Agriculture Cooperative Closing in 6 days TDR #56421154

Bids Are invited for Works Related To Semikestner 1000 Msq Pipeline - Fabrication And Installation Of 6 Inch Tee In The Pipeline Complete As Required , Works Related To Semikestner 1000 Msq Pipeline - Dismantling Of Existing 8 Inch Ms Pipeline Comple

Issued by Cooperative · Bijnor, Uttar Pradesh
Tender Value
2 Lakhs
Estimated cost
Bid Submission
27 Jul 2026
6 days left
EMD
Ref. Documents
Bank guarantee accepted
Document Fee
Ref. Documents
Non-refundable
Tender Type
Gem

Tender Overview

Competition Type
NCB
Bidding Type
Tender
Location / State
Bijnor → Uttar Pradesh
EMD Exemption
Not Available
Quantity
3551

Project Description

Bids Are invited for Works Related To Semikestner 1000 Msq Pipeline - Fabrication And Installation Of 6 Inch Tee In The Pipeline Complete As Required , Works Related To Semikestner 1000 Msq Pipeline - Dismantling Of Existing 8 Inch Ms Pipeline Complete , Works Related To Semikestner 1000 Msq Pipeline - Reinstallation Of 8 Inch Ms Pipeline At The Designated Position Including Alignment Welding Testing And Successful Trial Run , Works Related To Semikestner 1000 Msq Pipeline - Opening/Removal Of Existing 8 Inch Valve , Works Related To Semikestner 1000 Msq Pipeline - Installation Of 8 Inch Valve At The Designated Location Complete , Works Related To Semikestner 1000 Msq Pipeline - Supply Fabrication And Installation Of 8 Inch Flange Complete , Wash Out Pipeline Header To New Quad Body No 1 - Supply And Installation Of 8 Inch Nipple Complete , Wash Out Pipeline Header To New Quad Body No 1 - Dismantling Of Existing 8 Inch And 6 Inch Pipelines Including Removal From Site , Wash Out Pipeline Header To New Quad Body No 1 - Reinstallation Of 8 Inch And 6 Inch Pipelines At The Designated Position Including Alignment Welding Testing And Successful Trial Run , Raw Juice Pump Pipeline - Dismantling Of Existing 8 Inch Raw Juice Pump Pipeline And Disposal Of Dismantled Material At The Designated Scrap Yard , Raw Juice Pump Pipeline - Reinstallation Of 8 Inch Ms Pipeline Including Alignment Welding Testing And Successful Trial Run , Raw Juice Pump Pipeline - Fabrication And Installation Of 8 Inch X 6 Inch Reducer Complete , Raw Juice Pump Pipeline - Fabrication And Installation Of 8 Inch Flange Complete , Raw Juice Pump Pipeline - Removal And Reinstallation Of 8 Inch Valve At The Designated Location Complete , Syrup Pipeline Cleaning Work - Fabrication And Installation Of 8 Inch Nipple Complete , Syrup Pipeline Cleaning Work - Dismantling Of Existing 6 Inch Syrup Pipeline From Syrup Pump To Syrup Tank Complete , Syrup Pipeline Cleaning Work - Fabrication And Installation Of 6 Inch X 3 Inch Reducer Complete , Syrup Pipeline Cleaning Work - Fabrication And Installation Of 2 Inch Flange Complete , Syrup Pipeline Cleaning Work - Fabrication Of 6 Inch Nipple Complete , Syrup Pipeline Cleaning Work - Opening/Removal Of Existing 6 Inch Valve , Syrup Pipeline Cleaning Work - Refitting And Fastening Of 6 Inch Valve After Maintenance Complete , Syrup Sulphiter Pipeline - Fabrication And Installation Of 6 Inch Tee Complete , Syrup Sulphiter Pipeline - Fabrication And Installation Of 8 Inch Bend Complete , Syrup Sulphiter Pipeline - Fabrication And Installation Of 800 Mm Diameter Nipple Complete , Syrup Sulphiter Pipeline - Dismantling Of Existing 8 Inch Pipeline Complete , Syrup Sulphiter Pipeline - Reinstallation Of 8 Inch Pipeline At The Designated Position Including Alignment Welding Testing And Successful Trial Run , Syrup Sulphiter Pipeline - Fabrication And Installation Of 8 Inch Flange Complete , Syrup Sulphiter Pipeline - Fabrication And Installation Of 8 Inch Tee Complete , Syrup Sulphiter Pipeline - Fabrication And Installation Of 8 Inch Bend Complete , New Quad No 4 Extension Catcher Vapour Body - Dismantling Of Damaged Extension Catcher Vapour Body Of New Quad No 4 Removal Of Corroded Angle Channels Disposal Of Scrap At The Designated Scrap Yard Fabrication Of A New Catcher From 10 Mm Thick Ms Plate By Bending Installation At Site Completion Of All Necessary Connections And Successful Trial Run Approximate Size Diameter 160 M X Length 620 M , Bagassilo Fan Repair - Cutting And Removing Damaged Casing Of Bagassilo Fan Fabrication Using Supplied 8/10 Mm Ms Plate Installation And Satisfactory Trial , Big Filter Mud Tray Repair - Cutting And Removing Damaged Mud Tray Of Big Filter Disposal Of Scrap Fabrication Using Supplied 8/10 Mm Ms Plate Installation And Satisfactory Trial (Approx Dia 375 M X Length 860 M) , Vacuum Air Line Work - Dismantling Of 6 Inch Vacuum Air Line With Filter , Vacuum Air Line Work - Fixing Of 6 Inch Vacuum Air Line In Position Including Alignment And Satisfactory Trial , Pipe Fabrication - Fabrication And Installation Of 6 Inch Ms Flange , Pipe Fabrication - Fabrication And Installation Of 6 Inch Ms Tee , Pipe Fabrication - Fabrication And Installation Of 6 Inch Ms Nipple , Clear Juice Tank Repair - Cutting And Removing Corroded Box Of Clear Juice Liquidation Tank Door Fabrication Using 8 Mm Ms Plate Installation All Connections And Satisfactory Trial (Approx Size 10 M X 10 M) , Pump And Motor Alignment - Fitting Fixing Alignment Of Ms Band For 120 Hp Clear Juice Pump And Motor Including Satisfactory Trial , Juice Heater Repair - Replacement Of Strip And Flat Iron For Top And Bottom Header Rubber Packing Fixing New Rubber Packing And Satisfactory Trial , Condensate Bottle Fabrication - Removal Of Condensate Bottle Of Juice Heater/Quad Semicaser/Vapor Cell Fabrication Of New Bottle Using Supplied 8/10 Mm Ms Plate And Installation , Clarifier Repair - Removal Of Corroded Distributor From Clarifier Compartment Disposal Of Scrap Fabrication Of New Distributor Using 6/8 Mm Ms Plate Installation And Satisfactory Trial , Cane Carrier Repair - Replacement Of Damaged Side And Bottom Plates Of Cane Carrier Using Supplied 6 Mm Ms Plate , Secondary Rack Carrier Repair - Replacement Of Damaged Side And Bottom Plates Using Supplied 6 Mm Ms Plate , Rack Carrier Repair - Replacement Of Damaged Side And Bottom Plates Of Rack Carrier No1 2 & 3 Using Supplied 6 Mm Ms Plate , Cane Carrier Runner Replacement - Cutting And Removing Old Runner And Fixing New Runner For Cane Carrier , Secondary Rack Carrier Runner Replacement - Cutting And Removing Old Runner And Fixing New Runner , Rack Carrier Runner Replacement - Cutting And Removing Old Runner And Fixing New Runner For Rack Carrier No1 2 & 3 , Cane Carrier Structural Repair - Removal Of Corroded Supporting Angles/Channels And Installation Of New Supporting Angle , Rack Carrier Structural Repair - Removal Of Corroded Angles/Channels And Installation Of New Angle , Cane Carrier Chain Beam Repair - Replacement Of 150 Mm Chain Beam , Inter Rack Carrier Trough Repair - Removal Of Old Trough Of Inter Rack Carrier No1 2 & 3 Fabrication Using Supplied 8/10 Mm Ms Plate And Installation , Mill Trough Repair - Cutting And Replacing Damaged Trough Of Mill No3 & 4 Including Satisfactory Trial , Trpf Lower Plate Repair - Removal Of Damaged Lower Plate Under Trpf Of Mill No2 & 3 Fabrication Using Supplied 10/12 Mm Ms Plate And Installation , Mill Roller Repair - Fabrication Of New Juice Rings For Mill Rollers Using Supplied 6/8 Mm Ms Plate As Per S Le , Leveler Repair - Dismantling Damaged Side Plates Of Leveler Disposal Of Scrap Fabrication And Installation Of New 8/10 Mm Ms Side Plates , Fiberizer Repair - Dismantling Damaged Side Plate Of Fiberizer Disposal Of Scrap Fabrication And Installation Of New 8/10 Mm Ms Side Plate , Secondary Rack Carrier Trough Repair - Removal Of Old Trough Fabrication Using Supplied 8/10/12 Mm Ms Plate And Installation , Tail Shaft Bed Repair - Cutting And Removing Worn Tail Shaft Bed Of Secondary Rack Carrier Fabrication Using Supplied 200 Mm Beam And Installation , Mill Pinion Repair - Fabrication And Installation Of New Pinion Gear For Mill No3 Removal Of Old Gear And Disposal To Scrap Yard , Cane Carrier Angle Replacement - Removal Of Damaged Angles From Cane Carrier Side Plate/Inter Rack Carrier 2 & 3 And Installation Of New Angles , Secondary Rack Carrier Angle Replacement - Removal Of Damaged Angles From Secondary Rack Carrier/Inter Rack Carrier 2 & 3 Fabrication And Installation Of New Angles , Trpf Roller Juice Plate Repair - Removal Of Damaged Juice Plate Of Trpf Rollers Fabrication Using Supplied 8/10 Mm Ms Plate And Installation , Cold Water Pipeline Work - Dismantling Of Existing 4 Inch Cold Water Pipeline From Mill No1 To Mill No3 And Installation Of New Pipeline , Bearing Cooling Line Replacement - Removal Of Worn Bearing Cooling Line From Mill No1 To 4 And Installation Of New 3 Inch Pipeline Complete With Flange And Nipple , Pipe Fittings - Supply/Fabrication And Installation Of 3 Inch Flange , Pipe Fittings - Supply/Fabrication And Installation Of 1 Inch Nipple , Mill Juice Pipeline Work - Cutting And Removing Old 6 Inch Mill Juice Pipeline From Mill Juice Pump No 3 To Mill No 1 And Installing New 6 Inch Ms Pipeline Complete With Fitting And Testing , Hot Water Pipeline Work - Dismantling Existing 4 Inch Dia Hot Water Pipeline From Mill No 3 To Mill No 4 And Installing New Pipeline Complete With Fittings And Testing , Mill Juice Pipeline Work - Cutting And Removing Old Pipeline From Mill Juice Pump No 4 To Mill No 2 And Installing New 6 Inch Ms Pipeline Complete With Fittings And Testing , Screen Juice Pipeline Work - Cutting And Removing Old Pipeline From Mill Screen Juice Pump To Raw Juice Tank And Installing New 6 Inch & 8 Inch Pipeline Complete With Fittings And Testing , Flange Work - Dismantling And Installation Of 6 Inch Flange , Flange Work - Dismantling And Installation Of 8 Inch Flange , Flange Work - Dismantling And Installation Of 10 Inch Flange , Nipple Work - Dismantling And Installation Of 4 Inch Nipple , Nipple Work - Dismantling And Installation Of 6 Inch Nipple , Nipple Work - Dismantling And Installation Of 8 Inch Nipple , Mill Fabrication Work - Fabrication And Preparation Of Mill Beds Complete As Required , Header Fabrication - Removing Existing 12 Inch Screen Juice Header Fabricating New Header As Per S Le Erection Reconnection And Satisfactory Trial , Delivery Header Fabrication - Fabrication And Installation Of New 10 Inch Delivery Header (21 M Long) For Screen Juice Tank Including 8 Inch & 10 Inch Nipples Erection And Testing , Trpf Tank Repair - Cutting Damaged Top Cover Of Trpf Tank Fabrication Using Supplied 8/10 Mm Ms Plate Installation And Satisfactory Trial , Transmission Gear Repair - Inspection And Repair/Checking Of Bottom Cover Of Transmission Gear Of Mill No 4 As Per S Le , Juice Pump Pipeline Work - Installation Of 6 Inch Juice Pump Pipeline Complete With Fitting And Testing , Reducer Fabrication - Fabrication And Installation Of 6 Inch Reducer In The Pipeline , Reducer Fabrication - Fabrication And Installation Of 8 Inch Reducer In The Pipeline , Flange Fabrication - Fabrication And Installation Of 6 Inch Flange In The Pipeline , Flange Fabrication - Fabrication And Installation Of 4 Inch Flange In The Pipeline , Band Fabrication - Fabrication And Installation Of 6 Inch Pipe Band/Support , Trpf Cover Fabrication - Fabrication Of Top Cover For Trpf Sluice Installed In Mill House , Cane Carrier Structural Repair - Removing Damaged Angles Of Cane Carrier Side Plate And Inter Rack Carrier No 2 & 3 And Installing New Angles , Rack Carrier Structural Repair - Removing Damaged Angles Of Secondary Rack Carrier And Inter Rack Carrier No 2 & 3 And Installing New Angles , Trpl Chute Repair - Dismantling Damaged Side And Back Plates Of Trpl Chute Of Mill No 2 Fabrication Using Supplied 10/12 Mm Ms Plate Installation And Satisfactory Trial , Crane Unloader Rail Replacement - Removing Damaged Rail Of Crane Unloader Trolley Installing New 40 X 40 Mm Rail Strengthening And Testing , Bearing Housing Repair - Fabrication And Installation Of New Cover For Mill Bearing Housing , Juice Distribution Tray Fabrication - Fabrication And Installation Of Juice Distribution Trays In Mill Juice Pipeline At Designated Locations , Trpf Roller Repair - Welding And Repair Of Trpf Rollers Including Welding And Correction Of Damaged Side Plates , Rack Repair Work - Repair Of Secondary Rack Carrier And Inter Rack Carrier Racks , Crown Pinion Guard Repair - Removing Damaged Water Guard Of Crown Pinion Of Mill No 3 Fabrication Of New Guard From Supplied 2/3 Mm Plate And Installation , Tail Bar Repair - Welding And Fabrication Of Cut Tail Bars Of Mill No 1 & 3 As Per Required Dimensions , Trpf Water Cover Repair - Dismantling Damaged Trpf Water Cover Of Mill No 2 Fabrication Using Supplied 8/10 Mm Ms Plate Installation And Satisfactory Trial , Mill Roller Grooving - Carrying Out Pineapple (Chevron) Grooving/Cutting Work On Mill Rollers , Chain Link Forging Work - Forging Of Side Links Of Cane Carrier Bagasse Carrier Elevator And Rbc Chain Including Fitting Of Pins And Bushes Profiling And Finishing To Required Size Total Quantity : 3551

BOQ

Sl. No. Item TitleItem Description
1Works Related to Semikestner 1000 mSq PipelineFabrication and installation of 6 inch Tee in the pipeline complete as required
2Works Related to Semikestner 1000 mSq PipelineDismantling of existing 8 inch MS pipeline complete
3Works Related to Semikestner 1000 mSq PipelineReinstallation of 8 inch MS pipeline at the designated position including alignment welding testing and successful trial run
4Works Related to Semikestner 1000 mSq PipelineOpening/removal of existing 8 inch valve
5Works Related to Semikestner 1000 mSq PipelineInstallation of 8 inch valve at the designated location complete
6Works Related to Semikestner 1000 mSq PipelineSupply fabrication and installation of 8 inch flange complete
7Wash Out Pipeline Header to New Quad Body No 1Supply and installation of 8 inch nipple complete
8Wash Out Pipeline Header to New Quad Body No 1Dismantling of existing 8 inch and 6 inch pipelines including removal from site
9Wash Out Pipeline Header to New Quad Body No 1Reinstallation of 8 inch and 6 inch pipelines at the designated position including alignment welding testing and successful trial run
10Raw Juice Pump PipelineDismantling of existing 8 inch raw juice pump pipeline and disposal of dismantled material at the designated scrap yard
11Raw Juice Pump PipelineReinstallation of 8 inch MS pipeline including alignment welding testing and successful trial run
12Raw Juice Pump PipelineFabrication and installation of 8 inch X 6 inch reducer complete
13Raw Juice Pump PipelineFabrication and installation of 8 inch flange complete
14Raw Juice Pump PipelineRemoval and reinstallation of 8 inch valve at the designated location complete
15Syrup Pipeline Cleaning WorkFabrication and installation of 8 inch nipple complete
16Syrup Pipeline Cleaning WorkDismantling of existing 6 inch syrup pipeline from syrup pump to syrup tank complete
17Syrup Pipeline Cleaning WorkFabrication and installation of 6 inch X 3 inch reducer complete
18Syrup Pipeline Cleaning WorkFabrication and installation of 2 inch flange complete
19Syrup Pipeline Cleaning WorkFabrication of 6 inch nipple complete
20Syrup Pipeline Cleaning WorkOpening/removal of existing 6 inch valve
21Syrup Pipeline Cleaning WorkRefitting and fastening of 6 inch valve after maintenance complete
22Syrup Sulphiter PipelineFabrication and installation of 6 inch Tee complete
23Syrup Sulphiter PipelineFabrication and installation of 8 inch bend complete
24Syrup Sulphiter PipelineFabrication and installation of 800 mm diameter nipple complete
25Syrup Sulphiter PipelineDismantling of existing 8 inch pipeline complete
26Syrup Sulphiter PipelineReinstallation of 8 inch pipeline at the designated position including alignment welding testing and successful trial run
27Syrup Sulphiter PipelineFabrication and installation of 8 inch flange complete
28Syrup Sulphiter PipelineFabrication and installation of 8 inch Tee complete
29Syrup Sulphiter PipelineFabrication and installation of 8 inch bend complete
30New Quad No 4 Extension Catcher Vapour BodyDismantling of damaged extension catcher vapour body of New Quad No 4 removal of corroded angle channels disposal of scrap at the designated scrap yard fabrication of a new catcher from 10 mm thick MS plate by bending installation at site completion of all necessary connections and successful trial run Approximate size Diameter 160 m X Length 620 m
31Bagassilo Fan RepairCutting and removing damaged casing of Bagassilo fan fabrication using supplied 8/10 mm MS plate installation and satisfactory trial
32Big Filter Mud Tray RepairCutting and removing damaged mud tray of big filter disposal of scrap fabrication using supplied 8/10 mm MS plate installation and satisfactory trial (Approx Dia 375 m X Length 860 m)
33Vacuum Air Line WorkDismantling of 6 inch vacuum air line with filter
34Vacuum Air Line WorkFixing of 6 inch vacuum air line in position including alignment and satisfactory trial
35Pipe FabricationFabrication and installation of 6 inch MS flange
36Pipe FabricationFabrication and installation of 6 inch MS tee
37Pipe FabricationFabrication and installation of 6 inch MS nipple
38Clear Juice Tank RepairCutting and removing corroded box of clear juice liquidation tank door fabrication using 8 mm MS plate installation all connections and satisfactory trial (Approx Size 10 m X 10 m)
39Pump and Motor AlignmentFitting fixing alignment of MS band for 120 HP clear juice pump and motor including satisfactory trial
40Juice Heater RepairReplacement of strip and flat iron for top and bottom header rubber packing fixing new rubber packing and satisfactory trial
41Condensate Bottle FabricationRemoval of condensate bottle of juice heater/quad semicaser/vapor cell fabrication of new bottle using supplied 8/10 mm MS plate and installation
42Clarifier RepairRemoval of corroded distributor from clarifier compartment disposal of scrap fabrication of new distributor using 6/8 mm MS plate installation and satisfactory trial
43Cane Carrier RepairReplacement of damaged side and bottom plates of cane carrier using supplied 6 mm MS plate
44Secondary Rack Carrier RepairReplacement of damaged side and bottom plates using supplied 6 mm MS plate
45Rack Carrier RepairReplacement of damaged side and bottom plates of Rack Carrier No1 2 & 3 using supplied 6 mm MS plate
46Cane Carrier Runner ReplacementCutting and removing old runner and fixing new runner for cane carrier
47Secondary Rack Carrier Runner ReplacementCutting and removing old runner and fixing new runner
48Rack Carrier Runner ReplacementCutting and removing old runner and fixing new runner for Rack Carrier No1 2 & 3
49Cane Carrier Structural RepairRemoval of corroded supporting angles/channels and installation of new supporting angle
50Rack Carrier Structural RepairRemoval of corroded angles/channels and installation of new angle
51Cane Carrier Chain Beam RepairReplacement of 150 mm chain beam
52Inter Rack Carrier Trough RepairRemoval of old trough of Inter Rack Carrier No1 2 & 3 fabrication using supplied 8/10 mm MS plate and installation
53Mill Trough RepairCutting and replacing damaged trough of Mill No3 & 4 including satisfactory trial
54TRPF Lower Plate RepairRemoval of damaged lower plate under TRPF of Mill No2 & 3 fabrication using supplied 10/12 mm MS plate and installation
55Mill Roller RepairFabrication of new juice rings for mill rollers using supplied 6/8 mm MS plate as per sample
56Leveler RepairDismantling damaged side plates of leveler disposal of scrap fabrication and installation of new 8/10 mm MS side plates
57Fiberizer RepairDismantling damaged side plate of fiberizer disposal of scrap fabrication and installation of new 8/10 mm MS side plate
58Secondary Rack Carrier Trough RepairRemoval of old trough fabrication using supplied 8/10/12 mm MS plate and installation
59Tail Shaft Bed RepairCutting and removing worn tail shaft bed of secondary rack carrier fabrication using supplied 200 mm beam and installation
60Mill Pinion RepairFabrication and installation of new pinion gear for Mill No3 removal of old gear and disposal to scrap yard
61Cane Carrier Angle ReplacementRemoval of damaged angles from cane carrier side plate/inter rack carrier 2 & 3 and installation of new angles
62Secondary Rack Carrier Angle ReplacementRemoval of damaged angles from secondary rack carrier/inter rack carrier 2 & 3 fabrication and installation of new angles
63TRPF Roller Juice Plate RepairRemoval of damaged juice plate of TRPF rollers fabrication using supplied 8/10 mm MS plate and installation
64Cold Water Pipeline WorkDismantling of existing 4 inch cold water pipeline from Mill No1 to Mill No3 and installation of new pipeline
65Bearing Cooling Line ReplacementRemoval of worn bearing cooling line from Mill No1 to 4 and installation of new 3 inch pipeline complete with flange and nipple
66Pipe FittingsSupply/Fabrication and installation of 3 inch flange
67Pipe FittingsSupply/Fabrication and installation of 1 inch nipple
68Mill Juice Pipeline WorkCutting and removing old 6 inch mill juice pipeline from Mill Juice Pump No 3 to Mill No 1 and installing new 6 inch MS pipeline complete with fitting and testing
69Hot Water Pipeline WorkDismantling existing 4 inch dia hot water pipeline from Mill No 3 to Mill No 4 and installing new pipeline complete with fittings and testing
70Mill Juice Pipeline WorkCutting and removing old pipeline from Mill Juice Pump No 4 to Mill No 2 and installing new 6 inch MS pipeline complete with fittings and testing
71Screen Juice Pipeline WorkCutting and removing old pipeline from Mill Screen Juice Pump to Raw Juice Tank and installing new 6 inch & 8 inch pipeline complete with fittings and testing
72Flange WorkDismantling and installation of 6 inch flange
73Flange WorkDismantling and installation of 8 inch flange
74Flange WorkDismantling and installation of 10 inch flange
75Nipple WorkDismantling and installation of 4 inch nipple
76Nipple WorkDismantling and installation of 6 inch nipple
77Nipple WorkDismantling and installation of 8 inch nipple
78Mill Fabrication WorkFabrication and preparation of mill beds complete as required
79Header FabricationRemoving existing 12 inch screen juice header fabricating new header as per sample erection reconnection and satisfactory trial
80Delivery Header FabricationFabrication and installation of new 10 inch delivery header (21 m long) for Screen Juice Tank including 8 inch & 10 inch nipples erection and testing
81TRPF Tank RepairCutting damaged top cover of TRPF tank fabrication using supplied 8/10 mm MS plate installation and satisfactory trial
82Transmission Gear RepairInspection and repair/checking of bottom cover of transmission gear of Mill No 4 as per sample
83Juice Pump Pipeline WorkInstallation of 6 inch juice pump pipeline complete with fitting and testing
84Reducer FabricationFabrication and installation of 6 inch reducer in the pipeline
85Reducer FabricationFabrication and installation of 8 inch reducer in the pipeline
86Flange FabricationFabrication and installation of 6 inch flange in the pipeline
87Flange FabricationFabrication and installation of 4 inch flange in the pipeline
88Band FabricationFabrication and installation of 6 inch pipe band/support
89TRPF Cover FabricationFabrication of top cover for TRPF sluice installed in mill house
90Cane Carrier Structural RepairRemoving damaged angles of cane carrier side plate and Inter Rack Carrier No 2 & 3 and installing new angles
91Rack Carrier Structural RepairRemoving damaged angles of Secondary Rack Carrier and Inter Rack Carrier No 2 & 3 and installing new angles
92TRPL Chute RepairDismantling damaged side and back plates of TRPL chute of Mill No 2 fabrication using supplied 10/12 mm MS plate installation and satisfactory trial
93Crane Unloader Rail ReplacementRemoving damaged rail of crane unloader trolley installing new 40 X 40 mm rail strengthening and testing
94Bearing Housing RepairFabrication and installation of new cover for mill bearing housing
95Juice Distribution Tray FabricationFabrication and installation of juice distribution trays in mill juice pipeline at designated locations
96TRPF Roller RepairWelding and repair of TRPF rollers including welding and correction of damaged side plates
97Rack Repair WorkRepair of secondary rack carrier and inter rack carrier racks
98Crown Pinion Guard RepairRemoving damaged water guard of crown pinion of Mill No 3 fabrication of new guard from supplied 2/3 mm plate and installation
99Tail Bar RepairWelding and fabrication of cut tail bars of Mill No 1 & 3 as per required dimensions
100TRPF Water Cover RepairDismantling damaged TRPF water cover of Mill No 2 fabrication using supplied 8/10 mm MS plate installation and satisfactory trial
101Mill Roller GroovingCarrying out pineapple (chevron) grooving/cutting work on mill rollers
102Chain Link Forging WorkForging of side links of cane carrier bagasse carrier elevator and RBC chain including fitting of pins and bushes profiling and finishing to required size

AI Tender Summary

OUR REF NO 56421154
AUTHORITY Cooperative
TENDER VALUE 2 Lakhs
LAST DATE 27-07-2026
Authority
Authority Name Uttar Pradesh Cooperative Sugar Factories Federation Limited
Work Description Bids Are invited for Works Related To Semikestner 1000 Msq Pipeline - Fabrication And Installation Of 6 Inch Tee In The Pipeline Complete As Required , Works Related To Semikestner 1000 Msq Pipeline - Dismantling Of Existing 8 Inch Ms Pipeline Complete , Works Related To Semikestner 1000 Msq Pipeline - Reinstallation Of 8 Inch Ms Pipeline At The Designated Position Including Alignment Welding Testing And Successful Trial Run , Works Related To Semikestner 1000 Msq Pipeline - Opening/Removal Of Existing 8 Inch Valve , Works Related To Semikestner 1000 Msq Pipeline - Installation Of 8 Inch Valve At The Designated Location Complete , Works Related To Semikestner 1000 Msq Pipeline - Supply Fabrication And Installation Of 8 Inch Flange Complete , Wash Out Pipeline Header To New Quad Body No 1 - Supply And Installation Of 8 Inch Nipple Complete , Wash Out Pipeline Header To New Quad Body No 1 - Dismantling Of Existing 8 Inch And 6 Inch Pipelines Including Removal From Site , Wash Out Pipeline Header To New Quad Body No 1 - Reinstallation Of 8 Inch And 6 Inch Pipelines At The Designated Position Including Alignment Welding Testing And Successful Trial Run , Raw Juice Pump Pipeline - Dismantling Of Existing 8 Inch Raw Juice Pump Pipeline And Disposal Of Dismantled Material At The Designated Scrap Yard , Raw Juice Pump Pipeline - Reinstallation Of 8 Inch Ms Pipeline Including Alignment Welding Testing And Successful Trial Run , Raw Juice Pump Pipeline - Fabrication And Installation Of 8 Inch X 6 Inch Reducer Complete , Raw Juice Pump Pipeline - Fabrication And Installation Of 8 Inch Flange Complete , Raw Juice Pump Pipeline - Removal And Reinstallation Of 8 Inch Valve At The Designated Location Complete , Syrup Pipeline Cleaning Work - Fabrication And Installation Of 8 Inch Nipple Complete , Syrup Pipeline Cleaning Work - Dismantling Of Existing 6 Inch Syrup Pipeline From Syrup Pump To Syrup Tank Complete , Syrup Pipeline Cleaning Work - Fabrication And Installation Of 6 Inch X 3 Inch Reducer Complete , Syrup Pipeline Cleaning Work - Fabrication And Installation Of 2 Inch Flange Complete , Syrup Pipeline Cleaning Work - Fabrication Of 6 Inch Nipple Complete , Syrup Pipeline Cleaning Work - Opening/Removal Of Existing 6 Inch Valve , Syrup Pipeline Cleaning Work - Refitting And Fastening Of 6 Inch Valve After Maintenance Complete , Syrup Sulphiter Pipeline - Fabrication And Installation Of 6 Inch Tee Complete , Syrup Sulphiter Pipeline - Fabrication And Installation Of 8 Inch Bend Complete , Syrup Sulphiter Pipeline - Fabrication And Installation Of 800 Mm Diameter Nipple Complete , Syrup Sulphiter Pipeline - Dismantling Of Existing 8 Inch Pipeline Complete , Syrup Sulphiter Pipeline - Reinstallation Of 8 Inch Pipeline At The Designated Position Including Alignment Welding Testing And Successful Trial Run , Syrup Sulphiter Pipeline - Fabrication And Installation Of 8 Inch Flange Complete , Syrup Sulphiter Pipeline - Fabrication And Installation Of 8 Inch Tee Complete , Syrup Sulphiter Pipeline - Fabrication And Installation Of 8 Inch Bend Complete , New Quad No 4 Extension Catcher Vapour Body - Dismantling Of Damaged Extension Catcher Vapour Body Of New Quad No 4 Removal Of Corroded Angle Channels Disposal Of Scrap At The Designated Scrap Yard Fabrication Of A New Catcher From 10 Mm Thick Ms Plate By Bending Installation At Site Completion Of All Necessary Connections And Successful Trial Run Approximate Size Diameter 160 M X Length 620 M , Bagassilo Fan Repair - Cutting And Removing Damaged Casing Of Bagassilo Fan Fabrication Using Supplied 8/10 Mm Ms Plate Installation And Satisfactory Trial , Big Filter Mud Tray Repair - Cutting And Removing Damaged Mud Tray Of Big Filter Disposal Of Scrap Fabrication Using Supplied 8/10 Mm Ms Plate Installation And Satisfactory Trial (Approx Dia 375 M X Length 860 M) , Vacuum Air Line Work - Dismantling Of 6 Inch Vacuum Air Line With Filter , Vacuum Air Line Work - Fixing Of 6 Inch Vacuum Air Line In Position Including Alignment And Satisfactory Trial , Pipe Fabrication - Fabrication And Installation Of 6 Inch Ms Flange , Pipe Fabrication - Fabrication And Installation Of 6 Inch Ms Tee , Pipe Fabrication - Fabrication And Installation Of 6 Inch Ms Nipple , Clear Juice Tank Repair - Cutting And Removing Corroded Box Of Clear Juice Liquidation Tank Door Fabrication Using 8 Mm Ms Plate Installation All Connections And Satisfactory Trial (Approx Size 10 M X 10 M) , Pump And Motor Alignment - Fitting Fixing Alignment Of Ms Band For 120 Hp Clear Juice Pump And Motor Including Satisfactory Trial , Juice Heater Repair - Replacement Of Strip And Flat Iron For Top And Bottom Header Rubber Packing Fixing New Rubber Packing And Satisfactory Trial , Condensate Bottle Fabrication - Removal Of Condensate Bottle Of Juice Heater/Quad Semicaser/Vapor Cell Fabrication Of New Bottle Using Supplied 8/10 Mm Ms Plate And Installation , Clarifier Repair - Removal Of Corroded Distributor From Clarifier Compartment Disposal Of Scrap Fabrication Of New Distributor Using 6/8 Mm Ms Plate Installation And Satisfactory Trial , Cane Carrier Repair - Replacement Of Damaged Side And Bottom Plates Of Cane Carrier Using Supplied 6 Mm Ms Plate , Secondary Rack Carrier Repair - Replacement Of Damaged Side And Bottom Plates Using Supplied 6 Mm Ms Plate , Rack Carrier Repair - Replacement Of Damaged Side And Bottom Plates Of Rack Carrier No1 2 & 3 Using Supplied 6 Mm Ms Plate , Cane Carrier Runner Replacement - Cutting And Removing Old Runner And Fixing New Runner For Cane Carrier , Secondary Rack Carrier Runner Replacement - Cutting And Removing Old Runner And Fixing New Runner , Rack Carrier Runner Replacement - Cutting And Removing Old Runner And Fixing New Runner For Rack Carrier No1 2 & 3 , Cane Carrier Structural Repair - Removal Of Corroded Supporting Angles/Channels And Installation Of New Supporting Angle , Rack Carrier Structural Repair - Removal Of Corroded Angles/Channels And Installation Of New Angle , Cane Carrier Chain Beam Repair - Replacement Of 150 Mm Chain Beam , Inter Rack Carrier Trough Repair - Removal Of Old Trough Of Inter Rack Carrier No1 2 & 3 Fabrication Using Supplied 8/10 Mm Ms Plate And Installation , Mill Trough Repair - Cutting And Replacing Damaged Trough Of Mill No3 & 4 Including Satisfactory Trial , Trpf Lower Plate Repair - Removal Of Damaged Lower Plate Under Trpf Of Mill No2 & 3 Fabrication Using Supplied 10/12 Mm Ms Plate And Installation , Mill Roller Repair - Fabrication Of New Juice Rings For Mill Rollers Using Supplied 6/8 Mm Ms Plate As Per S Le , Leveler Repair - Dismantling Damaged Side Plates Of Leveler Disposal Of Scrap Fabrication And Installation Of New 8/10 Mm Ms Side Plates , Fiberizer Repair - Dismantling Damaged Side Plate Of Fiberizer Disposal Of Scrap Fabrication And Installation Of New 8/10 Mm Ms Side Plate , Secondary Rack Carrier Trough Repair - Removal Of Old Trough Fabrication Using Supplied 8/10/12 Mm Ms Plate And Installation , Tail Shaft Bed Repair - Cutting And Removing Worn Tail Shaft Bed Of Secondary Rack Carrier Fabrication Using Supplied 200 Mm Beam And Installation , Mill Pinion Repair - Fabrication And Installation Of New Pinion Gear For Mill No3 Removal Of Old Gear And Disposal To Scrap Yard , Cane Carrier Angle Replacement - Removal Of Damaged Angles From Cane Carrier Side Plate/Inter Rack Carrier 2 & 3 And Installation Of New Angles , Secondary Rack Carrier Angle Replacement - Removal Of Damaged Angles From Secondary Rack Carrier/Inter Rack Carrier 2 & 3 Fabrication And Installation Of New Angles , Trpf Roller Juice Plate Repair - Removal Of Damaged Juice Plate Of Trpf Rollers Fabrication Using Supplied 8/10 Mm Ms Plate And Installation , Cold Water Pipeline Work - Dismantling Of Existing 4 Inch Cold Water Pipeline From Mill No1 To Mill No3 And Installation Of New Pipeline , Bearing Cooling Line Replacement - Removal Of Worn Bearing Cooling Line From Mill No1 To 4 And Installation Of New 3 Inch Pipeline Complete With Flange And Nipple , Pipe Fittings - Supply/Fabrication And Installation Of 3 Inch Flange , Pipe Fittings - Supply/Fabrication And Installation Of 1 Inch Nipple , Mill Juice Pipeline Work - Cutting And Removing Old 6 Inch Mill Juice Pipeline From Mill Juice Pump No 3 To Mill No 1 And Installing New 6 Inch Ms Pipeline Complete With Fitting And Testing , Hot Water Pipeline Work - Dismantling Existing 4 Inch Dia Hot Water Pipeline From Mill No 3 To Mill No 4 And Installing New Pipeline Complete With Fittings And Testing , Mill Juice Pipeline Work - Cutting And Removing Old Pipeline From Mill Juice Pump No 4 To Mill No 2 And Installing New 6 Inch Ms Pipeline Complete With Fittings And Testing , Screen Juice Pipeline Work - Cutting And Removing Old Pipeline From Mill Screen Juice Pump To Raw Juice Tank And Installing New 6 Inch & 8 Inch Pipeline Complete With Fittings And Testing , Flange Work - Dismantling And Installation Of 6 Inch Flange , Flange Work - Dismantling And Installation Of 8 Inch Flange , Flange Work - Dismantling And Installation Of 10 Inch Flange , Nipple Work - Dismantling And Installation Of 4 Inch Nipple , Nipple Work - Dismantling And Installation Of 6 Inch Nipple , Nipple Work - Dismantling And Installation Of 8 Inch Nipple , Mill Fabrication Work - Fabrication And Preparation Of Mill Beds Complete As Required , Header Fabrication - Removing Existing 12 Inch Screen Juice Header Fabricating New Header As Per S Le Erection Reconnection And Satisfactory Trial , Delivery Header Fabrication - Fabrication And Installation Of New 10 Inch Delivery Header (21 M Long) For Screen Juice Tank Including 8 Inch & 10 Inch Nipples Erection And Testing , Trpf Tank Repair - Cutting Damaged Top Cover Of Trpf Tank Fabrication Using Supplied 8/10 Mm Ms Plate Installation And Satisfactory Trial , Transmission Gear Repair - Inspection And Repair/Checking Of Bottom Cover Of Transmission Gear Of Mill No 4 As Per S Le , Juice Pump Pipeline Work - Installation Of 6 Inch Juice Pump Pipeline Complete With Fitting And Testing , Reducer Fabrication - Fabrication And Installation Of 6 Inch Reducer In The Pipeline , Reducer Fabrication - Fabrication And Installation Of 8 Inch Reducer In The Pipeline , Flange Fabrication - Fabrication And Installation Of 6 Inch Flange In The Pipeline , Flange Fabrication - Fabrication And Installation Of 4 Inch Flange In The Pipeline , Band Fabrication - Fabrication And Installation Of 6 Inch Pipe Band/Support , Trpf Cover Fabrication - Fabrication Of Top Cover For Trpf Sluice Installed In Mill House , Cane Carrier Structural Repair - Removing Damaged Angles Of Cane Carrier Side Plate And Inter Rack Carrier No 2 & 3 And Installing New Angles , Rack Carrier Structural Repair - Removing Damaged Angles Of Secondary Rack Carrier And Inter Rack Carrier No 2 & 3 And Installing New Angles , Trpl Chute Repair - Dismantling Damaged Side And Back Plates Of Trpl Chute Of Mill No 2 Fabrication Using Supplied 10/12 Mm Ms Plate Installation And Satisfactory Trial , Crane Unloader Rail Replacement - Removing Damaged Rail Of Crane Unloader Trolley Installing New 40 X 40 Mm Rail Strengthening And Testing , Bearing Housing Repair - Fabrication And Installation Of New Cover For Mill Bearing Housing , Juice Distribution Tray Fabrication - Fabrication And Installation Of Juice Distribution Trays In Mill Juice Pipeline At Designated Locations , Trpf Roller Repair - Welding And Repair Of Trpf Rollers Including Welding And Correction Of Damaged Side Plates , Rack Repair Work - Repair Of Secondary Rack Carrier And Inter Rack Carrier Racks , Crown Pinion Guard Repair - Removing Damaged Water Guard Of Crown Pinion Of Mill No 3 Fabrication Of New Guard From Supplied 2/3 Mm Plate And Installation , Tail Bar Repair - Welding And Fabrication Of Cut Tail Bars Of Mill No 1 & 3 As Per Required Dimensions , Trpf Water Cover Repair - Dismantling Damaged Trpf Water Cover Of Mill No 2 Fabrication Using Supplied 8/10 Mm Ms Plate Installation And Satisfactory Trial , Mill Roller Grooving - Carrying Out Pineapple (Chevron) Grooving/Cutting Work On Mill Rollers , Chain Link Forging Work - Forging Of Side Links Of Cane Carrier Bagasse Carrier Elevator And Rbc Chain Including Fitting Of Pins And Bushes Profiling And Finishing To Required Size Total Quantity : 3551
Basic Detail
Tender No GEM/2026/B/7772500
Bidding Type Tender
Location
City Bijnor
State Uttar Pradesh
Key Dates
Publish Date 11 Jul 2026
Submission Date 27 Jul 2026
Open Date 27 Jul 2026
Finance
Tender Value 2 Lakhs
Tender Fee Ref. Documents
EMD Ref. Documents
Exemption Not Available
Document List
c0021c29-50c9-4cbc-850d-9eccdbcd2dc8.pdf
9590206_Boq_1.xlsx
mechanical_fab_11zon_2026-07-10-16-19-08_27dfd08928392e1adb9c5e8df70af94a.pdf

Unlock Full AI Tender Summary

Get instant access to the complete AI-generated analysis — scope, eligibility, timeline & more.

Instant Access Secure Free
Your details are secure and used only for document delivery.

Tender Timeline

Jul 11, 2026
11:30 IST

Tender Published

Tender notice published.

Completed
Jul 27, 2026
17:00 IST

Bid Submission Deadline

Online submission via eProcurement portal.

Upcoming · 6 days
Jul 27, 2026

Bid Opening Date

Technical bids will be opened and evaluated.

Upcoming · 6 days

Tender Documents

Download All (ZIP) ↓
pdf

c0021c29-50c9-4cbc-850d-9eccdbcd2dc8.pdf

xlsx

9590206_Boq_1.xlsx

pdf

mechanical_fab_11zon_2026-07-10-16-19-08_27dfd08928392e1adb9c5e8df70af94a.pdf