT STICKERS. |
| 730 | OVERHAULING ,CLEANING AND DECARBONISATION OF DBs TO BE UNDERTAKEN VIEW POOR CONDITION. QTY - 03 |
| 731 | REPLACE DEFECTIVE MCBS OF DBs. (SPECIFICATION OF MCBS - 3 POLE 16 AMPS) QTY - 20 NOS |
| 732 | ENGINE ROOM 415 DB WORN OUT. MANUFACTURING OF DB TO BE UNDERTAKEN AS PER SAMPLE. MAT - MS, QTY - 5 Nos |
| 733 | CLEANING AND DECARBONISATION OF DBs TO BE UNDERTAKEN.QTY - 07 NOS |
| 734 | REPLACE DEFECTIVE MCBs.1. 2 POLE 20 AMPS - 05 NOS2. 2 POLE 16 AMPS - 15 NOS3. 2 POLE 10 AMPS - 10 NOS |
| 735 | REPLACE THE FOLLOWING MCBS.1. 2 POLE 32 AMPS - 03 NOS2. 2 POLE 20 AMPS - 04 NOS3. 2 POLE 16 AMPS - 05 NOS4. 2 POLE 10 AMPS - 05 NOS |
| 736 | MAIN DC PANEL 24V E/R -CLEANING AND DECARBONISATION OF HCOS IN MAIN DC PANEL TO BE UNDERTAKEN VIEW POOR CONDITION. HCOS HANDLE BROKEN.HANDLE TO BE REPLACED. QTY - 02 |
| 737 | MAIN DC PANEL 24V E/R -OVERHAULING, CLEANING AND DECARBONISATION OF DBS TO BE UNDERTAKEN VIEW POOR CONDITION. QTY - 01 NOS |
| 738 | MAIN DC PANEL 24V E/R - CALIBRATION OF FOLLOWING METERS-1. VOLTMETER - 012. AMMETER - 01 |
| 739 | MAIN DC PANEL 24V E/R -CARRY OUT CALIBRATION OF THE MCBs. REPLACE THE MCBS IF FOUND DEFECTIVE. QTY - 10 NOS |
| 740 | CLEANING AND DECARBONISATION OF HCOS IN ENGINE ROOM. |
| 741 | REPLACEMENT OF DEFECTIVE OF HCOS |
| 742 | HCOS HANDLE BROKEN. HANDLE TO BE REPLACEDQTY - 02 NOS |
| 743 | MAIN CONTROL PANEL TO BE RENEWED VIEW FAULTY |
| 744 | REPLACE 25 FIRE SENSORS |
| 745 | REPLACEMENT OF FOLLOWING:PCBS (MAIN CONTROL PANEL), MANUAL CALL POINTS (QTY-05), HOOTERS(QTY-03), ISOLATOR(QTY-02) |
| 746 | REPLACE DEFECTIVE FLOOD SENSORS. |
| 747 | STERN LIGHT CABLE IN QUARTERDECK DETERIORATED. RENEWAL OF CABLE ALONG WITH METALLIC CONDUIT TO BE UNDERTAKEN.CABLE SPECIFICATION: - 2 CORE CABLE, 2*1.5 SQ MM. QTY - 20 MTR |
| 748 | REPLACE NAVIGATION LIGHTS - 25 |
| 749 | CONTINUITY CHECKS OF SYSTEM TO BE UNDERTAKEN. RENEW FAULTY CABLES AND WIRES. |
| 750 | RENEW CONTROL PANEL VIEW FAULTY AND WORKING SUB OPTIMALLY |
| 751 | RENEWAL OF SOCKETS (BRASS MADE) OF RIGGING LIGHTS TO BE UNDERTAKEN VIEW MATERIAL FAILURE AND CONTACT WORN OUT.QTY- 25 |
| 752 | REPLACE ALL WEATHER DECK METALLIC CONDUIT WITH RUBBER COVERING VIEW RUSTED. SECURING AND EARTHING OF METALLIC CONDUIT TO BE UNDERTAKEN. QTY - 200 MTR |
| 753 | WIRING FROM MSB TO JR. SAILOR BATHROOM TO BE UNDERTAKEN FOR SUPPLY TO WASHING MACHINE VIEW CABLE DETERIORATED.CABLE SPECIFICATIONS:- 3 CORE CABLE, 3*2.5 SQ MM. QTY - 100 MTR |
| 754 | MARINE TYPE 230V, 50HZ SWITCHES IN ENGINE ROOM NOT WORKING, REPLACEMENT TO BE UNDERTAKEN. QTY - 12 NOS |
| 755 | UNIT LAN: -1. WIRING FOR LAN (SCREENED CAT 6 CABLES) TO BE LAID OUT TO THE FOLLOWING LOCATIONS FROM DUTY WATCH LOBBY VIEW CABLE DETERIORATED: -1. CO CABIN2. EXO CABIN3. SHIPS OFFICE4. CLASSROOM5. DUTY WATCH LOBBY6. CHART HOUSE |
| 756 | REPLACEMENT OF DEFECTIVE BUNK LIGHTS AT VARIOUS MESS. QTY - 25 |
| 757 | WIRING OF MARINE AC SUPPLY FROM COCKPIT STORE TO OFFICERS CABIN DETERIORATED. REPLACEMENT OF CABLE TO BE UNDERTAKEN AND OLD CABLE TO BE REMOVED. CABLE SPECIFICATION:- 3 CORE CABLE, 3*4 SQ MMQTY - 50 MTR |
| 758 | CABLE FROM 230V AC DB IN ENGINE ROOM TO THEIR DOMESTIC SUPPLY SOCKETS DETERIORATED. RENEWAL OF CABLE TO UNDERTAKEN AND OLD CABLE TO BE REMOVED.CABLE SPECIFICATION: - 2 CORE CABLE, 2*2.55 SQ MM. QTY - 150 MTR |
| 759 | CABLES FROM 24V DC MAIN PANEL TO SHIPS OFFICE DB DETERIORATED. RENEWAL OF CABLE TO BE UNDERTAKEN AND OLD CABLE TO BE REMOVED.CABLE SPECIFICATIONS: - 2 CORE CABLE, 2*2.55 SQ MM. QTY - 80 MTR |
| 760 | REPLACEMENT OF DFECTIVE WARDROOM & OFFICERS' CABIN PANEL LIGHTS (LED). QTY - 10 NOS |
| 761 | CABLE SECURING TO BE CARRIED OUT USING METALLIC TIES. LENGTH - 500 MTR |
| 762 | MANUFACTURING AND FITMENT OF CABLE TRAYS TO IMPROVE ELECTRICAL HYGIENE LENGTH - 50 MTR. MAT - GI SHEET |
| 763 | WIRING OF GREY WATER PUMP NO 02 IN AFT PUMP ROOM PERISHED, TO BE RENEWED AND OLD CABLE TO BE REMOVED.CABLE SPECIFICATIONS: - 3 CORE CABLE, 3*2.55 SQ MM. QTY - 25 MTR |
| 764 | RENEWAL OF DTH CABLE FROM QUARTER DECK TO FOLLOWING LOCATION VIEW PERISHED- 1. CO CABIN 2. EXO CABIN3. WARD ROOM 4. CLASSROOM QTY-120 MTR. |
| 765 | RENEWAL OF HEATING ELEMENTS OF 15KW (QTY-04) AND 7.5KW (QTY-02) COOKING RANGE AND OVEN (QTY-01) TO BE UNDERTAKEN VIEW LOW INSULATION. QTY - 07 |
| 766 | 15KW AND 7.5KW COOKING RANGE CONTROL PANEL BODY DETERIORATED AND RUSTED. RENEWAL OF PANEL TO BE UNDERTAKEN. QTY - 02 |
| 767 | RENEWAL OF GALLEY INDICATION PANEL VIEW DEFECTIVE COMPONENTS AND POOR MATERIAL CONDITION WITH NEW INDICATION PANEL BOX WHICH INCLUDES FOLLOWING INDICATIONS (AMBER, RED AND GREEN), (TOTAL: 15): -1. GALLEY ISOLATION SWITCH NO. 1 AND 2 SUPPLY AVAILABLE, BREAKER OFF AND BREAKER ON. (QTY-06). 2. 15 KW COOKING RANGE SUPPLY AVAILABLE, HOT PLATE OFF AND HOTPLATE ON. (QTY-03)3. 7.5 KW COOKING RANGE SUPPLY AVAILABLE, HOT PLATE OFF AND HOTPLATE ON. (QTY-03)4. 12 KW DEEP FAT FRYER SUPPLY AVAILABLE, FRYER OFF AND FRYER ON.(QTY-03)5. TALLES TO BE PLACED FOR EACH INDICATION |
| 768 | CABLING TO BE CARRIED OUT FROM MAIN INCOMER BREAKERS/ ROTARY SWITCHES OF 15 KW COOKING RANGE, 7.5 KW COOKING RANGE AND FROM GALLEY ISOLATION PANEL TO GALLEY INDICATION PANEL. (CABLE SPECIFICATION: 2X1SQ.MM, 70MTRS). ADDITIONALLY REMOVAL AND REFIT OF PANELLING TO BE UNDERTAKEN AS REQUIRED. |
| 769 | ATTA KNEEDING MACHINE CONTROL PANEL DETERIORATED AND RUSTED. REPLACEMENT OF PANEL TO BE UNDERTAKEN. QTY -01 |
| 770 | OVERHAULING OF ATTA KNEEDING MACHINE MOTOR TO BE UNDERTAKEN VIEW ABNORMAL NOISE. REPLACE BEARING. |
| 771 | OPERATING PANEL OF ANCHOR WINDLASS (QTY-01) AND MOORING WINCH (QTY-04) IS PERISHED TO BE RENEWED WITH NEW IP-65 COMPATIBLE BOX. DETAILED SOW INCLUDE THE FOLLOWING: -1. RENEWAL OF THE BOX (IP 65 COMPATIBLE) (QTY-05)2. RENEW THE PANEL WITH NEW NO/NC PUSH BUTTONS AND INDICATION LAMPS AS PER DIAGRAM. (QTY-05)3. CALIBRATE THE AMPERE METER. REPLACE IF DEFECTIVE (QTY-05) |
| 772 | OVERHAULING OF ANCHOR WINDLASS MOTOR TO BE UNDERTAKEN VIEW HIGH CURRENT. TRIALS OF MOTOR AND BRAKE ASSEMBLY TO BE CARRIED OUT. |
| 773 | RENEWAL OF BATTERY CONNECTIONS WITH NEW LUGS AND PROTECTION COVERS. QTY - 20 NOS |
| 774 | 24V DC CABLES FROM PORT AND STBD BATTERY BANK TO BOTH HCOS IN ENGINE ROOM ARE PERISHED TO BE RENEWED.CABLE SPECIFICATION : 2 CORE CABLE, 2*2.55 SQ MM. QTY - 30 MTR |
| 775 | REPLACEMENT OF BOTH RPM SENSORS AND PCB UNIT TO BE UNDERTAKEN VIEW MALFUNCTIONING. QTY - 02 NOS |
| 776 | MOTOR MONITORING SYSTEM NOT WORKING. FOLLOWING TO BE UNDERTAKEN:MAKE - E3 TECH. COMPLETE REPLACEMENT OF SYSTEM INCLUDING SOFTWARE |
| 777 | TRIALS AND TESTING OF ENTIRE SYSTEM TO BE UNDERTAKEN |
| 778 | ABNORMAL NOISE OBSERVED FROM SUPPLY/EXHAUST MOTORS FROM VARIOUS LOCATION. OVERHAULING OF 14 MOTORS OUT OF 42 TO BE CARRIED OUT. JOB INCLUDES REMOVAL OF MOTORS FROM TRUNKING AND FITMENT POST OVERHAULING. CARRY OUT PERFORMANCE TRIALS POST OVERHAUL.QTY - 14 NOS. MOTOR SPECIFICATION :- 0.75 KW |
| 779 | RENEWAL OF GALLEY VENTILATION MOTORS SUPPLY CABLE VIEW CABLE DAMAGED FROM MULTIPLE LOCATIONS. QTY- 30 MTRCABLE SPECIFICATION: 3 CORE CABLE, 3*6 SQ MM |
| 780 | CABLE FROM 415V DB IN ENGINE ROOM TO VENTILATION MOTOR GROUP STARTERS DETERIORATED AND SHOWING LOW INSULATION. NEW CABLES TO BE RENEWED AND OLD CABLES TO BE REMOVED.SPECIFICATION:- 3 CORE CABLE, 3*6 SQ MM. QTY - 300 MTR |
| 781 | OVERHAULING OF VENTILATION MOTOR STARTER PANEL VIEW DEFECTIVE PUSH BUTTONS QTY - 06 |
| 782 | OVERHAULING OF STARTER CONTROL PANEL - 5.5kW (05) AND 3.75kW(05) |
| 783 | CALIBRATE OVER-LOAD MECHANISM OF THE STARTERS :-1) FIRE MAIN MOTOR - 02 2) BILGE PUMP MOTOR - 023) MOTOR FRESH WATER HYDROPHORE PUMP - 02 4) F.O. TRANSFER PUMP MOTOR - 01 5) HOT WATER CIRCULATION PUMP - 01 6) GREY WATER PUMP SYSTEM - 02 7) F.O. PURIFIER PUMP - 01 |
| 784 | GPS FEED TO NAVTEX RECEIVER FOR FITMENT OF NEW BUFFER UNIT OF MAXIMUM OUTPUT IS NOT AVAILABLE. DEFECT RECTIFICATION TO BE UNDERTAKEN. QTY - 01 |
| 785 | BRIDGE GPS FEED NOT AVAILABLE IN ECDIS. SUSPECTED NMEA POWER CABLE FAULTY. RENEWAL OF THE SAME. QTY - 50 MTRCABLE SPECIFICATION:- NMEA CABLE |
| 786 | RENEWAL OF ANTENNA POWER SUPPLY CABLE AND DATA CABLE VIEW CABLE DAMAGE(SHIPS OFFICE TO BRIDGE AND POOP DECK)SPECIFICATION - POWER CABLE CABLE 2 CORE (0.5 SQ MM)QTY - 50 MTR |
| 787 | RENEWAL OF DATA CABLE VIEW CABLE DAMAGE(SHIPS OFFICE TO BRIDGE AND POOP DECK) SPECIFICATION - CAT 5/6 cable. QTY - 50 MTR |
| 788 | FITMENT OF FOOT IN MIC FOR QUARTER MASTER IN BRIDGE VIEW HAND MIC NOT WORKING. QTY - 01 |
| 789 | 5 IN NOS INTERPHONE SYSTEM IS NOT WORKING.POINT TO POINT CALL NOT HAPPENING FROM INTERPHONE SYSTEM. MB ANNOUNCEMENT NOT WORKING FROM IP PHONE TO BE REPAIRED AND PROVED. QTY - 01 LOT |
| 790 | ABNORMAL NOISE OBSERVED FROM RADAR ANTENNA ROTATION. BEARING REPLACEMENT OF RADAR ANTENNA. QTY-01 |
| 791 | LAYOUT OF HDMI CABLE FROM ECDIS PROCESSOR UNIT IN CHART HOUSE TO ECDIS SLAVE DISPLAY ON BRIDGE DAMAGED. RENEWAL TO BE UNDERTAKEN.QTY - 50 MTR. CABLE SPECIFICATION:- HDMI CABLE |
| 792 | SERVICEABILITY CHECKS OF WSDS SYSTEM TO BE CARRIED OUT VIEW SENSOR DATA NOT GETTING IN THE DISPLAY AND ERROR BUZZER INTERMITENDLY COMING FROM MIU UNIT. MIU UNIT IS TO BE REPAIRED/ RENEWED. |
| 793 | SERVICEABILITY CHECKS OF WSDI SYSTEM TO BE CARRIED OUT VIEW SENSOR DATA NOT GETTING IN THE DISPLAY AND ERROR BUZZER INTERMITENDLY COMING FROM MIU UNIT. MIU UNIT IS TO BE REPAIRED/ RENEWED. |
| 794 | MARINE TYPE 230V, 50HZ, DOUBLE POLE SOCKETS TO BE REPLACE WITH METAL BASE |
| 795 | MULTIPLE DEFECTS OBSERVED ON MAGAZINE SECURITY ALARM IN DUTY WATCH LOBBY. DETAILED SOW INCLUDES THE FOLLOWING: -1. REPLACEMENT OF DEFECTIVE INDICATION ALARM PANEL WHICH INCLUDES SUPPLY AVAILABLE (AMBER), DOOR CLOSE (GREEN), DOOR OPEN (RED) AND ACKNOWLEDGE (BLUE) INDICATIONS, ACKNOWLEDGE AND RESET PUSH BUTTONS AND CONTROL RELAYS/ CONTACTORS. |
| 796 | 2. REPLACEMENT OF DEFECTIVE LIMIT SWITCH INSIDE MAGAZINE LOCKER. QTY- 03 |
| 797 | 3. FITMENT OF RED BEAKON AND BELL IN DUTY WATCH LOBBY. QTY- 15 |
| 798 | OVERHAULING OF SUBMERSIBLE PUMP STARTERS ARE TO BE CARRIED OUT VIEW NON OPERATIONAL |
| 799 | 05 TELEPHONE NOT WORKING. OVERHAULING OF TELEHONE EXCHANGE TO BE UNDERTAKEN |
| 800 | ONE NOS RECTIFIER FLATPACK MODULE IS MALFUNCTIONING TO BE RENEWED. |
| 801 | PRESSURE TESTING OF CALORIFIER TO BE UNDERTAKEN VIEW LEAKAGE FROM BODY. REFURBISH THE DAMAGED AREA AND PRESSURE TESTING TO BE UNDERTAKEN. |
| 802 | HEATING ELEMENT IS SHOWING LOW INSULATION, TO BE REPAIRED/ RENEWED. |
| 803 | WIRING FROM JUNCTION BOX TO OPERATING PANEL OF ALL THE FOUR WINCHES PERISHED TO BE RENEWED. MARKING OF CABLES TO BE MADE. POST RENEWAL, CABLE GLANDS TO BE SEALED USING GLAND PACKING MATERIAL. CARRY OUT TRIALS ON COMPLETION OF REPAIRS. (CABLE SPECIFICATION: 15X1.5SQ.MM) |
| 804 | 05 ALARM DEFECTIVE TO BE RENEWED. |
| 805 | 15 DEFECTIVE UNIT SWITCH TO BE REPLACED OF HYDRAULIC DOOR INDICATION. |
| 806 | REPLACEMENT OF ELECTRIC HORN TO BE CARRIED OUT VIEW OVERHEATING. QTY - 01 |
| 807 | SIGNAL PROJECTOR FRAME CORRODED AND LIGHT INTENSITY REDUCED. REPAIRS TO BE UNDERTAKEN. QTY - 01 |
| 808 | OVERHAULING OF 415V 3 PHASE 50 HZ TRANSFORMER BE CARRIED OUT VIEW OVERHEATING. QTY - 05 |
| 809 | PACKING OF CABLE GLAND TO IMPROVE ELECTRICAL HYGIENE ONBOARD. |
| 810 | UNDERTAKE CONTINUITY CHECKS OF COMPLETE SYSTEM AND RENEW CABLING AS PER REQUIREMENT. |
| 811 | REPLACE 20 DEFECTIVE RIGGING LIGHT. (24V DC, 50W) |
| 812 | UNDERTAKE CONTINUITY CHECKS OF COMPLETE SYSTEM AND RENEW CABLING IF FOUND DEFECTIVE |
| 813 | REPLACE DEFECTIVE MAST LIGHTS. |
| 814 | REPLACEMENT OF DEFECTIVE FLUSH LIGHTS AT VARIOUS LOCATIONS. QTY - 15 |
| 815 | RENEWAL CABLING OF WEATHER DECK LIGHTS |
| 816 | REPLACEMENT OF DEFECTIVE WEATHER DECK LIGHTS AT VATIOUS LOCATIONS. QTY - 05 |
| 817 | REPLACEMENT OF DEFECTIVE LED TUBE LIGHTS AT VARIOUS LOCATIONS. QTY 20 |
| 818 | REPLACEMENT OF DEFECTIVE TWO-IN-ONE LIGHTS AT BRIDGE AND CANTEEN LOBBY. QTY - 03 |
| 819 | REPLACEMENT OF DEFECTIVE REFLECTOR LIGHTS AT CHART HOUSE TOP AND ENGINE ROOM. QTY - 03 |
| 820 | REPLACEMENT OF DEFECTIVE TWO-IN-ONE PENDENT LIGHTS AT VARIOUS LOCATIONS. QTY - 10 |
| 821 | FITMENT OF 20 I/O BOX WITH RJ 45 CONNECTORS ON ABOVE LOCATIONS VIEW EXITING POINTS MALFUNCTIONING. |
| 822 | OVERHAULING OF 7.5 KW MOTORS |
| 823 | FABRICATION OF CABLE TALLIES AS PER SAMPLE . MAT- BRASS QTY - 150 |
| 824 | FABRICATION OF EQUIPMENT TALLIES AS PER SAMPLE.MAT- SS QTY - 150 |
| 825 | FABRICATION OF RACKS FOR NCN EQUIPMENT VIZ. UPS AND NETWORK SWITCHES . QTY- 03 |
| 826 | INSTRUCTIONS ON SECURITY, SAFETY AND MOVEMENT |
| 827 | (A) SHIPYARD TO QUOTE FOR ALL SERIALS. BULK/LUMPSUM COSTING IS NOT ALLOWED. ALL PAYMENTS WILL BE ON ACTUALS ON NOT EXCEEDING BASIS. (B) ALL SPARES ARE TO BE SOURCED THROUGH OEM AND OEM SUPERVISION IS TO BE ENSURED FOR ROUTINE/REPAIRS OF ALL EQUIPMENT.(C) IF SHIP REFIT AT SHIPYARD CONTINUES BEYOND 150 DAYS FOR ANY REASON INCLUDING FORCE MAJEURE, ALL ADMIN/GENERAL SERVICES ARE TO BE EXTENDED WITHOUT ADDITIONAL COST. |
| 828 | PASSES OF ALL SUDARSHINI PERSONNEL TO BE MADE AND PRIORITY CLEARANCE FOR ALL PERSONNEL OF THE SHIP DURING ENTIRE DURATION OF REFIT |
| 829 | SHIPYARD IS REPONSIBLE FOR THE SAFETY OF THE VESSEL AND THE VESSEL'S PROPERTY FROM INCLEMENT AND ADVERSE WEATHER, FOR SAFETY AND SECURITY OF ALL ITEMS/ MATERIAL/EQUIPMENT THAT IS DEGUTTED/REMOVED FROM ONBOARD THE SHIP AND THE SAME ITEM IS TO BE FITTED ONBOARD. SHIPYARD IS TO ESTABLISH A SECURITY PERIMETER AROUND THE VESSEL WITH 2 SENTRIES ROUND THE CLOCK. SHIPYARD EXECUTIVES/STAFF/WORKERS/CONTRACTORS SHALL STRICTLY ABIDE BY ALL NAVAL PROCEDURES / INSTRUCTIONS INTIMATED VERBALLY OR IN WRITING BY SHIP'S OFFICERS AND PROJECT MONITORING OFFICERS. ALL SHIPYARD WORKERS /CONTRACTORS /STAFF ENTERING ONBOARD FOR WORK SHALL BE IN POSSESSION OF VALID ID CARDS AND SHALL SHOW THE SAME WHILE ENTERING/LEAVING OR AS DIRECTED. THE PASSES FOR OFFICERS, PMT AND SAILORS (INCLUDING CAR & BIKE) TO BE ISSUED WITHIN 5 DAYS OF THE ARRIVAL OF THE VESSEL WITH VALIDITY TILL COMPLETEION OF REFIT. THE ENTRY/ EXIT TO SHIP YARD WILL CONTINUE EVEN IN ABSENCE OF SHIP YARD PASSES. PRIORITY CLEARANCE TO ALL NAVAL OFFICERS FOR ENTRY/EXIT TO SHIPYARD, SAILORS OF THE SHIP AND PROJECT MONITORING TEAM TO BE GIVEN SPECIAL CHANNEL FOR UNINTERRUPTED MOVEMENT). |
| 830 | SHIPYARD TO PERMIT UNRESTRICTED ENTRY /EXIT OF MATERIAL/ SPARES/ ITEMS/ EQUIPMENTS ON SHIP'S AND PROJECT MONITORING OFFICER'S LETTER AT ANY HOUR OF THE DAY. IMMEDIATE CLEARANCE (WITHIN 05 MIN) TO BE GIVEN BY SHIPYARD ON VERBAL INTIMATION/EMAIL/LETTER FROM SHIP AND PROJECT MONITORING TEAM.SHIPYARD TO PERMIT ENTRY/EXIT OF INDIVIDUALS OF ANY FIRM /COMPANY/ORGANIZATION /GUESTS ONBOARD THE VESSEL ON SHIPS AND PROJECT MONITORING OFFICERS LETTER. PREFERRENTIAL /IMMEDIATE CLEARANCE(WITHIN 05 MIN) TO BE GIVEN BY SHPYARD BY VERBAL INTIMATION /EMAIL/LETTER FROMN SHIP OR PROJCT MONITORING TEAM. ALL SHIPYARD WORKERS/SUBCONTRACTORS ETC TO BE CHECKED/SCANNED PRIOR ENTRY ONBOARD THE SHIP AND ALSO ALL ITEMS/BAGS TO BE X-RAYED. CCTV RECORD (WITH NIGHT VISION) OF THE ENTIRE SHIP'S PERIMETER TO BE MAINTAINED FOR THE DURATION OF REFIT AND BACK UP OF ATLEAST 30 DAYS TO BE MAINTAINED. |
| 831 | INSTRUCTIONS ON DD & WHARFAGE |
| 832 | PD1 - THE REFITTING AUTHORITY IS TO TAKE ALL ACTIONS TO ENSURE THAT THE DOCKING IS CARRIED OUT IN ACCORDANCE WITH THE LATEST ISSUE OF THE DOCKING PLAN FOR THE PLANNED VERSION OF THE DOCKING WHICH IS SPECIFIC TO THE VESSEL (AND NOT GENERIC TO A CLASS OF VESSELS) AND FOR A PARTICULAR DOCKING PROCEDURE. THE REFITTING AUTHORITIES ARE TO FORWARD DOCKING PLAN, ALONG WITH THE CHECK OFF LIST PROMULGATED VIDE NC/POLICY/H-134/REFIT DATED 11 MAY 18, TO IHQ(N)/DNA THROUGH COMMAND HQS FOR APPROVAL. THE DOCKING FACILITY IS TO BE PREPARED IN ACCORDANCE WITH THE REQUIREMENTS OF THE DOCKING PLAN AND DOCKING PROCEDURES. SR- 26 |
| 833 | PD2 - A DOCK MASTER IS TO BE APPOINTED BY THE REFITTING AUTHORITY FOR EACH DOCKING EVOLUTION AND THE SAME IS TO THE INTIMATED TO COMMANDING OFFICER/ MASTER OF THE VESSEL AS PER FORMAT OF NO STR 01/11, PREFERABLY 72 HOURS IN ADVANCE OF THE COMMENCEMENT OF DOCKING EVOLUTION.SR- 26 |
| 834 | PD4 - REFITTING AUTHORITY (DOCK MASTER AND PLANNER) ARE TO REVIEW THE CALCULATION SUBMITTED BY THE SHIP. THE DOCKING/ UNDOCKING CONFERENCES ARE TO BE ORGANISED BY THE REFITTING AUTHORITY (DOCK MASTER AND REFIT PLANNER) TO REVIEW READINESS FOR DOCKING/ UNDOCKING OPERATIONS, AT LEAST 24 HOURS PRIOR DOCKING/ UNDOCKING. FURTHER, IN ORDER TO UNDERSTAND CRITICALITY OF EACH OPERATION, AND DEMARCATION OF RESPONSIBILITIES OF THE STAKEHOLDERS, THE DOCK MASTER IS TO CONDUCT A CENTRALISED BRIEFING FOR ALL THE STAKEHOLDERS 24 HOURS PRIOR EVERY DOCKING/ UNDOCKING OPERATION.SR- 26 |
| 835 | DRY DOCKING & WHARFAGE |
| 836 | DOCK BLOCK PREPARATION FOR DOCKING OF SHIP IN VERSION - II, BOTH CENTER LINE AND SIDE BLOCKS. SHIPYARD TO ARRANGE FOR THIRD PARTY INSPECTION AND HAND OVER DULY RECOMMENDED CERTIFICATE FOR DOCK BLOCK PREPARATION TO NAVY POST INSPECTION |
| 837 | DOCKING AND UNDOCKING OF THE VESSEL IN VERSION- I. (DURATION 30 DAYS). SHIPYARD TO PLAN AND COMPLETE ALL DRY DOCK RELATED WORK WITH IN DRY DOCK TIME. ELSE SHIPYARD TO CONTINUE DOCKING OF SHIP ALONG WITH ALL ALLIED SERVICES TILL COMPLETION OF WORK WITH OUT ANY EXTRA COST. PAYMENT WILL BE RESTRICTED TO ACCEPTED PERIOD OF CONTRACT |
| 838 | DOCKING & UNDOCKING (QUOTE AS ONE UNIT) |
| 839 | SUBSEQUENT DAYS IN DOCK. |
| 840 | ARRANGE TUG AND PILOTAGE FOR TAKING THE VESSEL FROM NAVAL JETTY TO THE DOCK, DOCKING, UNDOCKING & DELIVERY OF VESSEL BACK AT NAVAL JETTY. PAYMENT BASED ON THE ACTUAL TIMES AS PER WCC ON NOT EXCEEDING BASIS. |
| 841 | MOORING/UNMOORING AND LINE HANDLING FOR EACH OPERATION |
| 842 | PROVIDE WHARFAGE / WET BASIN FACILITIES (WITH 6M DEPTH AT ALL CONDITIONS) AS REQUIRED FOR COMPLETION OF WORK PACKAGE. DREDGING AS REQUIRED TO BE CARRIED OUT PRIOR TO COMMENCEMENT OF REFIT AT SHIPYARD'S COST. PAYMENT WILL BE RESTRICTED TO ACCEPTED PERIOD IN THE CONTRACT |
| 843 | ON DOCKING OF SHIP, ALL MARINE GROWTH ON PROPELLER TO BE SCRAPPED OF USING SUITABLE METHOD BY SHIPYARD. PROPELLER TO BE PRESERVED AND ALSO CLEANING TO BE UNDERTAKEN AS PER IN STANDARDS |
| 844 | TECHNICAL SUPPORT SERVICES |
| 845 | SHIPYARD IS REPONSIBLE FOR THE SAFETY OF THE VESSEL AND THE VESSEL'S PROPERTY FROM INCLEMENT AND ADVERSE WEATHER |
| 846 | SHIPYARD IS RESPONSIBLE FOR SAFETY AND SECURITY OF ALL ITEMS/ MATERIAL/EQUIPMENT THAT IS DEGUTTED/REMOVED FROM ONBOARD THE SHIP AND THE SAME ITEM IS TO BE FITTED ONBOARD |
| 847 | SHIPYARD EXECUTIVES/ STAFF/ WORKERS/CONTRACTORS SHALL STRICTLY ABIDE BY ALL NAVAL PROCEDURES / INSTRUCTIONS INTIMATED VERBALLY OR IN WRITING BY SHIP'S OFFICERS AND PROJECT MONITORING OFFICERS. |
| 848 | ALL SHIPYARD WORKERS /CONTRACTORS /STAFF ENTERING ONBOARD FOR WORK SHALL BE IN POSSESSION OF VALID ID CARDS AND SHALL SHOW THE SAME WHILE ENTERING/LEAVING OR AS DIRECTED |
| 849 | THE PASSES FOR OFFICERS, PMT AND SAILORS TO BE ISSUED WITHIN 02 DAYS OF THE ARRIVAL OF THE VESSEL WITH VALIDITY TILL COMPLETION OF REFIT. THE ENTRY/ EXIT TO SHIP YARD WILL CONTINUE EVEN IN ABSENCE OF SHIP YARD PASSES |
| 850 | PRIORITY CLEARANCE TO ALL NAVAL OFFICERS FOR ENTRY/EXIT TO SHIPYARD, SAILORS OF THE SHIP AND PROJECT MONITORING TEAM TO BE GIVEN SPECIAL CHANNEL FOR EASE OF MOVEMENT. |
| 851 | SHIPYARD TO PERMIT UNRESTRICTED ENTRY /EXIT OF MATERIAL/ SPARES/ ITEMS/ EQUIPMENTS ON SHIP'S AND PROJECT MONITORING OFFICER'S LETTER AT ANY HOUR OF THE DAY. IMMEDIATE CLEARANCE (WITHIN 05 MIN) TO BE GIVEN BY SHIPYARD ON VERBAL INTIMATION/EMAIL/LETTER FROM SHIP AND PROJECT MONITORING TEAM |
| 852 | SHIPYARD TO PERMIT ENTRY/EXIT OF INDIVIDUALS OF ANY FIRM /COMPANY/ORGANIZATION /GUESTS ONBOARD THE VESSEL ON SHIPS AND PROJECT MONITORING OFFICERS LETTER. PREFERRENTIAL /IMMEDIATE CLEARANCE(WITHIN 05 MIN) TO BE GIVEN BY SHIPYARD BY VERBAL INTIMATION /EMAIL/LETTER FROMN SHIP OR PROJECT MONITORING TEAM |
| 853 | ALL SHIPYARD WORKERS/SUBCONTRACTORS ETC TO BE CHECKED/SCANNED PRIOR ENTRY ONBOARD THE SHIP AND ALSO ALL ITEMS/BAGS TO BE X-RAYED. |
| 854 | CCTV RECORD (WITH NIGHT VISION) OF THE ENTIRE SHIP'S PERIMETER TO BE KEPT FOR LAST THIRTY DAYS |
| 855 | PROVIDE QA COVERAGE FOR ENTIRE WORK PACKAGE BY A REGISTERED THIRD PARTY INSPECTING AGENCIES EX - LRS, IRS, ABS ETC. SHIPYARD TO ENSURE QA/QC COVER BY OEMs, FOR WORK BEING UNDERTAKEN THROUGH OEM REPS / OEM AUTHORISED THIRD PARTY FIRMS. |
| 856 | SHIPYARD TO SUBMIT QAP AND QIP WITH IN 2 WEEKS OF SIGNING OF CONTRACT |
| 857 | A DETAILED PERT /GANTT CHART TO BE SUMITTED TO NSRY AND SHIP (IN HARD AND SOFT MEDIA) ON TWO WEEKS PRIOR COMMENCEMENT OF REFIT. THE PERT/GANT CHART TO BE UPDATED TWICE EVERY MONTH AS PER THE PROGRESS OF REFIT. |
| 858 | PROVISION OF SHORE POWER 3 PHASE, 415V, 50HZ, FOR 20 DAYS IN DRY DOCK & FOR THE DURATION OF STAY FOR COMPLETE REFIT INCLUDING NECESSARY CONNECTION / DISCONNECTION (RATES AS PER ACTUAL READING ON BOARD/ENERGY METER READING INSTALLED BY SHIPYARD) POWER SUPPLY CABLE AND METER TO BE PROVIDED BY SHIPYARD. QUOTE FOR 1000 KWH/DAY. PAYMENT BASED ON THE ACTUAL DAYS AS PER WCC ON NOT EXCEEDING BASIS. SHIPYARDS TO INSTALL POWER METER . SHIP SHOULD BE EARTHED AT 04POINTS WHILE IN DRY DOCK. EARTHING CABLE TO BE SUPPLIED BY SHIPYARD. PROPER EARTHING AND ELECTRICAL SAFETY TO BE ENSURED |
| 859 | PROVIDE 03 SEA WATER FIRE MAINS WITH 08 BAR PRESSURE FOR ENTIRE DURATION WITH CONTROL VALVES, MANIFOLDS AND INCLUDE NECESSARY CONNECTION / DISCONNECTION. SHIPYARD TO CONNECT REFERENCE PRESSURE GAUGE AT ALL MANIFOLDS DISCHARGE LINE. CALIBERATION CERTIFICATE OF PRESSURE GAUGES TO BE SUBMITTED ON COMMENCEMENT OF REFIT. PAYMENT BASED ON THE ACTUAL DAYS AS PER WCC ON NOT EXCEEDING BASIS. |
| 860 | SHIPYARD TO PROVIDE 02 PORTABLE AC UNITS (TOTAL 80 TR CAPACITY) WITH AIR HOSES AND VENT PIPES TO SHIP DURING THE PERIOD OF WHARFAGE AND DRY DOCKING. ADEQUATE FLEXIBLE HOSES (MINIMUM)TO CARRY CHILLED AIR FROM PORTABLE AC UNITS TO ACCOMODATION AREAS, IN SHIP'S SUPERSTRUCTURE AND BELOW DECKS AND ELECTRONICS/ CONTROLS/ SENSOR COMPARTMENTS OF THE SHIP TO BE CATERED BY SHIP YARD. PAYMENT BASED ON THE ACTUAL DAYS AS PER WCC ON NOT EXCEEDING BASIS. RIGGING OF REQUIRED HOSES WIL BE RESPONSIBILITY OF THE SHIPYARD |
| 861 | PROVIDE FRESH WATER 04 TONS PER DAY. PAYMENT BASED ON THE ACTUAL DAYS AS PER WCC ON NOT EXCEEDING BASIS. QUOTE TO INCLUDE NECESSARY CONNECTION / DISCONNECTION |
| 862 | PROVIDE FACILITIES FOR GARBAGE COLLECTION AND DISPOSAL ARRANGEMENTS (15 KG EACH) TWICE PER DAY FROM SHIP PAYMENT BASED ON THE ACTUAL DAYS AS PER WCC ON NOT EXCEEDING BASIS. |
| 863 | PROVIDE CRANE 10-15 TON CAPACITY DURING THE REFIT (FOR NAVY'S REQUIREMENT ONLY. SHIPYARD REQUIREMENTS ARE TO BE CATERED IN SEPERATELY). PAYMENT BASED ON THE ACTUAL DAYS AS PER WCC ON NOT EXCEEDING BASIS. |
| 864 | PROVIDE SERVICES OF ONE LISTERS DURING THE REFIT (FOR NAVY'S REQUIREMENT ONLY. SHIPYARD REQUIREMENTS ARE TO BE CATERED IN SEPERATELY). PAYMENT BASED ON THE ACTUAL HOURS AS PER WCC ON NOT EXCEEDING BASIS. |
| 865 | PROVIDE SERVICES OF ONE FORK-LIFT DURING THE REFIT (FOR NAVY'S REQUIREMENT ONLY. SHIPYARD REQUIREMENTS ARE TO BE CATERED IN SEPERATELY). PAYMENT BASED ON THE ACTUAL HOURS AS PER WCC ON NOT EXCEEDING BASIS. |
| 866 | PROVIDE MOBILE CRANE 40 TON CAPACITY DURING THE REFIT (FOR NAVY'S REQUIREMENT ONLY). PAYMENT BASED ON THE ACTUAL HOURS AS PER WCC ON NOT EXCEEDING BASIS. |
| 867 | CLEANING OF ALL TANKS, VENTILLATION AND OBTAINING GAS FREE CERTIFICATE IS THE RESPONSIBILITY OF SHIPYARD. SHIPYARD TO PROVIDE FACILITY TO DUMP DIRTY FUEL, SLUDGE AND LUB OIL. QTY- 15 TANKS. PAYMENT BASED ON THE ACTUALS AS PER WCC ON NOT EXCEEDING BASIS. |
| 868 | PROVIDE 15 FIRE FIGHTING TRAINED HOT WORK SENTRIES WITH 02 SUPERVISORS FOR 16 HRS EACH DAY FOR THE DURATION OF REFIT.NUMBER OF SENTRIES REQUIRED WILL BE INTIMATED BASED ON SHIP YARD'S REQUISITION FOR HOT WORK RECEIVED THE PREVIOUS DAY. PAYMENT BASED ON THE ACTUAL DAYS AS PER WCC ON NOT EXCEEDING BASIS. |
| 869 | TEMPORARY LIGHTING AND VENTILLATION ONBOARD FOR THE ENTIRE DURATION OF REFIT TO BE PROVIDED IN ALL MACHINERY COMPARTMENTS, COMPARTMENTS WITHIN SUPERSTRUCTURE, ALL ALLEYWAYS/ PASSAGE WAYS, CARGO SPACE, BALLAST TANKS MUST BE WELL LIT WITH 24 VDC LAMPS. PROVISION OF MAXIMUM 20 LIGHT POINTS PER DAY. PAYMENT BASED ON THE ACTUAL DAYS AS PER WCC ON NOT EXCEEDING BASIS. |
| 870 | PROVIDE LOAD BANK 100 KW FOR LOAD TRIALS OF DAS WITH M-LOAD TRIALS CAPACITY INCLUDING HIRE CHARGES WITH OPERATOR CREW AND NECESSARY CONNECTION/SHIFTING. (FOR NAVY'S ADDITIONAL REQUIREMENT,IF ANY ONLY. SHIPYARD REQUIREMENTS VIZ. MANDATORY TRIALS POST ROUTINES ARE TO BE CATERED IN SEPERATELY). PAYMENT BASED ON THE ACTUAL DAYS AS PER WCC ON NOT EXCEEDING BASIS. |
| 871 | PROVIDE PORTABLE 100 KW DA INCLUDING HIRE CHARGES WITH OPERATOR CREW AND NECESSARY CONNECTION/SHIFTING. (FOR NAVY'S ADDITIONAL REQUIREMENT,IF ANY ONLY. SHIPYARD REQUIREMENTS VIZ. DA REQUIREMENT VIEW NON AVAILABILITY OF SHORE SUPPLY TO BE CATERED SEPERATELY). PAYMENT BASED ON THE ACTUAL DAYS AS PER WCC ON NOT EXCEEDING BASIS. |
| 872 | 10 NOS PORTABLE VENTILATION BLOWERS NEED TO BE SUPPLIED FOR THE DURATION OF REFIT FOR VENTILATION OF THE COMPARTMENTS AND TANKS (FOR NAVY'S REQUIREMENT ONLY. SHIPYARD REQUIREMENTS ARE TO BE CATERED IN SEPERATELY) PAYMENT BASED ON THE ACTUAL DAYS AS PER WCC ON NOT EXCEEDING BASIS. |
| 873 | 02 NOS LP AIR COMPRESSOR NEED TO BE SUPPLIED FOR THE DURATION OF REFIT FOR LP AIR SUPPLY. (FOR NAVY'S REQUIREMENT ONLY. SHIPYARD REQUIREMENTS ARE TO BE CATERED IN SEPERATELY). PAYMENT BASED ON THE ACTUAL DAYS AS PER WCC ON NOT EXCEEDING BASIS. |
| 874 | SHIPYARD TO ENSURE MOVEMENT OF STEEL FROM MO (KOC) / NSRY (KOC) TO SHIPYARD INCLUDING LOADING / UNLOADING, MANPOWER (04 MEN), TRAILOR, MOBILE CRANE (02 NOS, 5 TONNE EACH), FORK LIFT AND OTHER REQUIRED ACCESSORIES. PAYMENT BASED ON THE ACTUAL DAYS AS PER WCC ON NOT EXCEEDING BASIS. |
| 875 | ANALYSIS OF LUB OIL, COOLENT, HYDRAULIC OIL AND PORTABLE WATER. PAYMENT BASED ON THE ACTUAL DAYS AS PER WCC ON NOT EXCEEDING BASIS. ANALYSIS OF LUB OIL, COOLENT AND PORTABLE WATER OF ALL MAIN ENGINES, DIESEL ALTERNATORS, GEAR BOXES AND AUXILARY MACHINERIES TO BE CARRIED THROUGH NABL CERTIFIED LABORATRY AND TWO COPIES OF THE EACH REPORT TO BE SUBMITTED WITHIN 24 HOURS OF TEST UNDERTAKEN. |
