Tender For Consultancy Services For Preparation Of detail project report And Project Management Upto Completion Of Entire Project Reconstruction Of Naval Hospital (Inhs Jeevanti) At Vasco-Da-Gama, Goa
Tender Value
1.19 Crore
Estimated cost
Bid Submission
30 Jul 2026
21 days left
EMD
1.94 Lakhs
Bank guarantee accepted
Document Fee
1000
Non-refundable
Tender Type
Online
Tender Overview
Organization
Tender ID
Competition Type
NCB
Bidding Type
Tender
Location / State
goa → Goa
EMD Exemption
Available
Quantity
Not Available
Website
Contact Person
Address
Project Description
Tender for Consultancy Services For Preparation Of detail project report And Project Management Upto Completion Of Entire Project Reconstruction Of Naval Hospital (Inhs Jeevanti) At Vasco-Da-Gama, Goa
BOQ
| Sl. No. | Item Description |
| 1 | Providing comprehensive Design and Consultancy Services for Reconstruction of Naval Hospital (INHS JEEVANTI) at Vasco-da-gama, Goa. comprising 79 Bedded hospital with all wards and facility in G+3 or G+4 configuration buildings, including preparation of all architectural, structural and services drawings, detailed estimates, and GRIHA compliance documentation, complete in all respects. The building shall be well planned, designed and detailes as per latest norms, energy efficient, ensuring functionality, safety, economy and modern aesthetics, as the facility if already existing for external sevices integration of such facilities and upgradation to new facility is also to consider, all as per the directions of GE/AGE/CENM/E-in-Cs and NHQ complete all as specified and as directed. |
| 2 | Phase- I (Pre Construction stage) |
| 3 | Surveys and Studies: -Carrying out detailed topographical /contour survey plan including the Marking of contours at every 3 mtrs of intervals on site etc and all ground visible features like building, roads, drain, trees, Electrical poles and other similar permanent features over the different location/areas complete in all respect. The survey to be done by using Electronic Total Station digital instrument or by drone.The consultant shall prepare detailed level sheet and contour plans of the proposed building footprint to be superimposed on the survey showing proposed Plinth level, Floor finish level nearest RL, drain levels, spot levels, and benchmarking details required for design and execution. Preparation of survey drawing and calculation of survey/plot area with traingulation method on computer using Auto CAD or other suitable software including supply of CD and three sets of drawing of appropriate size, preferably on A-1 size complete as per terms and conditions and as directed by Engineer-in-Charge. Architecture consultancy containing Preparation of Concept Plan, Master Plan, and Preliminary Architectural Layouts plans conceptual drawings such as sketch, P&Q of married accomodation,Preparation of site plan, floor plans, elevations and sections, modern front elevation, |
| 4 | Soil Investigation: - Mobilization and demobilization of personnel, tools, and equipment required for the execution of the work, including lodging and boarding expenses, will be carried out. Soil investigation will be conducted in accordance with IS:1892-2021, using manual, hydraulic, or Calyx rotary drilling methods with 50–150 mm diameter, employing casing pipes or bentonite slurry where necessary to support collapsible strata below the water table. 5 nos of Boreholes will be drilled using pot holes or helical augers in all types of soil up to a depth of 15 m, and in soft to hard rock up to the depth of refusal (N > 50), except in soft soil or boulder zones. Standard Penetration Tests (SPT) will be performed and undisturbed samples (UDS) collected at regular intervals. A comprehensive Soil Bearing Capacity (SBC) report will be prepared and submitted, including analytical and graphical representation, detailed calculations, and recommendations on foundation type and design in accordance with codal provisions. The report will be reviewed and vetted by IIT/NIT experts prior to final submission. |
| 5 | Demolition Planning:-Comprehensive assessment, and planning services to ensure safe, compliant, and efficient execution of the demolition. Carry out a detailed reconnaissance survey and preliminary documentation of the existing site, including review of available architectural, structural, and service drawings, and identification of hazardous materials and utilities such as water supply, sewerage, electrical systems, STP, ETP, DG sets, and HVAC networks. Plan safe demolition sequencing, identifying structures requiring special handling such as underground tanks, basements, or adjoining operational facilities. Based on these assessments, a detailed demolition plan shall be prepared, outlining methodology, phasing, and safety measures, and recommending appropriate demolition techniques, manual, mechanical, or hybrid, depending on site conditions. The scope further includes advising on statutory clearances, preparing a Safety, Health, and Environment Plan, and ensuring compliance with the Demolition Waste Management Rules, 2016 (as amended) as well aspreparation of estimates for demolition and safe disposal of waste. |
| 6 | Concept Design: -1. Requirement Analysis, spatial and functional requirements formulation2. Zoning, ciruculation pattens, movement patterns, key activity zones design3. Conceptual Design Development- Max. of 2 Concepts using 2D and 3D visualization.4. Area Program and compliance alignment in accordance with applicable design principles5. Preparation of Conceptual Plans including master plan and schematic plan of all floors.(Sketch P & Q). This stage will also include preparation of proposed preliminary Schedule of Finishes and Preliminary Block Estimates. 6. BIM(Building information Model) with LOD 350 and clash detection and resolution should be done for architechtural, structural. MEP and other services and should be prepared and presented to HQ CE (navy) Mumbai before finalisaton of DPR. |
| 7 | 7.Building plan, and layout of external services (water supply, drainage, electrical, road network, including unit plan 2D and 3D render of major bldgs and master plan 3D bird view as per scaling A2 size, conceptual drawing prepare as per authorisation of army hospital , NBC norms, Architectural Norms/ Bye-Laws. The conceptual and detailed drawings shall be submitted in duplicate hard copies for approval of User INHS Jeevanti, Vasco and HQ CE (Navy) Mumbai (secions E2 (plg), E2(des), E4, E6, E3,& E8). Presentation to User/HQ CE/E-in-Cs br/NHQ and obtaining approval at all stage shall be the responsibility of the consultant. .Preparation of complete conceptual plans, architectural drawings (Elevation, Sections and Schedule of finishes), Site Plan including 3D views (interior & exterior). The drawings will cover detailed working drawings to minutest details (including all furnitures, plumbing,sanitary fittings, hospital equipments) with reference to technical, architectural, and functional requirements in soft & hard copy. Space/Area analysis in tabular graphical formats. |
| 8 | Preparation of Accommodation Statement & Approximate Estimate:- Consultant has to prepare of the Accommodation Statement (Part-II) as per SoA for hospitals and user requirements and consultation with GE(P)Vasco and CENM. |
| 9 | Detailed Project Report: -B/R Services1. Site Plan and Landscape Design inclusing roads, paths, culverts, and all site services. 2. Architectural Design including Plans, Elevations, Sections, Site Plan including 3D rendered views (interior & exterior). The consultant shall prepare and submit detailed 3D architectural day and night models (scale not exceeding 1:100) 3. Building & Site Services Design including, calculations, Sewage and Wastewater Management, Storm Water Drawinage, Soild and Biomedical Waste Management, MGPS, Plumbing, Specialised Hospital Systems, BMS, Roads, Pavements, Parkings, Retaining walls, Boundary walls etc. and approval of all services and NHQ). 4. Providing comprehensive Structural Design & Consultancy Services including analysis, design, preparation of detailed structural drawings, proof checking, and vetting forReconstruction of Naval Hospital (INHS JEEVANTI), complete in all respects Scope of Work:(A) Structural Design & AnalysisStructural analysis and design of buildings using approved software (ETAB-23 and SAFE).Design of RCC framed structure with suitable grade of concrete.The Structural system shall comply with latest relevant IS codes and incorporating results of Soil Investigation of site. The methodology shall be FEA analysis with the help of Computer Aided Software. To simulate the structure so as to get accurate behaviour, the structure shall be modelled in ETABS-23 and above for Ultimate Limit State (ULS) as well as Serviceability Limit State (SLS). The floor slabs be modelled in accordance with flexibility as applicable with a break in the diaphragm where cut-outs are planned. Shear Walls wherever considered shall be modelled as shell elements and designed to resist Earthquake effect and Wind loads and designed as ductile shear wall. The frames/shear walls in either direction be designed considering various codal combinations of Dead load, Live load and Earthquake/Wind loads. Live loads and unit weights shall be used for analysis as per latest IS Codes. The building be checked for serviceability for both cracked and un-cracked sections as per codes IS 1893 and IS 16700. |
