| 1 | Demolishing brick work manually/ by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer-in-charge.(a) In cement mortar |
| 2 | Demolishing cement concrete manually/ by mechanical means including disposal of material within 50 metres lead as per direction of Engineer - in - charge.(a) Nominal concrete 1:3:6 or richer mix (i/c equivalent design mix) |
| 3 | Earth work in excavation by mechanical means (Hydraulic excavator) / manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift upto 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m.(a) All kinds of soil. |
| 4 | Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundations etc. in layers not exceeding 20cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 and for all lift. |
| 5 | Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level :(a) 1:5:10 (1 cement : 5 coarse sand (zone-lll) derived from natural sources : 10 graded stone aggregate 40 mm nominal size derived from natural sources) |
| 6 | Brick work with common burnt clay F.P.S. (non modular) bricks of class designation 7.5 in foundation and plinth in:(a) Cement mortar 1:6 (1 cement : 6 coarse sand) |
| 7 | Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level :(a) 1:2:4 (1 cement : 2 coarse sand (zone-III) derived from natural sources : 4 graded stone aggregate 20 mm nominal size derived from natural sources) |
| 8 | Structural steel work riveted, bolted or welded in built up sections, trusses and framed work, including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer all complete. |
| 9 | 12 mm cement plaster of mix : (a) 1:6 (1 cement: 6 coarse sand) |
| 10 | 15 mm cement plaster on rough side of single or half brick wall of mix: (a) 1:6 (1 cement: 6 coarse sand) |
| 11 | Painting with synthetic enamel paint of approved brand and manufacture to give an even shade :(a) Two or more coats on new work |
| 12 | Finishing walls with Acrylic Smooth exterior paint of required shade :(a) New work (Two or more coat applied @ 1.67 ltr/10 sqm over and including priming coat of exterior primer applied @ 2.20 kg/10 sqm) |
| 13 | 40 mm thick fine dressed stone flooring over 20 mm (average) thick base of cement mortar 1:5 (1 cement : 5 coarse sand), including pointing with cement mortar 1:2 (1 cement : 2 stone dust) with an admixture of pigment to match the shade of stone.(a) Red sand stone |
| 14 | Steel work in built up tubular (round, square or rectangular hollow tubes etc.) trusses etc., including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer, including welding and bolted with special shaped washers etc. complete. (a) Hot finished welded type tubes |
| 15 | Disposal of building rubbish / malba / similar unserviceable, dismantled or waste materials by mechanical means, including loading, transporting, unloading to approved municipal dumping ground or as approved by Engineer-in-charge, beyond 50 m initial lead, for all leads including all lifts involved. |
| 16 | Providing and fixing Polycarbonate sheets (size, shape ,colour, multilayered as approved by Engineer-in-Charge) of total thickness 10mm. Including Screwing/riveting/bolting to fix sheet on MS frame & connecting the sheet using Glazing bar(aluminum) & silicon adhesive as sealent wherever necessary and sanding the sheet edge with fine sandpaper to give a tidy finish.(MS frame shall be paid separately). |
| 17 | Painting with synthetic enamel paint of approved brand and manufacture of required colour to give an even shade :(a) Two or more coats on new work over an under coat of suitable shade with ordinary paint of approved brand and manufacture |
| 18 | Centering and shuttering including strutting, propping etc. and removal of form for(a) Foundations, footings, bases of columns, etc. for mass concrete |
| 19 | Total = 2,888,358.00 |
| 20 | After GST correction factor of 0.973 = 2,810,372.00 |
| 21 | Add 3% Cost Index except 0.973 times the item no. 15 = Please Enable Macros to View BoQ information |