Tender For Construction Of Lilo Of 400 Kv Hindaun-Chhabra Tps Line (Twin Moose) At Proposed 400 Kv Gss Sawai Madhopur= Length 22.0 Km Approx.
Tender Value
84.72 Crore
Estimated cost
Bid Submission
05 Aug 2026
22 days left
EMD
1.69 Crore
Bank guarantee accepted
Document Fee
23600
Non-refundable
Tender Type
Online
Tender Overview
Organization
Tender ID
Competition Type
NCB
Bidding Type
Tender
Location / State
Jaipur → Rajasthan
EMD Exemption
Not Available
Quantity
Not Available
Website
Contact Person
Address
Project Description
Tender for Construction Of Lilo Of 400 Kv Hindaun-Chhabra Tps Line (Twin Moose) At Proposed 400 Kv Gss Sawai Madhopur= Length 22.0 Km Approx.
BOQ
| Sl. No. | Item Description |
| 1 | Tower: Fabrication, galvanising and supply of various types of towers (including special towers), & its body / leg (equal & unequal) extensions (complete) including stubs and hangers, D-shackles, Bird Guard, U-Bolt, Pack washer, Anticlimbing devices etc. |
| 2 | High Tensile Steel |
| 3 | Mild Steel |
| 4 | Supply of Bolts & Nuts for towers and stubs (including step bolts & nuts, anti theft bolts & nuts and Spring Washers Etc. ) |
| 5 | River Crossing Tower: Fabrication, galvenizing and supply of special river crossing tower parts including stub/ base plate, anchor bolt, platforms, ladders, hangers, D-Schakles, gusset plates, pack plates & pack washers excluding bolts & nuts |
| 6 | High Tensile Steel |
| 7 | Mild Steel |
| 8 | Supply of bolts & nuts including step bolts and spring washers etc. |
| 9 | Hexagonal Bolts and Nuts for towers |
| 10 | Supply of Earthing material of Towers |
| 11 | Pipe Type |
| 12 | Counterpoise Type |
| 13 | Supply of following Tower Accessories |
| 14 | Danger Plate |
| 15 | Number Plate |
| 16 | Phase Plate (Set of three) |
| 17 | Circuit Plate |
| 18 | Anti Climbing Device (Fork Type) |
| 19 | Supply of following items for Aviation Requirements |
| 20 | Span Marker |
| 21 | Obstruction lights(To be proved as per IS:5613) |
| 22 | a) 1 Medium + 2 Low intensity |
| 23 | Design, manufacture and supply of following line material. ***11/kv 120KN |
| 24 | i) Disc Insulators, or |
| 25 | ii) Long Rod Insulators, or |
| 26 | iii) Composite Long Rod Insulators |
| 27 | Design, manufacture and supply of following line material. ***11/kv 160KN |
| 28 | i) Disc Insulators, or |
| 29 | ii) Long Rod Insulators, or |
| 30 | iii) Composite Long Rod Insulators |
| 31 | Hardware Fittings |
| 32 | Single 'I' suspension H/W fittings armour grip type complete set suitable for Twin ACSR Moose conductor (suitable for 1x23, 120 KN Disc Insulators or 1x1 Long Rod Insulators or 1x1 Composite Long Rod Insulator). |
| 33 | Single suspension H/W fittings conventional envelop type complete set suitable for Twin ACSR Moose conductor for pilot string (suitable for 1x23, 120 KN Disc Insulators or 1x1 Long Rod Insulators or 1x1 Composite Long Rod Insulator). |
| 34 | Double 'I' suspension H/W fittings armour grip type complete set suitable for Twin ACSR Moose conductor (suitable for 2x23, 120 KN Disc Insulators or 2x3 Long Rod Insulators or 2x3 Composite Long Rod Insulator). |
| 35 | Double tension H/W fittings compression type for Twin ACSR Moose conductor (suitable for 2x24, 160 KN Disc Insulators or 2x3 Long Rod Insulators or 2x3 Composite Long Rod Insulator). |
| 36 | ACSR Moose Conductor |
| 37 | Accessories for ACSR Moose Conductor |
| 38 | Mid Span Compression Joint for ACSR Moose conductor |
| 39 | Repair Sleeve for ACSR Moose conductor |
| 40 | Vibration dampers for Twin ACSR 'MOOSE' conductor |
| 41 | Line spacers with retaining rod for Twin ACSR Moose conductor |
| 42 | Rigid Spacer for jumper for Twin ACSR Moose Conductor |
| 43 | GSS Earthwire- size 7/3.66 mm |
| 44 | Accessories for Earthwire |
| 45 | Vibration Damper for 7/3.66 mm GS Earthwire |
| 46 | Mid Span Compression Joint for 7/3.66 mm GS Earthwire |
| 47 | Repair Sleeve for 7/3.66 mm GS Earthwire |
| 48 | Suspension Clamp with flexible Copper Bond for 7/3.66 mm GS Earthwire |
| 49 | Tension Clamp with flexible Copper Bond for 7/3.66 mm GS Earthwire |
| 50 | Power Connector |
| 51 | Counter Weight |
| 52 | OPGW Cable |
| 53 | 48 Fibre (DWSM) OPGW fibre optic cable |
| 54 | Installation Hardware set for 48 Fibre OPGW Fibre Optic cabling including all cable fittings & accessories except joint box** |
| 55 | Joint box (48 Fibre) |
| 56 | Any Other item required for successful completion of work |
| 57 | Note: * Quantity indicated is for evaluation purpose. Actual quantity to be supplied after getting approval. **One set of installation hardware shall contain all installation hardware fittings as may be required for 1 km of OPGW. ** Bidder will quote either for Disc or Long Rod or Composite Long Rod Insulator. In case of bidder quote for more than one types of insulators, then in evaluation, highest cost of insulators will be considered. |
| 58 | Detailed Survey, including route alignment, profiling, tower optimization & spotting, check survey and Geotechnical Investigations etc. |
| 59 | Land Identification and compensation |
| 60 | For Scope of work as specified at Item No. a (i to iv) in Annexure-A (enclosed). |
| 61 | For Scope of work as specified at Item No. b (i to iv) in Annexure-A (enclosed). |
| 62 | Setting of Stub excluding cost of excavation and concreting but including back filling. |
| 63 | (A) 400 kV D/C Towers. |
| 64 | a) Tangent Tower TTA |
| 65 | b) Small Angle Tension Tower TTB |
| 66 | c) Medium Angle Tension Tower TTC |
| 67 | d) Large Angle Tension Tower TTD |
| 68 | e) Special/ River Crossing Tower |
| 69 | Excavation excluding back filling, including shoring, shuttering, De-watering etc. for |
| 70 | a) Normal Dry |
| 71 | b) Wet/Sandy soil |
| 72 | c) Soft/disintegrated rock |
| 73 | d) Hard rock (blasting prohibited) |
| 74 | e) Hard soil/ Soil mixed with boulders |
| 75 | f) Wet Black Cotton Soil |
| 76 | Excavation for benching and transportation of soil at a suitable place |
| 77 | a) Normal Dry |
| 78 | b) Wet/Sandy soil |
| 79 | c) Soft/disintegrated rock |
| 80 | d) Hard rock (blasting prohibited) |
| 81 | e) Hard soil/ Soil mixed with boulders |
| 82 | f) Wet Black Cotton Soil |
| 83 | De-watering of pits during concerting |
| 84 | a) Manual |
| 85 | b) Mechanical pump |
| 86 | c) Power driven pump |
| 87 | Rock anchors as necessary including cost of drilling holes in rock, grouting reinforcement dowel bars etc. (complete including bottom plugging with contractor’s material as per approved drawings and specification. |
| 88 | Cement Concrete M-20 (1:1.5:3) |
| 89 | Providing and laying cement Concrete M-20 grade (1:1.5:3) with single sized aggregate of nominal size 20 mm including preparing surfaces, shuttering mixing, placing, temping curing and finishing with leads and lifts etc as per specification and drawings. |
| 90 | Cement Concrete M-10 (1:3:6) |
| 91 | Providing and laying cement Concrete M-10 grade (1:3:6) with single sized aggregate of nominal size 20 mm including preparing surfaces, shuttering mixing, placing, temping curing and finishing with leads and lifts etc as per specification and drawings. |
| 92 | Steel Reinforcement |
| 93 | Supply, Cutting, Bending, binding, welding of joints if required, fixing and placing of steel reinforcement of Fe 500 grade as per specification and drawings. |
| 94 | Erection of all types of super structures towers, their extensions and special/river crossing towers etc. with its bolts, nuts and washers and bird guard etc. |
| 95 | Erection of Tower Accessories |
| 96 | a) Erection of Anti-climbing devices |
| 97 | b) Fixing of Danger plate, Circuit Plates, Number plate and Phase plates etc. |
| 98 | Conductor Stringing |
| 99 | Mounting of insulators and stringing of six numbers twin bundle ACSR Moose conductor including laying, jointing, tensioning, sagging, clamping and fixing of all line accessories etc. |
| 100 | Earthwire Stringing |
| 101 | Stringing of one number 7/3.66 mm galvanised steel wire including laying, jointing, tensioning etc. |
| 102 | Earthing of Transmission line Towers |
| 103 | a) By pipe type earthing sets, excluding cost of all materials. |
| 104 | a) By counterpoise earthing sets, excluding cost of all materials. |
| 105 | Cement Concrete M-15 (1:2:4) |
| 106 | Rates for Providing and laying cement concrete M-15 grade 1:2:4 with single sized aggregate of nominal size 20 mm including preparing surfaces, shuttering mixing, placing, temping curing and finishing with leads and lifts etc. as per specification and drawings. |
| 107 | Rates for Dry stone revetment (including excavation back filling and levelling) |
| 108 | Rates for Random stone masonary with cement sand mortar with (1:6) (including cement & back filling and levelling) by surplus excavation earth including pointing (flush and ruled type) with cement sand mortar 1:3 |
| 109 | Random rubble dry stone pitching including preparing surface etc. complete with raised & cut pointing in cement sand mortar 1:3 , curing etc. |
| 110 | Cement concrete coping grade 1:2:4 ( 1 Cement :2 coarse sand :4 graded stone aggregate ) rounding off edges etc. but excluding the cost of nosing of steps etc. complete for 75 mm thick with 20 mm thick nominal size aggregate |
| 111 | Rates for Back filling and levelling of the volumes enclosed by the revetment walls with excavated earth at locations. |
| 112 | Rates for Back-filling with borrowed earth |
| 113 | i) Beyond 50 m upto 100 m |
| 114 | ii) Beyond 100 m |
| 115 | Tack welding of Bolts & Nuts up to bottom cross arm of the tower |
| 116 | Erection, testing and commissioning of Aviation Warning Light System in accordance with IS-5613, with one medium and two low intensity aviation warning lights. |
| 117 | Erection of globules (Day marking sphere) 600 mm dia conforming to the latest ICAO regulations suitable for clamping on stranded steel earthwire alongwith the clamp etc. complete in all respect. |
| 118 | Painting of tower above 45m from ground level for Aviation purpose |
| 119 | OPGW Cable and Accessories |
| 120 | Stringing of 48 Fibre (DWSM) OPGW fibre optic cable |
| 121 | Installation Hardware set for 48 Fibre OPGW Fibre Optic cabling including all cable fittings & accessories except joint box** |
| 122 | Joint box (48 Fibre) |
| 123 | Mounting of insulators and stringing of six Nos. twin bundle ACSR Moose conductor including laying, jointing, tensioning. Sagging, clamping and fixing of all line accessories and incuding Stringing of 48 Fibre (DWSM) OPGW fibre optic cable & one Nos. 7/3.66 mm galvanised steel wire including laying, jointing. tensioning etc. for RIVER CROSSING |
| 124 | PILE FOUNDATION |
| 125 | Detailed soil investigation for river crossing/pile foundation upto 40 mtr depth |
| 126 | River Crossing Foundation (4 nos foundations for RIVER CROSSING Towers) |
| 127 | Pile FoundationDesign, Boring, Providing and installation of bored Cast-in-situ RCC vertical piles of specified diameter and of any length below the pile cap with M25 grade of cement concrete excluding the cost of supply & placing the reinforcement steel but including the cost of boring with temporary guide casing, bentonite solution and the length of pile to be embeded in the pile cap (length of pile cap for payment shall be measured from bottom of pile cap), all necessary labour, materials, plants, tools & tackles etc complete as necessary for proper execution of the job.(Boring in weathered rock, shale, fissured rock and soft rock excluded) |
| 128 | a) 1200 mm diameter RCC vertical bored pile from bottom of pile cap |
| 129 | b) Extra over item a) for boring including socketing, anchoring (if required) with required size , nos & depth of Reinforcement in weathered rock, shale,fissured rock soft rock and hard rock upto a maximum depth of 5.0m.tr depth |
| 130 | a) Supply & placing of steel reinforcement of FE 500 grade grade for RCC work in pile, pile cap, pedestal/chimney including straighting, cutting, bending, binding etc all complete incleuding placement upto 28 m depth and 5 meter height in chimney |
| 131 | b) Supply & placing of 8MM Thick Liner |
| 132 | a) Providing and laying in position M25 Grade concrete of specified 28 days strength for pile cap, pedestal/chimney,(including special arrangement like shoring shuttering and huge form work) & excavation. |
| 133 | b) Lean Concrete M15 using 40MM Coarse Aggregate |
| 134 | Conducting Integraty Test on piles using electronic control unit, hand held hammer, accelerometer, computer with required software to assess as-installed pile characteristics including mobilisation of necessary manpower, equipment, materials etc required |
| 135 | Any Other item required for successful completion of work |
| 136 | Note: * Quantity indicated is for evaluation purpose. Actual quantity to be supplied after getting aproval.**One set of installation hardware shall contain all installation hardware fittings as may be required for 1 km of OPGW/Approach Fibre Optic cable. |
| 137 | Tower: Fabrication, galvanising and supply of various types of towers (including special towers), & its body / leg (equal & unequal) extensions (complete) including stubs and hangers, D-shackles, Bird Guard, U-Bolt, Pack washer, Anticlimbing devices etc. |
| 138 | High Tensile Steel |
| 139 | Mild Steel |
| 140 | Supply of Bolts & Nuts for towers and stubs (including step bolts & nuts and anti theft bolts & nuts, Spring Washers Etc. ) |
| 141 | Supply of Earthing material of Towers |
| 142 | Pipe Type |
| 143 | Counterpoise Type |
| 144 | Supply of following Tower Accessories |
| 145 | Danger Plate |
| 146 | Number Plate |
| 147 | Phase Plate (Set of three) |
| 148 | Circuit Plate |
| 149 | Design, manufacture and supply of following line material. **11/ kV 70KN |
| 150 | i) Disc Insulators or |
| 151 | ii) Long Rod Insulators |
| 152 | Design, manufacture and supply of following line material. **11/ kV 120KN |
| 153 | i) Disc Insulators or |
| 154 | ii) Long Rod Insulators |
| 155 | Hardware Fittings for ACSR Zebra Conductor |
| 156 | Single Suspension H/W fittings for ACSR Zebra Conductor |
| 157 | Single Tension H/W fittings for ACSR Zebra Conductor |
| 158 | Double Suspension H/W fittings for ACSR Zebra Conductor |
| 159 | Double Tension H/W fittings for ACSR Zebra Conductor |
| 160 | ACSR Zebra Conductor (54/ 3.18 mm AL+7/ 3.18 mm Steel) |
| 161 | Accessories for ACSR Zebra Conductor |
| 162 | Mid Span Compression Joint for ACSR Zebra Conductor |
| 163 | Repair Sleeve for ACSR Zebra Conductor |
| 164 | Preformed Armour Rod for ACSR Zebra Conductor |
| 165 | Vibration Damper for ACSR Zebra Conductor |
| 166 | OPGW Cable |
| 167 | 48 Fibre (DWSM) OPGW fibre optic cable |
| 168 | Installation Hardware set for 48 Fibre OPGW Fibre Optic cabling including all cable fittings & accessories except joint box** |
| 169 | Joint Box (48 Fibre) |
| 170 | Any Other item required for successful completion of work |
| 171 | Note: * Quantity indicated is for evaluation purpose. Actual quantity to be supplied after getting approval. **One set of installation hardware shall contain all installation hardware fittings as may be required for 1 km of OPGW.** Bidder will quote either for Disc or Long Rod Insulator. In case of bidder quote for more than one types of insulators, then in evaluation highest cost of insulators will be considered. |
| 172 | DETAIL SURVEY AS PER TENTATIVE ROUTE- Which includes the following major activities-Pegging of line route, providing of survey pillar at an interval of 3-4 KM in the line route with required jungle clearance for survey, profile preparation of approved route on graph sheet and marking of offset on either side of line, marking of side clearance for hills, sand dunes etc, as per specification and tower scheduling. |
| 173 | Check survey as per approved route of line which includes-Re-checking of the line route as per approved profile, chainage, tower center marking, pit marking, bisection of angle tower as required at site. |
| 174 | Land Identification and compensation |
| 175 | For Scope of work as specified at Item No. a (i to iv) in Annexure-A (enclosed). |
| 176 | For Scope of work as specified at Item No. b (i to iv) in Annexure-A (enclosed). |
| 177 | Excavation-Excavation, excluding back filling, including shoring,shuttering, dewatering, etc. upto the required depth as per foundation specification/drawings. |
| 178 | (i) Any soil, soft rock other than hard rock |
| 179 | (ii) Hard Rock (with blasting subject to permission or without blasting) |
| 180 | SETTING OF TEMPLATE & STUB/ANCHOR BOLT:-Setting of template & stub/ anchor bolt & removal after concreting, excluding cost of excavation and concreting but including back filling with excavated/ borrowed earth (with lead & lift) in layers with ramming andwatering as per specification. |
| 181 | Tower including extension upto 9 Meter |
| 182 | Special towers for any span including extension |
| 183 | CONCRETING: Providing and laying cement concrete for all types of foundation as per latest ISS:456 including cement, sand, stone aggregate 20mm nominal size,water etc., preparing surfaces, shuttering, mixing, placing, ramming, curing, finishing as per specification and drawings. |
| 184 | 1:3:6 Mix (M-10) |
| 185 | 1:2:4 Mix (M -15) |
| 186 | 1:1.5:3 Mix (M -20) |
| 187 | Steel Reinforcement |
| 188 | Supply, Cutting, bending, welding of joints if required,fixing and placing of steel reinforcement as per specification and drawings including material. |
| 189 | EARTHING: |
| 190 | Earthing of towers with pipe type earthing excluding the supply of pipes, wires, flats &connectors, but including coke/charcoal, etc.,excavation,augering and backfilling in all types of soil. |
| 191 | Earthing of towers legs with counterpoise typeearthings excluding supply of materialsbut including excavation and backfilling in all types of soil.(i) Each set by laying 4 wires each 15m long at a depth of 600 mm |
| 192 | ERECTION OF TOWERS: Erection of super structures including D-shackles,ACD, Hangers, U-Bolts, step bolts, danger plate, phase plate, number plate etc. Also including tack welding of bolts & nuts upto bottom cross arm/beam level including application of Zinc Rich paint |
| 193 | (i) Erection of tower (with extension upto 9 Meters) |
| 194 | (ii) Erection of special towers(with extensions) |
| 195 | CONDUCTOR STRINGING: Stringing of ACSR Zebra including hoisting of insulator string, laying, jointing & tensioning of conductor, clamping with Armour rods and fixing of vibration damper per route KM of the line. |
| 196 | (i) Single Conductor |
| 197 | (ii) Single Conductor for River Crossing |
| 198 | REVETMENT OF TOWERS |
| 199 | Providing & laying cement concrete including curing compaction etc. complete using stone aggregate 40 mm nominal size (Crusher broken) in foundation plinth using 1 cement : 5 sand : 10 Aggregate mix |
| 200 | Random rubble stone massonary for rivetment in 1:5 cement sand mortat including providing and fixing 100 mm dia PCC drain pipe and raised and cut pointing on stone masonary in 1:3 cement sand mortar excluding excavation but including Back filling inside rivetment using excavated/ borrowed earth (with all lead & lift) in layers not exceeding 20cm in depth & consolidating each depositing layer by ramming and watering. |
| 201 | Random rubble dry stone pitching including preparing surface etc. complete with raised & cut pointing in cement sand mortar 1:3, curing etc. |
| 202 | Cement concrete coping grade 1:2:4(1cement:2coarse sand :4 graded stone aggregate) rounding off edges etc. but excluding the cost of nosing of steps etc. complete for 75 mm thick with 20mm thick nominal size aggregate |
| 203 | Brick masonary in foundation & plinth with bricks of class designation 75 in cement mortar 1:5 (1 cement: 5 coarse sand) |
| 204 | Brick on edge flooring with bricks of class designation 75 including pointing in cement mortar (l:3) complete laid on 12mm thick bed of cement sand mortar 1:6. |
| 205 | STRINGING OF 48 FIBRE (DWSM) OPGW FIBRE OPTIC CABLE |
| 206 | Stringing of 48 Fibre (DWSM) OPGW fibre optic cable |
| 207 | Installation Hardware set for 48 Fibre OPGW Fibre Optic cabling including all cable fittings & accessories except joint box |
| 208 | Joint box (48 Fibre) |
| 209 | Any Other item required for successful completion of work |
| 210 | Note: * Quantity indicated is for evaluation purpose. Actual quantity to be supplied after getting aproval. Please Enable Macros to View BoQ information |
AI Tender Summary
Tender Timeline
Jul 06, 2026
11:30 IST
Tender Published
Tender notice published.
CompletedAug 05, 2026
17:00 IST
Bid Submission Deadline
Online submission via eProcurement portal.
Upcoming · 22 daysAug 06, 2026
Bid Opening Date
Technical bids will be opened and evaluated.