| 10 | (B) Preparation of DrawingsPreparation of detailed structural CAD drawings including:Foundation layoutColumn, beam and slab detailsStaircase and structural componentsReinforcement detailing (RCC)Incorporation of all design details required for execution.Detailed structural analysis and design should be submitted of CENM for proof checking before submitting to IIT for vetting as per NBC, IS codes and Scales of Hospital. (C) Submission of Design DataSubmission of:Approved structural drawings (all sizes)Design calculations and analysis reportsETABS and SAFE files (soft copy)Submission in hard & soft copies as per Engineer-in-Charge requirements. |
| 11 | (D) Proof Checking & VettingThe results of computer model analysis shall be discussed with E2 (Design) Section of HQ CE (Navy) Mumbai at various stages till reaching to a final detailed design. The documents and models shall be processed for vetting to IITs after clearance from HQ CE (Navy) Mumbai.Incorporation of observations (if any) and final approval of structural design.(E) Codes & StandardsAll designs shall conform to: Latest Indian Standard (IS) Codes Relevant NBC provisions Good engineering practices5. DPR Preparation.6. Preparation of BoQ and Estimates 7. DPR will get approved from CENM/E-in-Cs br/NHQE/M Services1. The scope of work of the consultancy services for E/M work shall be comparising of the designing of the following services as per the authorization provided in the scale of the Armed Force Hospitals-2003A. Electrical and mechanical system1. Electrical:-1.1 Lighting (general & individual)1.2 Night lighting1.3 Shadow less light |
| 12 | 14 Light & power sockets1.5 Call bells1.6 Emergency light1.7 Voltage stabilizers1.8 Stand by generators1.9 Lightning protection1.10 Red-green bulb indicators1.11 UPS1.12 Information Technology System1.13 Automatic Hand dryers1.14 Automatic soap dispenser1.15 Electronic call system in OPD1.16 Sign posts for all wards/depts./centres incl day and night signs and patient Guidance system1.17 Designing of External Electric Supply system from identified Tapping point2. Ventilation:-2.1 Ceiling fans2.2 Pedestal fans2.3 Exhaust fans3. Water Supply:-3.1 Designing of External water supply & tapping point (checking of water availability from existing sources or to enhance)3.2 Hot water supply through geyser system3.3 Filtered/ soft water supply3.4 Potable Localised water purification system |
| 13 | 4. GRIHA Compliance:-4.1 Roof top solar4.2 EV charging5.Refrigeration:-5.1 Refrigerators5.2 Deep freezers5.3 Walk in coolers5.4 Water coolers6. Air conditioning (Air Cooling & Air heating):-6.1 Air cooling6.2 Air heating6.3 HV/AC System7. Gas supply:-7.1 Medicinal gas (Oxygen and Nitrous Oxide)7.2 Cooking gas7.3 Laboratory gas74 Central suction system7.5. Compressed air7.6 Central gas lines to all wardsB. Traction & communication system1. Ramp2. Lifts3 Telephone & intercom4. Nurse/doctor call cum sound & video system5 Public address system |
| 14 | C. Fire Protection System1. Safety against fire2. First aid fire equipments3. Fire alarm4. Fire detector system5. Fire fighting & Fire suppression systemD. Waster Disposal System by IncineratorE. Laundry EquipmentsF. Sewage Treatment Plant with treated water supplyG. Project Delieverable(i) Electric load calculation, AC load calculation, water supply requirement calculation and all other calculation necessitated for this project.(ii) Complete design including preparation of specifications, BOQ & draft tender.(iii) All the drawings shall be submitted in Autocad/Revit MEP format with 3D modelling.(iv) Coordination drawings to be submitted in BIM/(Row 350)(v) All the design data shall be provided alongwith the detailed project report in hard & soft copies.Note:- Consultancy to check the servicebality condition of existing E/M assets such as DG,Transformer, VCB, Central AC plant, STP, Lift and other equipments as per policy and integrate the same in the scope of work. |
| 15 | H. Applicable standardised services shall be designed in accordance with the provision made under following:-(i) Scales of Accomodation for Armed forces Hospitals - 2003 (or latest at the time of bid submission end date)(ii) NABH Accredition standard for Hospitals (latest Edition)(iii) MES/CPWD specification(iv) SSR/Delhi schedule of rates (Latest)2 All above defined scopes and project details shall be considered in preparing the consultancy report for the project. However, applicable standards, codes, Hospital scales statutory provisions and Medical infrastructure requirements etc shall be referred to independently without limitation to the above scope3 All schedules shall be prepared accordingly and pricing shall be based on DSR/SSR. |
| 16 | 3 D Visualization:- The scope of 3D visualization includes developing high-quality 3D views and a walkthrough video of approved interior and exterior designs based on final approved concept drawings and client-approved finishes. The objective is to provide an accurate representation of the proposed built environment to support stakeholder approvals. 3D views will cover all key spaces, such as lobbies, OPDs, wards, OTs, ICUs, waiting and administrative areas, exterior elevations, landscape zones, and site elements, modeled with realistic proportions, textures and materials as per the approved design intent. A 5 minute full HD walkthrough (1920×1080) will illustrate sequential spatial flow and design articulation with optional background music. Two rounds of client feedback are included for minor adjustments; major revisions beyond approved drawings will be treated as additional scope. Final outputs will be delivered in MP4 format for walkthroughs and high-resolution JPEG/PNG formats for static views. ( Duration Min 3 minutes) |
| 17 | Physical Model:- Preparation of a scaled physical day and night model (not exceeding scale of 1:100) of the proposed hospital complex accurately depicting site layout, building configuration, landscape features,circulation, and spatial relationships for presentations, reviews, and approvals. |
| 18 | GFC Drawing:- Preparation of Good for Construction (GFC) drawings for all disciplines, incorporating design refinements, coordination inputs, and site-specific requirements to ensure clarity and constructability. |
| 19 | Technical Inputs to Tender DocumentationScope of Work:(A) Detailed Estimates Preparation of detailed cost estimates based on approved drawings (Architectural, Structural, E/M, Fire Fighting, and External Services).Measurement and quantity take-off for all items of work.(B) BOQ Preparation Preparation of item-wise Bill of Quantities (BOQ) with:Detailed descriptions Units and quantities BOQ to be aligned with tendering requirements. (C) Rate Analysis Preparation of rate analysis for all non-schedule and major items based on:Prevailing market ratesLabour and material inputs(D) Schedule of Rates (SOR) ComplianceEstimates to be based on: SSR 2020 / DSR (latest applicable)Standard Schedule of Rates and norms(E) Yardstick Preparation :Preparation of yardsticks for all the buildings as per the approved architectural and structural drawings as per SSR 2020 or DSR (latest applicable) for cost comparison and benchmarking of similar works.(F) Market Analysis:Conducting market survey and analysis for validation of rates and cost optimization.(G) Draft tender : Draft tender as per relevant IAFW shall be prepared including all the relevant conditions and specifications(H) Estimates, yardstick, Market Analysis and draft tender documents will be duly approved by Dir(C) /E 8 HQ CENM (I) Documentation & Submission :Submission of: Detailed estimate report, BOQ, Rate analysis sheets In hard & soft copies as directed by Engineer-in-Charge |
| 20 | Technical Inputs to Tender Documentation (Contd) Estimates, yardstick, MA and draft tender documents will be duly approved by Dir(C) /E 8 HQ CENM (H) Documentation & Submission :Submission of:Detailed estimate report ,BOQ,Rate analysis sheets In hard & soft copies as directed by Engineer-in-Charge |
| 21 | GRIHA/IGBC CertificationConsultant will prepare and submit report pertains to GRIHA for achieve min GRIHA 3 star rating for the project considering 1.Site Planning & Landscape 2. Energy Efficiency 3. Water Management 4. Solid Waste Management 5. Sustainable Materials |
| 22 | Design (Green Building GRIHA III)The consultant shall ensure the project achieves a minimum 3-Star GRIHA rating, with the quoted consultancy fees being inclusive of all required efforts. The scope of work includes:1. Design and Documentation: Ensure all Architectural, Structural, Firefighting, Landscape and MEP designs, along with their associated BOQs, specifications, material selections and calculations are developed in strict compliance with the latest GRIHA and ECBC guidelines.2. Modeling and Simulations: Conduct whole-building energy modeling, as well as solar and daylighting simulations, as required for certification.3. Tender Incorporation and Approvals: Submit the complete GRIHA report, vetted by a GRIHA consultant for 3-star rating compliance and ensure it is fully approved by various sections of CENM (E6, E2Plg, E2 Design, E4) before incorporation into the draft tender. |