| 876 | (1.2) ADVANCE TEST :- THE ADVANCE TEST OF LUB OIL SHOULD COVERS THE FOLLOWING BY USING ASTM D5185 METHOD:- (1.1.1) WEAR METALIC PARTICALS OF FE, CR, NI, AL, CU, SN, PB AND AG TO BE ANALISED IN TERMS OF PPM IN THE GIVEN SAMPLES OF LUB OIL. (1.1.2) CONTAMINANTS OF SI, NA AND MG TO BE ANALISED IN TERMS OF PPM IN THE GIVEN SAMPLES OF LUB OIL. PAYMENT BASED ON THE ACTUALS AS PER WCC ON NOT EXCEEDING BASIS. |
| 877 | (2)COOLANT TEST / FRESH WATER ADDITIVE TEST - THE FOLLOWING PARAMETERS TO BE ANALYSIS FOR GIVEN SAMPLE: -(2.1) PH VALUE (2.2) CHLORIDE CONTENT (2.3) PERCENTAGE OF INHIBITOR (2.4) HARDNESS (2.5) ANY OTHER TEST REQUIRED. PAYMENT BASED ON THE ACTUALS AS PER WCC ON NOT EXCEEDING BASIS. |
| 878 | (4) HYDRAULIC TEST:-(4.1) BASIC TEST SHOULD COVERS THE FOLLOWING :- (4.1.1) VISCOSITY @ 20% IN TERMS OF CST BY USING METHOD OF ASTM D445(4.1.2) VISCOSITY @ 50% IN TERMS OF CST BY USING METHOD OF ASTM D446(4.1.3) VISCOSITY INDEX RESULTS BY CALICULATIONS BY USING METHOD OF ASTM D447(4.1.4) TESTING BY VISUAL / APPREARANCE(4.1.5) WATER CONTENT TEST BY CRACKLE (4.1.6) WATER CONTENT TEST IN TERMS % VOL BY USING METHOD OF ASTM D95(4.1.7) PENTANE INSOLUBLE TEST IN TERMS OF % WT BY USING METHOD OF ASTM D893(4.1.8) TOLUENE INSOLUBLE TEST IN TERMS OF % WT BY USING METHOD OF ASTM D893(4.1.9) TAN TEST IN TERMS OF MG KOH/G BY USING METHOD OF ASTM D644(4.1.10) SALT CONTENT TEST IN TERMS OF PPM BY USING METHOD OF IP 77(4.1.11) FLASH POINT TEST IN TERMS OF DEGREE CENTIGRADE BY USING METHOD OF ASTM D92/ 93PAYMENT BASED ON THE ACTUALS AS PER WCC ON NOT EXCEEDING BASIS. |
| 879 | (4.3) PROVISION OF CONTAINERS/ SAMPLE BOTTLES:- STANDARD CONTAINERS/ SAMPLE BOTTLES (CAPACITY OF 250 ML) TO BE PROVIDED BY SHIPYARDS FOR LANDING THE SAMPLES OF LUB OILS, COOLANTS, HYDRAULIC OILS ETC FOR ANALYSIS. PAYMENT BASED ON THE ACTUALS AS PER WCC ON NOT EXCEEDING BASIS. |
| 880 | COMPRESSION TESTING FOLLOWED BY GROUPING OF VIBRATION MOUNTS, REPLACE T DAs,BMEs Of ABER ABER REPLACEMENT / ROUTINE ALL REQUIRED TO BE CARRIED OUT AS PER NAVAL STANDARDS |
| 881 | PROVISION OF ONE MINI LORRY OF FOUR TONNE CAPACITY FOR TRANSPORTING SHIP'S MATERIALS/ITEMS/ SPARES.(15 HRS/150 KMS PER DAY). PAYMENT BASED ON THE ACTUAL DAYS AS PER WCC ON NOT EXCEEDING BASIS |
| 882 | TWO BATTERY OPERATED TROLLEY FOR MAN / MATERIAL SHIFTING WITHIN THE SHIPYARD PREMISIS. PAYMENT BASED ON THE ACTUAL DAYS AS PER WCC ON NOT EXCEEDING BASIS |
| 883 | ADMIN SERVICES |
| 884 | SEPARATE SHORE TOILETS AND WASHROOMS FOR SHIP'S OFFICERS AND CREW SUITABLE FOR 20 OFFICERS AND 150 SAILORS NEAR TO SHIPS BERTH / DOCK (WITHIN 100 MTRS). PAYMENT BASED ON THE ACTUAL DAYS AS PER WCC ON NOT EXCEEDING BASIS. |
| 885 | 01 AC DINING HALL WITH LEATHER SOFA SET, DINING TABLE TV WITH DTH CONNECTION,MUSIC SYSTEM AND ADEQUATE CUTLERY AND CHAIRS, CLOSE TO CO'S OFFICE. DINING OF 07 OFFICERS AT A TIME NEAR SHIPS BERTH (WITHIN 200 MTRS). PAYMENT BASED ON THE ACTUAL DAYS AS PER WCC ON NOT EXCEEDING BASIS. |
| 886 | 01 AC DINING HALL SUITABLE FOR DINING TABLE AND CHAIRS FOR DINING OF 50 JUNIOR SAILORS AT A TIME NEAR SHIPS BERTH (WITHIN 200 MTRS). PAYMENT BASED ON THE ACTUAL DAYS AS PER WCC ON NOT EXCEEDING BASIS. |
| 887 | PROVISION OF SHORE GALLEY WITH 04 LPG BURNERS/ELECTRIC HOT PLATES, INCLUDING COST OF GAS/ELECTRICITY AND SINK WITH WATER CONNECTION FOR WASHING OF PLATES, UTENSILS ETC. FRESH WATER RO PURIFIER/ HEAVY DUTY AQUAGUARD TO BE FITTED FOR MEETING GALLEY AND SHIPS CREW WATER REQUIREMENT (AT TWO LOCATIONS VIZ GALLEY AND DINING HALL). PAYMENT BASED ON THE ACTUAL DAYS AS PER WCC ON NOT EXCEEDING BASIS |
| 888 | ONE AIR CONDITIONED SPACE FOR STORAGE SPACE (12 FEET X 12 FEET) FOR FRESH RATION. ONE MAINTAINED AT TEMPERATURE (1-3°C) AND OTHER AT (-10°C). SPACE FOR RATION IF REQUIRED. PAYMENT BASED ON THE ACTUAL DAYS AS PER WCC ON NOT EXCEEDING BASIS |
| 889 | AIR CONDITIONED SPACE FOR STOWAGE OF DRY RATION. ( 12 FEET X 12 FFET). PAYMENT BASED ON THE ACTUAL DAYS AS PER WCC ON NOT EXCEEDING BASIS |
| 890 | PROVISION OF 02 NOS 40 FT CONTAINERS FOR STOWAGE OF DEGUTTED ITEMS DURING SR. PAYMENT BASED ON THE ACTUAL DAYS AS PER WCC ON NOT EXCEEDING BASIS |
| 891 | SUPPLY 300 LITRES OF DRINKING WATER (AQUAFINA/ KINLEY/ BISLERY) PER DAY ONBOARD SHIP AND OFFICE SPACES. PAYMENT BASED ON THE ACTUAL DAYS AS PER WCC ON NOT EXCEEDING BASIS |
| 892 | WATER CONNECTION, HEAVY DUTY WASHING MACHINE, DRIER AND DRYING AREA FOR SHIP'S DHOBI FOR REFIT DURATION PAYMENT BASED ON THE ACTUAL DAYS AS PER WCC ON NOT EXCEEDING BASIS |
| 893 | AIR CONDITIONED & FULLY FURNISHED OFFICE SPACE (INCLUDING OFFICE TABLE, EXECUTIVE CHAIR, VISITORS SOFA, TV WITH DTH, FIRMLY MOUNTED GODREJ SAFE, 01 STRONG LOCKER AND 03 VISITORS CHAIRS AND DINNING TABLE WITH CHAIR) WITH ATTACHED TOILET AND WASHROOM FOR COMMANDING OFFICER FOR REFIT DURATION. PAYMENT BASED ON THE ACTUAL DAYS AS PER WCC ON NOT EXCEEDING BASIS |
| 894 | AC OFFICE SPACE FOR REFIT OFFICE (HALL WITH SEPERATORS/ ROOMS (04)/ CONTAINERS (04) FOR OFFICES VIZ, ENGG OFFICE, ELE OFFICE, HULL OFFICE, GUNNERY/SS OFFICE, SHIPS/REG OFFICE AND REFIT OFFICE, SIX TABLES, 20 CHAIRS AND 08 RACKS WITH LOCK FOR FILE KEEPING ARE TO BE PROVIDED FOR REFIT DURATION. PAYMENT BASED ON THE ACTUAL DAYS AS PER WCC ON NOT EXCEEDING BASIS |
| 895 | PROVIDE 01 AC OFFICE SPACE / CONTAINER WITH REFRIGERATOR FOR SHIPS SICK BAY FOR REFIT DURATION INCLUDING BEDS, TABLES AND STORAGE CUPBOARDS (TWO EACH). CLEARNCE OF MEDICAL WASTE ON DAILY BASIS PAYMENT BASED ON THE ACTUAL DAYS AS PER WCC ON NOT EXCEEDING BASIS |
| 896 | PROVIDE INTERNET CONNECTION AT ONE LOCATION AS INDICATED BY SHIP STAFF FOR REFIT DURATION. PAYMENT BASED ON THE ACTUAL DAYS AS PER WCC ON NOT EXCEEDING BASIS |
| 897 | PROVIDE 02 NO 40 FT CONTAINERS/LAY-APART STORE FOR STOWAGE AND PRESERVATION OF ON BOARD SPARES DURING REFIT TIME. PAYMENT BASED ON THE ACTUAL DAYS AS PER WCC ON NOT EXCEEDING BASIS |
| 898 | PROVIDE AC 01 CONTAINERS/LAY-APART STORE FOR STOWAGE AND PRESERVATION OF CRITICAL ELECTRONIC SPARES / ITEMS DURING REFIT TIME. PAYMENT BASED ON THE ACTUAL DAYS AS PER WCC ON NOT EXCEEDING BASIS |
| 899 | PROVIDE TWO SEPARATE AC PORTABLE CABINS FOR OOD AND DUTY WATCH DURING NIGHT ADJACENT TO SHIP IN JETTY FOR THE FULL REFIT DURATION. PAYMENT BASED ON THE ACTUAL DAYS AS PER WCC ON NOT EXCEEDING BASIS |
| 900 | PROVIDE THREE PORTABLE WC's ON JETTY (01 FOR SHIPS OFFICERS AND 02 FOR CREW)PAYMENT BASED ON THE ACTUAL DAYS AS PER WCC ON NOT EXCEEDING BASIS |
| 901 | (A) PROVIDE FULLY FURNISHED OFFICE SPACE( 400 SQFT) WITH FOR OI/C PROJECT MONITORING TEAM OF NSRY(KOC) WITH TWO ACs, WORK STATION, LOCKERS, STORAGE, ATTACHED TOILET, WASHROOM, CHANGING ROOM, LAND LINE TELEPHONE WITH STD AND 01 BROAD BAND CONNECTION , TV (44 INCH ATLEAST WITH DISH CONNECTION) AND DAILY HOUSEKEEPING. CARTRIDGE FOR PRINTER QTY 08 PAYMENT BASED ON THE ACTUAL DAYS AS PER WCC ON NOT EXCEEDING BASIS. |
| 902 | (B) FULLY OPERATIONAL PANTRY WITH DAILY HOUSEKEEPING, CLEANING AND HYGIENE UPKEEP TO BE PROVIDED WITH BELL AND ATTENDENT(16 HOURS PER DAY). TEA, COFFEE AND SNACKS WITH SUITABLE CROCKERY AND CUTTLERY TO BE PROVIDED AS REQUIRED DURING THE PERIOD OF 16 HRS PER DAY. PAYMENT BASED ON THE ACTUAL DAYS AS PER WCC ON NOT EXCEEDING BASIS. |
| 903 | (C) ONE FULLY FURNISHED AC OFFICE SPACE FOR FIVE(05) MEMBERS OF THE PROJECT MONITORING TEAM WITH FIVE(05) INDIVIDUAL WORKSTATIONS, STORAGE AND LOCKERS, ATTACHED TOILET, WASHROOM, CHANGING ROOM AND LAND LINE TELEPHONE WITH STD, 01 BROAD BAND CONNECTION AND PAPER SHREDDER ALL OFFICE STATIONARY ITEMS / SUPPLIES AS REQUIRED, FOR THE ENTIRE DURATION OF THE REFIT IS TO BE PROVIDED. PAYMENT BASED ON THE ACTUAL DAYS AS PER WCC ON NOT EXCEEDING BASIS. |
| 904 | ONE OFFICE ASSISTANT/CLEANING STAFF FOR DAILY MAINTENANCE TO BE AVAILABLE 12 HRS IN A DAY FOR REFIT DURATION |
| 905 | PROVIDE INTERNET CONNECTION AT FOUR LOCATIONS AS INDICATED BY RMT OF NSRY FOR REFIT DURATION |
| 906 | SHIPYARD TO PROVIDE FULLY EQUIPED AMBULANCE ON SHORT NOTICE.PAYMENT BASED ON THE ACTUAL DAYS AS PER WCC ON NOT EXCEEDING BASIS |
| 907 | STATIONARY, AS INDICATED BY RMT, IS TO BE PROVIDED FOR SMOOTH FUNCTIONING OF RMT(PLANNING & COMMERCIAL) OFFICE OF NSRY FOR Rs 35,000/- PER MONTH. PAYMENT BASED ON THE ACTUALS AS PER WCC ON NOT EXCEEDING BASIS |
| 908 | ACCOMODATION FOR OFFICERS AND SAILORS (INCLUDING CONSERVENCY, HOT WATER, HOUSE KEEPING,LAUNDRY SERVICE AND FULYY FURNISHED RECREATIONAL AREA/ ANTE ROOM OFFICERS, SENIOR SAILORS & JUNIOR SAILORS): PAYMENT BASED ON THE ACTUAL DAYS AS PER WCC ON NOT EXCEEDING BASIS: |
| 909 | AC DELUXE SUITS FOR CO, AC DELUXE ROOMS FOR 07 OFFICERS WITH ATTACHED TOILETS AND BATHROOMS DURING REFIT DURATION:FULLY FURNISHED WITH ACCESSORIES AND CABLE TV WITH DISPLAY UNIT AT EACH ACCOMODATION: PAYMENT BASED ON THE ACTUAL DAYS AS PER WCC ON NOT EXCEEDING BASIS: ) |
| 910 | AC CABINS FOR 10 SENIOR SAILORS OF SHIP ON TWIN SHARING BASIS WITH ATTACHED TOILETS AND BATHROOMS: FULLY FURNISHED WITH ACCESSORIES, CABLE TV AND DISPLAY UNITS DURING REFIT DURATION: PAYMENT BASED ON THE ACTUAL DAYS AS PER WCC ON NOT EXCEEDING BASIS: |
| 911 | AC DORMITORY FOR JUNIOR SAILORS (40 MEN) OF SHIP WITH ATTACHED TOILETS, BATHROOMS, FULLY FURNISHED WITH ACCESSORIES, CABLE TV AND DISPLAY UNITS DURING THE ENTIRE REFIT DURATION: PAYMENT BASED ON THE ACTUAL DAYS AS PER WCC ON NOT EXCEEDING BASIS: |
| 912 | AC DELUXE SUITS FOR OFFICER OF PROJECT (REFIT) MOINTORING TEAM OF DOCKYARD WITH ATTACHED TOILETS AND BATHROOMS DURING REFIT DURATION: FULLY FURNISHED WITH ACCESSORIES AND CABLE TV WITH DISPLAY UNIT AT EACH ACCOMODATION, QTY -03: PAYMENT BASED ON THE ACTUAL DAYS AS PER WCC ON NOT EXCEEDING BASIS: |
| 913 | SINGLE AC CABIN WITH ATTACHED TOILET/BATH: FULLY FURNSIHED WITH ACCESSORIES TV AND DISPLAY UNITS FOR REFIT REVIEW OFFICERS DEPUTED BY COA, QTY-5, PAYMENT BASED ON THE ACTUAL DAYS AS PER WCC ON NOT EXCEEDING BASIS: |
| 914 | TWO ROOMS NEAR SAILORS ACCOMODATION FOR FUNCTIONING OF SHIP'S BARBER SHOP AND DOBHI: PAYMENT BASED ON THE ACTUAL DAYS AS PER WCC ON NOT EXCEEDING BASIS: |
| 915 | PROVIDE 04 DATA ENTRY OPERATORS WITH 1-2 YEARS EXPERIENCE HAVING ADEQUATE COMPUTER KNOWLEDGE AND EXPERIENCE IN MS PROJECT, OFFICE(PPT, WORD, EXCEL, ETC). (ADDITIONAL DAYS INCLUDED FOR PRE-REFIT AND POST-REFIT ACTIVITIES) FOR PLANNING (02 NOS) & COMMERCIAL (02 NOS) DEPARTMENT OF NSRY. SHIPYARD TO PROVIDE A PROOF OF MINIMUM WAGES OF RS 1465/- PER DAY (EXCLUDING EPF AND ESI CONTRIBUTION OF EMPOLYEE & EMPLOYER) PAID TO THE REFIT DATA ENTRY OPERATORS. PAYMENT BASED ON THE ACTUAL DAYS AS PER WCC ON NOT EXCEEDING BASIS. |
| 916 | 01 OFFICE ASSISTANCE TO BE PROVIDED TO PROJECT MONITORING TEAM/ OFFICE FOR MOVEMENT OF DOCUMENTS/REPORTS. PEON / OFFICE ASSISTANCE IS REQUIRED TO VISIT ONBOARD SHIP AND LOCATIONS (AS REQUIRED) FOR MOVEMENT OF FILES /OTHER ASSISTANCES ROUND THE CLOCK ON SHIFT BASIS. SHIPYARD TO PROVIDE A PROOF OF MINIMUM WAGES OF RS 1250/- PER DAY (EXCLUDING EPF AND ESI CONTRIBUTION OF EMPOLYEE & EMPLOYER) PAID TO THE POEN / OFFICE ASSISTANCE. PAYMENT BASED ON THE ACTUAL DAYS AS PER WCC ON NOT EXCEEDING BASIS. |
| 917 | PROVIDE 01 REFIT COORDINATORS EACH WITH MINIMUM B.TECH WITH ATLEAST TWO YEAR EXPERIENCE. SALARY TO MATCH SHIPYARD ASSISTANT/ DEPUTY MANAGER LEVEL. (ADDITIONAL DAYS INCLUDED FOR PRE-REFIT AND POST-REFIT ACIVITIES) FOR RMT OF NSRY. PAYMENT AT ACTUALS.SHIPYARD TO PROVIDE A PROOF OF MINIMUM WAGES OF RS 2565/- PER DAY (EXCLUDING EPF AND ESI CONTRIBUTION OF EMPOLYEE & EMPLOYER) PAID TO THE REFIT COORDINATORS. PAYMENT BASED ON THE ACTUAL DAYS AS PER WCC ON NOT EXCEEDING BASIS. |
| 918 | PROVIDE 01 ACCOUNTANTS CUM AUDITORS WITH ATLEAST BCOM DEGREE AND HAVING 2 YEARS EXPERIENCE IN ACCOUNTING AND AUDIT FOR HANDLING BILLS AND CONTRACTS FOR COMMERCIAL DEPARTMENT OF NSRY. (ADDITIONAL DAYS INCLUDED FOR PRE-REFIT AND POST-REFIT ACIVITIES) PAYMENT AT ACTUALS. SHIPYARD TO PROVIDE A PROOF OF MINIMUM WAGES OF RS 2198/- PER DAY (EXCLUDING EPF AND ESI CONTRIBUTION OF EMPOLYEE & EMPLOYER) PAID TO THE REFIT ACCOUNTANT-CUM-AUDITORS. PAYMENT BASED ON THE ACTUAL DAYS AS PER WCC ON NOT EXCEEDING BASIS. |
| 919 | PROVIDE ONE TONNER TRUCK (WITH TRANSIT INSURANCE, PACKING AND LOADING) FOR TRANSPORTING SHIPS MATERIAL/SPARES FROM SHIPYARD TO MO(K)/NSRY(K) FOR 12 HRS/100 KMS PER DAY WHICHEVER IS LESS: REQUIREMENT FOR TRANSPORT WILL BE INTIMATED ONE DAY IN ADVANCE: PAYMENT BASED ON THE ACTUAL DAYS AS PER WCC ON NOT EXCEEDING BASIS: |
| 920 | PROVIDE ONE FIVE SEATER AC CAR FOR PROJECT OFFICER OF NSRY, KOCHI (15 HRS/150 KMS PER DAY). (CAR REGISTRATION NOT TO BE OLDER THAN 2024, WHITE COLOUR, FITTED WHITE SEAT COVERS, SANITISATION DAILY, DRIVER TO BE WELL GROOMED AND MUST WEAR SHIRT, TROUSER AND SHOES WITH VALID POLICE CLEARANCE CERTIFICATE FOR DRIVERS). PAYMENT BASED ON THE ACTUAL DAYS AS PER WCC ON NOT EXCEEDING BASIS. |
| 921 | PROVIDE ONE SEVEN SEATER AC CAR FOR RMT(NSRY) ) (15 HRS/150 KMS PER DAY). (CAR REGISTRATION NOT TO BE OLDER THAN 2024, WHITE COLOUR, FITTED WHITE SEAT COVERS, SANITISATION DAILY, DRIVER TO BE WELL GROOMED AND MUST WEAR SHIRT, TROUSER AND SHOES WITH VALID POLICE CLEARANCE CERTIFICATE FOR DRIVERS). PAYMENT BASED ON THE ACTUAL DAYS AS PER WCC ON NOT EXCEEDING BASIS. |
| 922 | ONE 05 SEATER AC CAR FOR SHIPS REFIT OFFICERS (15 HRS/100 KMS PER DAY) (CAR REGISTRATION NOT TO BE OLDER THAN 2024, WHITE COLOUR, FITTED WHITE SEAT COVERS, SANITISATION DAILY, DRIVER TO BE WELL GROOMED AND MUST WEAR SHIRT, TROUSER AND SHOES WITH VALID POLICE CLEARANCE CERTIFICATE FOR DRIVERS). PAYMENT BASED ON THE ACTUAL DAYS AS PER WCC ON NOT EXCEEDING BASIS. |
| 923 | PROVIDE ONE AC CAR FOR CO (15 HRS/150 KMS PER DAY) (**CAR REGISTRATION NOT TO BE OLDER THAN 2024). PAYMENT BASED ON THE ACTUAL DAYS AS PER WCC ON NOT EXCEEDING BASIS. |
| 924 | 02 AC 05 SEATER CARS FOR SHIP'S OFFICERS (15 HRS/150 KMS PER DAY) (**CAR REGISTRATION NOT TO BE OLDER THAN 2024) PAYMENT BASED ON THE ACTUAL DAYS AS PER WCC ON NOT EXCEEDING BASIS. |
| 925 | ONE AC BUS EACH OF 50 SEATER & 25 SEATER (15 HRS/150 KMS PER DAY). PAYMENT BASED ON THE ACTUAL DAYS AS PER WCC ON NOT EXCEEDING BASIS. |
| 926 | FOLLOWING TO BE ENSURED FOR ALL ABOVE OFFICE SPACES (A) DRINKING WATER THROUGH RO/AQUAGAUARD WITHIN 50 M (B) SEPARATE TOILETS FOR OFFICERS AND CREW ARE TO BE PROVIDED WITHIN 50M (C) DAILY MAINTENANCE / CLEANING PAYMENT BASED ON THE ACTUALS AS PER WCC ON NOT EXCEEDING BASIS |
| 927 | LIST OF SPARES TO BE QUOTED BY THE SHIPYARDS |
| 928 | ALUMINIUM ALLOY ANODE WELDABLE (MK - 11) |
| 929 | ALUMINIUM ALLOY ANODE WELDABLE(MK - 111) |
| 930 | ALUMINIUM ALLOY ANODE WELDABLE (MK - 1V) |
| 931 | PORT HOLE/ACCESSORIES |
| 932 | SCTTULES RUBBER BEADING |
| 933 | SCTTULES GLASS |
| 934 | SCTTULES RETAINER |
| 935 | TUMBLER BOLTS |
| 936 | HAND PUMP SEAL KIT |
| 937 | LOCK NUT (APS) |
| 938 | OIL FILTER |
| 939 | GLAND NUT EN 19 |
| 940 | HYDRAULIC OIL |
| 941 | HAND PUMP HANDLE LOCK WITH LOCK PIN MS DIA: 30MM LEN: 110MM |
| 942 | HAND PUMP HANDLE HINGE MS, LEN:70MM, THK:10MM |
| 943 | O RING |
| 944 | O RING |
| 945 | HYDRAULIC CYLINDER SEAL KIT |
| 946 | PUMP SEAL KIT |
| 947 | MUSHROOM HEAD SPINDLE WITH HAND WHEEL |
| 948 | MUSHROOM HEAD SPINDLE WITH HAND WHEEL |
| 949 | RUBBER BEADING 40 X 25MM. |
| 950 | TAPER ROLLER BEARING 30212 , SKF |
| 951 | SKF BEARING 6318 ZZ |
| 952 | BALL BEARING 16012 , SKF |
| 953 | BRAKE LINER 70 MM WIDTH X 15 MM THK X 1200 MM LONG. |
| 954 | TAPER ROLLER BEARING 32014 X/Q |
| 955 | TAPER ROLLER BEARING 30212 J2/Q |
| 956 | BELZONA 1311 |
| 957 | GEAR OIL SERVO SYSTEM 320 |
| 958 | SS SPACER OD-105 X ID-90 X THICK- 35 MM |
| 959 | GM BUSH PROOF MACHINED OD 115 X ID 70 X LENGTH 180MM |
| 960 | MARLIN SPIKES |
| 961 | CHAIN HOOKS |
| 962 | ROLLER MAT - PVC. DIA - 40MM, LENGTH- 60MM |
| 963 | HEALTH FAUCET ALONG WITH STAND |
| 964 | RUBBER BEADING |
| 965 | HINGES |
| 966 | RETAINING HOOK/CLIP |
| 967 | WIRE MESH |
| 968 | MORTISE LOCKS OF NWT DOORS |
| 969 | HYDRAULIC DOOR CLOSER |
| 970 | BOAT HOOK |
| 971 | PIPE SECURING CLAMPS |
| 972 | LOCKERS |
| 973 | SHUT -OF VALVE R 1/2'' |
| 974 | 3 WAY VALVE R 1/2\\" |
| 975 | NON RETURN VALVE 2\\" |
| 976 | SHUT -OF VALVE R 2\\" |
| 977 | MECHANICAL SEAL KIT |
| 978 | WEARING PLATE KIT |
| 979 | LOBE EXCHANGEKIT |
| 980 | VACUUM SENSOR WITH DISPLAY |
| 981 | SEAT AND COVER TOSCANA |
| 982 | CONTROL MECHANISM |
| 983 | WATER VALVE |
| 984 | DISCHARGE VALVE |
| 985 | MINI CHECK VALVE |
| 986 | VACUUM HOSE |
| 987 | HOSE CLAMP |
| 988 | FLUSHING RING |
| 989 | HOSE 4X2X1 |
| 990 | WATER SUPPLY KIT |
| 991 | CONNECTION HOSE |
| 992 | RAG SNAG RING |
| 993 | PNEUMATIC PUSH BUTTON |
| 994 | OUTLET PIPE |
| 995 | FASTENING ROD |
| 996 | WING NUT |
| 997 | FASTENING PLATE |
| 998 | INSTALLATION KIT |
| 999 | PROTECTION PIPE |
| 1000 | ACTIVATOR AND ADAPTOR FLANGE |
| 1001 | RUBBER BEND |
| 1002 | MEMBRANE |
| 1003 | FLOAT VALVE |
| 1004 | DISCHARGE VALVE |
| 1005 | VENTILATOR |
| 1006 | ELBOW |
| 1007 | T-CONNECTION |
| 1008 | FLUSHING VALVE,DN 15 |
| 1009 | GASKET, MOUNTING |
| 1010 | GASKET, SHREDDER |
| 1011 | SEAL KIT, BEARING |
| 1012 | BEARING LOWER |
| 1013 | RING, RETAINING |
| 1014 | COUPLING |
| 1015 | SCREW,SET |
| 1016 | RING, SNAP |
| 1017 | BEARING |
| 1018 | RING SLINGER |
| 1019 | SEAL, MECHANICAL |
| 1020 | GASKET, ADAPTER PLATE |
| 1021 | PIN ROTOR |
| 1022 | STATOR |
| 1023 | GASKET REDUCER |
| 1024 | SCREW |
| 1025 | TIP CUTTER |
| 1026 | CLAMP, CUTTER |
| 1027 | SCREW |
| 1028 | BEARING ,BALL |
| 1029 | WASHER,SLINGER |
| 1030 | REPAIR KIT |
| 1031 | CELL PROBE ASSEMBLY |
| 1032 | VALVE CHECK, 1 IN |
| 1033 | AMMETER,DC 0-30 AMPS |
| 1034 | RELAY, POWER,30 AMPS: |
| 1035 | SCR MODULE |
| 1036 | MODULE ASSSEMBLY ,CIRCUIT BOARD |
| 1037 | LEVEL FLOAT SWITCH |
| 1038 | SEDIMENT TANK COVER GASKET |
| 1039 | TREATMENT TANK COVER GASKET |
| 1040 | GAUGE, PRESSURE |
| 1041 | ANODE, SACRIFICAL |
| 1042 | CLAMP, WORM DRIVE |
| 1043 | CLAMP, WORM DRIVE |
| 1044 | CLAMP, WORM DRIVE |
| 1045 | VALVE SOLENOID |
| 1046 | VALVE ASSY,FLOAT |
| 1047 | LEVEL SWITCH |
| 1048 | CONTACTOR |
| 1049 | HYDROGEN SULPHIDE DETECTION HEAD |
| 1050 | BUZZER WITH MUTE FACILITY - RED |
| 1051 | BUZZER WITH MUTE FACILITY - YELLOW |
| 1052 | ENGINEERING |
| 1053 | WASHER,PLAIN |
| 1054 | HOSE,PLAIN |
| 1055 | PLUG,ZINC ELECTRODE |
| 1056 | SCREW,HEXAGON HEAD CAP |
| 1057 | HOSE,PLAIN |
| 1058 | CAP,FILLER |
| 1059 | CLAMP,T BOLT |
| 1060 | CLAMP,T BOLT |
| 1061 | SCREEN,FILTER |
| 1062 | SEAL,RECTANGULAR RING |
| 1063 | WASHER,PLAIN |
| 1064 | BALL,CHECK |
| 1065 | GASKET,INJECTOR |
| 1066 | RETAINER,SCREEN |
| 1067 | SEAL,O RING |
| 1068 | SEAL,O RING |
| 1069 | HOSE,PLAIN |
| 1070 | SHAFT,FUEL PUMP DRIVE |
| 1071 | GASKET,WTR TRF CONNECTION |
| 1072 | GASKET,AFT HOUSING |
| 1073 | NUT,REGULAR HEXAGON |
| 1074 | \\"GASKET,BREATHER\\" |
| 1075 | \\"ELEMENT,BREATHER\\" |
| 1076 | CAP,FILLER |
| 1077 | VALVOLINE PREMIUM BLUE 7800 PLUS 1/20 LTR |
| 1078 | SCREW,HEX FLANGE HEAD CAP |
| 1079 | GASKET,WTR TRF CONNECTION |
| 1080 | \\"SEAL,O RING\\" |
| 1081 | SEAL,O RING |
| 1082 | SCREW,CAPTIVE WASHER CAP |
| 1083 | SHAFT,TACHOMETER DRIVE |
| 1084 | HOSE,ELBOW |
| 1085 | GASKET,WTR TRF CONNECTION |
| 1086 | BELT,V |
| 1087 | PLUG,INJECTOR ORIFICE |
| 1088 | SPIDER,JAW COUPLING |
| 1089 | SCREEN,FILTER |
| 1090 | GASKET,SEA WATER PUMP |
| 1091 | GASKET,ROCKER LEVER COVER |
| 1092 | ELEMENT,LUB OIL FILTER |
| 1093 | KIT,FUEL FILTER AND RING |
| 1094 | VALVE,SOLENDID |
| 1095 | INDICATOR,RESTRICTION |
| 1096 | KIT,SUPER BYP:FILTER ELEM |
| 1097 | GASKET,HEAT EXCHANGER |
| 1098 | GASKET,HEAT EXCHANGER |
| 1099 | ELEMENT,AIR CLEANER |
| 1100 | ELEMENT,AIR CLEANER |
| 1101 | CLAMP,HOSE |
| 1102 | CLAMP,HOSE |
| 1103 | CLAMP,HOSE |
| 1104 | COOLANT,EG 50:50 PREMIXED 50 LT DRUM |
| 1105 | GASKET GOVERNOR SET |
| 1106 | NUT,REGULAR HEXAGON |
| 1107 | DRAINCOCK |
| 1108 | BEARING,BALL |
| 1109 | SCREW,SLOTTED SET |
| 1110 | CORE,COOLER |
| 1111 | GAUGE,SIGHT |
| 1112 | TUBE,EXPANSION TANK |
| 1113 | CORE,AFTERCOOLER |
| 1114 | PUMP,GEAR FUEL |
| 1115 | SHAFT,ROCKER LEVER |
| 1116 | ROD,PUSH |
| 1117 | ROD,PUSH |
| 1118 | INJECTOR |
| 1119 | DAMPER,VIBRATION |
| 1120 | TURBOCHARGER |
| 1121 | KIT,TUR REPAIR |
| 1122 | CORE COOLER |
| 1123 | DAMPER,FUEL PUMP |
| 1124 | KIT,BARREL PLUNGER & CUP |
| 1125 | CLAMP,T BOLT |
| 1126 | SEAL,O RING |
| 1127 | SEAL,O RING |
| 1128 | CLAMP,T BOLT |
| 1129 | HOSE,PLAIN |
| 1130 | HOSE,FLEXIBLE |
| 1131 | HOSE,FLEXIBLE |
| 1132 | GAUGE,SIGHT |
| 1133 | HOSE,PLAIN |
| 1134 | VALVOLINE PREMIUM BLUE 7800 PLUS 1/20 LTR |
| 1135 | HOSE,PLAIN |
| 1136 | SCREW,HEX FLANGE HEAD CAP |
| 1137 | SCREW,BANJO CONNECTOR |
| 1138 | ELEMENT,LUB OIL FILTER |
| 1139 | KIT,HX40 TURBO REPAIR |
| 1140 | KIT,LINER |
| 1141 | SET,LOWER ENGINE GASKET |
| 1142 | VALVE,EXHAUST |
| 1143 | KIT,ENGINE PISTON |
| 1144 | ELEMENT,AIR CLEANER |
| 1145 | ELEMENT,AIR CLEANER |
| 1146 | \\"HOSE,ELBOW\\" |
| 1147 | INDICATOR,RESTRICTION |
| 1148 | \\"HOSE,HUMP\\" |
| 1149 | GASKET,SEA WATER PUMP |
| 1150 | COLLET,VALVE |
| 1151 | RING,RETAINING |
| 1152 | PLUG,EXPANSION |
| 1153 | BRACE,TUBE |
| 1154 | BRACE,TUBE |
| 1155 | CLAMP,V BAND |
| 1156 | WASHER,SPRING |
| 1157 | HOSE,FLEXIBLE |
| 1158 | WASHER,PLAIN |
| 1159 | HOSE,FLEXIBLE |
| 1160 | BRACE,TUBE |
| 1161 | HOSE,ELBOW |
| 1162 | DRAINCOCK |
| 1163 | BRACE,TUBE |
| 1164 | BRACE,TUBE |
| 1165 | BRACE,TUBE |
| 1166 | GASKET,OIL COOLER CORE |
| 1167 | WASHER,SEALING |
| 1168 | HOSE,PLAIN |
| 1169 | BRACE,TUBE |
| 1170 | RING,RETAINING |
| 1171 | BRACE,TUBE |
| 1172 | BRACE,TUBE |
| 1173 | CLAMP,HOSE |
| 1174 | CLAMP,HOSE |
| 1175 | CLAMP,HOSE |
| 1176 | CLAMP,HOSE |
| 1177 | HOSE,FLEXIBLE |
| 1178 | VALVE,INTAKE |
| 1179 | INSERT,VALVE |
| 1180 | VALVE,CHECK |
| 1181 | HOSE,PLAIN |
| 1182 | SPRING,VALVE |
| 1183 | ROTATOR,VALVE |
| 1184 | GUIDE,VALVE STEM |
| 1185 | NUT,HEAVY HEXAGON |
| 1186 | THERMOSTAT |
| 1187 | BOLT,CONNECTING ROD |
| 1188 | INSERT,VALVE |
| 1189 | GASKET,LUB OIL CLR COVER |
| 1190 | FILTER,FUEL |
| 1191 | PIN,PISTON |
| 1192 | NUT,CONNECTING ROD |
| 1193 | SCREW,RKR LEVER ADJUSTING |
| 1194 | CLAMP,HOSE |
| 1195 | SEAL,O RING |
| 1196 | BEARING,CONNECTING ROD |
| 1197 | PLUG,ZINC ELECTRODE |
| 1198 | \\"RESISTOR,CORROSION\\" |
| 1199 | GASKET,LUB OIL CLR COVER |
| 1200 | ISOLATOR,VIBRATION |
| 1201 | ISOLATOR,VIBRATION |
| 1202 | ISOLATOR,VIBRATION |
| 1203 | ISOLATOR,VIBRATION |
| 1204 | MANIFOLD,FUEL |
| 1205 | SCREW,CAPTIVE WASHER CAP |
| 1206 | HOSE,PLAIN |
| 1207 | SCREW,HEX FLANGE HEAD CAP |
| 1208 | SEPARATOR,FUEL WATER |
| 1209 | SEAL,RECTANGULAR RING |
| 1210 | HOSE,PLAIN |
| 1211 | CAP,FILLER |
| 1212 | GASKET,CONNECTION |
| 1213 | KIT,WATER PUMP |
| 1214 | KIT,UPPER ENGINE GASKET |
| 1215 | CLAMP,HOSE |
| 1216 | CLAMP,HOSE |
| 1217 | HOSE,PLAIN |
| 1218 | HOSE,PLAIN |
| 1219 | HOSE,FLEXIBLE |
| 1220 | COOLANT,EG 50:50 PREMIXED 50 LT DRUM |
| 1221 | ISOLATOR,VIBRATION |
| 1222 | ACTUATOR,ETR FUEL CONTROL |
| 1223 | KIT,LINER |
| 1224 | KIT,ENGINE PISTON |
| 1225 | ALTERNATOR |
| 1226 | MANIFOLD,FUEL |
| 1227 | LEVER,ROCKER |
| 1228 | CLAMP,RETAINING |
| 1229 | ROD,PUSH |
| 1230 | GEAR,FLYWHEEL RING |
| 1231 | CAMSHAFT |
| 1232 | DAMPER,VIBRATION |
| 1233 | INJECTOR |
| 1234 | BOLT,CONNECTING ROD |
| 1235 | TAPPET,VALVE |
| 1236 | PIN,PISTON |
| 1237 | BEARING,CRANKSHAFT THRUST |
| 1238 | SET,MAIN BEARING (STD) |
| 1239 | BEARING,CONNECTING ROD |
| 1240 | TANK,EXPANSION |
| 1241 | EXCHANGER,HEAT |
| 1242 | KIT,TURBOCHARGER |
| 1243 | TUBE,INJECTOR FUEL SUPPLY |
| 1244 | TUBE,INJECTOR FUEL SUPPLY |
| 1245 | TUBE,INJECTOR FUEL SUPPLY |
| 1246 | TUBE,INJECTOR FUEL SUPPLY |
| 1247 | TUBE,INJECTOR FUEL SUPPLY |
| 1248 | TUBE,INJECTOR FUEL SUPPLY |
| 1249 | TANK,FUEL |
| 1250 | TUBE,FUEL DRAIN |
| 1251 | PICKUP,MAGNETIC |
| 1252 | PUMP,SEA WATER |
| 1253 | AFTERCOOLER |
| 1254 | ROD,ENGINE CONNECTING |
| 1255 | BUSHING |
| 1256 | TENSIONER,BELT |
| 1257 | MOTOR,STARTING |
| 1258 | KIT,LUBRICATING OIL PUMP |
| 1259 | CORE,COOLER |
| 1260 | SLEEVE GASKET |
| 1261 | NECK RING |
| 1262 | MECHANICAL SEAL |
| 1263 | ANODE PLUG |
| 1264 | SEAL KIT |
| 1265 | VALVE KIT |
| 1266 | SEAL RING ,CHARGING SCREW |
| 1267 | 0' RING FOR SAND FILTER HEAD |
| 1268 | 0' RING FOR C/F HEAD |
| 1269 | CARTRIDGE FILTER ELEMENT |
| 1270 | \\"0\\" RING HP CONNECTION |
| 1271 | PU 4 HOSE |
| 1272 | pu-9 HOSE |
| 1273 | VICTAULIC COUPLERS 1.1/4\\" |
| 1274 | 3/8M X PU9 ELBOW |
| 1275 | PVC ELBOW , 1/4\\" M X PlJ4 |
| 1276 | FESTO TEE PU 9 |
| 1277 | PU4 TEE |
| 1278 | 3/8M X PU9 STRAIGHT CONNECTOR |
| 1279 | RUBBER HOSE 20 MM |
| 1280 | PRODUCT WATER HOSE |
| 1281 | H.P. HOSE TO |
| 1282 | H.P. HOSE TO MODULE IN |
| 1283 | H.P. HOSE MODULE OUT TO VS60 |
| 1284 | H.p. HOSE MODULE 1 TO MODULE 2 |
| 1285 | H.P. PUMP CRANK CASE OIL |
| 1286 | JUBILEE CLIP 1/2 |
| 1287 | JUBILEE CLIP, 1A |
| 1288 | DOLOMITE |
| 1289 | ¼”(F)x PU4 Elbow |
| 1290 | H.p PUMP DRIVING BELTS, 05 TPD |
| 1291 | O-RING , OIL FILLER CAP |
| 1292 | A-V. MOUNTS |
| 1293 | ST.CONN. PVC 3/8\\" M XPU4 |
| 1294 | PRESSURE SWITCH |
| 1295 | PRE FILTER / FILTER PUMP MOTOR BEARING NDE |
| 1296 | REPAIR KIT (WEAR PART KIT) |
| 1297 | FEMALE ADAPTOR |
| 1298 | MALE ADAPTOR |
| 1299 | PVC NON RETURN VALVE 3/8\\" F |
| 1300 | PRESSURE SWITCH |
| 1301 | E - SPARE KIT |
| 1302 | IMPELLER |
| 1303 | SPACING PIPE ( POS 64.A ) |
| 1304 | OIL SEAL CRANK SHAFT |
| 1305 | OIL SEAL CRANK CASE |
| 1306 | VALVE PLUG |
| 1307 | LOW PRESSURE GAUGE - O - 10 BAR |
| 1308 | AIR PRESSURE GUAGE |
| 1309 | HIGH PRESSURE GAUGES -O - 100 BAR |
| 1310 | PK20 IN/OUT HOSE |
| 1311 | ABS SERVICE KIT |
| 1312 | S.S. SERVICE KIT |
| 1313 | SENSOR CABLE WITH PROBE, (NEW VERSION) |
| 1314 | AIR ELIMINATOR MAIN KIT |
| 1315 | COALESCER CARTRIDGE 11\\" |
| 1316 | END PLATE |
| 1317 | AGM SET |
| 1318 | WADDING CLOTH SET |
| 1319 | GASKET SET |
| 1320 | WING NUT & WASHER |
| 1321 | DRAW BOLT 11\\" |
| 1322 | SOLENOID COIL - 24V |
| 1323 | REPAIR KIT 1/2\\" INCH OIL VALVE |
| 1324 | REPAIR KIT 1\\" INCH OIL VALVE |
| 1325 | REPAIR KIT 1\\" DIVERTER VALVE |
| 1326 | ROTO 491 HOLE FOR DRY RUNNING |
| 1327 | DRY RUNNING PROTECTION |
| 1328 | HEATER |
| 1329 | AIR ELIMINATOR 1/2\\" |
| 1330 | 1ST STAGE PACK CSSOOO MK2 |
| 1331 | PRESSURE RELIEF VALVE 112\\" |
| 1332 | MEASURING CELL 24VAC |
| 1333 | OIL DUMP VALVE cm SOL-I\\" |
| 1334 | VALVE ANGLE SEAT/SOL 1/2\\" |
| 1335 | DIVERTER VALVE cm AIR SOLENOID |
| 1336 | PRESSURE GAUGE (0-7 BAR) |
| 1337 | OIL PROBE - PCB |
| 1338 | WATER VALVE 1\\" |
| 1339 | SOLENOID 1/4F 24V AC AIR |
| 1340 | PERFORATED PLATE |
| 1341 | HI-VOR CONE |
| 1342 | PROBE CP4 |
| 1343 | PUMP-FLANGE HOLE DRY RUNNING |
| 1344 | BIB CORK BEND |
