Tender For Providing Of Otm Accn For Corps Hq Complex At Sukna Under Ge (P) Siliguri
Tender Value
65.47 Crore
Estimated cost
Bid Submission
22 Jul 2026
13 days left
EMD
15 Lakhs
Bank guarantee accepted
Document Fee
3000
Non-refundable
Tender Type
Online
Tender Overview
Organization
Tender ID
Competition Type
NCB
Bidding Type
Tender
Location / State
siliguri → West Bengal
EMD Exemption
Available
Quantity
Not Available
Website
Contact Person
Address
Project Description
Tender For Providing Of Otm Accn For Corps Hq Complex At Sukna Under Ge (P) Siliguri
BOQ
| Sl. No. | Item Description |
| 1 | BUILDINGS & STRUCTURE (Sch 'A' PART-I) |
| 2 | Lump sum price worked out by the Contractor for “BUILDINGS & STRUCTURE” as listed in Schedule ‘A’ Part-I. Representing ** ___ % ______ percent *Above / Below the lump sum price of Rs. 43,23,70,400.00 inserted by the MES in Schedule ‘A’ Part-I. |
| 3 | EARTHWORK, SITE CLEARANCE AND SITE DEVELOPMENT (Sch 'A' PART-II) |
| 4 | Lump sum price worked out by the Contractor for “EARTHWORK, SITE CLEARANCE AND SITE DEVELOPMENT” as listed in Schedule ‘A’ Part-II. Representing ** ___ % ______ percent *Above / Below the lump sum price of Rs. 38,76,738.25 inserted by the MES in Schedule ‘A’ Part-II. |
| 5 | INTERNAL WATER SUPPLY (Sch 'A' PART-III) |
| 6 | Lump sum price worked out by the Contractor for “INTERNAL WATER SUPPLY” as listed in Schedule ‘A’ Part-III. Representing ** ___ % ______ percent *Above / Below the lump sum price of Rs. 12,22,638.62 inserted by the MES in Schedule ‘A’ Part-III. |
| 7 | INTERNAL ELECTRIFICATION (Sch 'A' PART-IV) |
| 8 | Lump sum price worked out by the Contractor for “(INTERNAL ELECTRIFICATION)” as listed in Schedule ‘A’ Part-IV. Representing ** ___ % ______ percent *Above / Below the lump sum price of Rs. 1,16,86,007.47 inserted by the MES in Schedule ‘A’ Part-IV. |
| 9 | ROAD, PATH, CULVERT & HARDSTANDING (Sch 'A' PART-V) |
| 10 | Lump sum price worked out by the Contractor for “(ROAD, PATH, CULVERT & HARDSTANDING)” as listed in Schedule ‘A’ Part-V. Representing ** ___ % ______ percent *Above / Below the lump sum price of Rs. 1,36,73,773.81 inserted by the MES in Schedule ‘A’ Part-V. |
| 11 | SEWAGE DISPOSAL (Sch 'A' PART-VI) |
| 12 | Lump sum price worked out by the Contractor for “(SEWAGE DISPOSAL)” as listed in Schedule ‘A’ Part-VI. Representing ** ___ % ______ percent *Above / Below the lump sum price of Rs. 18,24,836.95 inserted by the MES in Schedule ‘A’ Part-VI. |
| 13 | AREA DRAINAGE (Sch 'A' Part-VII) |
| 14 | Lump sum price worked out by the Contractor for “(AREA DRAINAGE)” as listed in Schedule ‘A’ Part-VII. Representing ** ___ % ______ percent *Above / Below the lump sum price of Rs. 55,63,845.36 inserted by the MES in Schedule ‘A’ Part-VII. |
| 15 | FALSE CEILING (Sch 'A' Part-VIII) |
| 16 | Lump sum price worked out by the Contractor for “(FALSE CEILING)” as listed in Schedule ‘A’ Part-VIII. Representing ** ___ % ______ percent *Above / Below the lump sum price of Rs. 71,24,306.40 inserted by the MES in Schedule ‘A’ Part-VIII. |
| 17 | SECURITY WALL, FENCING & GATE (Sch 'A' Part-IX) |
| 18 | Lump sum price worked out by the Contractor for “(SECURITY WALL, FENCING & GATE)” as listed in Schedule ‘A’ Part-IX. Representing ** ___ % ______ percent *Above / Below the lump sum price of Rs. 76,17,103.76 inserted by the MES in Schedule ‘A’ Part-IX. |
| 19 | EXTERNAL WATER SUPPLY (Sch 'A' Part-X) |
| 20 | Lump sum price worked out by the Contractor for “(EXTERNAL WATER SUPPLY)” as listed in Schedule ‘A’ Part-X. Representing ** ___ % ______ percent *Above / Below the lump sum price of Rs. 4,94,379.42 inserted by the MES in Schedule ‘A’ Part-X. |
| 21 | EXTERNAL ELECTRIFICATION (Sch 'A' PART-XI) |
| 22 | Lump sum price worked out by the Contractor for “(EXTERNAL ELECTRIFICATION)” as listed in Schedule ‘A’ Part-XI. Representing ** ___ % ______ percent *Above / Below the lump sum price of Rs.65,18,412.94 inserted by the MES in Schedule ‘A’ Part-XI. |
| 23 | FIRE FIGHTING (Sch 'A' Part-XII) |
| 24 | Lump sum price worked out by the Contractor for “(FIRE FIGHTING)” as listed in Schedule ‘A’ Part-XII. Representing ** ___ % ______ percent *Above / Below the lump sum price of Rs. 83,97,629.72 inserted by the MES in Schedule ‘A’ Part-XII. |
| 25 | FIRE ALARM SYSTEM (Sch 'A' Part-XIII) |
| 26 | Lump sum price worked out by the Contractor for “(FIRE ALARM SYSTEM)” as listed in Schedule ‘A’ Part-XIII. Representing ** ___ % ______ percent *Above / Below the lump sum price of Rs. 25,25,089.00 inserted by the MES in Schedule ‘A’ Part-XIII. |
| 27 | CONDUIT FOR TELEPHONE / INTERNET (Sch 'A' Part-XIV) |
| 28 | Lump sum price worked out by the Contractor for “(CONDUIT FOR TELEPHONE / INTERNET)” as listed in Schedule ‘A’ Part-XIV. Representing ** ___ % ______ percent *Above / Below the lump sum price of Rs. 8,09,280.00 inserted by the MES in Schedule ‘A’ Part-XIV. |
| 29 | LIGHTNING PROTECTION (Sch 'A' Part-XV) |
| 30 | Lump sum price worked out by the Contractor for “(LIGHTNING PROTECTION) ” as listed in Schedule ‘A’ Part-XV. Representing ** ___ % ______ percent *Above / Below the lump sum price of Rs. 5,10,689.60 inserted by the MES in Schedule ‘A’ Part-XV. |
| 31 | LIFT (Sch 'A' Part-XVI) |
| 32 | Lump sum price worked out by the Contractor for “(LIFT)” as listed in Schedule ‘A’ Part-XVI. Representing ** ___ % ______ percent *Above / Below the lump sum price of Rs. 1,02,52,510.80 inserted by the MES in Schedule ‘A’ Part-XVI. |
| 33 | AIR CONDITIONING (Sch 'A' Part-XVII) |
| 34 | Lump sum price worked out by the Contractor for “(AIR CONDITIONING)” as listed in Schedule ‘A’ Part-XVII. Representing ** ___ % ______ percent *Above / Below the lump sum price of Rs. 16,82,087.96 inserted by the MES in Schedule ‘A’ Part-XVII. |
| 35 | MISCELLANEOUS ITEMS REQUIRED FOR B/R & E/M SERVICES (Sch 'A' Part-XVIII) Please Enable Macros to View BoQ information |
| 36 | MISCELLANEOUS ITEMS REQUIRED FOR B/R & E/M SERVICES (Sch 'A' Part-XVIII) Please Enable Macros to View BoQ information |
AI Tender Summary
Tender Timeline
Jul 01, 2026
11:30 IST
Tender Published
Tender notice published.
CompletedJul 22, 2026
17:00 IST
Bid Submission Deadline
Online submission via eProcurement portal.
Upcoming · 13 daysJul 29, 2026
Bid Opening Date
Technical bids will be opened and evaluated.
Upcoming · 20 daysTender Documents
Download All (ZIP) ↓
Disclaimer
We takes all possible care for accurate & authentic tender information. However users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender