Power Boards / Undertakings / PSU Closing in 37 days TDR #56416928

Tender For Balance Of Plant (Bop) Turnkey Package For Durgapur Thermal Power Station (1 X 800 Mw)

Issued by Boards / Undertakings / PSU · Paschim Bardhaman, West Bengal
Tender Value
Ref. Documents
Estimated cost
Bid Submission
17 Aug 2026
37 days left
EMD
25.69 Crore
Bank guarantee accepted
Document Fee
Ref. Documents
Non-refundable
Tender Type
Online

Tender Overview

Competition Type
NCB
Bidding Type
Tender
Location / State
Paschim Bardhaman → West Bengal
EMD Exemption
Not Available
Quantity
Not Available

Project Description

Tender for Balance Of Plant (Bop) Turnkey Package For Durgapur Thermal Power Station (1 X 800 Mw)

BOQ

Name of Work:- Balance of Plant (BOP) Turnkey Package for Durgapur Thermal Power Station (1 x 800 MW)
Sl. No. Item Description
1TOTAL OF SCHEDULE NO.1 Main Equipment (In INR)CIF Price of Main Equipment Excluding Type Test charges to be supplied from Abroad.
2TOTAL OF SCHEDULE NO.1 Main Equipment (In Foreign Currency 1 i.e. USD)CIF Price of Main Equipment Excluding Type Test charges to be supplied from Abroad.
3TOTAL OF SCHEDULE NO.1 Main Equipment (In Foreign Currency 2 i.e. EUR)CIF Price of Main Equipment Excluding Type Test charges to be supplied from Abroad.
4TOTAL OF SCHEDULE NO.1 Main Equipment (In Foreign Currency 3 i.e. JPY)CIF Price of Main Equipment Excluding Type Test charges to be supplied from Abroad.
5TOTAL OF SCHEDULE NO.1 Mandatory Spares (In INR)CIF Price of Mandatory Spares to be supplied from Abroad.
6TOTAL OF SCHEDULE NO.1 Mandatory Spares (In Foreign Currency 1 i.e. USD)CIF Price of Mandatory Spares to be supplied from Abroad.
7TOTAL OF SCHEDULE NO.1 Mandatory Spares (In Foreign Currency 2 i.e. EUR)CIF Price of Mandatory Spares to be supplied from Abroad.
8TOTAL OF SCHEDULE NO.1 Mandatory Spares (In Foreign Currency 3 i.e. JPY)CIF Price of Mandatory Spares to be supplied from Abroad.
9TOTAL OF SCHEDULE NO.1 Type Test Charges (In INR)Type Test Charges for Plant and Equipment to be supplied from Abroad.
10TOTAL OF SCHEDULE NO.1 Type Test Charges (In Foreign Currency 1 i.e. USD)Type Test Charges for Plant and Equipment to be supplied from Abroad.
11TOTAL OF SCHEDULE NO.1 Type Test Charges (In Foreign Currency 2 i.e. EUR)Type Test Charges for Plant and Equipment to be supplied from Abroad.
12TOTAL OF SCHEDULE NO.1 Type Test Charges (In Foreign Currency 3 i.e. JPY)Type Test Charges for Plant and Equipment to be supplied from Abroad.
13TOTAL OF SCHEDULE NO.2 Main Equipment (In INR)Ex-works Price of Main Equipment Excluding Type Test charges to be supplied from Employer's Country.
14TOTAL OF SCHEDULE NO.2 Main Equipment (In Foreign Currency 1 i.e. USD)Ex-works Price of Main Equipment Excluding Type Test charges to be supplied from Employer's Country.
15TOTAL OF SCHEDULE NO.2 Main Equipment (In Foreign Currency 2 i.e. EUR)Ex-works Price of Main Equipment Excluding Type Test charges to be supplied from Employer's Country.
16TOTAL OF SCHEDULE NO.2 Main Equipment (In Foreign Currency 3 i.e. JPY)Ex-works Price of Main Equipment Excluding Type Test charges to be supplied from Employer's Country.
17TOTAL OF SCHEDULE NO.2 Mandatory Spares (In INR)Ex-works Price of Mandatory Spares to be supplied from Employer's Country.
18TOTAL OF SCHEDULE NO.2 Mandatory Spares (In Foreign Currency 1 i.e. USD)Ex-works Price of Mandatory Spares to be supplied from Employer's Country.
19TOTAL OF SCHEDULE NO.2 Mandatory Spares (In Foreign Currency 2 i.e. EUR)Ex-works Price of Mandatory Spares to be supplied from Employer's Country.
20TOTAL OF SCHEDULE NO.2 Mandatory Spares (In Foreign Currency 3 i.e. JPY)Ex-works Price of Mandatory Spares to be supplied from Employer's Country.
21TOTAL OF SCHEDULE NO.2 Type Test Charges (In INR)Type Test Charges for Plant and Equipment to be supplied from Employer's Country.
22TOTAL OF SCHEDULE NO.2 Type Test Charges (In Foreign Currency 1 i.e. USD)Type Test Charges for Plant and Equipment to be supplied from Employer's Country.
23TOTAL OF SCHEDULE NO.2 Type Test Charges (In Foreign Currency 2 i.e. EUR)Type Test Charges for Plant and Equipment to be supplied from Employer's Country.
24TOTAL OF SCHEDULE NO.2 Type Test Charges (In Foreign Currency 3 i.e. JPY)Type Test Charges for Plant and Equipment to be supplied from Employer's Country.
25TOTAL OF SCHEDULE NO.3 (In INR)Local Transportation including Port Handling, Port Clearance, custom reconciliation & inland transit insurance and other local costs incidental to delivery of Main Equipment.
26TOTAL OF SCHEDULE NO.3 (In INR)Local Transportation including Port Handling, Port Clearance, custom reconciliation & inland transit insurance and other local costs incidental to delivery of Mandatory Spares.
27TOTAL OF SCHEDULE NO.4 (In INR)Installation Services including Erection, Testing & commissioning works, Insurance covers other than inland transit insurance and other services and Civil works Price
28TOTAL OF SCHEDULE NO.4 (In Foreign Currency 1 i.e. USD)Installation Services including Erection, Testing & commissioning works, Insurance covers other than inland transit insurance and other services, training and Civil works Price.
29TOTAL OF SCHEDULE NO.4 (In Foreign Currency 2 i.e. EUR)Installation Services including Erection, Testing & commissioning works, Insurance covers other than inland transit insurance and other services, training and Civil works Price.
30TOTAL OF SCHEDULE NO.4 (In Foreign Currency 3 i.e. JPY)Installation Services including Erection, Testing & commissioning works, Insurance covers other than inland transit insurance and other services, training and Civil works Price.
31TOTAL OF SCHEDULE NO.7 (In INR)Goods and Services Tax (GST), applicable on Schedules - 2,3 & 4 not included in bid price.
32TOTAL OF SCHEDULE NO.7 (In Foreign Currency 1 i.e. USD)Goods and Services Tax (GST), applicable on Schedules - 2,3 & 4 not included in bid price.
33TOTAL OF SCHEDULE NO.7 (In Foreign Currency 2 i.e. EUR)Goods and Services Tax (GST), applicable on Schedules - 2,3 & 4 not included in bid price.
34TOTAL OF SCHEDULE NO.7 (In Foreign Currency 3 i.e. JPY)Goods and Services Tax (GST), applicable on Schedules - 2,3 & 4 not included in bid price.
35TOTAL OF SCHEDULE NO.7A (In INR)Custom Duty/ Import Duty and Goods and Services Tax (GST), applicable on Schedule - 1 not included in bid price.
36TOTAL OF SCHEDULE NO.7A (In Foreign Currency 1 i.e. USD)Custom Duty/ Import Duty and Goods and Services Tax (GST), applicable on Schedule - 1 not included in bid price.
37TOTAL OF SCHEDULE NO.7A (In Foreign Currency 2 i.e. EUR)Custom Duty/ Import Duty and Goods and Services Tax (GST), applicable on Schedule - 1 not included in bid price.
38TOTAL OF SCHEDULE NO.7A (In Foreign Currency 3 i.e. JPY)Custom Duty/ Import Duty and Goods and Services Tax (GST), applicable on Schedule - 1 not included in bid price. BALANCE OF PLANT(BOP) TURNKEY PACKAGE FOR DURGAPUR THERMAL POWER STATION (1 X 800 MW) ,BIDDING DOCUMENT NO. : DVC/C&M/ENGINEERING/DTPS(1X800MW)/EPC/BOP SCHEDULE OF RATES AND PRICES: Bidder's Name and Address : SCHEDULE- 1 : Plant and Equipment including type test charges and mandatory spares to be supplied from Abroad. (BREAK-UP TO BE FURNISHED BEFORE AWARD) Description Code* TOTAL PRICE (Currency to be specified by Bidder) Currency 1 Currency 2 Currency 3 Currency 4 INR USD EUR JPY FOB CIF (Indian port of entry) FOB CIF (Indian port of entry) FOB CIF (Indian port of entry) FOB CIF (Indian port of entry)
392.0 A
40Main Equipments for Balance of Plant Systems (Excl. Factory Fabricated Steel Structures, Electrical Systems and C&I System)[For one (1) no. Power Generating Unit having rated output of 800 MW]
41Main Equipments for Electrical System and C&I System[For one (1) no. Power Generating Unit having rated output of 800 MW]
42Factory Fabricated Steel Structures[For one (1) no. Power Generating Unit having rated output of 800 MW]
43Any other Main Equipments not covered in 1 to 3 above but required for the Scope of work under the package TOTAL (A) MAIN EQUIPMENT [(1) + (2) + (3) +(4)] 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 B MANDATORY SPARES [BOQ AS SPECIFIED IN VOLUME-2-TECHNCIAL SPECIFICATION](Bidder is required to fill the prices of all the items serially as specified in VOLUME-2-TECHNCIAL SPECIFICATION) C SUB-TOTAL OF TYPE TEST CHARGES(AS PER FURTHER BREAK-UP OF TYPE TEST CHARGES GIVEN IN SCHEDULE-8A) GRAND TOTAL (A+B+C) 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 * Bidders shall enter a code representing the country of origin of all imported plant and equipment including mandatory spares. S.No. Code Country
44....................................................................................................
45....................................................................................................
46....................................................................................................
47....................................................................................................
48....................................................................................................
49....................................................................................................
50....................................................................................................(ATTACH SEPARATE SHEET, IF REQUIRED) Note:
51Not used
52The summation of quantity of Factory fabricated structural works quoted by bidder, in Schedule-1 and/or Schedule-2 and the site fabricated steel structural works quoted by bidder in Schedule-4 shall be equal to total quantity of structural works envisaged by the bidder under the package. Installation Services price for factory fabricated steel structural items shall be separately indicated by the bidder in Schedule-4.
53Bidder to note that only factory fabricated items and not the raw material shall be quoted in Schedule-1 and/or Schedule-2
54Sequence of painting of structures as given in Technical Specification shall be followed.
55Items listed above but priced in Schedule 2 shall be quoted as \\"0\\" by the Bidder in this Schedule 1.
56Bidders are required to quote lumpsum price separately for various systems/equipments of main equipment and mandatory spares as sought in this schedule based on BOQ for main equipment & mandatory spares specified in Technical Specification.
57Bidders are required to indicate the break up of Type Test Charges as per Schedule-8A.
58Interchangebility and Packings:All spares supplied under this contract shall be strictly interchangeable with parts for which they are intended for replacements. These spares should include all mounted accessories like components, boards, add or items, fitting, connectors etc. and be complete in all respects so that the replacement of the main items by these spares does not require any additional item. The vendors must conform the pair to pair compatibility of each electrical spares modules with the modules supplied in the original package. All electronic modules should be pre set and/or preprogrammed for ready use at site. Alternatively, suitable instruction sheet indicating the details of required PCB jumper position, BCD switch setting, EPROM/PROM listing etc should be packed along with each module. Also a caution mark sign should be put on all such module which needs pre setting/pre programming before putting them in to service. The spare shall be treated and properly packed for long term storage
59Identification: Each spare shall be clearly marked and labeled on the outside of the packing with its description. When more than one spare part is packed in single case, a general description of the contents shall be shown on the outside of such case and a detailed list enclosed. All cases, containers and other packages must be suitably marked and numbered for the purpose of identification.
60In case the description / quantity for any item mentioned in Schedule is at variance from what has been stated in Technical Specification and its subsequent amendments and clarifications, the stipulations of Technical Specification and its subsequent amendment and clarification shall prevail.
61DVC may place the award for any mandatory spares with NOA and/or within three years from the date of NOA as per mutually agreed despatch schedule and as per the price quoted by the bidder in their bid in accordance with the relevant clauses. However, the sum of the price quoted for all the mandatory spares shall be considered for evaluation purpose.
62Bidder to refer ITB clause 11.1(d) while quoting its bid price. BALANCE OF PLANT(BOP) TURNKEY PACKAGE FOR DURGAPUR THERMAL POWER STATION (1X 800 MW) ,BIDDING DOCUMENT NO. :DVC/C&M/ENGINEERING/DTPS(1X800MW)/EPC/BOP SCHEDULE OF RATES AND PRICES: Bidder's Name and Address : SCHEDULE- 2 : Plant and Equipment including Type tests and Mandatory Spares to be supplied from within the Employer's Country. (BREAK-UP TO BE FURNISHED BEFORE AWARD) Item Description TOTAL Ex-Works (India) Price Currency 1 Currency 2 Currency 3 Currency 4 INR USD EUR JPY
632.0 A
64Main Equipments for Balance of Plant Systems (Excl. Factory Fabricated Steel Structures, Electrical Systems and C&I System)[For ONE (1) no. Power Generating Unit having rated output of 800 MW]
65Main Equipments for Electrical System and C&I System[For ONE (1) no. Power Generating Unit having rated output of 800 MW]
66Factory Fabricated Steel Structures[For ONE (1) no. Power Generating Unit having rated output of 800 MW]
67Any other Main Equipments not covered in 1 to 3 above but required for the Scope of work under the package TOTAL (A) MAIN EQUIPMENT [(1) + (2) + (3) +(4)] 0.0 0.0 0.0 0.0 B MANDATORY SPARES [BOQ AS SPECIFIED IN VOLUME-2-TECHNCIAL SPECIFICATION](Bidder is required to fill the prices of all the items serially as specified in VOLUME-2-TECHNCIAL SPECIFICATION C SUB-TOTAL OF TYPE TEST CHARGES(AS PER FURTHER BREAK-UP OF TYPE TEST CHARGES GIVEN IN SCHEDULE-8B) GRAND TOTAL (A+B+C) 0.0 0.0 0.0 0.0 Note:
