| Sl. No. | Item Description |
| 1 | Survey, Supply, Transportation, Carriage, Erection, Testing and Commissioning for erection of 11KV line on 9 mtr long PCC poles, with 30 mm sq. ACSR Weasel Conductor for Creation of 63 KVA Sub Station at Parla Chak under UT Capex Budget 2026-27. |
| 2 | 9 mtr. Long PCC Pole (PCC -WL-300Kg) |
| 3 | GI V Cross -arm with top Bracket including clamps |
| 4 | GI Channel X-arm including clamps and Angle for braces |
| 5 | 30 mm sq. ACSR Weasel conductor |
| 6 | 11 KV Polymer composite Pin Insulator 12 KV, 5 KN, lighting impulse 75 KV Positive and 80 KV Negative, Creepage distance 320mm. |
| 7 | 11 KV Polymeric Composite Disc insulator 12 KV, min failing load 45 kn, lightening impulse 75 Positive and 80 KV Negative, creepage distance 320mm with fitting |
| 8 | Galvanized Nuts and Bolts |
| 9 | Danger Plates with clamps |
| 10 | Anti Climbing device with clamps |
| 11 | Earthing complete by GI Rod 20 mm, 2.5 mtr long through G.I. Strip 25X3 mm for LT |
| 12 | Painting of 9 mtr ST poles with two coat of Aluminium Paint. |
| 13 | Galvanised Stay Set with 50x8mm stay clamp, guy insulator (2Nos.), anchor plate (200x 200 x 6 mm), nut-bolts, 2 Nos turn-buckles, 1.8m long, 16 mm diameter solid GS stay rod & 7/3.15 mm dia GI stranded wire complete |
| 14 | Survey, Supply, Transportation, Carriage, Erection, Testing and Commissioning for Creation of 63 KVA Sub Station atParla Chak under UT Capex Budget 2026-27. |
| 15 | 11/0.433kV, 3-phase 63 KVA Distribution Transformer of latest Energy efficiency Level-2 (NEW) , IS 1180 Part-I 2014 as per latest uptodate commendment with externally fitted MCCB with cable Box 4x4 mtrs suitable cable of ratings |
| 16 | Gapless surge arrestor 9KV, 10KA, LA with polymer housing station type |
| 17 | 11 KV GO, AB Switch 3-phase, 3-pole, 200 Amp. Vertical |
| 18 | 11 kV Horn Gap Fuse Set 3 Phase 200A |
| 19 | 120 mm² Single Core Cable,1.1kV Grade, PVC Insulated Alumnium Stranded Conductor FRLS type |
| 20 | 9 mtr. Long ST Pole (ST 410 SP-33) |
| 21 | 11kV Polymeric composite Disc Insulator 12kV, min failing load 45kN, Lightening Impulse 75kV Positive and 80kV Negative, creepage distance 320mm with tension fitting |
| 22 | GI Channel/Angle/Flat of sizes including clamps |
| 23 | Galvanized Nuts and Bolts. |
| 24 | Earthing of substation --Excavation of earth pit of dia 650 mm & depth 3000 mm, installation of Earthing pipe of 40 mm Nominal bore & 4mm wall thickness & length 2.5 mtr long as Per IS 1239. GI Strip for neutral earthing of size 50 mm x 6 mm & 32mm x 3mm for connection of transformer body, G.O Set & lightening arrestor as per IS 2629/85, GI nuts & bolts,refilled with earth enhancement materials and earth Chamber with RCC slab cover. |
| 25 | 11 KV Polymer composite Pin Insulator 12 KV, 5 KN, lighting impulse 75 KV Positive and 80 KV Negative, Creepage distance 320mm. |
| 26 | Galvanised Stay Set with 50x8mm stay clamp, guy insulator (2Nos.), anchor plate (200x 200 x 6 mm), nut-bolts, 2 Nos turn-buckles, 1.8m long, 16 mm diameter solid GS stay rod & 7/3.15 mm dia GI stranded wire complete |
| 27 | PG Clamps |
| 28 | Danger Plates with clamps |
| 29 | GI Barbed wire for Anticlimbing |
| 30 | 3-phase 4 wire LT Prodigy meter |
| 31 | Cement Bottoming 1:2:4 mix as per REC Standards 0.5 cum per pole |
| 32 | Painting of 9 mtr ST poles with two coat of Aluminium Paint and one coat of Red oxide (Asian/Nerolac make). |
| 33 | Survey, Supply, Transportation, Carriage, Erection, Testing and Commissioning for erection of LT line on 8 mtr long PCC poles, with 30 mm sq. ACSR Weasel Conductor for Creation of 63 KVA Sub Station at Parla Chak under UT Capex Budget 2026-27.. |
| 34 | 8 Mtr. Long PCC Poles( PCC-Wl-200Kg) |
| 35 | GI M Clamps for Shackle Insulator |
| 36 | 30 mm sq. ACSR Weasel Condutor. |
| 37 | Shakle Insulator |
| 38 | Galvinized Nuts and Bolts. |
| 39 | Earthing composite by GI pipe 40 mm or GI Rod 20 mm 2.5 mtr. long through GI strip |
| 40 | Survey, Supply, Transportation, Carriage, Erection, Testing and Commissioning for erection of 11KV line on 9 mtr long PCC poles, with 30 mm sq. ACSR Weasel Conductor for Creation of 63 KVA Sub Station at Plah Danga(Kambal Danga) under UT Capex Budget 2026-27. |
| 41 | 9 mtr. Long PCC Pole (PCC -WL-300Kg) |
| 42 | GI V Cross -arm with top Bracket including clamps |
| 43 | GI Channel X-arm including clamps and Angle for braces |
| 44 | 30 mm sq. ACSR Weasel conductor |
| 45 | 11 KV Polymer composite Pin Insulator 12 KV, 5 KN, lighting impulse 75 KV Positive and 80 KV Negative, Creepage distance 320mm. |
| 46 | 11 KV Polymeric Composite Disc insulator 12 KV, min failing load 45 kn, lightening impulse 75 Positive and 80 KV Negative, creepage distance 320mm with fitting |
| 47 | Galvanized Nuts and Bolts |
| 48 | Danger Plates with clamps |
| 49 | Anti Climbing device with clamps |
| 50 | Earthing complete by GI Rod 20 mm, 2.5 mtr long through G.I. Strip 25X3 mm for LT |
| 51 | Galvanised Stay Set with 50x8mm stay clamp, guy insulator (2Nos.), anchor plate (200x 200 x 6 mm), nut-bolts, 2 Nos turn-buckles, 1.8m long, 16 mm diameter solid GS stay rod & 7/3.15 mm dia GI stranded wire complete |
| 52 | Survey, Supply, Transportation, Carriage, Erection, Testing and Commissioning for Creation of 63 KVA Sub Station at Plah Danga(Kambal Danga) under UT Capex Budget 2026-27. |
| 53 | 11/0.433kV, 3-phase 63 KVA Distribution Transformer of latest Energy efficiency Level-2 (NEW) , IS 1180 Part-I 2014 as per latest uptodate commendment with externally fitted MCCB with cable Box 4x4 mtrs suitable cable of ratings |
| 54 | Gapless surge arrestor 9KV, 10KA, LA with polymer housing station type |
| 55 | 11 KV GO, AB Switch 3-phase, 3-pole, 200 Amp. Vertical |
| 56 | 11 kV Horn Gap Fuse Set 3 Phase 200A |
| 57 | 120 mm² Single Core Cable,1.1kV Grade, PVC Insulated Alumnium Stranded Conductor FRLS type |
| 58 | 9 mtr. Long ST Pole (ST 410 SP-33) |
| 59 | 11kV Polymeric composite Disc Insulator 12kV, min failing load 45kN, Lightening Impulse 75kV Positive and 80kV Negative, creepage distance 320mm with tension fitting |
| 60 | GI Channel/Angle/Flat of sizes including clamps |
| 61 | Galvanized Nuts and Bolts. |
| 62 | Earthing of substation --Excavation of earth pit of dia 650 mm & depth 3000 mm, installation of Earthing pipe of 40 mm Nominal bore & 4mm wall thickness & length 2.5 mtr long as Per IS 1239. GI Strip for neutral earthing of size 50 mm x 6 mm & 32mm x 3mm for connection of transformer body, G.O Set & lightening arrestor as per IS 2629/85, GI nuts & bolts,refilled with earth enhancement materials and earth Chamber with RCC slab cover. |
| 63 | 11 KV Polymer composite Pin Insulator 12 KV, 5 KN, lighting impulse 75 KV Positive and 80 KV Negative, Creepage distance 320mm. |
| 64 | Galvanised Stay Set with 50x8mm stay clamp, guy insulator (2Nos.), anchor plate (200x 200 x 6 mm), nut-bolts, 2 Nos turn-buckles, 1.8m long, 16 mm diameter solid GS stay rod & 7/3.15 mm dia GI stranded wire complete |
| 65 | PG Clamps |
| 66 | Danger Plates with clamps |
| 67 | GI Barbed wire for Anticlimbing |
| 68 | 3-phase 4 wire LT Prodigy meter |
| 69 | Cement Bottoming 1:2:4 mix as per REC Standards 0.5 cum per pole |
| 70 | Painting of 9 mtr ST poles with two coat of Aluminium Paint and one coat of Red oxide (Asian/Nerolac make). |
| 71 | Survey, Supply, Transportation, Carriage, Erection, Testing and Commissioning for erection of LT line on 8 mtr long PCC poles, with 30 mm sq. ACSR Weasel Conductor for Creation of 63 KVA Sub Station at Plah Danga(Kambal Danga) under UT Capex Budget 2026-27. |
| 72 | 8 Mtr. Long PCC Poles( PCC-Wl-200Kg) |
| 73 | GI M Clamps for Shackle Insulator |
| 74 | 30 mm sq. ACSR Weasel Condutor. |
| 75 | Shakle Insulator |
| 76 | Galvinized Nuts and Bolts. |
| 77 | Earthing composite by GI pipe 40 mm or GI Rod 20 mm 2.5 mtr. long through GI strip |
| 78 | Survey, Supply, Transportation, Carriage, Erection, Testing and Commissioning for erection of 11KV line on 9 mtr long PCC poles, with 30 mm sq. ACSR Weasel Conductor for Creation of 63 KVA Sub Station at Tharmat Mohalla under UT Capex Budget 2026-27. |
| 79 | 9 mtr. Long PCC Pole (PCC -WL-300Kg) |
| 80 | GI V Cross -arm with top Bracket including clamps |
| 81 | GI Channel X-arm including clamps and Angle for braces |
| 82 | 30 mm sq. ACSR Weasel conductor |
| 83 | 11 KV Polymer composite Pin Insulator 12 KV, 5 KN, lighting impulse 75 KV Positive and 80 KV Negative, Creepage distance 320mm. |
| 84 | 11 KV Polymeric Composite Disc insulator 12 KV, min failing load 45 kn, lightening impulse 75 Positive and 80 KV Negative, creepage distance 320mm with fitting |
| 85 | Galvanized Nuts and Bolts |
| 86 | Danger Plates with clamps |
| 87 | Anti Climbing device with clamps |
| 88 | Earthing complete by GI Rod 20 mm, 2.5 mtr long through G.I. Strip 25X3 mm for LT |
| 89 | Survey, Supply, Transportation, Carriage, Erection, Testing and Commissioning for Creation of 63 KVA Sub Station at Tharmat Mohalla under UT Capex Budget 2026-27 |
| 90 | 11/0.433kV, 3-phase 63 KVA Distribution Transformer of latest Energy efficiency Level-2 (NEW) , IS 1180 Part-I 2014 as per latest uptodate commendment with externally fitted MCCB with cable Box 4x4 mtrs suitable cable of ratings |
| 91 | Gapless surge arrestor 9KV, 10KA, LA with polymer housing station type |
| 92 | 11 KV GO, AB Switch 3-phase, 3-pole, 200 Amp. Vertical |
| 93 | 11 kV Horn Gap Fuse Set 3 Phase 200A |
| 94 | 120 mm² Single Core Cable,1.1kV Grade, PVC Insulated Alumnium Stranded Conductor FRLS type |
| 95 | 9 mtr. Long ST Pole (ST 410 SP-33) |
| 96 | 11kV Polymeric composite Disc Insulator 12kV, min failing load 45kN, Lightening Impulse 75kV Positive and 80kV Negative, creepage distance 320mm with tension fitting |
| 97 | GI Channel/Angle/Flat of sizes including clamps |
| 98 | Galvanized Nuts and Bolts. |
| 99 | Earthing of substation --Excavation of earth pit of dia 650 mm & depth 3000 mm, installation of Earthing pipe of 40 mm Nominal bore & 4mm wall thickness & length 2.5 mtr long as Per IS 1239. GI Strip for neutral earthing of size 50 mm x 6 mm & 32mm x 3mm for connection of transformer body, G.O Set & lightening arrestor as per IS 2629/85, GI nuts & bolts,refilled with earth enhancement materials and earth Chamber with RCC slab cover. |
| 100 | 11 KV Polymer composite Pin Insulator 12 KV, 5 KN, lighting impulse 75 KV Positive and 80 KV Negative, Creepage distance 320mm. |
| 101 | Galvanised Stay Set with 50x8mm stay clamp, guy insulator (2Nos.), anchor plate (200x 200 x 6 mm), nut-bolts, 2 Nos turn-buckles, 1.8m long, 16 mm diameter solid GS stay rod & 7/3.15 mm dia GI stranded wire complete |
| 102 | PG Clamps |
| 103 | Danger Plates with clamps |
| 104 | GI Barbed wire for Anticlimbing |
| 105 | 3-phase 4 wire LT Prodigy meter |
| 106 | Cement Bottoming 1:2:4 mix as per REC Standards 0.5 cum per pole |
| 107 | Painting of 9 mtr ST poles with two coat of Aluminium Paint and one coat of Red oxide (Asian/Nerolac make). |
| 108 | Survey, Supply, Transportation, Carriage, Erection, Testing and Commissioning for erection of LT line on 8 mtr long PCC poles, with 30 mm sq. ACSR Weasel Conductor for Creation of 63 KVA Sub Station at Tharmat Mohalla under UT Capex Budget 2026-27 under UT Capex Budget 2026-27. |
| 109 | 8 Mtr. Long PCC Poles( PCC-Wl-200Kg) |
| 110 | GI M Clamps for Shackle Insulator |
| 111 | 30 mm sq. ACSR Weasel Condutor. |
| 112 | Shakle Insulator |
| 113 | Galvinized Nuts and Bolts. |
| 114 | Earthing composite by GI pipe 40 mm or GI Rod 20 mm 2.5 mtr. long through GI strip |
| 115 | Survey, Supply, Transportation, Carriage, Erection, Testing and Commissioning for erection of 11KV line on 9 mtr long PCC poles, with 30 mm sq. ACSR Weasel Conductor for Creation of 63 KVA Sub Station at Upper Hartyan Aura under UT Capex Budget 2026-27. |
| 116 | 9 mtr. Long PCC Pole (PCC -WL-300Kg) |
| 117 | GI V Cross -arm with top Bracket including clamps |
| 118 | GI Channel X-arm including clamps and Angle for braces |
| 119 | 30 mm sq. ACSR Weasel conductor |
| 120 | 11 KV Polymer composite Pin Insulator 12 KV, 5 KN, lighting impulse 75 KV Positive and 80 KV Negative, Creepage distance 320mm. |
| 121 | 11 KV Polymeric Composite Disc insulator 12 KV, min failing load 45 kn, lightening impulse 75 Positive and 80 KV Negative, creepage distance 320mm with fitting |
| 122 | Galvanized Nuts and Bolts |
| 123 | Danger Plates with clamps |
| 124 | Anti Climbing device with clamps |
| 125 | Earthing complete by GI Rod 20 mm, 2.5 mtr long through G.I. Strip 25X3 mm for LT |
| 126 | Survey, Supply, Transportation, Carriage, Erection, Testing and Commissioning for Creation of 63 KVA Sub Station at Upper Hartyan Aura under UT Capex Budget 2026-27. |
| 127 | 11/0.433kV, 3-phase 63 KVA Distribution Transformer of latest Energy efficiency Level-2 (NEW) , IS 1180 Part-I 2014 as per latest uptodate commendment with externally fitted MCCB with cable Box 4x4 mtrs suitable cable of ratings |
| 128 | Gapless surge arrestor 9KV, 10KA, LA with polymer housing station type |
| 129 | 11 KV GO, AB Switch 3-phase, 3-pole, 200 Amp. Vertical |
| 130 | 11 kV Horn Gap Fuse Set 3 Phase 200A |
| 131 | 120 mm² Single Core Cable,1.1kV Grade, PVC Insulated Alumnium Stranded Conductor FRLS type |
| 132 | 9 mtr. Long ST Pole (ST 410 SP-33) |
| 133 | 11kV Polymeric composite Disc Insulator 12kV, min failing load 45kN, Lightening Impulse 75kV Positive and 80kV Negative, creepage distance 320mm with tension fitting |
| 134 | GI Channel/Angle/Flat of sizes including clamps |
| 135 | Galvanized Nuts and Bolts. |
| 136 | Earthing of substation --Excavation of earth pit of dia 650 mm & depth 3000 mm, installation of Earthing pipe of 40 mm Nominal bore & 4mm wall thickness & length 2.5 mtr long as Per IS 1239. GI Strip for neutral earthing of size 50 mm x 6 mm & 32mm x 3mm for connection of transformer body, G.O Set & lightening arrestor as per IS 2629/85, GI nuts & bolts,refilled with earth enhancement materials and earth Chamber with RCC slab cover. |
| 137 | 11 KV Polymer composite Pin Insulator 12 KV, 5 KN, lighting impulse 75 KV Positive and 80 KV Negative, Creepage distance 320mm. |
| 138 | Galvanised Stay Set with 50x8mm stay clamp, guy insulator (2Nos.), anchor plate (200x 200 x 6 mm), nut-bolts, 2 Nos turn-buckles, 1.8m long, 16 mm diameter solid GS stay rod & 7/3.15 mm dia GI stranded wire complete |
| 139 | PG Clamps |
| 140 | Danger Plates with clamps |
| 141 | GI Barbed wire for Anticlimbing |
| 142 | 3-phase 4 wire LT Prodigy meter |
| 143 | Cement Bottoming 1:2:4 mix as per REC Standards 0.5 cum per pole |
| 144 | Painting of 9 mtr ST poles with two coat of Aluminium Paint and one coat of Red oxide (Asian/Nerolac make). |
| 145 | Survey, Supply, Transportation, Carriage, Erection, Testing and Commissioning for erection of LT line on 8 mtr long PCC poles, with 30 mm sq. ACSR Weasel Conductor for Creation of 63 KVA Sub Station at Upper Hartyan Aura under UT Capex Budget 2026-27. |
| 146 | 8 Mtr. Long PCC Poles( PCC-Wl-200Kg) |
| 147 | GI M Clamps for Shackle Insulator |
| 148 | 30 mm sq. ACSR Weasel Condutor. |
| 149 | Shakle Insulator |
| 150 | Galvinized Nuts and Bolts. |
| 151 | Earthing composite by GI pipe 40 mm or GI Rod 20 mm 2.5 mtr. long through GI strip |
| 152 | Survey, Supply, Transportation, Carriage, Erection, Testing and Commissioning for erection of 11KV line on 9 mtr long PCC poles, with 30 mm sq. ACSR Weasel Conductor for Creation of 63 KVA Sub Station at Leray Battal under UT Capex Budget 2026-27. |
| 153 | 9 mtr. Long PCC Pole (PCC -WL-300Kg) |
| 154 | GI V Cross -arm with top Bracket including clamps |
| 155 | GI Channel X-arm including clamps and Angle for braces |
| 156 | 30 mm sq. ACSR Weasel conductor |
| 157 | 11 KV Polymer composite Pin Insulator 12 KV, 5 KN, lighting impulse 75 KV Positive and 80 KV Negative, Creepage distance 320mm. |
| 158 | 11 KV Polymeric Composite Disc insulator 12 KV, min failing load 45 kn, lightening impulse 75 Positive and 80 KV Negative, creepage distance 320mm with fitting |
| 159 | Galvanized Nuts and Bolts |
| 160 | Danger Plates with clamps |
| 161 | Anti Climbing device with clamps |
| 162 | Earthing complete by GI Rod 20 mm, 2.5 mtr long through G.I. Strip 25X3 mm for LT |
| 163 | Galvanised Stay Set with 50x8mm stay clamp, guy insulator (2Nos.), anchor plate (200x 200 x 6 mm), nut-bolts, 2 Nos turn-buckles, 1.8m long, 16 mm diameter solid GS stay rod & 7/3.15 mm dia GI stranded wire complete |
| 164 | Survey, Supply, Transportation, Carriage, Erection, Testing and Commissioning for Creation of 63 KVA Sub Station at Leray Battal under UT Capex Budget 2026-27. |
| 165 | 11/0.433kV, 3-phase 63 KVA Distribution Transformer of latest Energy efficiency Level-2 (NEW) , IS 1180 Part-I 2014 as per latest uptodate commendment with externally fitted MCCB with cable Box 4x4 mtrs suitable cable of ratings |
| 166 | Gapless surge arrestor 9KV, 10KA, LA with polymer housing station type |
| 167 | 11 KV GO, AB Switch 3-phase, 3-pole, 200 Amp. Vertical |
| 168 | 11 kV Horn Gap Fuse Set 3 Phase 200A |
| 169 | 120 mm² Single Core Cable,1.1kV Grade, PVC Insulated Alumnium Stranded Conductor FRLS type |
| 170 | 9 mtr. Long ST Pole (ST 410 SP-33) |
| 171 | 11kV Polymeric composite Disc Insulator 12kV, min failing load 45kN, Lightening Impulse 75kV Positive and 80kV Negative, creepage distance 320mm with tension fitting |
| 172 | GI Channel/Angle/Flat of sizes including clamps |
| 173 | Galvanized Nuts and Bolts. |
| 174 | Earthing of substation --Excavation of earth pit of dia 650 mm & depth 3000 mm, installation of Earthing pipe of 40 mm Nominal bore & 4mm wall thickness & length 2.5 mtr long as Per IS 1239. GI Strip for neutral earthing of size 50 mm x 6 mm & 32mm x 3mm for connection of transformer body, G.O Set & lightening arrestor as per IS 2629/85, GI nuts & bolts,refilled with earth enhancement materials and earth Chamber with RCC slab cover. |
| 175 | 11 KV Polymer composite Pin Insulator 12 KV, 5 KN, lighting impulse 75 KV Positive and 80 KV Negative, Creepage distance 320mm. |
| 176 | Galvanised Stay Set with 50x8mm stay clamp, guy insulator (2Nos.), anchor plate (200x 200 x 6 mm), nut-bolts, 2 Nos turn-buckles, 1.8m long, 16 mm diameter solid GS stay rod & 7/3.15 mm dia GI stranded wire complete |
| 177 | PG Clamps |
| 178 | Danger Plates with clamps |
| 179 | GI Barbed wire for Anticlimbing |
| 180 | 3-phase 4 wire LT Prodigy meter |
| 181 | Cement Bottoming 1:2:4 mix as per REC Standards 0.5 cum per pole |
| 182 | Painting of 9 mtr ST poles with two coat of Aluminium Paint and one coat of Red oxide (Asian/Nerolac make). |
| 183 | Survey, Supply, Transportation, Carriage, Erection, Testing and Commissioning for erection of LT line on 8 mtr long PCC poles, with 30 mm sq. ACSR Weasel Conductor for Creation of 63 KVA Sub Station at Leray Battal under UT Capex Budget 2026-27. |
| 184 | 8 Mtr. Long PCC Poles( PCC-Wl-200Kg) |
| 185 | GI M Clamps for Shackle Insulator |
| 186 | 30 mm sq. ACSR Weasel Condutor. |
| 187 | Shakle Insulator |
| 188 | Galvinized Nuts and Bolts. |
| 189 | Earthing composite by GI pipe 40 mm or GI Rod 20 mm 2.5 mtr. long through GI strip |
| 190 | Survey, Supply, Transportation, Carriage, Erection, Testing and Commissioning for erection of 11KV line on 9 mtr long PCC poles, with 30 mm sq. ACSR Weasel Conductor for Creation of 63 KVA Sub Station at Kuryalta under UT Capex Budget 2026-27. |
| 191 | 9 mtr. Long PCC Pole (PCC -WL-300Kg) |
| 192 | GI V Cross -arm with top Bracket including clamps |
| 193 | GI Channel X-arm including clamps and Angle for braces |
| 194 | 30 mm sq. ACSR Weasel conductor |
| 195 | 11 KV Polymer composite Pin Insulator 12 KV, 5 KN, lighting impulse 75 KV Positive and 80 KV Negative, Creepage distance 320mm. |
| 196 | 11 KV Polymeric Composite Disc insulator 12 KV, min failing load 45 kn, lightening impulse 75 Positive and 80 KV Negative, creepage distance 320mm with fitting |
| 197 | Galvanized Nuts and Bolts |
| 198 | Danger Plates with clamps |
| 199 | Anti Climbing device with clamps |
| 200 | Earthing complete by GI Rod 20 mm, 2.5 mtr long through G.I. Strip 25X3 mm for LT |
| 201 | Galvanised Stay Set with 50x8mm stay clamp, guy insulator (2Nos.), anchor plate (200x 200 x 6 mm), nut-bolts, 2 Nos turn-buckles, 1.8m long, 16 mm diameter solid GS stay rod & 7/3.15 mm dia GI stranded wire complete |
| 202 | Survey, Supply, Transportation, Carriage, Erection, Testing and Commissioning for Creation of 63 KVA Sub Station atKuryalta under UT Capex Budget 2026-27. |
| 203 | 11/0.433kV, 3-phase 63 KVA Distribution Transformer of latest Energy efficiency Level-2 (NEW) , IS 1180 Part-I 2014 as per latest uptodate commendment with externally fitted MCCB with cable Box 4x4 mtrs suitable cable of ratings |
| 204 | Gapless surge arrestor 9KV, 10KA, LA with polymer housing station type |
| 205 | 11 KV GO, AB Switch 3-phase, 3-pole, 200 Amp. Vertical |
| 206 | 11 kV Horn Gap Fuse Set 3 Phase 200A |
| 207 | 120 mm² Single Core Cable,1.1kV Grade, PVC Insulated Alumnium Stranded Conductor FRLS type |
| 208 | 9 mtr. Long ST Pole (ST 410 SP-33) |
| 209 | 11kV Polymeric composite Disc Insulator 12kV, min failing load 45kN, Lightening Impulse 75kV Positive and 80kV Negative, creepage distance 320mm with tension fitting |
| 210 | GI Channel/Angle/Flat of sizes including clamps |
| 211 | Galvanized Nuts and Bolts. |
| 212 | Earthing of substation --Excavation of earth pit of dia 650 mm & depth 3000 mm, installation of Earthing pipe of 40 mm Nominal bore & 4mm wall thickness & length 2.5 mtr long as Per IS 1239. GI Strip for neutral earthing of size 50 mm x 6 mm & 32mm x 3mm for connection of transformer body, G.O Set & lightening arrestor as per IS 2629/85, GI nuts & bolts,refilled with earth enhancement materials and earth Chamber with RCC slab cover. |
| 213 | 11 KV Polymer composite Pin Insulator 12 KV, 5 KN, lighting impulse 75 KV Positive and 80 KV Negative, Creepage distance 320mm. |
| 214 | Galvanised Stay Set with 50x8mm stay clamp, guy insulator (2Nos.), anchor plate (200x 200 x 6 mm), nut-bolts, 2 Nos turn-buckles, 1.8m long, 16 mm diameter solid GS stay rod & 7/3.15 mm dia GI stranded wire complete |
| 215 | PG Clamps |
| 216 | Danger Plates with clamps |
| 217 | GI Barbed wire for Anticlimbing |
| 218 | 3-phase 4 wire LT Prodigy meter |
| 219 | Cement Bottoming 1:2:4 mix as per REC Standards 0.5 cum per pole |
| 220 | Painting of 9 mtr ST poles with two coat of Aluminium Paint and one coat of Red oxide (Asian/Nerolac make). |
| 221 | Survey, Supply, Transportation, Carriage, Erection, Testing and Commissioning for erection of LT line on 8 mtr long PCC poles, with 30 mm sq. ACSR Weasel Conductor for Creation of 63 KVA Sub Station at Kuryalta under UT Capex Budget 2026-27. |
| 222 | 8 Mtr. Long PCC Poles( PCC-Wl-200Kg) |
| 223 | GI M Clamps for Shackle Insulator |
| 224 | 30 mm sq. ACSR Weasel Condutor. |
| 225 | Shakle Insulator |
| 226 | Galvinized Nuts and Bolts. |
| 227 | Earthing composite by GI pipe 40 mm or GI Rod 20 mm 2.5 mtr. long through GI strip |
| 228 | Survey, Supply, Transportation, Carriage, Erection, Testing and Commissioning for erection of 11KV line on 9 mtr long PCC poles, with 30 mm sq. ACSR Weasel Conductor for Creation of 63 KVA Sub Station at Manowa (Chai Ritti) under UT Capex Budget 2026-27. |
| 229 | 9 mtr. Long PCC Pole (PCC -WL-300Kg) |
| 230 | GI V Cross -arm with top Bracket including clamps |
| 231 | GI Channel X-arm including clamps and Angle for braces |
| 232 | 30 mm sq. ACSR Weasel conductor |
| 233 | 11 KV Polymer composite Pin Insulator 12 KV, 5 KN, lighting impulse 75 KV Positive and 80 KV Negative, Creepage distance 320mm. |
| 234 | 11 KV Polymeric Composite Disc insulator 12 KV, min failing load 45 kn, lightening impulse 75 Positive and 80 KV Negative, creepage distance 320mm with fitting |
| 235 | Galvanized Nuts and Bolts |
| 236 | Danger Plates with clamps |
| 237 | Anti Climbing device with clamps |
| 238 | Earthing complete by GI Rod 20 mm, 2.5 mtr long through G.I. Strip 25X3 mm for LT |
| 239 | Galvanised Stay Set with 50x8mm stay clamp, guy insulator (2Nos.), anchor plate (200x 200 x 6 mm), nut-bolts, 2 Nos turn-buckles, 1.8m long, 16 mm diameter solid GS stay rod & 7/3.15 mm dia GI stranded wire complete |
| 240 | Survey, Supply, Transportation, Carriage, Erection, Testing and Commissioning for Creation of 63 KVA Sub Station at Manowa (Chai Ritti) under UT Capex Budget 2026-27. |
| 241 | 11/0.433kV, 3-phase 63 KVA Distribution Transformer of latest Energy efficiency Level-2 (NEW) , IS 1180 Part-I 2014 as per latest uptodate commendment with externally fitted MCCB with cable Box 4x4 mtrs suitable cable of ratings |
| 242 | Gapless surge arrestor 9KV, 10KA, LA with polymer housing station type |
| 243 | 11 KV GO, AB Switch 3-phase, 3-pole, 200 Amp. Vertical |
| 244 | 11 kV Horn Gap Fuse Set 3 Phase 200A |
| 245 | 120 mm² Single Core Cable,1.1kV Grade, PVC Insulated Alumnium Stranded Conductor FRLS type |
| 246 | 9 mtr. Long ST Pole (ST 410 SP-33) |
| 247 | 11kV Polymeric composite Disc Insulator 12kV, min failing load 45kN, Lightening Impulse 75kV Positive and 80kV Negative, creepage distance 320mm with tension fitting |
| 248 | GI Channel/Angle/Flat of sizes including clamps |
| 249 | Galvanized Nuts and Bolts. |
| 250 | Earthing of substation --Excavation of earth pit of dia 650 mm & depth 3000 mm, installation of Earthing pipe of 40 mm Nominal bore & 4mm wall thickness & length 2.5 mtr long as Per IS 1239. GI Strip for neutral earthing of size 50 mm x 6 mm & 32mm x 3mm for connection of transformer body, G.O Set & lightening arrestor as per IS 2629/85, GI nuts & bolts,refilled with earth enhancement materials and earth Chamber with RCC slab cover. |
| 251 | 11 KV Polymer composite Pin Insulator 12 KV, 5 KN, lighting impulse 75 KV Positive and 80 KV Negative, Creepage distance 320mm. |
| 252 | Galvanised Stay Set with 50x8mm stay clamp, guy insulator (2Nos.), anchor plate (200x 200 x 6 mm), nut-bolts, 2 Nos turn-buckles, 1.8m long, 16 mm diameter solid GS stay rod & 7/3.15 mm dia GI stranded wire complete |
| 253 | PG Clamps |
| 254 | Danger Plates with clamps |
| 255 | GI Barbed wire for Anticlimbing |
| 256 | 3-phase 4 wire LT Prodigy meter |
| 257 | Cement Bottoming 1:2:4 mix as per REC Standards 0.5 cum per pole |
| 258 | Painting of 9 mtr ST poles with two coat of Aluminium Paint and one coat of Red oxide (Asian/Nerolac make). |
| 259 | Survey, Supply, Transportation, Carriage, Erection, Testing and Commissioning for erection of LT line on 8 mtr long PCC poles, with 30 mm sq. ACSR Weasel Conductor for Creation of 63 KVA Sub Station at Manowa (Chai Ritti) under UT Capex Budget 2026-27. |
| 260 | 8 Mtr. Long PCC Poles( PCC-Wl-200Kg) |
| 261 | GI M Clamps for Shackle Insulator |
| 262 | 30 mm sq. ACSR Weasel Condutor. |
| 263 | Shakle Insulator |
| 264 | Galvinized Nuts and Bolts. |
| 265 | Earthing composite by GI pipe 40 mm or GI Rod 20 mm 2.5 mtr. long through GI strip |
| 266 | Survey, Supply, Transportation, Carriage, Erection, Testing and Commissioning for erection of 11KV line on 9 mtr long PCC poles, with 30 mm sq. ACSR Weasel Conductor for Creation of250 KVA Sub Station at Sangoor under UT Capex Budget 2026-27. |
| 267 | 9 mtr. Long PCC Pole (PCC -WL-300Kg) |
| 268 | GI V Cross -arm with top Bracket including clamps |
| 269 | GI Channel X-arm including clamps and Angle for braces |
| 270 | 30 mm sq. ACSR Weasel conductor |
| 271 | 11 KV Polymer composite Pin Insulator 12 KV, 5 KN, lighting impulse 75 KV Positive and 80 KV Negative, Creepage distance 320mm. |
| 272 | 11 KV Polymeric Composite Disc insulator 12 KV, min failing load 45 kn, lightening impulse 75 Positive and 80 KV Negative, creepage distance 320mm with fitting |
| 273 | Galvanized Nuts and Bolts |
| 274 | Danger Plates with clamps |
| 275 | Anti Climbing device with clamps |
| 276 | Earthing complete by GI Rod 20 mm, 2.5 mtr long through G.I. Strip 25X3 mm for LT |
| 277 | Survey, Supply, Transportation, Carriage, Erection, Testing and Commissioning for Creation of 250 KVA Sub Station at Sangoor under UT Capex Budget 2026-27. |
| 278 | 11/0.433kV, 3-phase 250 KVA Copper Wound Distribution Transformer of latest Energy efficiency Level-2 (NEW) , IS 1180 Part-I 2014 as per latest uptodate commendment with externally fitted MCCB with cable Box 4x4 mtrs suitable cable of ratings |
| 279 | Gapless surge arrestor 9KV, 10KA, LA with polymer housing station type |
| 280 | 11 KV GO, AB Switch 3-phase, 3-pole, 200 Amp. Vertical |
| 281 | 11 kV Horn Gap Fuse Set 3 Phase 200A |
| 282 | 185 mm² Single Core Cable,1.1kV Grade, PVC Insulated Alumnium Stranded Conductor FRLS type |
| 283 | 9 mtr. Long ST Pole (ST 410 SP-33) |
| 284 | 11kV Polymeric composite Disc Insulator 12kV, min failing load 45kN, Lightening Impulse 75kV Positive and 80kV Negative, creepage distance 320mm with tension fitting |
| 285 | GI Channel/Angle/Flat of sizes including clamps |
| 286 | Galvanized Nuts and Bolts. |
| 287 | Earthing of substation --Excavation of earth pit of dia 650 mm & depth 3000 mm, installation of Earthing pipe of 40 mm Nominal bore & 4mm wall thickness & length 2.5 mtr long as Per IS 1239. GI Strip for neutral earthing of size 50 mm x 6 mm & 32mm x 3mm for connection of transformer body, G.O Set & lightening arrestor as per IS 2629/85, GI nuts & bolts,refilled with earth enhancement materials and earth Chamber with RCC slab cover. |
| 288 | 11 KV Polymer composite Pin Insulator 12 KV, 5 KN, lighting impulse 75 KV Positive and 80 KV Negative, Creepage distance 320mm. |
| 289 | Galvanised Stay Set with 50x8mm stay clamp, guy insulator (2Nos.), anchor plate (200x 200 x 6 mm), nut-bolts, 2 Nos turn-buckles, 1.8m long, 16 mm diameter solid GS stay rod & 7/3.15 mm dia GI stranded wire complete |
| 290 | PG Clamps |
| 291 | Danger Plates with clamps |
| 292 | GI Barbed wire for Anticlimbing |
| 293 | 3-phase 4 wire LT Trivector |
| 294 | Cement Bottoming 1:2:4 mix as per REC Standards 0.5 cum per pole |
| 295 | Painting of 9 mtr ST poles with two coat of Aluminium Paint and one coat of Red oxide (Asian/Nerolac make). |
| 296 | Survey, Supply, Transportation, Carriage, Erection, Testing and Commissioning for erection of LT line on 8 mtr long PCC poles, with 30 mm sq. ACSR Weasel Conductor for Creation of 63 KVA Sub Station at Sangoor under UT Capex Budget 2026-27. |
| 297 | 8 Mtr. Long PCC Poles( PCC-Wl-200Kg) |
| 298 | GI M Clamps for Shackle Insulator |
| 299 | 30 mm sq. ACSR Weasel Condutor. |
| 300 | Shakle Insulator |
| 301 | Galvinized Nuts and Bolts. |
| 302 | Earthing composite by GI pipe 40 mm or GI Rod 20 mm 2.5 mtr. long through GI strip |
| 303 | Survey, Supply, Transportation, Carriage, Erection, Testing and Commissioning for erection of 11KV line on 9 mtr long ST poles, with 30 mm sq. ACSR Weasel Conductor for Creation of 25 KVA Sub Station at at W.No. 07 Motati Ponara under UT Capex Budget 2026-27. |
| 304 | 9 mtr. Long ST Pole (ST 410 SP-33) |
| 305 | GI V Cross -arm with top Bracket including clamps |
| 306 | GI Channel X-arm including clamps and Angle for braces |
| 307 | 30 mm sq. ACSR Weasel conductor |
| 308 | 11 KV Polymer composite Pin Insulator 12 KV, 5 KN, lighting impulse 75 KV Positive and 80 KV Negative, Creepage distance 320mm. |
| 309 | 11 KV Polymeric Composite Disc insulator 12 KV, min failing load 45 kn, lightening impulse 75 Positive and 80 KV Negative, creepage distance 320mm with fitting |
| 310 | Galvanized Nuts and Bolts |
| 311 | Danger Plates with clamps |
| 312 | Anti Climbing device with clamps |
| 313 | Earthing complete by GI Rod 20 mm, 2.5 mtr long through G.I. Strip 25X3 mm for LT |
| 314 | Painting of 9 mtr long ST poles with two coat of Aluminium paint. |
| 315 | Galvanised Stay Set with 50x8mm stay clamp, guy insulator (2Nos.), anchor plate (200x 200 x 6 mm), nut-bolts, 2 Nos turn-buckles, 1.8m long, 16 mm diameter solid GS stay rod & 7/3.15 mm dia GI stranded wire complete |
| 316 | Survey, Supply, Transportation, Carriage, Erection, Testing and Commissioning for Creation of 25 KVA Sub Station at W.No. 07 Motati Ponara under UT Capex Budget 2026-27 |
| 317 | 11/0.433kV, 3-phase 25 KVA Distribution Transformer WITH Bimetallic Connectors Energy Level-2, Aluminium wound and LV Cable Box Having Detachable Aluminium Gland plate |
| 318 | Gapless surge arrestor 9KV, 10KA, LA with polymer housing station type |
| 319 | 11 KV GO, AB Switch 3-phase, 3-pole, 200 Amp. Vertical |
| 320 | 11 kV Horn Gap Fuse Set 3 Phase 200A |
| 321 | 70mm² Single Core Cable,1.1kV Grade, PVC Insulated Alumnium Stranded Conductor FRLS type |
| 322 | 9 mtr. Long ST Pole (ST 410 SP-33) |
| 323 | 11kV Polymeric composite Disc Insulator 12kV, min failing load 45kN, Lightening Impulse 75kV Positive and 80kV Negative, creepage distance 320mm with tension fitting |
| 324 | GI Channel/Angle/Flat of sizes including clamps |
| 325 | Galvanized Nuts and Bolts. |
| 326 | Earthing of substation --Excavation of earth pit of dia 650 mm & depth 3000 mm, installation of Earthing pipe of 40 mm Nominal bore & 4mm wall thickness & length 2.5 mtr long as Per IS 1239. GI Strip for neutral earthing of size 50 mm x 6 mm & 32mm x 3mm for connection of transformer body, G.O Set & lightening arrestor as per IS 2629/85, GI nuts & bolts,refilled with earth enhancement materials and earth Chamber with RCC slab cover. |
| 327 | Cement Bottoming 1:2:4 mix as per REC Standards 0.5 cum per pole |
| 328 | Painting of 9 mtr ST poles with two coat of Aluminium Paint and one coat of Red oxide (Asian/Nerolac make). |
| 329 | LT Fuse Switch made of angle Iron 50X50X6mm, with aluminium Bus Bar strip 50X6mm fixed on Bus Bar Insualtor including clamps for fixing of switch |
| 330 | Survey, Supply, Transportation, Carriage, Erection, Testing and Commissioning for erection of LT line on 8 mtr long ST poles, with 30 mm sq. ACSR Weasel Conductor for Creation of 25 KVA Sub Station at W.No. 07 Motati Ponara under UT Capex Budget 2026-27 |
| 331 | 8 mtr. Long ST Pole (ST 410 SP-15) |
| 332 | GI M Clamps for Shackle Insulator |
| 333 | 30 mm sq. ACSR Weasel Condutor. |
| 334 | Shakle Insulator |
| 335 | Galvinized Nuts and Bolts. |
| 336 | Earthing composite by GI pipe 40 mm or GI Rod 20 mm 2.5 mtr. long through GI strip |
| 337 | Galvanised Stay Set with 50x8mm stay clamp, guy insulator (2Nos.), anchor plate (200x 200 x 6 mm), nut-bolts, 2 Nos turn-buckles, 1.8m long, 16 mm diameter solid GS stay rod & 7/3.15 mm dia GI stranded wire complete |
| 338 | Survey, Supply, Transportation, Carriage, Erection, Testing and Commissioning for erection of 11KV line on 9 mtr long ST poles, with 30 mm sq. ACSR Weasel Conductor for Creation of 63 KVA Sub Station at at W.No. 06 Keya near the house of Sh. Sher Singh under UT Capex Budget 2026-27. |
| 339 | 9 mtr. Long ST Pole (ST 410 SP-33) |
| 340 | GI V Cross -arm with top Bracket including clamps |
| 341 | GI Channel X-arm including clamps and Angle for braces |
| 342 | 30 mm sq. ACSR Weasel conductor |
| 343 | 11 KV Polymer composite Pin Insulator 12 KV, 5 KN, lighting impulse 75 KV Positive and 80 KV Negative, Creepage distance 320mm. |
| 344 | 11 KV Polymeric Composite Disc insulator 12 KV, min failing load 45 kn, lightening impulse 75 Positive and 80 KV Negative, creepage distance 320mm with fitting |
| 345 | Galvanized Nuts and Bolts |
| 346 | Danger Plates with clamps |
| 347 | Anti Climbing device with clamps |
| 348 | Earthing complete by GI Rod 20 mm, 2.5 mtr long through G.I. Strip 25X3 mm for LT |
| 349 | Painting of 9 mtr long ST poles with two coat of Aluminium paint. |
| 350 | Galvanised Stay Set with 50x8mm stay clamp, guy insulator (2Nos.), anchor plate (200x 200 x 6 mm), nut-bolts, 2 Nos turn-buckles, 1.8m long, 16 mm diameter solid GS stay rod & 7/3.15 mm dia GI stranded wire complete |
| 351 | Survey, Supply, Transportation, Carriage, Erection, Testing and Commissioning for Creation of 63 KVA Sub Station at W.No. 06 Keya near the house of Sh. Sher Singh under UT Capex Budget 2026-27 |
| 352 | 11/0.433kV, 3-phase 63 KVA Distribution Transformer of latest Energy efficiency Level-2 (NEW) , IS 1180 Part-I 2014 as per latest uptodate commendment with externally fitted MCCB with cable Box 4x4 mtrs suitable cable of ratings |
| 353 | Gapless surge arrestor 9KV, 10KA, LA with polymer housing station type |
| 354 | 11 KV GO, AB Switch 3-phase, 3-pole, 200 Amp. Vertical |
| 355 | 11 kV Horn Gap Fuse Set 3 Phase 200A |
| 356 | 185 mm² Single Core Cable,1.1kV Grade, PVC Insulated Alumnium Stranded Conductor FRLS type |
| 357 | 9 mtr. Long ST Pole (ST 410 SP-33) |
| 358 | 11kV Polymeric composite Disc Insulator 12kV, min failing load 45kN, Lightening Impulse 75kV Positive and 80kV Negative, creepage distance 320mm with tension fitting |
| 359 | GI Channel/Angle/Flat of sizes including clamps |
| 360 | Galvanized Nuts and Bolts. |
| 361 | Earthing of substation --Excavation of earth pit of dia 650 mm & depth 3000 mm, installation of Earthing pipe of 40 mm Nominal bore & 4mm wall thickness & length 2.5 mtr long as Per IS 1239. GI Strip for neutral earthing of size 50 mm x 6 mm & 32mm x 3mm for connection of transformer body, G.O Set & lightening arrestor as per IS 2629/85, GI nuts & bolts,refilled with earth enhancement materials and earth Chamber with RCC slab cover. |
| 362 | 11 KV Polymer composite Pin Insulator 12 KV, 5 KN, lighting impulse 75 KV Positive and 80 KV Negative, Creepage distance 320mm. |
| 363 | Galvanised Stay Set with 50x8mm stay clamp, guy insulator (2Nos.), anchor plate (200x 200 x 6 mm), nut-bolts, 2 Nos turn-buckles, 1.8m long, 16 mm diameter solid GS stay rod & 7/3.15 mm dia GI stranded wire complete |
| 364 | PG Clamps |
| 365 | Danger Plates with clamps |
| 366 | GI Barbed wire for Anticlimbing |
| 367 | 3-phase 4 wire LT Prodigy meter |
| 368 | Cement Bottoming 1:2:4 mix as per REC Standards 0.5 cum per pole |
| 369 | Painting of 9 mtr ST poles with two coat of Aluminium Paint and one coat of Red oxide (Asian/Nerolac make). |
| 370 | Survey, Supply, Transportation, Carriage, Erection, Testing and Commissioning for erection of LT line on 8 mtr long ST poles, with 30 mm sq. ACSR Weasel Conductor for Creation of 63 KVA Sub Station at W.No. 07 Keya near the house of Sh. Sher Singh under UT Capex Budget 2026-27 |
| 371 | 8 mtr. Long ST Pole (ST 410 SP-15) |
| 372 | GI M Clamps for Shackle Insulator |
| 373 | 30 mm sq. ACSR Weasel Condutor. |
| 374 | Shakle Insulator |
| 375 | Galvinized Nuts and Bolts. |
| 376 | Earthing composite by GI pipe 40 mm or GI Rod 20 mm 2.5 mtr. long through GI strip |
| 377 | Galvanised Stay Set with 50x8mm stay clamp, guy insulator (2Nos.), anchor plate (200x 200 x 6 mm), nut-bolts, 2 Nos turn-buckles, 1.8m long, 16 mm diameter solid GS stay rod & 7/3.15 mm dia GI stranded wire complete |
| 378 | Survey, Supply, Transportation, Carriage, Erection, Testing and Commissioning for erection of 11KV line on 9 mtr long ST poles, with 30 mm sq. ACSR Weasel Conductor for Creation of 25 KVA Sub Station at at Upper Damak Pyt. Ressain under UT Capex Budget 2026-27. |
| 379 | 9 mtr. Long ST Pole (ST 410 SP-33) |
| 380 | GI V Cross -arm with top Bracket including clamps |
| 381 | GI Channel X-arm including clamps and Angle for braces |
| 382 | 30 mm sq. ACSR Weasel conductor |
| 383 | 11 KV Polymer composite Pin Insulator 12 KV, 5 KN, lighting impulse 75 KV Positive and 80 KV Negative, Creepage distance 320mm. |
| 384 | 11 KV Polymeric Composite Disc insulator 12 KV, min failing load 45 kn, lightening impulse 75 Positive and 80 KV Negative, creepage distance 320mm with fitting |
| 385 | Galvanized Nuts and Bolts |
| 386 | Danger Plates with clamps |
| 387 | Anti Climbing device with clamps |
| 388 | Earthing complete by GI Rod 20 mm, 2.5 mtr long through G.I. Strip 25X3 mm for LT |
| 389 | Painting of 9 mtr long ST poles with two coat of Aluminium paint. |
| 390 | Galvanised Stay Set with 50x8mm stay clamp, guy insulator (2Nos.), anchor plate (200x 200 x 6 mm), nut-bolts, 2 Nos turn-buckles, 1.8m long, 16 mm diameter solid GS stay rod & 7/3.15 mm dia GI stranded wire complete |
| 391 | Survey, Supply, Transportation, Carriage, Erection, Testing and Commissioning for Creation of 25 KVA Sub Station at Upper Damak Pyt. Ressain under UT Capex Budget 2026-27 |
| 392 | 11/0.433kV, 3-phase 25 KVA Distribution Transformer WITH Bimetallic Connectors Energy Level-2, Aluminium wound and LV Cable Box Having Detachable Aluminium Gland plate |
| 393 | Gapless surge arrestor 9KV, 10KA, LA with polymer housing station type |
| 394 | 11 KV GO, AB Switch 3-phase, 3-pole, 200 Amp. Vertical |
| 395 | 11 kV Horn Gap Fuse Set 3 Phase 200A |
| 396 | 70mm² Single Core Cable,1.1kV Grade, PVC Insulated Alumnium Stranded Conductor FRLS type |
| 397 | 9 mtr. Long ST Pole (ST 410 SP-33) |
| 398 | 11kV Polymeric composite Disc Insulator 12kV, min failing load 45kN, Lightening Impulse 75kV Positive and 80kV Negative, creepage distance 320mm with tension fitting |
| 399 | GI Channel/Angle/Flat of sizes including clamps |
| 400 | Galvanized Nuts and Bolts. |
| 401 | Earthing of substation --Excavation of earth pit of dia 650 mm & depth 3000 mm, installation of Earthing pipe of 40 mm Nominal bore & 4mm wall thickness & length 2.5 mtr long as Per IS 1239. GI Strip for neutral earthing of size 50 mm x 6 mm & 32mm x 3mm for connection of transformer body, G.O Set & lightening arrestor as per IS 2629/85, GI nuts & bolts,refilled with earth enhancement materials and earth Chamber with RCC slab cover. |
| 402 | Cement Bottoming 1:2:4 mix as per REC Standards 0.5 cum per pole |
| 403 | Painting of 9 mtr ST poles with two coat of Aluminium Paint and one coat of Red oxide (Asian/Nerolac make). |
| 404 | LT Fuse Switch made of angle Iron 50X50X6mm, with aluminium Bus Bar strip 50X6mm fixed on Bus Bar Insualtor including clamps for fixing of switch |
| 405 | Survey, Supply, Transportation, Carriage, Erection, Testing and Commissioning for erection of LT line on 8 mtr long ST poles, with 30 mm sq. ACSR Weasel Conductor for Creation of 25 KVA Sub Station at Upper Damak Pyt. Ressain under UT Capex Budget 2026-27 |
| 406 | 8 mtr. Long ST Pole (ST 410 SP-15) |
| 407 | GI M Clamps for Shackle Insulator |
| 408 | 30 mm sq. ACSR Weasel Condutor. |
| 409 | Shakle Insulator |
| 410 | Galvinized Nuts and Bolts. |
| 411 | Earthing composite by GI pipe 40 mm or GI Rod 20 mm 2.5 mtr. long through GI strip |
| 412 | Galvanised Stay Set with 50x8mm stay clamp, guy insulator (2Nos.), anchor plate (200x 200 x 6 mm), nut-bolts, 2 Nos turn-buckles, 1.8m long, 16 mm diameter solid GS stay rod & 7/3.15 mm dia GI stranded wire complete |
| 413 | Survey, Supply, Transportation, Carriage, Erection, Testing and Commissioning for erection of 11KV line on 9 mtr long ST poles, with 30 mm sq. ACSR Weasel Conductor for Creation of 25 KVA Sub Station at at Trober Basantgarh under UT Capex Budget 2026-27. |
| 414 | 9 mtr. Long ST Pole (ST 410 SP-33) |
| 415 | GI V Cross -arm with top Bracket including clamps |
| 416 | GI Channel X-arm including clamps and Angle for braces |
| 417 | 30 mm sq. ACSR Weasel conductor |
| 418 | 11 KV Polymer composite Pin Insulator 12 KV, 5 KN, lighting impulse 75 KV Positive and 80 KV Negative, Creepage distance 320mm. |
| 419 | 11 KV Polymeric Composite Disc insulator 12 KV, min failing load 45 kn, lightening impulse 75 Positive and 80 KV Negative, creepage distance 320mm with fitting |
| 420 | Galvanized Nuts and Bolts |
| 421 | Danger Plates with clamps |
| 422 | Anti Climbing device with clamps |
| 423 | Earthing complete by GI Rod 20 mm, 2.5 mtr long through G.I. Strip 25X3 mm for LT |
| 424 | Painting of 9 mtr long ST poles with two coat of Aluminium paint. |
| 425 | Galvanised Stay Set with 50x8mm stay clamp, guy insulator (2Nos.), anchor plate (200x 200 x 6 mm), nut-bolts, 2 Nos turn-buckles, 1.8m long, 16 mm diameter solid GS stay rod & 7/3.15 mm dia GI stranded wire complete |
| 426 | Survey, Supply, Transportation, Carriage, Erection, Testing and Commissioning for Creation of 25 KVA Sub Station at Upper Trober Basantgarh under UT Capex Budget 2026-27 |
| 427 | 11/0.433kV, 3-phase 25 KVA Distribution Transformer WITH Bimetallic Connectors Energy Level-2, Aluminium wound and LV Cable Box Having Detachable Aluminium Gland plate |
| 428 | Gapless surge arrestor 9KV, 10KA, LA with polymer housing station type |
| 429 | 11 KV GO, AB Switch 3-phase, 3-pole, 200 Amp. Vertical |
| 430 | 11 kV Horn Gap Fuse Set 3 Phase 200A |
| 431 | 70mm² Single Core Cable,1.1kV Grade, PVC Insulated Alumnium Stranded Conductor FRLS type |
| 432 | 9 mtr. Long ST Pole (ST 410 SP-33) |
| 433 | 11kV Polymeric composite Disc Insulator 12kV, min failing load 45kN, Lightening Impulse 75kV Positive and 80kV Negative, creepage distance 320mm with tension fitting |
| 434 | GI Channel/Angle/Flat of sizes including clamps |
| 435 | Galvanized Nuts and Bolts. |
| 436 | Earthing of substation --Excavation of earth pit of dia 650 mm & depth 3000 mm, installation of Earthing pipe of 40 mm Nominal bore & 4mm wall thickness & length 2.5 mtr long as Per IS 1239. GI Strip for neutral earthing of size 50 mm x 6 mm & 32mm x 3mm for connection of transformer body, G.O Set & lightening arrestor as per IS 2629/85, GI nuts & bolts,refilled with earth enhancement materials and earth Chamber with RCC slab cover. |
| 437 | Cement Bottoming 1:2:4 mix as per REC Standards 0.5 cum per pole |
| 438 | Painting of 9 mtr ST poles with two coat of Aluminium Paint and one coat of Red oxide (Asian/Nerolac make). |
| 439 | LT Fuse Switch made of angle Iron 50X50X6mm, with aluminium Bus Bar strip 50X6mm fixed on Bus Bar Insualtor including clamps for fixing of switch |
| 440 | Survey, Supply, Transportation, Carriage, Erection, Testing and Commissioning for erection of LT line on 8 mtr long ST poles, with 30 mm sq. ACSR Weasel Conductor for Creation of 25 KVA Sub Station at Trober Basantgarh under UT Capex Budget 2026-27 |
| 441 | 8 mtr. Long ST Pole (ST 410 SP-15) |
| 442 | GI M Clamps for Shackle Insulator |
| 443 | 30 mm sq. ACSR Weasel Condutor. |
| 444 | Shakle Insulator |
| 445 | Galvinized Nuts and Bolts. |
| 446 | Earthing composite by GI pipe 40 mm or GI Rod 20 mm 2.5 mtr. long through GI strip |
| 447 | Galvanised Stay Set with 50x8mm stay clamp, guy insulator (2Nos.), anchor plate (200x 200 x 6 mm), nut-bolts, 2 Nos turn-buckles, 1.8m long, 16 mm diameter solid GS stay rod & 7/3.15 mm dia GI stranded wire complete |
| 448 | Survey, Supply, Transportation, Carriage, Erection, Testing and Commissioning for erection of 11KV line on 9 mtr long ST poles, with 30 mm sq. ACSR Weasel Conductor for Creation of 100 KVA Sub Station at at Samroli Narsoo under UT Capex Budget 2026-27. |
| 449 | 9 mtr. Long ST Pole (ST 410 SP-33) |
| 450 | GI V Cross -arm with top Bracket including clamps |
| 451 | GI Channel X-arm including clamps and Angle for braces |
| 452 | 30 mm sq. ACSR Weasel conductor |
| 453 | 11 KV Polymer composite Pin Insulator 12 KV, 5 KN, lighting impulse 75 KV Positive and 80 KV Negative, Creepage distance 320mm. |
| 454 | 11 KV Polymeric Composite Disc insulator 12 KV, min failing load 45 kn, lightening impulse 75 Positive and 80 KV Negative, creepage distance 320mm with fitting |
| 455 | Galvanized Nuts and Bolts |
| 456 | Danger Plates with clamps |
| 457 | Anti Climbing device with clamps |
| 458 | Earthing complete by GI Rod 20 mm, 2.5 mtr long through G.I. Strip 25X3 mm for LT |
| 459 | Painting of 9 mtr long ST poles with two coat of Aluminium paint. |
| 460 | Galvanised Stay Set with 50x8mm stay clamp, guy insulator (2Nos.), anchor plate (200x 200 x 6 mm), nut-bolts, 2 Nos turn-buckles, 1.8m long, 16 mm diameter solid GS stay rod & 7/3.15 mm dia GI stranded wire complete |
| 461 | Survey, Supply, Transportation, Carriage, Erection, Testing and Commissioning for Creation of 100 KVA Sub Station at Samroli Narsoo under UT Capex Budget 2026-27 |
| 462 | 11/0.433kV, 3-phase 100 KVA Distribution Transformer of latest Energy efficiency Level-2 (NEW) , IS 1180 Part-I 2014 as per latest uptodate commendment with externally fitted MCCB with cable Box 4x4 mtrs suitable cable of ratings |
| 463 | Gapless surge arrestor 9KV, 10KA, LA with polymer housing station type |
| 464 | 11 KV GO, AB Switch 3-phase, 3-pole, 200 Amp. Vertical |
| 465 | 11 kV Horn Gap Fuse Set 3 Phase 200A |
| 466 | 120 mm² Single Core Cable,1.1kV Grade, PVC Insulated Alumnium Stranded Conductor FRLS type |
| 467 | 9 mtr. Long ST Pole (ST 410 SP-33) |
| 468 | 11kV Polymeric composite Disc Insulator 12kV, min failing load 45kN, Lightening Impulse 75kV Positive and 80kV Negative, creepage distance 320mm with tension fitting |
| 469 | GI Channel/Angle/Flat of sizes including clamps |
| 470 | Galvanized Nuts and Bolts. |
| 471 | Earthing of substation --Excavation of earth pit of dia 650 mm & depth 3000 mm, installation of Earthing pipe of 40 mm Nominal bore & 4mm wall thickness & length 2.5 mtr long as Per IS 1239. GI Strip for neutral earthing of size 50 mm x 6 mm & 32mm x 3mm for connection of transformer body, G.O Set & lightening arrestor as per IS 2629/85, GI nuts & bolts,refilled with earth enhancement materials and earth Chamber with RCC slab cover. |
| 472 | 11 KV Polymer composite Pin Insulator 12 KV, 5 KN, lighting impulse 75 KV Positive and 80 KV Negative, Creepage distance 320mm. |
| 473 | Galvanised Stay Set with 50x8mm stay clamp, guy insulator (2Nos.), anchor plate (200x 200 x 6 mm), nut-bolts, 2 Nos turn-buckles, 1.8m long, 16 mm diameter solid GS stay rod & 7/3.15 mm dia GI stranded wire complete |
| 474 | PG Clamps |
| 475 | Danger Plates with clamps |
| 476 | GI Barbed wire for Anticlimbing |
| 477 | 3-phase 4 wire LT Prodigy meter |
| 478 | Cement Bottoming 1:2:4 mix as per REC Standards 0.5 cum per pole |
| 479 | Painting of 9 mtr ST poles with two coat of Aluminium Paint and one coat of Red oxide (Asian/Nerolac make). |
| 480 | Survey, Supply, Transportation, Carriage, Erection, Testing and Commissioning for erection of LT line on 8 mtr long ST poles, with 30 mm sq. ACSR Weasel Conductor for Creation of 100 KVA Sub Station at Samroli Narsoo under UT Capex Budget 2026-27 |
| 481 | 8 mtr. Long ST Pole (ST 410 SP-15) |
| 482 | GI M Clamps for Shackle Insulator |
| 483 | 30 mm sq. ACSR Weasel Condutor. |
| 484 | Shakle Insulator |
| 485 | Galvinized Nuts and Bolts. |
| 486 | Earthing composite by GI pipe 40 mm or GI Rod 20 mm 2.5 mtr. long through GI strip |
| 487 | Galvanised Stay Set with 50x8mm stay clamp, guy insulator (2Nos.), anchor plate (200x 200 x 6 mm), nut-bolts, 2 Nos turn-buckles, 1.8m long, 16 mm diameter solid GS stay rod & 7/3.15 mm dia GI stranded wire complete |
| 488 | Survey, Supply, Transportation, Carriage, Erection, Testing and Commissioning for erection of 11KV line on 9 mtr long ST poles, with 30 mm sq. ACSR Weasel Conductor for Creation of 100 KVA Sub Station at at Narda Dharmthal under UT Capex Budget 2026-27. |
| 489 | 9 mtr. Long ST Pole (ST 410 SP-33) |
| 490 | GI V Cross -arm with top Bracket including clamps |
| 491 | GI Channel X-arm including clamps and Angle for braces |
| 492 | 30 mm sq. ACSR Weasel conductor |
| 493 | 11 KV Polymer composite Pin Insulator 12 KV, 5 KN, lighting impulse 75 KV Positive and 80 KV Negative, Creepage distance 320mm. |
| 494 | 11 KV Polymeric Composite Disc insulator 12 KV, min failing load 45 kn, lightening impulse 75 Positive and 80 KV Negative, creepage distance 320mm with fitting |
| 495 | Galvanized Nuts and Bolts |
| 496 | Danger Plates with clamps |
| 497 | Anti Climbing device with clamps |
| 498 | Earthing complete by GI Rod 20 mm, 2.5 mtr long through G.I. Strip 25X3 mm for LT |
| 499 | Painting of 9 mtr long ST poles with two coat of Aluminium paint. |
| 500 | Galvanised Stay Set with 50x8mm stay clamp, guy insulator (2Nos.), anchor plate (200x 200 x 6 mm), nut-bolts, 2 Nos turn-buckles, 1.8m long, 16 mm diameter solid GS stay rod & 7/3.15 mm dia GI stranded wire complete |
| 501 | Survey, Supply, Transportation, Carriage, Erection, Testing and Commissioning for Creation of 100 KVA Sub Station at Narda Dharmthal under UT Capex Budget 2026-27 |
| 502 | 11/0.433kV, 3-phase 100 KVA Distribution Transformer of latest Energy efficiency Level-2 (NEW) , IS 1180 Part-I 2014 as per latest uptodate commendment with externally fitted MCCB with cable Box 4x4 mtrs suitable cable of ratings |
| 503 | Gapless surge arrestor 9KV, 10KA, LA with polymer housing station type |
| 504 | 11 KV GO, AB Switch 3-phase, 3-pole, 200 Amp. Vertical |
| 505 | 11 kV Horn Gap Fuse Set 3 Phase 200A |
| 506 | 120 mm² Single Core Cable,1.1kV Grade, PVC Insulated Alumnium Stranded Conductor FRLS type |
| 507 | 9 mtr. Long ST Pole (ST 410 SP-33) |
| 508 | 11kV Polymeric composite Disc Insulator 12kV, min failing load 45kN, Lightening Impulse 75kV Positive and 80kV Negative, creepage distance 320mm with tension fitting |
| 509 | GI Channel/Angle/Flat of sizes including clamps |
| 510 | Galvanized Nuts and Bolts. |
| 511 | Earthing of substation --Excavation of earth pit of dia 650 mm & depth 3000 mm, installation of Earthing pipe of 40 mm Nominal bore & 4mm wall thickness & length 2.5 mtr long as Per IS 1239. GI Strip for neutral earthing of size 50 mm x 6 mm & 32mm x 3mm for connection of transformer body, G.O Set & lightening arrestor as per IS 2629/85, GI nuts & bolts,refilled with earth enhancement materials and earth Chamber with RCC slab cover. |
| 512 | 11 KV Polymer composite Pin Insulator 12 KV, 5 KN, lighting impulse 75 KV Positive and 80 KV Negative, Creepage distance 320mm. |
| 513 | Galvanised Stay Set with 50x8mm stay clamp, guy insulator (2Nos.), anchor plate (200x 200 x 6 mm), nut-bolts, 2 Nos turn-buckles, 1.8m long, 16 mm diameter solid GS stay rod & 7/3.15 mm dia GI stranded wire complete |
| 514 | PG Clamps |
| 515 | Danger Plates with clamps |
| 516 | GI Barbed wire for Anticlimbing |
| 517 | 3-phase 4 wire LT Prodigy meter |
| 518 | Cement Bottoming 1:2:4 mix as per REC Standards 0.5 cum per pole |
| 519 | Painting of 9 mtr ST poles with two coat of Aluminium Paint and one coat of Red oxide (Asian/Nerolac make). |
| 520 | Survey, Supply, Transportation, Carriage, Erection, Testing and Commissioning for erection of LT line on 8 mtr long ST poles, with 30 mm sq. ACSR Weasel Conductor for Creation of 100 KVA Sub Station at Narda Dharmthal under UT Capex Budget 2026-27 |
| 521 | 8 mtr. Long ST Pole (ST 410 SP-15) |
| 522 | GI M Clamps for Shackle Insulator |
| 523 | 30 mm sq. ACSR Weasel Condutor. |
| 524 | Shakle Insulator |
| 525 | Galvinized Nuts and Bolts. |
| 526 | Earthing composite by GI pipe 40 mm or GI Rod 20 mm 2.5 mtr. long through GI strip |
| 527 | Galvanised Stay Set with 50x8mm stay clamp, guy insulator (2Nos.), anchor plate (200x 200 x 6 mm), nut-bolts, 2 Nos turn-buckles, 1.8m long, 16 mm diameter solid GS stay rod & 7/3.15 mm dia GI stranded wire complete |
| 528 | Survey, Supply, Transportation, Carriage, Erection, Testing and Commissioning for erection of 11KV line on 9 mtr long ST poles, with 30 mm sq. ACSR Weasel Conductor for Creation of 63 KVA Sub Station at at Katwalt W.No. 08 (Gourikund) under UT Capex Budget 2026-27. |
| 529 | 9 mtr. Long ST Pole (ST 410 SP-33) |
| 530 | GI V Cross -arm with top Bracket including clamps |
| 531 | GI Channel X-arm including clamps and Angle for braces |
| 532 | 30 mm sq. ACSR Weasel conductor |
| 533 | 11 KV Polymer composite Pin Insulator 12 KV, 5 KN, lighting impulse 75 KV Positive and 80 KV Negative, Creepage distance 320mm. |
| 534 | 11 KV Polymeric Composite Disc insulator 12 KV, min failing load 45 kn, lightening impulse 75 Positive and 80 KV Negative, creepage distance 320mm with fitting |
| 535 | Galvanized Nuts and Bolts |
| 536 | Danger Plates with clamps |
| 537 | Anti Climbing device with clamps |
| 538 | Earthing complete by GI Rod 20 mm, 2.5 mtr long through G.I. Strip 25X3 mm for LT |
| 539 | Painting of 9 mtr long ST poles with two coat of Aluminium paint. |
| 540 | Galvanised Stay Set with 50x8mm stay clamp, guy insulator (2Nos.), anchor plate (200x 200 x 6 mm), nut-bolts, 2 Nos turn-buckles, 1.8m long, 16 mm diameter solid GS stay rod & 7/3.15 mm dia GI stranded wire complete |
| 541 | Survey, Supply, Transportation, Carriage, Erection, Testing and Commissioning for Creation of 63 KVA Sub Station at Katwalt W.No. 08 (Gourikund) under UT Capex Budget 2026-27 |
| 542 | 11/0.433kV, 3-phase 63 KVA Distribution Transformer of latest Energy efficiency Level-2 (NEW) , IS 1180 Part-I 2014 as per latest uptodate commendment with externally fitted MCCB with cable Box 4x4 mtrs suitable cable of ratings |
| 543 | Gapless surge arrestor 9KV, 10KA, LA with polymer housing station type |
| 544 | 11 KV GO, AB Switch 3-phase, 3-pole, 200 Amp. Vertical |
| 545 | 11 kV Horn Gap Fuse Set 3 Phase 200A |
| 546 | 120 mm² Single Core Cable,1.1kV Grade, PVC Insulated Alumnium Stranded Conductor FRLS type |
| 547 | 9 mtr. Long ST Pole (ST 410 SP-33) |
| 548 | 11kV Polymeric composite Disc Insulator 12kV, min failing load 45kN, Lightening Impulse 75kV Positive and 80kV Negative, creepage distance 320mm with tension fitting |
| 549 | GI Channel/Angle/Flat of sizes including clamps |
| 550 | Galvanized Nuts and Bolts. |
| 551 | Earthing of substation --Excavation of earth pit of dia 650 mm & depth 3000 mm, installation of Earthing pipe of 40 mm Nominal bore & 4mm wall thickness & length 2.5 mtr long as Per IS 1239. GI Strip for neutral earthing of size 50 mm x 6 mm & 32mm x 3mm for connection of transformer body, G.O Set & lightening arrestor as per IS 2629/85, GI nuts & bolts,refilled with earth enhancement materials and earth Chamber with RCC slab cover. |
| 552 | 11 KV Polymer composite Pin Insulator 12 KV, 5 KN, lighting impulse 75 KV Positive and 80 KV Negative, Creepage distance 320mm. |
| 553 | Galvanised Stay Set with 50x8mm stay clamp, guy insulator (2Nos.), anchor plate (200x 200 x 6 mm), nut-bolts, 2 Nos turn-buckles, 1.8m long, 16 mm diameter solid GS stay rod & 7/3.15 mm dia GI stranded wire complete |
| 554 | PG Clamps |
| 555 | Danger Plates with clamps |
| 556 | GI Barbed wire for Anticlimbing |
| 557 | 3-phase 4 wire LT Prodigy meter |
| 558 | Cement Bottoming 1:2:4 mix as per REC Standards 0.5 cum per pole |
| 559 | Painting of 9 mtr ST poles with two coat of Aluminium Paint and one coat of Red oxide (Asian/Nerolac make). |
| 560 | Survey, Supply, Transportation, Carriage, Erection, Testing and Commissioning for erection of LT line on 8 mtr long ST poles, with 30 mm sq. ACSR Weasel Conductor for Creation of 63 KVA Sub Station at Katwalt W.No. 08 (Gourikund) under UT Capex Budget 2026-27 |
| 561 | 8 mtr. Long ST Pole (ST 410 SP-15) |
| 562 | GI M Clamps for Shackle Insulator |
| 563 | 30 mm sq. ACSR Weasel Condutor. |
| 564 | Shakle Insulator |
| 565 | Galvinized Nuts and Bolts. |
| 566 | Earthing composite by GI pipe 40 mm or GI Rod 20 mm 2.5 mtr. long through GI strip |
| 567 | Galvanised Stay Set with 50x8mm stay clamp, guy insulator (2Nos.), anchor plate (200x 200 x 6 mm), nut-bolts, 2 Nos turn-buckles, 1.8m long, 16 mm diameter solid GS stay rod & 7/3.15 mm dia GI stranded wire complete |
| 568 | Survey, Supply, Transportation, Carriage, Erection, Testing and Commissioning for erection of 11KV line on 9 mtr long ST poles, with 30 mm sq. ACSR Weasel Conductor for Creation of 63 KVA Sub Station at at Kossar under UT Capex Budget 2026-27. |
| 569 | 9 mtr. Long ST Pole (ST 410 SP-33) |
| 570 | GI V Cross -arm with top Bracket including clamps |
| 571 | GI Channel X-arm including clamps and Angle for braces |
| 572 | 30 mm sq. ACSR Weasel conductor |
| 573 | 11 KV Polymer composite Pin Insulator 12 KV, 5 KN, lighting impulse 75 KV Positive and 80 KV Negative, Creepage distance 320mm. |
| 574 | 11 KV Polymeric Composite Disc insulator 12 KV, min failing load 45 kn, lightening impulse 75 Positive and 80 KV Negative, creepage distance 320mm with fitting |
| 575 | Galvanized Nuts and Bolts |
| 576 | Danger Plates with clamps |
| 577 | Anti Climbing device with clamps |
| 578 | Earthing complete by GI Rod 20 mm, 2.5 mtr long through G.I. Strip 25X3 mm for LT |
| 579 | Painting of 9 mtr long ST poles with two coat of Aluminium paint. |
| 580 | Galvanised Stay Set with 50x8mm stay clamp, guy insulator (2Nos.), anchor plate (200x 200 x 6 mm), nut-bolts, 2 Nos turn-buckles, 1.8m long, 16 mm diameter solid GS stay rod & 7/3.15 mm dia GI stranded wire complete |
| 581 | Survey, Supply, Transportation, Carriage, Erection, Testing and Commissioning for Creation of 63 KVA Sub Station at Kossar under UT Capex Budget 2026-27 |
| 582 | 11/0.433kV, 3-phase 63 KVA Distribution Transformer of latest Energy efficiency Level-2 (NEW) , IS 1180 Part-I 2014 as per latest uptodate commendment with externally fitted MCCB with cable Box 4x4 mtrs suitable cable of ratings |
| 583 | Gapless surge arrestor 9KV, 10KA, LA with polymer housing station type |
| 584 | 11 KV GO, AB Switch 3-phase, 3-pole, 200 Amp. Vertical |
| 585 | 11 kV Horn Gap Fuse Set 3 Phase 200A |
| 586 | 120 mm² Single Core Cable,1.1kV Grade, PVC Insulated Alumnium Stranded Conductor FRLS type |
| 587 | 9 mtr. Long ST Pole (ST 410 SP-33) |
| 588 | 11kV Polymeric composite Disc Insulator 12kV, min failing load 45kN, Lightening Impulse 75kV Positive and 80kV Negative, creepage distance 320mm with tension fitting |
| 589 | GI Channel/Angle/Flat of sizes including clamps |
| 590 | Galvanized Nuts and Bolts. |
| 591 | Earthing of substation --Excavation of earth pit of dia 650 mm & depth 3000 mm, installation of Earthing pipe of 40 mm Nominal bore & 4mm wall thickness & length 2.5 mtr long as Per IS 1239. GI Strip for neutral earthing of size 50 mm x 6 mm & 32mm x 3mm for connection of transformer body, G.O Set & lightening arrestor as per IS 2629/85, GI nuts & bolts,refilled with earth enhancement materials and earth Chamber with RCC slab cover. |
| 592 | 11 KV Polymer composite Pin Insulator 12 KV, 5 KN, lighting impulse 75 KV Positive and 80 KV Negative, Creepage distance 320mm. |
| 593 | Galvanised Stay Set with 50x8mm stay clamp, guy insulator (2Nos.), anchor plate (200x 200 x 6 mm), nut-bolts, 2 Nos turn-buckles, 1.8m long, 16 mm diameter solid GS stay rod & 7/3.15 mm dia GI stranded wire complete |
| 594 | PG Clamps |
| 595 | Danger Plates with clamps |
| 596 | GI Barbed wire for Anticlimbing |
| 597 | 3-phase 4 wire LT Prodigy meter |
| 598 | Cement Bottoming 1:2:4 mix as per REC Standards 0.5 cum per pole |
| 599 | Painting of 9 mtr ST poles with two coat of Aluminium Paint and one coat of Red oxide (Asian/Nerolac make). |
| 600 | Survey, Supply, Transportation, Carriage, Erection, Testing and Commissioning for erection of LT line on 8 mtr long ST poles, with 30 mm sq. ACSR Weasel Conductor for Creation of 63 KVA Sub Station at Kossar under UT Capex Budget 2026-27 |
| 601 | 8 mtr. Long ST Pole (ST 410 SP-15) |
| 602 | GI M Clamps for Shackle Insulator |
| 603 | 30 mm sq. ACSR Weasel Condutor. |
| 604 | Shakle Insulator |
| 605 | Galvinized Nuts and Bolts. |
| 606 | Earthing composite by GI pipe 40 mm or GI Rod 20 mm 2.5 mtr. long through GI strip |
| 607 | Galvanised Stay Set with 50x8mm stay clamp, guy insulator (2Nos.), anchor plate (200x 200 x 6 mm), nut-bolts, 2 Nos turn-buckles, 1.8m long, 16 mm diameter solid GS stay rod & 7/3.15 mm dia GI stranded wire complete |
| 608 | Supply of Aluminium Ladder Telescopic 15 feet long to Divisional Store ED udhampur Please Enable Macros to View BoQ information |
| SR No | FileName | File Description |
| 1 | Click here to download tender document | Tender Documents |
| 2 | Click here to download tender document | Tender Documents |
| 3 | Click here to download tender document | Tender Documents |
| 4 | Click here to download tender document | Tender Documents |
| 5 | Click here to download tender document | Tender Documents |
Copyright © 2026 · All Rights Reserved. Terms of Usage | Privacy Policy
For Tender Information Services Visit : TenderDetail