Petroleum and Natural Gas Government Departments Closing in 9 days TDR #56332807

Tender For Tender For Rerouting Of Steel Pipeline (Hot Tapping And Double Stopple Method) And Mdpe Pipeline At Pune Ga

Issued by Government Departments · Pune, Maharashtra
Tender Value
Ref. Documents
Estimated cost
Bid Submission
20 Jul 2026
9 days left
EMD
2 Lakhs
Bank guarantee accepted
Document Fee
Ref. Documents
Non-refundable
Tender Type
Online

Tender Overview

Competition Type
NCB
Bidding Type
Tender
Location / State
Pune → Maharashtra
EMD Exemption
Available
Quantity
Not Available

Project Description

Tender for Tender For Rerouting Of Steel Pipeline (Hot Tapping And Double Stopple Method) And Mdpe Pipeline At Pune Ga

BOQ

Name of Work:- Tender for Rerouting of steel pipeline (Hot Tapping and double stopple method) and MDPE pipeline at Pune GA
Sl. No. Item Description
1Re-routing of UG Steel PipelineThe SOR covers re-routing of steel pipe line by Transportation of Pipe, loading, unloading of the line pipes to the site, (Excluding Trench) laying of pipeline with dewatering and cleaning of pit or trench if required, Welding, NDT, DPT, joint coating, holiday testing, backfilling, laying of warning mat, hydrotesting, pigging, swabbing of pipes, N2 purging etc. which required to complete the pipeline mechanically and commissioning of pipeline as per approval by EIC. Surface and bevel preparation, DP checking, Drying of the section if required etc. and as per requirement at site and direction given by EIC. Contractor to carry out all the activities involved in Pre- commissioning and commissioning and ensure the safety requirements such as PPEs, barricading, sign boards, blinking light etc. to complete the section work in day and night as directed by EIC. Contractor to arrange all necessary equipment, DG, pipe line fittings, consumables, manpower with PPE's, Fire extinguishers, Fire fighting services and local coordination as required etc. to complete the job. After Completion of the job all related documents to be submitted. Job shall be carried out as per ASME B 31.8/ API 1104 in all aspect as per the satisfaction of MNGL.
2Tenching for 10'' & 4'' steel pipeline laying at rocky terrain area at 1.2 Meter top cover
34'' Dia Re-routing/Laying UG PIPELINE
410'' Dia Re-routing/Laying UG PIPELINE
5Mobilization for Hook Up (UG Pipeline)The SOR covers additional manpower, site coordination,Liasioning, tools, equipments, machines, excavation, welding, NDT, Coating, backfilling, etc. whichever is required to complete the given hook up work in totality for all size of UG Pipeline. vendor can claim only 1 hook up qty per site/job/location.The SOR also covers, distribution of notice/ intimation letter to societies, police station, corporation, fire brigade etc. to execute the decommissioning and commissioning of the pipeline/ section including support for closing of both sides valves, venting the natural gas of the section, Nitrogen purging including supply, vaporizer, checking LEL etc. as per requirement at site and direction given by EIC. Contractor to carry out all the activities involved in De-commissioning and commissioning and ensure all safety requirements such as PPEs, barricading, sign boards, blinking light etc. to complete the section work in day and night as directed by EIC.
6Hook Up of steel line for 10'' Dia
7MDPE PIPELINE LAYING & Stop-off Valve Installation
8Laying OF MDPE Pipeline Dia=125 MM
9Stop-off Valve Dia=125 MM (Including construction of valve chamber)
10Installation of Steel Valves (Butt Welded) :-Valve which is installed on steel pipe line network Activity shall be carried including transportation of Pipe, Valves from MNGL store., loading, unloading of the Pipe, valves to the site, excavating the trench for new valve installation, dewatering and cleaning of pit or trench, Construction of RCC valve chamber, Chamber cover frame fabrication work I,C,T angle/channel upto 10 mm for chamber, Chamber covers with RCC heavy duty 50T covers/chequre plate upto 12 mm thickness as per drawing, Painting, R-95,Welding the section for valve assembly, NDT, DPT, joint coating holiday testing, laying, cleaning section by pneumatic pressure, hydrotesting of valve assembly, closing the valves of both sides of the work place. if the tapping in between the section same to be close. venting the natural gas of the section, Nitrogen purging, Re-installation of purge valves (wherever required), barricading the site with sign boards, cutting the line from both ends of existing pipeline/valve section, surface and bevel preparation, DP checking and welding the pipe with the new section, NDT(Radiography, UT,) MPT coat and wrap for golden joints, Holiday testing, laying of warning mat and back-filling the same etc. Drying of the section if required & construction of valve chamber by RCC Grade M:20 (water proof Chamber) Pre-cast/Steel cover with necessary fabrication (50Ton load capacity). Contractor to carry out all the activities involved in Pre- commissioning and commissioning of the complete section work as directed by OWNER EIC. Contractor to arrange all necessary equipment, pipe line fittings, consumables, manpower with PPE's, Fire extinguishers, Fire fighting services of local corporation as required etc. to complete the job. After Completion of the job all related documents to be submitted. Job shall be carried out as per ASME B 31.8/ API 1104. Transportation, Pneumatic testing, Nitrogen Purging, Hydrotesting, Flushing, Swabbing, Drying and NDT etc.
11INSTALL,VALVE,STEEL,2''NB
12INSTALL,VALVE,STEEL, 10''
13Construction of STEEL VALVE Chambers for 10'' & 4'' Including Chamber cover frame, Chamber Cover (Approx 2m x 2m). No additional cost for change in dimensions at site.
14Supply and installation of Steel Pipeline Pole, Route MarkerSOR covers the supply of manpower , materials, fabrication, civil work, etc. which required to installed the route markers viz,(Direction, Warning & KM Post) markers with painting as per drawing
15Pipeline RCC boundary / route marker
16Pipeline Pole markers with post & foundations
17Supply & laying of RCC tiles as per drawing if any other location needed as per request by EIC
18Supply of 150 Class Spiral wound Gasket (Inner & Outer SS 316 with graphite filled)
19SUPPLY,GASKET,SPIRAL,WOUND 2'' Dia
20Excavation of Built up surface/Hard Rock/Asphalt Surface/concrete road for U/G steel pipeline, shutdown activity, etc. on steel networkExcavation below1.5 meter (For additional excavation) by Man or Machine Providing Shuttering to entire Pits Providing Hard Barricading to entire Pit Shifting of Soil from site. Backfilling is also to be done if required
21EXCAVATION MUDDY SOIL,MANUAL/M/C, Backfilling (if required)
22Weld Neck RF Flange (B-16.5, # A105)
232\\" NB, RF End thickness to match with pipe wall thickness 150#
24Blind Flanges (B-16.5, # A105)
252\\" NB, RF End thickness to match with pipe wall thickness 150#
26Elbow (Seamless)90° Elbow (A234 Gr. WPB, B-16.9, 1.5D)
2710\\" NB Sch. Std.
28Elbow (Seamless) 45° Elbow (A234 Gr. WPB, B-16.9, 1.5D)
2910\\" NB Sch. Std.
30Elbow (Seamless) 90° Elbow (A234 Gr. WPB, B-16.9, R= 3 D)
3110\\" NB Sch. Std.
32Elbow (Seamless) 45° Elbow (A234 Gr. WPB, B-16.9, R= 3 D)
3310\\" NB Sch. Std.
34Elbow (Seamless)22½° Elbow (A234 Gr. WPB, B-16.9, R= 3 D)
3510\\" NB Sch. Std.
36Elbow (Seamless)11/½° Elbow (A234 Gr. WPB, B-16.9, R= 3 D)
3710\\" NB Sch. Std.
38Tees (Seamless)Equal Tee/Unequal Tee (A234 Gr. WPB, B16.9)
3910\\" NB x 10\\" NB x 10\\" NB Sch. Std.x Sch. Std.
40Weldolet and SockoletWeldolet (A 234 Gr. WPB, BW)
4110\\" NB x 2\\" NB Sch. Std.
42End Cap
4310\\" Dia Sch. Std.
44Supply and installation of Transition Fittings for 4' CS to 125 mm MDPE pipeline
45Supply & Installation Stud Bolts for Flange Joint (Stud-ASTM A193-Gr-B7, Nut-2H)
46Stud Bolts 5/8’’, 7/8’’
47Supply of Nitrogen Contractor to arrange manifold to connect up to 5 nos. cylinders with regulatorsIn case of liquid nitrogen with tubing/hose & vaporizer, purity certificate
48N2 Cylinders (7 Cub. Meter)
49Hot Tapping & Double StoppleSupply & Service charges for carryout our 10” Double line stopple with permanent bypass line (laid by MNGL) along with in-service welding of for 10”x10”x10”-300# Fully Encircled 3 Way Line stopple Tee, 2” TOR & 4” gas Bag fittings, end caps to pipeline after disconnection (2 locations), protection to installed hot tap equipment (eg chamber, sand filling, PCC etc).
5010”x10”x10”-300# Fully Encircled 3 Way Line stopple Tee, 2” TOR & 4” gas Bag fittings Please Enable Macros to View BoQ information

AI Tender Summary

OUR REF NO 56332807
AUTHORITY Government Departments
TENDER VALUE Ref. Documents
LAST DATE 20-07-2026
Authority
Authority Name Maharashtra Natural Gas Ltd
Work Description Tender for Tender For Rerouting Of Steel Pipeline (Hot Tapping And Double Stopple Method) And Mdpe Pipeline At Pune Ga
Basic Detail
Tender No MNGL/CP/2026-27/62
Bidding Type Tender
Location
City Pune
State Maharashtra
Key Dates
Publish Date 06 Jul 2026
Submission Date 20 Jul 2026
Open Date 21 Jul 2026
Finance
Tender Value Ref. Documents
Tender Fee Ref. Documents
EMD 2 Lakhs
Exemption Available
Document List
4583c43b-329d-474d-806b-d2fe2424518f.html
BOQ_330348.xls
Drawings.pdf
HotTappingDrawing.pdf
Tender62.pdf
Tendernotice_1 (2).pdf

Unlock Full AI Tender Summary

Get instant access to the complete AI-generated analysis — scope, eligibility, timeline & more.

Instant Access Secure Free
Your details are secure and used only for document delivery.

Tender Timeline

Jul 06, 2026
11:30 IST

Tender Published

Tender notice published.

Completed
Jul 20, 2026
17:00 IST

Bid Submission Deadline

Online submission via eProcurement portal.

Upcoming · 9 days
Jul 21, 2026

Bid Opening Date

Technical bids will be opened and evaluated.

Upcoming · 10 days

Tender Documents

Download All (ZIP) ↓
html

4583c43b-329d-474d-806b-d2fe2424518f.html

xls

BOQ_330348.xls

pdf

Drawings.pdf

pdf

HotTappingDrawing.pdf

pdf

Tender62.pdf

pdf

Tendernotice_1 (2).pdf

Disclaimer

We takes all possible care for accurate & authentic tender information. However users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender

TenderDetail
Loading tenders