| 1345 | AIR REGULATOR |
| 1346 | SEAL KIT, H60/90/110 HELM PUMP |
| 1347 | SEAL KIT, S-400 CYLINDER |
| 1348 | SPHERICAL BEARING, S-400 |
| 1349 | MOUNTING PAD PIN, S-400 |
| 1350 | TILLER PIN, S-400 |
| 1351 | SEAL KIT, 3-WAY VALVE (-12) |
| 1352 | FLEX HOSE, -12 JEC ENDS W/ELBOW |
| 1353 | FLEX HOSE, EXTRA LONG (-08) |
| 1354 | SEAL KIT, DARB 10, PUMP & MOTOR ASSEMBLY |
| 1355 | SEAL KIT, VIO PUMP, PUMP & MOTOR ASSEMBLY |
| 1356 | MOTOR BEARING, PUMP & MOTOR ASSEMBLY |
| 1357 | MOTOR BEARING, PUMP & MOTOR ASSEMBLY |
| 1358 | COUPLING INSERT, PUMP & MOTOR ASSEMBLY |
| 1359 | BREATHER, RESERVOIR & MANIFOLD ASSEMBLY |
| 1360 | LEVEL SWITCH, RESERVOIR & MANIFOLD ASSEMBLY |
| 1361 | SUCTION STRAINER, RESERVOIR & MANIFOLD ASSEMBLY |
| 1362 | FILTER ELEMENT, RESERVOIR & MANIFOLD ASSEMBLY |
| 1363 | SERVICE FILTER GAUGE, RESERVOIR & MANIFOLD ASSEMBLY |
| 1364 | FILTER CLOGGING SENSOR, RESERVOIR & MANIFOLD ASSEMBLY |
| 1365 | PRESSURE GAUGE, RESERVOIR & MANIFOLD ASSEMBLY |
| 1366 | SEAL KIT, PSM 200, RESERVOIR & MANIFOLD ASSEMBLY |
| 1367 | SEAL KIT, HIGH FLOW DHM |
| 1368 | SEAL KIT DH90/110 |
| 1369 | SEAL KIT HELM CONTROL VALVE |
| 1370 | MECCAN CHEMICAL |
| 1371 | TEFLON SEAT |
| 1372 | VALVE GLAND BUSH |
| 1373 | REFRIGRENT OIL |
| 1374 | REFRIGRENT GAS |
| 1375 | GASKET 4MM NEOPRENE SHEET |
| 1376 | ANODE / CORROSION PLUG |
| 1377 | INDUSTRIAL ICE BLOCK 2 NOS (50 KG EACH) |
| 1378 | Nitrogen |
| 1379 | OIL IN SEAL PACKAGE |
| 1380 | O RING SET |
| 1381 | LOWER BEARING |
| 1382 | UPPER BEARING |
| 1383 | LOWER BEARING BRACKET |
| 1384 | TOP BRACKET |
| 1385 | CONNECTOR |
| 1386 | GASKET FOR OUTLET |
| 1387 | SEAL HOUSING |
| 1388 | EXHAUST MIXING CHAMBER |
| 1389 | SUCTION STRAINER |
| 1390 | COUPLING GUARDS |
| 1391 | SUCTION/ DISCHARGE COMPENSATORS. |
| 1392 | SPECIAL TYPE O RING |
| 1393 | SPECIAL TYPE O RING |
| 1394 | LUBE OBM ENGINE OIL 4 STROKE 1LTR CAN |
| 1395 | VALVE NEEDLE |
| 1396 | SEAL VALVE STEM |
| 1397 | RING,CROSS PIN |
| 1398 | RECEIVER ASSY |
| 1399 | POWER HEAD GASKET KIT |
| 1400 | PLUG, OIL LEVEL |
| 1401 | PLUG SPARK |
| 1402 | PISTON RING SET (STD) |
| 1403 | PIN STRAIGHT |
| 1404 | PACKING, LOWER CASING |
| 1405 | OIL SEAL |
| 1406 | OIL SEAL |
| 1407 | OIL SEAL |
| 1408 | IMPELLER |
| 1409 | GEAR OIL 1 LTR CAN |
| 1410 | GASKET |
| 1411 | FLOAT |
| 1412 | ELEMENT ASSY OIL CLEANER |
| 1413 | CLUTCH DOG |
| 1414 | BRG,CYL-CAL ROLLER 0.19GNT |
| 1415 | BEARING, CYLINDRICAL(6J8) |
| 1416 | INTERMEDIATE SERVICE KIT |
| 1417 | MAJOR SERVICE KIT |
| 1418 | Pump Service kit |
| 1419 | BOWL SPINDLE |
| 1420 | WORM WHEEL SHAFT |
| 1421 | WORM WHEEL |
| 1422 | SIGHT GLASS |
| 1423 | GAUGE GLASS |
| 1424 | FRICTION BLOCK |
| 1425 | Top Bearing |
| 1426 | Cap Nut |
| 1427 | Set Of Tools |
| 1428 | GASKET MANIFOLD TO HSG MAIN |
| 1429 | GASKET COVER TOP |
| 1430 | RING 'O' BREATHER PIPE |
| 1431 | SLEEV DRIVE OIL PUMP |
| 1432 | GASKET PUMP MANIFOLD |
| 1433 | SPRING ROLLER BEARING REVERSE SHAFT |
| 1434 | BEARING BALL REV CLUTCH SHAFT& CARRIER BRG. |
| 1435 | SHAFT REVERSE ASSY |
| 1436 | RING SNAP ( PINION & SPIDER CLUTCH ) |
| 1437 | PLATE ,STELL |
| 1438 | PLATE ,SINTERED |
| 1439 | BLOCK RUBBER |
| 1440 | BRG CYLINDRICAL ROLLER |
| 1441 | SEAL OIL |
| 1442 | BRG BALL FORWARD CLUTCH SHAFT |
| 1443 | SHAFT FORWARD CLUTCH ASSEMBLY |
| 1444 | SEAL RUBBER |
| 1445 | GASKET RET BRG TO FRONT HSG |
| 1446 | PLATE LOCK |
| 1447 | WASHER RETAINER ( SHAFT & CLY ROLLER BRG) |
| 1448 | PIN ROLLER BRG FORWARD ,REVERSE & OUTPUT SHAFT |
| 1449 | GASKET HSG FRONT TO HSG MAIN |
| 1450 | GASKET COVER BOTTOM |
| 1451 | BRG TAPER ROLLER OUTPUT SHAFT |
| 1452 | SHIM BRG RET |
| 1453 | RING 'O' |
| 1454 | SEAL OIL |
| 1455 | SEAL RUBBER |
| 1456 | BRG BALL CLUTCH SHAFT |
| 1457 | RING PISTON CLUTCH SHAFT & MANIFOLD |
| 1458 | GASKET TROLLING VALVE HOLE |
| 1459 | PUMP OIL ASSY |
| 1460 | STRAINER OIL |
| 1461 | HOUSING STRAINER |
| 1462 | SELECTOR VALVE ASSY |
| 1463 | PISTON CLUTCH |
| 1464 | LOCK WASHER |
| 1465 | GASKET OIL RETURN PIPE CORPORENE RING |
| 1466 | BREATHER ASSY |
| 1467 | FILTER ELEMENT ASSY |
| 1468 | SLEEV RELEASE SPRING |
| 1469 | BRG BALL |
| 1470 | SPRING RELEASE CLUTCH |
| 1471 | RING PISTON |
| 1472 | RING PISTON |
| 1473 | RING PISTON |
| 1474 | RING PISTON |
| 1475 | SCREW LOCK |
| 1476 | NUT HEX |
| 1477 | BODY BANJO |
| 1478 | BOLT BANJO |
| 1479 | KEY PARALLEL TYPE -A |
| 1480 | KEY PARALLEL TYPE -B OUTPUT SHAFT |
| 1481 | PINION |
| 1482 | GEAR COUNTER SHAFT |
| 1483 | SHAFT OUTPUT |
| 1484 | SPIDER CLUTCH |
| 1485 | Ring Driving |
| 1486 | Gear Reverse Driven |
| 1487 | Pin Oil Pump Sleeve |
| 1488 | Gear Reverse Driving |
| 1489 | BRG (Cylinder Roller) |
| 1490 | Shaft output |
| 1491 | Plug Pipe Manifold |
| 1492 | Pipe Suction |
| 1493 | Pipe pump to Filter |
| 1494 | Spider Drive |
| 1495 | Circlip Ext |
| 1496 | Pin Roll |
| 1497 | Gasket Filter Cover |
| 1498 | Washer plain Copper |
| 1499 | Adaptor |
| 1500 | Shim Flange Propeller |
| 1501 | Shim Flange Propeller |
| 1502 | Shim Flange Propeller |
| 1503 | Grease Nipple |
| 1504 | Gasket Selector Valve |
| 1505 | Main Housing |
| 1506 | MECHANICAL SEAL(GENERAL)SHAFT DIA: 25MM |
| 1507 | MECHANICAL SEAL(GENERAL)SHAFT DIA: 25MM |
| 1508 | RUBBER COUPLING PAD L-100 |
| 1509 | NR FLAP VALVE OD 90MM |
| 1510 | NR FLAP VALVE OD 91MM SS |
| 1511 | BRASS SHIM THICKNESS 0 :3 MM |
| 1512 | BRASS SHIM THICKNESS 0 :2 MM |
| 1513 | NR FLAP VALVE OD 90MM |
| 1514 | MECHANICAL SEAL(GENERAL)SHAFT DIA: 25MM |
| 1515 | IMPELLER OD 170MM , GM APS |
| 1516 | MECHANICAL SEAL(GENERAL)SHAFT DIA: 25MM |
| 1517 | RUBBER COUPLING PAD L-100 |
| 1518 | MECHANICAL SEAL SHAFT DIA 25 MM (APS) |
| 1519 | BRASS IMPELLER OD 171, ID 20, THK 48MM |
| 1520 | NR FLAP VALVE OD 90MM |
| 1521 | MS STRAIGHT COUPLING - 64 OD 23:8 ID 48MM LENGTH |
| 1522 | RELIEF VALVE |
| 1523 | 1/2\\" BALL VALVE |
| 1524 | VALVE SEAT |
| 1525 | ROUND ROD 35MM SS 316L |
| 1526 | ROUND ROD 35MM SS 316L |
| 1527 | SPRINGWASHER SS M12 |
| 1528 | GRUB SCREW M8 X 12MM,SS |
| 1529 | MECHANICAL SEAL SHAFT DIA 25 MM (APS) |
| 1530 | WASHERPLATE SS M12 |
| 1531 | SS316 THREADED PIPE OD-72 ID-63 LEN-100MM |
| 1532 | MECHANICAL SEAL(GENERAL)SHAFT DIA: 25MM |
| 1533 | GM BUSH PROOF MACHINED OD 60 X ID 45 X LENGTH 100MM |
| 1534 | NR FLAP VALVE OD 55MM SS |
| 1535 | MECHANICAL SEAL (GENERAL SEAL)- SHAFT DIA 16MM,APS |
| 1536 | IMPELLER APS |
| 1537 | NR FLAP VALVE OD 55MM SS |
| 1538 | MS COUPLING - 54 OD 22 ID 15MM |
| 1539 | SERVICE KIT |
| 1540 | DIAPHRGAM ASSEMBLY |
| 1541 | SERVICE KIT |
| 1542 | ELECTRICAL |
| 1543 | FUSE KIT, DSC |
| 1544 | DSC - 100 CARD |
| 1545 | FUSE, MCP |
| 1546 | DSC 100 - 102 STEERING CONTROLLER |
| 1547 | SCP PCB ASSEMBLY, MCP |
| 1548 | MICRO SWITCH, RFU 2000 |
| 1549 | 1K POTENTIOMETER SUB ASSEMBLY, RFU 2000 |
| 1550 | IPD PCB REPLACEMENT KIT, RFU 2000 |
| 1551 | RAI 380 |
| 1552 | RAI/ROI 280 |
| 1553 | CONTACTOR, MSA |
| 1554 | OVERLOAD RELAY, MSA |
| 1555 | LDM PCB MSA |
| 1556 | PSS PCB MSA |
| 1557 | MSA 300 ON BOARD SPARES KIT |
| 1558 | N.O. CONTACT MSA |
| 1559 | N.C. CONTACT MSA |
| 1560 | N.o, N.C. CONTACT MSA |
| 1561 | ART VM RELAY MSA |
| 1562 | PHASE FAIL RELAY MSA |
| 1563 | IOA SPOT RELAY, 24VDC MSA |
| 1564 | LY4 RELAY, SOLENOID SELECTOR JUNCTtON BOX |
| 1565 | G2R-2-S RELAY, SOLENOID SELECTOR JUNCTION BOX |
| 1566 | CONTACTOR, POWER SWITCH UNIT |
| 1567 | 3 POS SWITCH, POWER SWITCH UNIT |
| 1568 | TORSION SPRING JOIOO JOG LEVER |
| 1569 | AP-36 ALARM PANEL (ECR) |
| 1570 | AP-36 ALARM PANEL {CHARTHOUSE) |
| 1571 | CP-33-1 MODE CONTROL PANEL |
| 1572 | CONNECTOR |
| 1573 | CONNECTOR |
| 1574 | CONNECT WELL CONNECTOR 35 SQ.MM |
| 1575 | CONNECT WELL CONNECTOR 2.5 SQ.MM |
| 1576 | END CLAMP FOR CONNECTWELL CONNECTORS |
| 1577 | MCB (03-POLE) 10A |
| 1578 | MCB, 3 POLES, 25 AMP |
| 1579 | 3 POLE MCB 32A 'C' CURVE |
| 1580 | MCB C-63,3 POLE |
| 1581 | MCB (03-POLE) 40A |
| 1582 | MCB, 2 POLES, 20 AMP |
| 1583 | MCB - 2 POLE, 16A |
| 1584 | MCB (02-POLE) 10A |
| 1585 | MCB C-06,2 POLE |
| 1586 | INDICATION LAMP UNIT WITH LED RED LAMP |
| 1587 | INDICATION LAMP UNIT WITH LED RED LAMP |
| 1588 | SINGLE CORE 16 SQMM MULTISTRANDED COPPER CONDUCTOR WITH PVC INSULATED FLEXIBLE (LFH)CABLE, 0.6/1KV,USED FOR CONTROL PANEL WIRING |
| 1589 | BHH SMOKE DETECTOR-BHH200 |
| 1590 | BF300 MANUAL CALL POINT (MCP) |
| 1591 | BHH 220 MULTI SENSOR |
| 1592 | BHH-500/EX SMOKE DETECTOR |
| 1593 | BG-201 FLAME DETECTOR |
| 1594 | BHH-300 SMOKE DETECTOR |
| 1595 | MCP GLASS |
| 1596 | CONDUIT BOX BWD-100 |
| 1597 | DETECTOR BASE BWA100 |
| 1598 | 1 X 6 SQ. MM SILICON HEAT RESISTANT CABLE |
| 1599 | OVEN HEATING COIL 415 V |
| 1600 | HOT PLATE |
| 1601 | HOT PLATE |
| 1602 | OVEN HEATING COIL 415 V |
| 1603 | OVEN DOOR BEADING APS |
| 1604 | MAGNETIC CONTACTOR 25A |
| 1605 | MCB 3 POLE, 40 AMPS |
| 1606 | 3 POLE MAGNETIC CONTACTOR |
| 1607 | MCB, 2 POLES, 20 AMP |
| 1608 | ZONE INTERFACE CARD |
| 1609 | CPU CARD |
| 1610 | LOOP CARD |
| 1611 | COMMUNICATION STATION WITH BUILT-IN SPEAKER |
| 1612 | OUTDOOR COMMUNICATION STATION |
| 1613 | HORN LS (15W) (WT) SET AT 4W |
| 1614 | HORN LS(15W) SET AT 8W |
| 1615 | RF CO-AXIAL CABLE |
| 1616 | UHF CONNECTORS |
| 1617 | NAVTEX ANTENNA |
| 1618 | INDICATION LAMP UNIT WITH BULB LED TYPE 24V,22MM DIA. RED COLOUR. |
| 1619 | INDICATION LAMP UNIT LED TYPE 230V COLOUR: WHITE 22 MM DIA. |
| 1620 | INDICATION LAMP LED TYPE, YELLOW 24V, DIA:22MM |
| 1621 | INDICATION LAMP UNIT LED TYPE 230V COLOUR: RED 22MM DIA. |
| 1622 | INDICATION LAMP LED TYPE YELLOW,230V AC,16MM DIA MAKE SCHNEIDER ELECTRIC |
| 1623 | INDICATION LAMP LED TYPE RED,230V AC,16MM DIA MAKE SCHNEIDER ELECTRIC |
| 1624 | INDICATION LAMP LED TYPE GREEN,230V AC,16MM DIA MAKE SCHNEIDER ELECTRIC |
| 1625 | INDICATION LAMP ASSEMBLY WITH LAMP, 230V, LED TYPE, DIA 22 MM, COLOUR GREEN, MAKE: SCHNEIDER ELECTRIC. |
| 1626 | 3 POLE MAGNETIC CONTACTOR |
| 1627 | ROTARY TYPE ON/OFF SELECTOR SWITCH 3 POLE 25A 440V. MAKE- KAYCEE SRPM-237. |
| 1628 | ON OFF PUSH BUTTON WITH 1NO AND 1NC PANEL CUTOUT DIA: 22MM |
| 1629 | PUSH BUTTON ACTUATOR BLACK COLOUR WITH ,2NO ELEMENT. 22MM DIA |
| 1630 | GLASS RELAY |
| 1631 | ROTARY SWITCH 3POLE 2WAY WITH OFF 440VAC, 40A MAKE: KAYCEE TYPE:SRPM337B |
| 1632 | HRC FUSE 2AMPS. |
| 1633 | BUZZER |
| 1634 | DR. BECK BECTOL RED |
| 1635 | BEARING SKF 6308 ZZ |
| 1636 | BEARING SKF 6307 2Z |
| 1637 | ENAMEL PAINT LIGHT GRAY |
| 1638 | BEARINGS SKF 6205 ZZ C3 |
| 1639 | EPOXY PRIMER |
| 1640 | MOTOR COOLING FAN, ID: 25MM, OD:165MM (PLASTIC) |
| 1641 | ENAMEL PAINT SMOKE GRAY |
| 1642 | MOTOR TERMINAL BLOCK 6 WAY 45X70MM |
| 1643 | RUBBER COUPLING PAD L-100 |
| 1644 | RUBBER COUPLING PAD APS |
| 1645 | 2 CORE CABLE |
| 1646 | 2 CORE CABLE |
| 1647 | INDICATION LAMP LED TYPE, RED 230V, DIA:22MM |
| 1648 | INDICATION LAMP UNIT WITH RED LAMP |
| 1649 | INDICATION LAMP UNIT WITH BLUE LED LAMP |
| 1650 | INDICATION LAMP UNIT WITH BLUE LED LAMP |
| 1651 | INDICATION LAMP UNIT LED TYPE 230V COLOUR: YELLOW22 MM DIA: |
| 1652 | INDICATION LAMP UNITWITH LED YELLOW LAMP |
| 1653 | INDICATION LAMP UNIT WITH WHITE LED LAMP |
| 1654 | INDICATION LAMP UNIT WITH WHITE LED LAMP |
| 1655 | INDICATION LAMP LED TYPE, GREEN 24V, DIA:22MM |
| 1656 | INDICATION LAMP LED TYPE, GREEN 230V, DIA:22MM |
| 1657 | PUSH BUTTON |
| 1658 | PUSH BUTTON |
| 1659 | PUSH BUTTON |
| 1660 | DOUBLE VOLTMETER O-500V,CLASS 1,50HZ AC ANALOG 90DEG SCALE VERTICAL PANEL DOOR MOUNTING TYPE SIZE -96X96MM MAKE- RISHABH WITH CERTIFICATE |
| 1661 | DOUBLE FREQUENCY METER 45-50-55 RM AT 50HZ |
| 1662 | AC VOLTMETER 0-500V SISE 96X96 |
| 1663 | DOOR LOCK |
| 1664 | POWER FACTOR METER0.5-1-0.5,440V,5A,3PJ,1 ELEMENT, SIZE 96 X 96 |
| 1665 | RUBBER GASKET |
| 1666 | TRIPLE POLE MINIATURE CRCUT BREAKER RATED 63 A |
| 1667 | TRIPLE POLE MINIATURE CRCUT BREAKER RATED 32 A |
| 1668 | TRIPLE POLE MINIATURE CRCUT BREAKER RATED 25 A |
| 1669 | TRIPLE POLE MINIATURE CRCUT BREAKER RATED 16 A |
| 1670 | TRIPLE POLE MINIATURE CRCUT BREAKER RATED 10 A |
| 1671 | DISPLAY |
| 1672 | FLATPACK2 24/1800 POWER SUPPLY INPUT = 35-290VACOUTPUT = 21-29VDC (1800W) |
| 1673 | SMARTPACKC2 BASIC |
| 1674 | ROTARY SWITCHES |
| 1675 | INDICATION LAMPS |
| 1676 | 11 PIN RELAY |
| 1677 | CONTROL CARD |
| 1678 | 2 CORE POWER CABLE |
| 1679 | BELL CIRCUITS LAMP |
| 1680 | HEATING ELEMENT - 01 |
| 1681 | CONTACTOR - 02 |
| 1682 | MCB - 02 |
| 1683 | TRANSDUCER PCB |
| 1684 | SUPPORTING LIQUID & DISTILLED WATER |
| 1685 | LIMIT SWITCHES. |
| 1686 | BEARING. (DE: 6205, NDE: 6205) |
| 1687 | BEARINGS |
| 1688 | VIBRATION MOUNTS |
| 1689 | RIGGING |
| 1690 | FORE MASTHEAD JIB HALLIARD |
| 1691 | FORE MASTHEAD JIB DOWNHAUL |
| 1692 | FORE MASTHEAD JIB TACK PURCHASE |
| 1693 | FORE MASTHEAD JIB SHEETS |
| 1694 | FORE TOPGALLANT OUTER JIB HALLIARD |
| 1695 | FORE TOPGALLANT OUTER JIB DOWNHAUL |
| 1696 | FORE TOPGALLANT OUTER JIB TACK PURCHASE |
| 1697 | FORE TOPGALLANT OUTER JIB SHEETS |
| 1698 | FORE TOPGALLANT INNER JIB HALLIARD |
| 1699 | FORE TOPGALLANT INNER JIB DOWNHAUL |
| 1700 | FORE TOPGALLANT INNER JIB TACK PURCHASE |
| 1701 | FORE TOPGALLANT INNER JIB SHEETS |
| 1702 | FORE STAYSAIL HALLIARD |
| 1703 | FORE STAYSAIL DOWNHAUL |
| 1704 | FORE STAYSAIL TACK PURCHASE |
| 1705 | FORE STAYSAIL SHEETS |
| 1706 | MAIN STAYSAIL HALLIARD, PURCHASE & TACK PENDANT |
| 1707 | MAIN STAYSAIL DOWNHAUL |
| 1708 | MAIN STAYSAIL SHEETS |
| 1709 | MAIN TOPMAST STAYSAIL HALLIARD |
| 1710 | MAIN TOPMAST STAYSAIL DOWNHAUL |
| 1711 | MAIN TOPMAST STAYSAIL SHEETS |
| 1712 | MIZZEN STAYSAIL HALLIARD & TACK PURCHASE |
| 1713 | MIZZEN STAYSAIL DOWNHAUL |
| 1714 | MIZZEN STAYSAIL SHEETS |
| 1715 | MIZZEN TOPMAST STAYSAIL HALLIARD, PURCHASE & TACK PENDANT |
| 1716 | MIZZEN TOPMAST STAYSAIL DOWNHAUL |
| 1717 | MIZZEN TOPMAST STAYSAIL SHEETS |
| 1718 | LOWER SPANKER PEAK HALLIARD |
| 1719 | LOWER SPANKER THROAT HALLIARD |
| 1720 | LOWER SPANKER GAFF VANGS |
| 1721 | SPANKER TOPPING LIFT |
| 1722 | LOWER SPANKER HEAD INHAUL & OUTHAUL |
| 1723 | LOWER SPANKER BRAILS |
| 1724 | LOWER SPANKER FOOT INHAUL |
| 1725 | LOWER SPANKER FOOT OUTHAUL |
| 1726 | SPANKER SHEETS |
| 1727 | MIZZEN BOOM PREVENTER |
| 1728 | UPPER SPANKER TOPPING LIFT |
| 1729 | UPPER SPANKER THROAT HALLIARD |
| 1730 | UPPER SPANKER GAFF VANGS |
| 1731 | UPPER SPANKER HEAD OUTHAUL |
| 1732 | UPPER SPANKER HEAD INHAUL |
| 1733 | UPPER SPANKER BRAILS |
| 1734 | UPPER SPANKER FOOT OUTHAUL |
| 1735 | UPPER SPANKER FOOT INHAUL |
| 1736 | SPANKER TOPSAIL HALLIARD |
| 1737 | SPANKER TOPSAIL OUTHAUL |
| 1738 | SPANKER TOPSAIL DOWNHAUL |
| 1739 | TRISAIL HALLIARD |
| 1740 | TRISAIL TACK PURCHASE |
| 1741 | TRISAIL SHEET |
| 1742 | FORE COURSE LIFTS |
| 1743 | FORE:COURSE BRACES |
| 1744 | FORE COURSE SHEETS |
| 1745 | FORE COURSE TACKS AND BOWLINES |
| 1746 | FORE COURSE BUNTLINES |
| 1747 | FORE COURSE CLEW LINES |
| 1748 | FORE COURSE REEF PURCHASES |
| 1749 | FORE TOPSAIL HALLIARD |
| 1750 | FORE TOPSAIL LIFTS |
| 1751 | FORE TOPSAIL BRACES |
| 1752 | FORE TOPSAIL SHEETS |
| 1753 | FORE TOPSAIL BUNTLINES |
| 1754 | FORE TOPSAIL CLEWLINES |
| 1755 | FORE TOPSAIL REEF PURCHASES |
| 1756 | FORE TOPGALLANT HALLIARD |
| 1757 | FORE TOPSAIL LIFTS |
| 1758 | FORE TOPGALLANT BRACES |
| 1759 | FORE TOPGALLANT SHEETS |
| 1760 | FORE TOPGALLANT BUNTLINES |
| 1761 | FORE TOPGALLANT CLEWLINES |
| 1762 | FORE ROYAL HALLIARD |
| 1763 | FORE ROYAL LIFTS |
| 1764 | FORE ROYAL BRACES |
| 1765 | FORE ROYAL SHEETS |
| 1766 | FORE ROYAL BUNTLINES |
| 1767 | FORE ROYAL CLEWLINES |
| 1768 | MAIN COURSE LIFTS |
| 1769 | MAIN COURSE BRACES |
| 1770 | MAIN COURSE SHEETS |
| 1771 | MAIN COURSE TACKS AND BOWLINES |
| 1772 | MAIN COURSE BUNTLINES |
| 1773 | MAIN COURSE CLEW LINES |
| 1774 | MAIN COURSE REEF PURCHASES |
| 1775 | MAIN TOPSAIL HALLIARD |
| 1776 | MAN TOPSAIL LIFTS |
| 1777 | MAIN TOPSAIL BRACES |
| 1778 | MAIN TOPSAIL SHEETS |
| 1779 | MAIN TOPSAIL BUNTLINES |
| 1780 | MAIN TOPSAIL CLEWLINES |
| 1781 | MAIN TOPSAIL REEF PURCHASES |
| 1782 | MAIN TOPGALLANT HALLIARD |
| 1783 | MAIN TOPSAIL LIFTS |
| 1784 | MAIN TOPGALLANT BRACES |
| 1785 | MAIN TOPGALLANT SHEETS |
| 1786 | MAIN TOPGALLANT BUNTLINES |
| 1787 | FORE TOPGALLANT CLEWLINES |
| 1788 | MAIN ROYAL HALLIARD |
| 1789 | MAIN ROYAL LIFTS |
| 1790 | MAIN ROYAL BRACES |
| 1791 | MAIN ROYAL SHEETS |
| 1792 | MAIN ROYAL BUNTLINES |
| 1793 | FORE ROYAL CLEWLINES |
| 1794 | FORE, MAIN AND MIZZEN GANTLINES |
| 1795 | HANDY BILLIES |
| 1796 | ENSIGN HALLIARD |
| 1797 | COURTESY FLAG HALLIARDS |
| 1798 | BOAT DAVIT MIDSHIP TACKLES |
| 1799 | BOAT DAVIT VEERING TACKLES |
| 1800 | FOOTROPES |
| 1801 | FLEMISH HORSES |
| 1802 | STURRUPS |
| 1803 | GASKETS |
| 1804 | CLEW LASHINGS |
| 1805 | FOREMAST CANELINES |
| 1806 | MAINMAST CRANELINES |
| 1807 | MIZZEN CRANELINES |
| 1808 | SAFETY LINE ON ALL YARDS |
| 1809 | SAFETY LINE ON BOWSPRIT |
| 1810 | SAFETY LINE ON ALL TOPS |
| 1811 | BOSUN CHAIRS |
| 1812 | DOLPHIN STRIKER |
| 1813 | SQUARE SAIL GASKETS |
| 1814 | FULL SET OF SAIL COVERS AND SAIL BAGS |
| 1815 | FULL SET OF SAILS |
| 1816 | YARD CHAIN SLINGS Please Enable Macros to View BoQ information |
AI Tender Summary
Tender Timeline
Jul 13, 2026
11:30 IST
Tender Published
Tender notice published.
CompletedAug 18, 2026
17:00 IST
Bid Submission Deadline
Online submission via eProcurement portal.
Upcoming · 34 daysAug 19, 2026
Bid Opening Date
Technical bids will be opened and evaluated.
Upcoming · 35 daysTender Documents
Download All (ZIP) ↓
Disclaimer
We takes all possible care for accurate & authentic tender information. However users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender