Power Boards / Undertakings / PSU Closing in 15 days TDR #56421413

Tender For Work Of Installation Of One (01) No. 12.5 Mva Power Transformer At 33/11 Kv Sub-Station, Dph Lohiyahead, Under Electricity Distribution Division, Khatima (Under Capital S.I. Head).( Rates Quoted Without Gst) (Gst Will Paid Extra)

Issued by Boards / Undertakings / PSU · Udam Singh Nagar, Uttarakhand
Tender Value
26.91 Lakhs
Estimated cost
Bid Submission
27 Jul 2026
15 days left
EMD
75000
Bank guarantee accepted
Document Fee
2360
Non-refundable
Tender Type
Online

Tender Overview

Competition Type
NCB
Bidding Type
Tender
Location / State
Udam Singh Nagar → Uttarakhand
EMD Exemption
Available
Quantity
Not Available

Project Description

Tender for Work Of Installation Of One (01) No. 12.5 Mva Power Transformer At 33/11 Kv Sub-Station, Dph Lohiyahead, Under Electricity Distribution Division, Khatima (Under Capital S.I. Head).( Rates Quoted Without Gst) (Gst Will Paid Extra)

BOQ

Name of Work:- Work of installation of one (01) No. 12.5 MVA Power Transformer at 33/11 kV Sub-Station, DPH Lohiyahead, under Electricity Distribution Division, Khatima (under Capital S.I. Head).( Rates Quoted without GST) (GST will paid extra)
Sl. No. Item Description
1Annexure-A (Supply of following material as per UPCL Norms.)
2Supply of 90 LBS Rail
3Supply of PG Clamp, All Alloy, Panther to Dog
4Supply of Nut & Bolts
5Supply of PG Clamp for Panther Conductor
6Supply of 33 kV CT, Ratio 600/300/1 A
7Supply of MS Flat 40 × 6 mm
8Annexure-B (Following work as per UPCL norms)
9Insurance of Power Transformer and allied substation assets during execution of work as per tender conditions.
10Earthwork in excavation for Power Transformer foundation, cable trench and equipment foundations in all types of soil including backfilling and disposal of surplus earth complete.
11Providing and applying cement plaster to Transformer Plinth, cable trench and associated civil structures complete.
12Providing, supplying, installing, testing and commissioning of maintenance-free chemical earthing for Power Transformer neutral, body, Lightning Arresters and associated equipment complete as per UPCL specifications.
13Fabrication of MS structures/supports required for installation of Power Transformer and associated switchyard equipment complete.
14Laying, dressing, termination and testing of 11 kV XLPE Underground Cable in cable trench complete.
15Brick masonry in CM (1:4) for construction of Power Transformer plinth complete.
16RR Massonry work for Transformer foundation/plinth complete.
17RCC work for Transformer plinth/foundation including reinforcement, centering, shuttering and curing complete.
18Erection, fixing, alignment, testing and commissioning of Lightning Arresters associated with Power Transformer.
19Providing and fixing of 11 kV XLPE Jointing Kit including testing complete.
20Cartage of petty materials by mechanical transport including loading and unloading complete, 101-150Km.
21Cartage of 33/11 kV PT/Isolator from store to site including loading and unloading complete, 51-70 Km.
22Cartage of 5/8 MVA Power Transformer by suitable transport complete, 100-150 Km.
23Cartage of 10/12.5 MVA Power Transformer by suitable transport complete, 100-150 Km.
24Head load/cartage of construction materials within substation premises complete.
25Dismantling of existing overhead line/AB line and associated structures interfering with transformer installation complete.
26Dismantling of existing fencing and gate for execution of transformer installation work complete.
27Dismantling of existing Power Transformer 5/8 MVA including disconnection of HT/LT connections and accessories complete.
28Manual shifting of 33 kV Isolator within switchyard complete.
29Shifting of 12.5 MVA Power Transformer using suitable lifting equipment complete.
30Loading of 12.5 MVA Power Transformer on vehicle using crane/hydra complete.
31Loading of 8/5 MVA Power Transformer on vehicle complete.
32Unloading of 12.5 MVA Power Transformer using crane/hydra complete.
33Unloading of 8/5 MVA Power Transformer complete.
34Erection, alignment, installation, oil filtration (if required), testing and commissioning of 10/12.5 MVA Power Transformer complete in all respects.
35Re-erection of fencing and gate after completion of transformer installation work complete.
36Grouting of structure Cement concrete (1:3:6) grouting of Transformer, structures and equipment foundations complete.
37Erection, alignment, testing and commissioning of 33 kV Vacuum Circuit Breaker associated with the Power Transformer bay complete.
38Disconnecting and reconnecting of 11/33 kV Power Cables complete including termination and testing.
39Headload cartage of 33 KV Bus Isolator.
40Dismantling of existing 33 kV CT/PT combined unit complete.
41Testing and commissioning of Power Transformer and all routine tests as per UPCL specifications.
42Laying, dressing and termination of control cable complete.
43Removal of existing jumpers/connectors from 33 kV Isolator complete.
44Disconnection of 33 kV cable jumpers complete.
45Erection of support structures for transformer bay equipment complete.
46Providing, fabrication and fixing of wire mesh fencing around Transformer yard complete.
47Fabrication of MS support structures for Power Transformer bay equipment complete.
48Erection of Bus Isolator support structure complete.
49Installation, alignment, testing and commissioning of Line/Bus Isolator complete.
50Head load/cartage of 33 kV Line Isolator within switchyard complete.
51Head load/cartage of 33 kV Vacuum Circuit Breaker within switchyard complete.
52Painting of 33 kV Isolator with approved primer and enamel paint complete.
53Painting of wire mesh fencing and structural steel complete.
54Painting of post insulator supporting structures complete.
55Complete control wiring of VCB including ferrules, cable lugs, glands, terminal connections, testing and commissioning complete. Please Enable Macros to View BoQ information

AI Tender Summary

OUR REF NO 56421413
AUTHORITY Boards / Undertakings / PSU
TENDER VALUE 26.91 Lakhs
LAST DATE 27-07-2026
Authority
Authority Name Uttarakhand Power Corporation Limited
Work Description Tender for Work Of Installation Of One (01) No. 12.5 Mva Power Transformer At 33/11 Kv Sub-Station, Dph Lohiyahead, Under Electricity Distribution Division, Khatima (Under Capital S.I. Head).( Rates Quoted Without Gst) (Gst Will Paid Extra)
Basic Detail
Tender No 28/2026-27/EDC(CH)
Bidding Type Tender
Location
City Udam Singh Nagar
State Uttarakhand
Key Dates
Publish Date 11 Jul 2026
Submission Date 27 Jul 2026
Open Date 28 Jul 2026
Finance
Tender Value 26.91 Lakhs
Tender Fee 2360
EMD 75000
Exemption Available
Document List
28d398f6-e23f-4c70-90a3-005d43bb4a63.html
BOQ_115176.xls
FormAandB.pdf
TenderDocument28.pdf
Tendernotice_1 (14).pdf

Unlock Full AI Tender Summary

Get instant access to the complete AI-generated analysis — scope, eligibility, timeline & more.

Instant Access Secure Free
Your details are secure and used only for document delivery.

Tender Timeline

Jul 11, 2026
11:30 IST

Tender Published

Tender notice published.

Completed
Jul 27, 2026
17:00 IST

Bid Submission Deadline

Online submission via eProcurement portal.

Upcoming · 15 days
Jul 28, 2026

Bid Opening Date

Technical bids will be opened and evaluated.

Upcoming · 16 days

Tender Documents

Download All (ZIP) ↓
html

28d398f6-e23f-4c70-90a3-005d43bb4a63.html

xls

BOQ_115176.xls

pdf

FormAandB.pdf

pdf

TenderDocument28.pdf

pdf

Tendernotice_1 (14).pdf

Disclaimer

We takes all possible care for accurate & authentic tender information. However users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender

TenderDetail
Loading tenders