| 1 | Supply, Fabrication and Erection of Embedded parts |
| 2 | 85.101:Supply of MS plates confirming to IS 2062GrB including cost of conveyance charges |
| 3 | 85.102:Supply of MS Tees, Angles, Joists, ISMB, ISMC confirming to IS2062GrA/B including cost of conveyance charges |
| 4 | 85.107:Supply of MS round bar including cost of conveyance charges |
| 5 | OD22281/2025-2026:Fabrication and erection of Embedded Parts for canal shutters(Up To 2 Tonne<br>Weight) and accessories as per approved specifications, drawing and direction of deptl. |
| 6 | 2.7.1:Earth work in excavation by mechanical means (Hydraulic excavator )/ manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including disposal of excavated earth, lead up to 50 m and lift up to 1.5 m, disposed earth to be levelled and neatly dressed.Ordinary rock |
| 7 | 5.22.6:Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete upto plinth levelThermo - Mechanically Treated bars of grade Fe-500D or more |
| 8 | 4.1.4:Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:2:4 (1 Cement : 2 coarse sand (zone-III) derived from natural sources : 4 gradedstone aggregate 40 mm nominal size derived from natural sources) |
| 9 | 4.3.1:Centering and shuttering including strutting, propping etc. and removal of form work for:Foundations, footings, bases for columns |
| 10 | 5.23:Smooth finishing of the exposed surface of RCC work with 6mm thick cement mortar 1:3 ( cement : 3 fine sand). |
| 11 | Supply, Fabrication and Erection of Gate |
| 12 | 85.101:Supply of MS plates confirming to IS 2062GrB including cost of conveyance charges |
| 13 | 85.102:Supply of MS Tees, Angles, Joists, ISMB, ISMC confirming to IS2062GrA/B including cost of conveyance charges |
| 14 | OD22276/2025-2026:Fabrication and supply of Struchural steel canal shutters ( Up to 2 tonne weight ) /Hoisting Bridge/ Platform and accessories etc. For the same as per approved specifications, drawings and directions of deptl officer at site including cost of labour, machinery, all leads and lifts, incidental and handling charges etc complete but excluding cost of material already supplied<br> |
| 15 | 85.114:Painting all the exposed surfaces of the gate and embedded parts with two coats of epoxy coal tar black paint confirming to IS14948 with a minimum film thickness of 150+/-5 microns per each coat over two coats of priming coat applied with zinc primer containing not less than 85% of zinc on dry film with a film thickness of 70+/-5 microns , so that the total film thickness of all coats including priming coat at any rate is not less than 350 microns after cleaning the surface using hand and power tool cleaning including cost of all materials, labour charges , cost of testing all painting materials, all incidental charges, hire of T&P etc. complete as per the direction of department officers at site |
| 16 | OD22278/2025-2026:Erection of the Canal Shutter (Up to 2 Tonne weight) /Hoisting Bridge/ Platform including hand rails, ladders etc for the same including. alignment correcting and setting complete including cost of labour, machinery, incidential and conveyance, lead and lift charges charges etc complete but excluding cost of material already supplied<br>Rate Analysis for 10qtl erection |
| 17 | Supply, Fabrication and Erection of Hoisting Bridge |
| 18 | 85.101:Supply of MS plates confirming to IS 2062GrB including cost of conveyance charges |
| 19 | 85.102:Supply of MS Tees, Angles, Joists, ISMB, ISMC confirming to IS2062GrA/B including cost of conveyance charges |
| 20 | OD22283/2025-2026:Fabrication and supply of Struchural steel canal shutters ( Up to 2 tonne weight ) /Hoisting Bridge/ Platform and accessories etc. For the same as per approved specifications, drawings and directions of deptl officer at site including cost of labour, machinery, all leads and lifts, incidental and handling charges etc complete but excluding cost of material already supplied<br> |
| 21 | 85.115:Cost of painting with 2 coats of enamel paint over 1 coat of zinchromate primer as per IS1477:1994 after hand and power tool cleaning including cost of all materials, labour charges, cost of testing all painting materials, all incidental charges, hire of T&P etc. complete as per the direction of department officers at site |
| 22 | OD22284/2025-2026:Erection of the Canal Shutter (Up to 2 Tonne weight) /Hoisting Bridge/ Platform including hand rails, ladders etc for the same including. alignment correcting and setting complete including cost of labour, machinery, incidential and conveyance, lead and lift charges charges etc complete but excluding cost of material already supplied<br>Rate Analysis for 10qtl erection |
| 23 | OD22286/2025-2026:Providing base and nut arrangement for hoisting the shutter including cost of material, labour etc for casting, machining and assembling<br> including cost of all materials, labour, hire charges and conveyance. |
| 24 | OD27226/2025-2026::Supply of Fastners ( bolts up to 300 mm long ), nuts and washers ) including cost of conveyance chargesData for supply of 1 kg fastners |
| 25 | OD22962/2025-2026:Providing EN-8 screw rod with one number of EN-8 screw shaft, hand operation including cost of all materials, labour, hire charges and conveyance.1 m Screw rod having screw shaft dia 53mm with single start square thread 50mm diameter screw Please Enable Macros to View BoQ information |