| 23 | Notes: (i) The consultant shall ensure that all Architectural, Structural Design Firefighting and associated engineering designs are planned, developed and coordinate in accordance with the latest GRIHA (Green Rating For Integrated Habitat Assessment) guidelines, so as to enable the project to achieve minimum 3-Star GRIHA rating.(ii) All drawings, specifications, BOQs, material selections, calculations, simulations and related documentation shall be prepared in compliance with the mandatory and requisite optional criteria required for achieving the minimum 3-Star rating and Consultant shall provide draft tender duly incorporated all the Griha Norms specification(iii) The quoted consultancy fees shall be deemed to be inclusive of all efforts required for planning in compliance with GRIHA norms unto 3-Star level complete. |
| 24 | Notes: |
| 25 | 1. Submission details for any missing datafound during execution within reasonable time as directed by accepting officer.. 2.Submission ofaltternate design & drawings in case of any discripancy or change in in plan due to site requirement or any other reasons. 3.Redesigning and submission of complete structural drawing anddetails in case of unsuitable soil and other technical reason without extra cost. 4. The conceptual drawings sall be submited in duplicate ard copies for approval of Users INS Jeevanti and HQ CE (Navy) Mumbai (sessions E2 (plg), E2 (des), E4,E6,E3,E8). Presenation to User/HQ CE and obtaining approval at all stage shall be the responsibility of the cosultant. Preparation of complete conceptual plans architectural drawings (Elevation,Sections and schedule of finishes), Site Plan including 3D views (interior exterior). The drawings will cover detailed working drawings to minutest details (including all furnitures, modular kitchen and plumbing, sanitary fittings) with reference to architectural, and functional requirements in soft & hard copy. Space/Area analysis in tabular graphical formats. |
| 26 | The consultant shall submit |
| 27 | 1.Design Basis Report (DBR)- 3 sets (Soft & hard copy) |
| 28 | 2.Conceptual design drawings 8 sets (Soft & hard copy) |
| 29 | 3.Final approved architectural drawings (Autocad + PDF) 8 sets hard copy |
| 30 | 4.Structural design report and drawings (Autocad +pdf) 8 sets hard and soft copy |
| 31 | 5.Working drawings for execution (8 Sets hard copy) |
| 32 | 6.BOQ-3 sets (Soft & hard copy) |
| 33 | 7.Rate analysis - 3 sets (Soft & hard copy) |
| 34 | 8.Tender documents - (3 sets (Soft & hard copy) |
| 35 | Providing BIM LOD 350 Providing BIM LOD 350 for all disciplines (Architectural, Structural, and MEP) during the execution phase, including generation of Shop Drawings / Good For Construction (GFC) drawings.Architectural & MEP Modelling (Autodesk Revit):- Includes precise modelling of walls, floors, openings, and detailed interfaces between finishing materials and structural elements. Covers clearances for accessibility, maintenance, and comprehensive MEP services integration. MEP includes critical coordination elements such as supports and hangers for piping/ductwork, clearance zones around equipment for maintenance access, and specific routing showing exactly how systems bypass one another at intersection points.Structural Modelling & ETABS Integration:- Includes structural connections, steel plates, and slab/beam penetrations. Features full bi-directional integration with ETABS-23 using the CSIxRevit plugin for structural analysis, allowing dynamic synchronization of elements (like beams and columns) alongside alternative data tracking via IFC, DXF, or DWG formats.Clash Detection & Coordination (Autodesk Navisworks):- Running comprehensive clash detection across all federated models (Architectural, Structural, MEP) to identify, track, and resolve hard, soft, and clearance conflicts prior to site execution.BOQ & Scheduling (MS Project):-Extraction of accurate Bill of Quantities (BOQ) directly from the coordinated Revit models, and generation of the Critical Path Method (CPM) network schedule in MS Project for synchronized project tracking and monitoring. |
| 36 | Deliverables & Submissions:-Provision and handover of all native soft copies of BIM and analysis files (.rvt, .edb, .nwf/.nwd), schedules (.mpp), and converted formats (.dwg, .pdf, .ifc), along with specified hard copies of all generated shop drawings and GFC drawings to the department. |
| 37 | PHASE II (After completion of Work) |
| 38 | Providing necessary tech support during construction stage till completion of work, including issue of clarification on drawings/designs, review of contractor queries, coordination with user/MES/ agencies, checking of working drawings and assistance during testing, commencing and handing over. Please Enable Macros to View BoQ information |
AI Tender Summary
Tender Timeline
Jul 02, 2026
11:30 IST
Tender Published
Tender notice published.
CompletedJul 30, 2026
17:00 IST
Bid Submission Deadline
Online submission via eProcurement portal.
Upcoming · 21 daysAug 01, 2026
Bid Opening Date
Technical bids will be opened and evaluated.
Upcoming · 23 daysTender Documents