68Not used
69The summation of quantity of Factory fabricated structural works quoted by bidder, in Schedule-1 and/or Schedule-2 and the site fabricated steel structural works quoted by bidder in Schedule-4 shall be equal to total quantity of structural works envisaged by the bidder under the package. Installation Services price for factory fabricated steel structural items shall be separately indicated by the bidder in Schedule-4.
70Bidder to note that only factory fabricated items and not the raw material shall be quoted in Schedule-1 and/or Schedule-2
71Sequence of painting of structures as given in Technical Specification shall be followed.
72Items listed above but priced in Schedule 1 shall be quoted as \\"0\\" by the Bidder in this Schedule 2.
73Bidders are required to quote lumpsum price separately for various systems/equipments of main equipment and mandatory spares as sought in this schedule based on BOQ for main equipment & mandatory spares specified in Technical Specification.
74Bidders are required to indicate the break up of Type Test Charges as per Schedule-8B.
75Interchangebility and Packings:All spares supplied under this contract shall be strictly interchangeable with parts for which they are intended for replacements. These spares should include all mounted accessories like components, boards, add or items, fitting, connectors etc. and be complete in all respects so that the replacement of the main items by these spares does not require any additional item. The vendors must conform the pair to pair compatibility of each electrical spares modules with the modules supplied in the original package. All electronic modules should be pre set and/or preprogrammed for ready use at site. Alternatively, suitable instruction sheet indicating the details of required PCB jumper position, BCD switch setting, EPROM/PROM listing etc should be packed along with each module. Also a caution mark sign should be put on all such module which needs pre setting/pre programming before putting them in to service. The spare shall be treated and properly packed for long term storage
76Identification: Each spare shall be clearly marked and labeled on the outside of the packing with its description. When more than one spare part is packed in single case, a general description of the contents shall be shown on the outside of such case and a detailed list enclosed. All cases, containers and other packages must be suitably marked and numbered for the purpose of identification.
77In case the description / quantity for any item mentioned in Schedule is at variance from what has been stated in Technical Specification and its subsequent amendments and clarifications, the stipulations of Technical Specification and its subsequent amendment and clarification shall prevail.
78DVC may place the award for any mandatory spares with NOA and/or within three years from the date of NOA as per mutually agreed despatch schedule and as per the price quoted by the bidder in their bid in accordance with the relevant clauses. However, the sum of the price quoted for all the mandatory spares shall be considered for evaluation purpose.
79Bidder to refer ITB clause 11.1(d) while quoting its bid price. BALANCE OF PLANT(BOP) TURNKEY PACKAGE FOR DURGAPUR THERMAL POWER STATION (1X800 MW) ,BIDDING DOCUMENT NO. :DVC/C&M/ENGINEERING/DTPS(1X800MW)/EPC/BOP SCHEDULE OF RATES AND PRICES: Bidder's Name and Address : SCHEDULE- 3 : Local Transportation including Port Handling, Port Clearance & Port Charges, Inland Transit Insurance and other local costs incidental to delivery of plant & equipment and mandatory spares at site. (BREAK-UP TO BE FURNISHED BEFORE AWARD) Item Description TOTAL PRICE (Indian Rupees)
802.0 I MAIN EQUIPMENT II MANDATORY SPARES TOTAL (I + II) 0.0 BALANCE OF PLANT(BOP) TURNKEY PACKAGE FOR DURGAPUR THERMAL POWER STATION (1 X 800 MW) ,BIDDING DOCUMENT NO. DVC/C&M/ENGINEERING/DTPS(1X800MW)/EPC/BOP SCHEDULE OF RATES AND PRICES: Bidder's Name and Address : SCHEDULE- 4 : Installation Services [Erection, Civil, Steel Structural works (Site fabricated structures as permitted as per Specifications), Factory Fabricated Steel Structural Works (Erection) & Allied works] including insurance (other than transit insurance and other services as specified in the Bidding Documents). (BREAK-UP TO BE FURNISHED BEFORE AWARD) Item Description TOTAL PRICE Currency 1 Currency 2 Currency 3 Currency 4 INR USD EUR JPY
812.0 (A)
82Main Equipments for Balance of Plant Systems (Excl. Factory Fabricated Steel Structures, Electrical Systems and C&I System)[For one (1) no. Power Generating Unit having rated output of 800 MW]
83Main Equipments for Electrical System and C&I System[For one (1) no. Power Generating Unit having rated output of 800 MW]
84Erection of Factory Fabricated Steel Structures (corresponding to structures whose supplies is covered under Schedule-1 & 2)
85Erection of Any other Main Equipments not covered in 1 to 5 above but required for the Scope of work under the package TOTAL (A) MAIN EQUIPMENT [(1) + (2) + (3) +(4)] 0.0 0.0 0.0 0.0 B. Civil, Structural (other than steel structures) & Architectural works C. Site Fabricated Steel Structures Supply, fabrication & erection of site fabricated steel structural works (structural works other than factory fabricated structures) permitted for fabrication at site. D. Training Charges for as specified in NIT document E. Deleted F. Amount linked to Safety Aspects/ compliance to Safety Rules TOTAL (A) + (B) + (C) + (D) + E+ (F) 0.0 0.0 0.0 0.0 Note: As per ITB clause 11.1(b) foreign component if any, of Installation Services (excluding civil, structural & allied works ) may be quoted in foreign currency.
86Not used
87The summation of quantity of Factory fabricated steel structural works quoted by bidder, in Schedule-1 and/or Schedule-2 and the site fabricated structural works quoted by bidder in Schedule-4 shall be equal to total quantity of structural works envisaged by the bidder under the package. Installation Services price for factory fabricated steel structural items shall be seperately indicated by the bidder in Schedule-4.
88Bidder to note that only factory fabricated items and not the raw material shall be quoted in Schedule-1 and/or Schedule-2
89Bidder to refer ITB clause 11.1(d) while quoting its bid price. BALANCE OF PLANT(BOP) TURNKEY PACKAGE FOR DURGAPUR THERMAL POWER STATION (1 X 800 MW) ,BIDDING DOCUMENT NO. DVC/C&M/ENGINEERING/DTPS(1X800MW)/EPC/BOP Schedule-6 IFB NO. : Bidder's Name and Address : Schedule No. 6 : Recommended Spare Parts: NOT USED Item Description Quantity Unit Price Total Price Local transportation charges (including inland insurance, port clearance & port charges (Indian Rs.) Total Price (as delivered at Project) CIF (Indian port of Entry) (For spares to be supplied from abroad) Ex-works (India) (For spares to be supplied from within the Employer’s country) CIF (Indian port of Entry) Ex-works (India) F.O.R Site (for spares to be supplied from abroad F.O.R. Site (for spares to be supplied from employer's country)
902.0 NOT USED TOTAL PRICE We also confirm that the items of Recommended Spares with same specification having same identification number but with different item code have been quoted by us at the same price. Further all such items of spares have been clubbed together and enclosed separately at Annexure... . to our offer. Annexure….... Note:1. Domestically manufactured spares shall be quoted on Ex-works (India) basis and the spares to be supplied from abroad shall be quoted on CIF (Indian Port of Entry) basis.2. Continuation sheets of like size and format may be used as per Bidder's requirements and annexed to this Schedule.2. Continuation sheets of like size and format may be used as per Bidder's requirements and annexed to this Schedule. BALANCE OF PLANT(BOP) TURNKEY PACKAGE FOR DURGAPUR THERMAL POWER STATION (1 X 800 MW) ,BIDDING DOCUMENT NO. DVC/C&M/ENGINEERING/DTPS(1X800MW)/EPC/BOP Bidder's Name and Address : Schedule No. 7A : Custom Duty/ Import Duty and Goods and Services Tax (GST), applicable on Schedules - 1 not included in bid price: BREAK-UP TO BE FURNISHED BEFORE AWARD The details of Custom Duty/ Import Duty and Goods and Services Tax (as on seven (07) days prior to the last date for submission of price bids) applicable on the price of goods and services quoted in Schedule-1, not included in the Bid Price and which may be payable by the Employer in accordance with the provisions of Bidding Documents are as under : A. Custom Duty/ Import Duty Bid Price Component Rate of Custom Duty/ Import Duty (%) Amount on which Custom/ Import duty applicable (in Bid Currency) Total Custom Duty/ Import Duty payable (in Bid Currency) Currency 1 Currency 2 Currency 3 Currency 4 Currency 1 Currency 2 Currency 3 Currency 4 INR USD EUR JPY INR USD EUR JPY CIF-Main Equipment(Schedule-1) CIF-Mandatory Spares(Schedule-1) Type Test charges(Schedule-1) B. GST Bid Price Component Rate of GST (%) Amount on which GST applicable (in Bid Currency) Total GST payable (in Bid Currency) Currency 1 Currency 2 Currency 3 Currency 4 Currency 1 Currency 2 Currency 3 Currency 4 INR USD EUR JPY INR USD EUR JPY CIF-Main Equipment(Schedule-1) CIF-Mandatory Spares(Schedule-1) Type Test charges(Schedule-1) Note: 1. In case rate of Custom Duty/ Import Duty and GST is different for various items, such different rates of Custom / Import duty and GST along with the amount on which such Custom/Import Duty and GST is applicable shall be suitably indicated by the bidders in this schedule. 2. The detailed breakup of items along with rate of Custom/ import duty and GST is required to be submitted prior to the placement of award. 3. Bidder to refer ITB clause 11.1(d) while quoting its bid price. Bidder to refer ITB clause 11.1(d) while quoting its bid price. BALANCE OF PLANT(BOP) TURNKEY PACKAGE FOR DURGAPUR THERMAL POWER STATION (1X800 MW) ,BIDDING DOCUMENT NO. DVC/C&M/ENGINEERING/DTPS(1X800MW)/EPC/BOP Bidder's Name and Address : Schedule No. 7 : Goods and Services Tax (GST), applicable on Schedules - 2,3 & 4 not included in bid price: BREAK-UP TO BE FURNISHED BEFORE AWARD The details of Goods and Services Tax (as on seven (07) days prior to the last date for submission of bids) applicable on the price of goods and services quoted in Schedule-2, 3 & 4, not included in the Bid Price and which may be payable by the Employer in accordance with the provisions of Bidding Documents are as under : S. No. Bid Price Component Total GST payable (in Bid Currency) Currency 1 Currency 2 Currency 3 Currency 4 INR EUR USD JPY
91Ex-Works-Main Equipment (Schedule-2)
92Ex-Works-Mandatory Spares (Schedule-2)
93Type Test charges (Schedule-2)
94F&I-Main Equipment (Schedule-3)
95F&I-Mandatory Spares (Schedule-3)
96Erection - Main Equipment (Schedule-4)
97Civil Works (Schedule-4)
98Training charges (Schedule-4)
99AMC / AMS (Annual Maintenance Services) (Schedule-4)
100Structural Works (Schedule-4)
101Amount linked to Safety Aspects/ compliance to Safety Rules (Schedule-4)
102Any other Price Component (not covered above) TOTAL (GST) 0.0 0.0 0.0 0.0 Notes:
103Bidder shall quote the GST as applicable in the Employer's country as on seven (7) days prior to the last date of submission of price bids.
104In case rate of GST is different for various items, such different rates of GST along with the amount on which such GST is applicable shall be suitably indicated by the bidders in this schedule.
105Bidder to refer ITB clause 11.1(d) while quoting its bid price. BALANCE OF PLANT(BOP) TURNKEY PACKAGE FOR DURGAPUR THERMAL POWER STATION (1X800 MW) ,BIDDING DOCUMENT NO. DVC/C&M/ENGINEERING/DTPS(1X800MW)/EPC/BOP Bidder's Name and Address : Schedule No. 8A : Break up of Type Test Charges for Equipment Priced in Schedule-1: BREAK-UP TO BE FURNISHED BEFORE AWARD Sl. No. Description of Test Charges for one Type /Rating Number of Type/Rating Total Charges Currency 1 Currency 2 Currency 3 Currency 4 Currency 1 Currency 2 Currency 3 Currency 4 INR USD EUR JPY INR USD EUR JPY
1062.0 I. LIST OF TYPE TESTS ON ELECTRICAL EQUIPMENTS
107Not Used.
108GIS SWITCHYARD (A) The following type tests on typical 400 kV Circuit Breaker (As Applicable) (i) Dielectric tests 0.0 0.0 0.0 0.0 (ii) Radio Interference Voltage test 0.0 0.0 0.0 0.0 (iii) Temperature rise test 0.0 0.0 0.0 0.0 (iv) Short time withstand current and peak withstand test 0.0 0.0 0.0 0.0 (v) Mechanical endurance test 0.0 0.0 0.0 0.0 (vi) Short circuit test duties 0.0 0.0 0.0 0.0 (vii) Short line fault test 0.0 0.0 0.0 0.0 (viii) Out of phase making and breaking test 0.0 0.0 0.0 0.0 (ix) Line charging current breaking test 0.0 0.0 0.0 0.0 (x) Corona Test 0.0 0.0 0.0 0.0 (xi) IP:55 Test on each type of Box 0.0 0.0 0.0 0.0 (xii) Sesimic withstand test with structure 0.0 0.0 0.0 0.0 (xiii) Test for reactor switching duty 0.0 0.0 0.0 0.0 (B) For Surge Arrestor and Bus VT following Type Test as per relevant IEC (a) Insulation withstand test on housing 0.0 0.0 0.0 0.0 (b) Residual voltage test 0.0 0.0 0.0 0.0 (c ) Long duration current impulse withstand test 0.0 0.0 0.0 0.0 (d) operating duty test 0.0 0.0 0.0 0.0 (e ) Partial Discharge test 0.0 0.0 0.0 0.0 (f) Leakage Test 0.0 0.0 0.0 0.0 ( C) 400KV Bus VT (as per relevant IEC) (a) Temperature rise test 0.0 0.0 0.0 0.0 (b) Lighting Impluse Test 0.0 0.0 0.0 0.0 (c ) Switching Impulse 0.0 0.0 0.0 0.0 (d) Determination of errors 0.0 0.0 0.0 0.0 (e ) Short Circuit withstand capabilities 0.0 0.0 0.0 0.0 (f) Chopped lighting impulse test 0.0 0.0 0.0 0.0
109 (A) INTERCONNECTING TRANSFORMER (ICT) (a) Short circuit test as per IEC-60076-5 0.0 0.0 0.0 0.0 (b) Measurement of harmonics of the no load current 0.0 0.0 0.0 0.0 (c) LTAC test as IEC 60076-3 0.0 0.0 0.0 0.0 (d) Measurement of accoustic noise level as per NEMA TR-1 0.0 0.0 0.0 0.0 (B) Station Transformer/Stand-by Transformer (a) Short circuit test as per IEC-60076-5 0.0 0.0 0.0 0.0 (b) Temperature rise test 0.0 0.0 0.0 0.0 (c) Zero sequence impedence measurement test 0.0 0.0 0.0 0.0 (d) Measurement of the power taken by fans& pumps (if applicable) 0.0 0.0 0.0 0.0 (e) Measurement of harmonics of the no load current 0.0 0.0 0.0 0.0 (f) LTAC test as IEC 60076-3 0.0 0.0 0.0 0.0 (g) Measurement of accoustic noise level as per NEMA TR-1 0.0 0.0 0.0 0.0 (C ) Deleted (D) Deleted (E) 12 KV class & above or equal / more than 10MVA transformer (For each type and rating) (a) Lighting impulse (Full & chopped wave) test on HV & LV winding (as per IEC-60076-3) 0.0 0.0 0.0 0.0 (b) Lightning impulse on Neutral 0.0 0.0 0.0 0.0 (c) Short circuit test as per IEC-60076-5 0.0 0.0 0.0 0.0 (d) Temperature rise test 0.0 0.0 0.0 0.0 (e) Measurement of accoustic noise level as per NEMA TR-1 0.0 0.0 0.0 0.0
110Not used.
111BUSDUCT
112Heat Run Test (i) Deleted 0.0 0.0 0.0 0.0 (ii) Medium Voltage Busduct 0.0 0.0 0.0 0.0 a) 11 KV Busduct 0.0 0.0 0.0 0.0 b) 3.3 KV Busduct 0.0 0.0 0.0 0.0
113Short circuit withstand test (i) Deleted (ii) Medium Voltage Busduct 0.0 0.0 0.0 0.0 a) 11 KV Busduct 0.0 0.0 0.0 0.0 b) 3.3 KV Busduct 0.0 0.0 0.0 0.0
114Impulse withstand test followed by HV test (i) Deleted ii) Medium Voltage Busduct 0.0 0.0 0.0 0.0 a) 11 KV Busduct 0.0 0.0 0.0 0.0 b) 3.3 KV Busduct 0.0 0.0 0.0 0.0
115One minute high voltage Power frequency withstand test (i) Deleted (ii) Medium Voltage Busduct 0.0 0.0 0.0 0.0 a) 11 KV Busduct 0.0 0.0 0.0 0.0 b) 3.3 KV Busduct 0.0 0.0 0.0 0.0
116Water Tightness Test (i) Deleted (ii) Medium Voltage Busduct 0.0 0.0 0.0 0.0 a) 11 KV Busduct 0.0 0.0 0.0 0.0 b) 3.3 KV Busduct 0.0 0.0 0.0 0.0
117Air Leakage Test (i) Deleted (ii) Medium Voltage Busduct 0.0 0.0 0.0 0.0 a) 11 KV Busduct 0.0 0.0 0.0 0.0 b) 3.3 KV Busduct 0.0 0.0 0.0 0.0
118HT MOTORS
119No load saturation and loss curves upto approximately 115% of rated voltage
120Measurement of noise at no load
121Momentary overload test (subject to test bed constraint)
122Full load test (Subject to test bed constraint)
123Temperature rise test at rated condition
124HT SWITCHGEARS a) circuit breaker / circuit breaker panels, of each voltage class and current rating 0.0 0.0 0.0 0.0 1) Short circuit duty test on circuit breaker, mounted inside the panel offered along with CTs, bushing and separators. 0.0 0.0 0.0 0.0 2) Short time withstand test on circuit breaker, mounted inside panel offered together with CTs, bushings and separators. 0.0 0.0 0.0 0.0 3) Power frequency withstand test on breaker mounted in side panel. 0.0 0.0 0.0 0.0 4) Lightning impulse withstand test on breaker mounted in side panel. 0.0 0.0 0.0 0.0 5) Temperature rise test on breaker and panel together. For this test, the test set up shall include three panels with breakers, the test breaker and panel being placed in the centre. The adjacent panels shall also be loaded to their rated current capacity. Alternatively, the test panel may be suitably insulated at the sides, which will be adjoining to other panels in actual site configuration 0.0 0.0 0.0 0.0 6) Internal Arc Test as per IEC 62271-200 0.0 0.0 0.0 0.0 7) Measurement of resistance of main circuit. 0.0 0.0 0.0 0.0 8) Mechanical operation test. 0.0 0.0 0.0 0.0 9) Degree of protection 0.0 0.0 0.0 0.0 b) Contactor and Contactor panels of each type and rating. 0.0 0.0 0.0 0.0 1) Verification of rated making and breaking capacities of the contactor. 0.0 0.0 0.0 0.0 2) Short time withstand test of panel. 0.0 0.0 0.0 0.0 3) Power frequency test on the contactor mounted in side panel. 0.0 0.0 0.0 0.0 4) Lightning impulse voltage withstand test of the contactor mounted in side panel. 0.0 0.0 0.0 0.0 5) Measurement of resistance of main circuit. 0.0 0.0 0.0 0.0 6) Test to confirm coordination between fuse and contactor. 0.0 0.0 0.0 0.0 c) Short circuit withstand test of earthing device (truck / switch). 0.0 0.0 0.0 0.0
125MV VFD system (IF APPLICABLE) (i) Overall efficiency determination of VFD system including transformer/ Harmonic filters etc at motor full load 0.0 0.0 0.0 0.0 (ii) Temperature rise test 0.0 0.0 0.0 0.0 (iii) Noise level 0.0 0.0 0.0 0.0 (iv) Harmonics of No load current.(Input/Output) 0.0 0.0 0.0 0.0 (v) Type Tests as per IS/ IES on Panels, AC/ DC reactors and Transformers 0.0 0.0 0.0 0.0 (vi) Allowable full load current versus speed 0.0 0.0 0.0 0.0 (vii) Dynamic performance 0.0 0.0 0.0 0.0 (viii) Current limit and current loop test 0.0 0.0 0.0 0.0 (ix) Speed loop test capability to ride through voltage less than 80% 0.0 0.0 0.0 0.0 (x) Test capability to restart the system and resynchronize converter onto running motor after a voltage interruption 0.0 0.0 0.0 0.0
126NUMERICAL RELAY As per relevent IS 0.0 0.0 0.0 0.0
127NEUTRAL GROUNDING RESISTOR
128Temperature rise test (on one unit of each voltage rating)
129Short time current test along with Temperature rise test (on one unit of each voltage rating)
130Degree of protection test for IPX3 on enclosure
131L.T. TRANSFORMERS
132Impulse withstand test
133Temperature rise test
134Measurement of acoustic sound level
135Partial discharge measurement
136Ingress Protection Test
137BATTERY AND BATTERY CHARGER
138On two cells of the Battery a) Test for capacity - test for voltage during discharge 0.0 0.0 0.0 0.0 b) Ampere hour & watt-hour efficiency test 0.0 0.0 0.0 0.0 c) Endurance test 0.0 0.0 0.0 0.0 d) Container shall be type tested as per IS: 1146 0.0 0.0 0.0 0.0 e) Sealing compound shall be type tested as per IS: 3116 0.0 0.0 0.0 0.0
139battery charger a) Dielectric tests. 0.0 0.0 0.0 0.0 b) Voltage regulation check from 0 to 100% load with +_10% input voltage variation. 0.0 0.0 0.0 0.0 c) Ripple content measurement. 0.0 0.0 0.0 0.0 d) Functional tests. 0.0 0.0 0.0 0.0 e) Heat run test on current limiting value. 0.0 0.0 0.0 0.0
140CABLES (HT & LT) As per relevent IS 0.0 0.0 0.0 0.0
141ILLUMINATION SYSTEM LM79 and LM80 0.0 0.0 0.0 0.0
142Cable trays and cable tray support system a) Deflection tests and slip tests on cable trays and cable tray support system 0.0 0.0 0.0 0.0 b) Weld Integrity test 0.0 0.0 0.0 0.0
143Deleted
144IDCT i) Fill Thermal Characteristic & Pressure Drop Test 0.0 0.0 0.0 0.0 ii) Distribution Nozzle Characteristic Test-Head vs Flow & Head vs spread area 0.0 0.0 0.0 0.0 iii) Gear Box Full Load Test 0.0 0.0 0.0 0.0 iv) Fan Scaled Down Model Test 0.0 0.0 0.0 0.0 v) Proof of Design (POD) for BFV 0.0 0.0 0.0 0.0
145Bidder to note that in case for the balance C&I systems/equipment, the type test certificates furnished by the Bidder is (are) not acceptable to the Owner on the grounds indicated in the C&I section of technical specifications (Part B) the relevant test(s) shall be conducted without any price repercussion to the Owner.
146TYPE TEST OF UF MEMBRANE i) Bubble point Test 0.0 0.0 0.0 0.0 ii) Integrity Test 0.0 0.0 0.0 0.0
147CW System i) CW Pump Model Test 0.0 0.0 0.0 0.0 II) POD of BFV 0.0 0.0 0.0 0.0
148FGD i) Leak tightness test at shop (for each type and size) 0.0 0.0 0.0 0.0 ii) Booster Fan (if applicable) 0.0 0.0 0.0 0.0 TOTAL (TO SCHEDULE-1) 0.0 0.0 0.0 0.0 Note : The currency for type test charges shall be same as the currency in which the corresponding equipment is being offered in Schedule-1. If Bidder is not intended to quote price against certain items in this schedule, then the bidder may mention \\"0\\" against such items. However, the bidder shall ensure to quote against such items in other schedules appropriately. If any Type Test is Not Applicable, the Bidder shall quote \\"0\\" for such Type test in Schedule 8A & 8B both. However, any Type test found applicable during detailed engineering, that Type Test shall be conducted by the Bidder without any cost implication to NTPC. BALANCE OF PLANT(BOP) TURNKEY PACKAGE FOR DURGAPUR THERMAL POWER STATION (1X800 MW) ,BIDDING DOCUMENT NO. DVC/C&M/ENGINEERING/DTPS(1X800MW)/EPC/BOP Bidder's Name and Address : Schedule No. 8B : Break up of Type Test Charges for Equipment Priced in Schedule-2: BREAK-UP TO BE FURNISHED BEFORE AWARD Sl. No. Description of Test Charges for one Type /Rating Number of Type/Rating Total Charges Currency 1 Currency 2 Currency 3 Currency 4 Currency 1 Currency 2 Currency 3 Currency 4 INR USD EUR JPY INR USD EUR JPY
1492.0 I. LIST OF TYPE TESTS ON ELECTRICAL EQUIPMENTS
150Not Used.
151GIS SWITCHYARD (A) The following type tests on typical 400 kV Circuit Breaker (As Applicable) (i) Dielectric tests 0.0 0.0 0.0 0.0 (ii) Radio Interference Voltage test 0.0 0.0 0.0 0.0 (iii) Temperature rise test 0.0 0.0 0.0 0.0 (iv) Short time withstand current and peak withstand test 0.0 0.0 0.0 0.0 (v) Mechanical endurance test 0.0 0.0 0.0 0.0 (vi) Short circuit test duties 0.0 0.0 0.0 0.0 (vii) Short line fault test 0.0 0.0 0.0 0.0 (viii) Out of phase making and breaking test 0.0 0.0 0.0 0.0 (ix) Line charging current breaking test 0.0 0.0 0.0 0.0 (x) Corona Test 0.0 0.0 0.0 0.0 (xi) IP:55 Test on each type of Box 0.0 0.0 0.0 0.0 (xii) Sesimic withstand test with structure 0.0 0.0 0.0 0.0 (xiii) Test for reactor switching duty 0.0 0.0 0.0 0.0 (B) For Surge Arrestor and Bus VT following Type Test as per relevant IEC (a) Insulation withstand test on housing 0.0 0.0 0.0 0.0 (b) Residual voltage test 0.0 0.0 0.0 0.0 (c ) Long duration current impulse withstand test 0.0 0.0 0.0 0.0 (d) operating duty test 0.0 0.0 0.0 0.0 (e ) Partial Discharge test 0.0 0.0 0.0 0.0 (f) Leakage Test 0.0 0.0 0.0 0.0 ( C) 400KV Bus VT (as per relevant IEC) (a) Temperature rise test 0.0 0.0 0.0 0.0 (b) Lighting Impluse Test 0.0 0.0 0.0 0.0 (c ) Switching Impulse 0.0 0.0 0.0 0.0 (d) Determination of errors 0.0 0.0 0.0 0.0 (e ) Short Circuit withstand capabilities 0.0 0.0 0.0 0.0 (f) Chopped lighting impulse test 0.0 0.0 0.0 0.0
152 (A) INTERCONNECTING TRANSFORMER (ICT) (a) Short circuit test as per IEC-60076-5 0.0 0.0 0.0 0.0 (b) Measurement of harmonics of the no load current 0.0 0.0 0.0 0.0 (c) LTAC test as IEC 60076-3 0.0 0.0 0.0 0.0 (d) Measurement of accoustic noise level as per NEMA TR-1 0.0 0.0 0.0 0.0 (B) Station Transformer/Stand-by Transformer (a) Short circuit test as per IEC-60076-5 0.0 0.0 0.0 0.0 (b) Temperature rise test 0.0 0.0 0.0 0.0 (c) Zero sequence impedence measurement test 0.0 0.0 0.0 0.0 (d) Measurement of the power taken by fans& pumps (if applicable) 0.0 0.0 0.0 0.0 (e) Measurement of harmonics of the no load current 0.0 0.0 0.0 0.0 (f) LTAC test as IEC 60076-3 0.0 0.0 0.0 0.0 (g) Measurement of accoustic noise level as per NEMA TR-1 0.0 0.0 0.0 0.0 (C ) Deleted (D) Deleted (E) 12 KV class & above or equal / more than 10MVA transformer (For each type and rating) (a) Lighting impulse (Full & chopped wave) test on HV & LV winding (as per IEC-60076-3) 0.0 0.0 0.0 0.0 (b) Lightning impulse on Neutral 0.0 0.0 0.0 0.0 (c) Short circuit test as per IEC-60076-5 0.0 0.0 0.0 0.0 (d) Temperature rise test 0.0 0.0 0.0 0.0 (e) Measurement of accoustic noise level as per NEMA TR-1 0.0 0.0 0.0 0.0
153Not used.
154BUSDUCT
155Heat Run Test (i) Deleted (ii) Medium Voltage Busduct a) 11 KV Busduct 0.0 0.0 0.0 0.0 b) 3.3 KV Busduct 0.0 0.0 0.0 0.0
156Short circuit withstand test (i) Deleted (ii) Medium Voltage Busduct 0.0 0.0 0.0 0.0 a) 11 KV Busduct 0.0 0.0 0.0 0.0 b) 3.3 KV Busduct 0.0 0.0 0.0 0.0
157Impulse withstand test followed by HV test (i) Deleted ii) Medium Voltage Busduct 0.0 0.0 0.0 0.0 a) 11 KV Busduct 0.0 0.0 0.0 0.0 b) 3.3 KV Busduct 0.0 0.0 0.0 0.0
158One minute high voltage Power frequency withstand test (i) Deleted 0.0 0.0 0.0 0.0 (ii) Medium Voltage Busduct 0.0 0.0 0.0 0.0 a) 11 KV Busduct 0.0 0.0 0.0 0.0 b) 3.3 KV Busduct 0.0 0.0 0.0 0.0
159Water Tightness Test (i) Deleted (ii) Medium Voltage Busduct 0.0 0.0 0.0 0.0 a) 11 KV Busduct 0.0 0.0 0.0 0.0 b) 3.3 KV Busduct 0.0 0.0 0.0 0.0
160Air Leakage Test (i) Deleted (ii) Medium Voltage Busduct 0.0 0.0 0.0 0.0 a) 11 KV Busduct 0.0 0.0 0.0 0.0 b) 3.3 KV Busduct 0.0 0.0 0.0 0.0
161HT MOTORS
162No load saturation and loss curves upto approximately 115% of rated voltage
163Measurement of noise at no load
164Momentary overload test (subject to test bed constraint)
165Full load test (Subject to test bed constraint)
166Temperature rise test at rated condition
167HT SWITCHGEARS a) circuit breaker / circuit breaker panels, of each voltage class and current rating 0.0 0.0 0.0 0.0 1) Short circuit duty test on circuit breaker, mounted inside the panel offered along with CTs, bushing and separators. 0.0 0.0 0.0 0.0 2) Short time withstand test on circuit breaker, mounted inside panel offered together with CTs, bushings and separators. 0.0 0.0 0.0 0.0 3) Power frequency withstand test on breaker mounted in side panel. 0.0 0.0 0.0 0.0 4) Lightning impulse withstand test on breaker mounted in side panel. 0.0 0.0 0.0 0.0 5) Temperature rise test on breaker and panel together. For this test, the test set up shall include three panels with breakers, the test breaker and panel being placed in the centre. The adjacent panels shall also be loaded to their rated current capacity. Alternatively, the test panel may be suitably insulated at the sides, which will be adjoining to other panels in actual site configuration 0.0 0.0 0.0 0.0 6) Internal Arc Test as per IEC 62271-200 0.0 0.0 0.0 0.0 7) Measurement of resistance of main circuit. 0.0 0.0 0.0 0.0 8) Mechanical operation test. 0.0 0.0 0.0 0.0 9) Degree of protection 0.0 0.0 0.0 0.0 b) Contactor and Contactor panels of each type and rating. 0.0 0.0 0.0 0.0 1) Verification of rated making and breaking capacities of the contactor. 0.0 0.0 0.0 0.0 2) Short time withstand test of panel. 0.0 0.0 0.0 0.0 3) Power frequency test on the contactor mounted in side panel. 0.0 0.0 0.0 0.0 4) Lightning impulse voltage withstand test of the contactor mounted in side panel. 0.0 0.0 0.0 0.0 5) Measurement of resistance of main circuit. 0.0 0.0 0.0 0.0 6) Test to confirm coordination between fuse and contactor. 0.0 0.0 0.0 0.0 c) Short circuit withstand test of earthing device (truck / switch). 0.0 0.0 0.0 0.0
168MV VFD system (IF APPLICABLE) (i) Overall efficiency determination of VFD system including transformer/ Harmonic filters etc at motor full load 0.0 0.0 0.0 0.0 (ii) Temperature rise test 0.0 0.0 0.0 0.0 (iii) Noise level 0.0 0.0 0.0 0.0 (iv) Harmonics of No load current.(Input/Output) 0.0 0.0 0.0 0.0 (v) Type Tests as per IS/ IES on Panels, AC/ DC reactors and Transformers 0.0 0.0 0.0 0.0 (vi) Allowable full load current versus speed 0.0 0.0 0.0 0.0 (vii) Dynamic performance 0.0 0.0 0.0 0.0 (viii) Current limit and current loop test 0.0 0.0 0.0 0.0 (ix) Speed loop test capability to ride through voltage less than 80% 0.0 0.0 0.0 0.0 (x) Test capability to restart the system and resynchronize converter onto running motor after a voltage interruption 0.0 0.0 0.0 0.0
169NUMERICAL RELAY As per relevent IS 0.0 0.0 0.0 0.0
170NEUTRAL GROUNDING RESISTOR
171Temperature rise test (on one unit of each voltage rating)
172Short time current test along with Temperature rise test (on one unit of each voltage rating)
173Degree of protection test for IPX3 on enclosure
174L.T. TRANSFORMERS
175Impulse withstand test
176Temperature rise test
177Measurement of acoustic sound level
178Partial discharge measurement
179Ingress Protection Test
180BATTERY AND BATTERY CHARGER
181On two cells of the Battery a) Test for capacity - test for voltage during discharge 0.0 0.0 0.0 0.0 b) Ampere hour & watt-hour efficiency test 0.0 0.0 0.0 0.0 c) Endurance test 0.0 0.0 0.0 0.0 d) Container shall be type tested as per IS: 1146 0.0 0.0 0.0 0.0 e) Sealing compound shall be type tested as per IS: 3116 0.0 0.0 0.0 0.0
182battery charger a) Dielectric tests. 0.0 0.0 0.0 0.0 b) Voltage regulation check from 0 to 100% load with +_10% input voltage variation. 0.0 0.0 0.0 0.0 c) Ripple content measurement. 0.0 0.0 0.0 0.0 d) Functional tests. 0.0 0.0 0.0 0.0 e) Heat run test on current limiting value. 0.0 0.0 0.0 0.0
183CABLES (HT & LT) As per relevent IS 0.0 0.0 0.0 0.0
184ILLUMINATION SYSTEM LM79 and LM80 0.0 0.0 0.0 0.0
185Cable trays and cable tray support system a) Deflection tests and slip tests on cable trays and cable tray support system 0.0 0.0 0.0 0.0 b) Weld Integrity test 0.0 0.0 0.0 0.0
186Deleted
187IDCT i) Fill Thermal Characteristic & Pressure Drop Test 0.0 0.0 0.0 0.0 ii) Distribution Nozzle Characteristic Test-Head vs Flow & Head vs spread area 0.0 0.0 0.0 0.0 iii) Gear Box Full Load Test 0.0 0.0 0.0 0.0 iv) Fan Scaled Down Model Test 0.0 0.0 0.0 0.0 v) Proof of Design (POD) for BFV 0.0 0.0 0.0 0.0
188Bidder to note that in case for the balance C&I systems/equipment, the type test certificates furnished by the Bidder is (are) not acceptable to the Owner on the grounds indicated in the C&I section of technical specifications (Part B) the relevant test(s) shall be conducted without any price repercussion to the Owner.
189TYPE TEST OF UF MEMBRANE i) Bubble point Test 0.0 0.0 0.0 0.0 ii) Integrity Test 0.0 0.0 0.0 0.0
190CW System i) CW Pump Model Test 0.0 0.0 0.0 0.0 II) POD of BFV 0.0 0.0 0.0 0.0
191FGD i) Leak tightness test at shop (for each type and size) 0.0 0.0 0.0 0.0 ii) Booster Fan (if applicable) 0.0 0.0 0.0 0.0 TOTAL (TO SCHEDULE-1) 0.0 0.0 0.0 0.0 Note : The currency for type test charges shall be same as the currency in which the corresponding equipment is being offered in Schedule-2. If Bidder is not intended to quote price against certain items in this schedule, then the bidder may mention \\"0\\" against such items. However, the bidder shall ensure to quote against such items in other schedules appropriately. If any Type Test is Not Applicable, the Bidder shall quote \\"0\\" for such Type test in Schedule 8A & 8B both. However, any Type test found applicable during detailed engineering, that Type Test shall be conducted by the Bidder without any cost implication to NTPC. BALANCE OF PLANT(BOP) TURNKEY PACKAGE FOR DURGAPUR THERMAL POWER STATION (1X800 MW) ,BIDDING DOCUMENT NO. DVC/C&M/ENGINEERING/DTPS(1X800MW)/EPC/BOP Bidder's Name and Address : Schedule No. 9: SCHEDULE OF TAKE OUT PRICE: NOT USED Take out price for certain items/services are indicated below. We confirm that the prices for these items are already included in the Bid Price. We further confirm that the Employer may delete from our scope any of the items given below based on the prices given in this schedule. Sl. No. Description Quantity Cost implication on the Lumpsum bid price i.e. reduction/decrease (-) in the bid price Reference of Bid where Technical Details have been furnished Remarks # FOB # CIF # Ex-works Local Transportation & Insurance (Indian Rupees) Installation
1922.0 NOT USED # Bidder shall quote the price on Ex-works/CIF basis in line with the price quoted in Schedule-1 and/or Schedule-2. Note :
193Take out price for each item (as applicable) mentioned above in this Schedule shall be included by the bidder in the lumpsum bid price. Employer reserves the right to exclude any of these items during placement of award.
194Employer shall finalise take out option up to 2 month of LOA. BALANCE OF PLANT(BOP) TURNKEY PACKAGE FOR DURGAPUR THERMAL POWER STATION (1X800 MW) ,BIDDING DOCUMENT NO. DVC/C&M/ENGINEERING/DTPS(1X800MW)/EPC/BOP Bidder's Name and Address : Schedule No. 10 : Schedule of Unit Rates- NOT USED The Unit Rates of various items are given as under. We confirm that the prices of these items as per the requirement of Technical Specifications are already included in the lump-sum prices quoted in Schedule-1 and/or Schedule-2, Schedule-3 and Schedule-4. We further confirm that these unit rates shall be used for contract price adjustment on account of quantity variation. S. No. Item Unit of Measurement #CIF/Ex-Works Price Local Transportation including Port clearance & Port charges and Inland insurance (Indian Rs.) Installation Services Prices
195NOT USED # Bidder shall quote the price on Ex-works / CIF basis in line with the prices quoted in Schedule-1 and/or Schedule-2. BALANCE OF PLANT(BOP) TURNKEY PACKAGE FOR DURGAPUR THERMAL POWER STATION (1X800 MW) ,BIDDING DOCUMENT NO. DVC/C&M/ENGINEERING/DTPS(1X800MW)/EPC/BOP Bidder's Name and Address : Schedule No. 11 : Schedule of Alternatives- NOT USED The prices indicated below are additional prices/rebates in Bid Price for providing the alternatives to the base offer as specified in the Technical Specifications. S. No. Item Description Weight/ Quantity Price Ex-works/CIF Local Transportation and other expenses incidental to delivery at site (Indian Rs.) Installation services Additional Price (+) Rebate (-) Additional Price (+) Rebate (-) Additional Price (+) Rebate (-)
196NOT USED Note : Bidder shall quote the price on Ex-works/CIF basis in line with the price quoted in Schedule-1 and/or Schedule-2.
1972.0 NOT USED Please Enable Macros to View BoQ information

AI Tender Summary

OUR REF NO 56416928
AUTHORITY Boards / Undertakings / PSU
TENDER VALUE Ref. Documents
LAST DATE 17-08-2026
Authority
Authority Name Damodar Valley Corporation
Work Description Tender for Balance Of Plant (Bop) Turnkey Package For Durgapur Thermal Power Station (1 X 800 Mw)
Basic Detail
Tender No DVC/CandM/ENGINEERING/DTPS 1X800MW/EPC/BOP
Bidding Type Tender
Location
City Paschim Bardhaman
State West Bengal
Key Dates
Publish Date 11 Jul 2026
Submission Date 17 Aug 2026
Open Date 18 Aug 2026
Finance
Tender Value Ref. Documents
Tender Fee Ref. Documents
EMD 25.69 Crore
Exemption Not Available
Document List
5f2a1b03-ba6e-418e-9117-ebb9c72c2313.html
BOQ_330361.xls
Pre_Bid_Meeting_link.pdf
Pre_Signed_IP.pdf
Tendernotice_1 (6).pdf
Vol-2_part1.pdf
Vol-2_Part10.pdf
Vol-2_part2.pdf
Vol-2_part3.pdf
Vol-2_part4.pdf
Vol-2_part5.pdf
Vol-2_part6.pdf
Vol-2_part7.pdf
Vol-2_part8.pdf
Vol-2_part9.pdf

Unlock Full AI Tender Summary

Get instant access to the complete AI-generated analysis — scope, eligibility, timeline & more.

Instant Access Secure Free
Your details are secure and used only for document delivery.

Tender Timeline

Jul 11, 2026
11:30 IST

Tender Published

Tender notice published.

Today
Aug 17, 2026
17:00 IST

Bid Submission Deadline

Online submission via eProcurement portal.

Upcoming · 37 days
Aug 18, 2026

Bid Opening Date

Technical bids will be opened and evaluated.

Upcoming · 38 days

Tender Documents

Download All (ZIP) ↓
html

5f2a1b03-ba6e-418e-9117-ebb9c72c2313.html

xls

BOQ_330361.xls

pdf

Pre_Bid_Meeting_link.pdf

pdf

Pre_Signed_IP.pdf

pdf

Tendernotice_1 (6).pdf

pdf

Vol-2_part1.pdf

pdf

Vol-2_Part10.pdf

pdf

Vol-2_part2.pdf

pdf

Vol-2_part3.pdf

pdf

Vol-2_part4.pdf

pdf

Vol-2_part5.pdf

pdf

Vol-2_part6.pdf

pdf

Vol-2_part7.pdf

pdf

Vol-2_part8.pdf

pdf

Vol-2_part9.pdf

Disclaimer

We takes all possible care for accurate & authentic tender information. However users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender

TenderDetail
Loading tenders