Tender for Permanent Restoration By Way Of Providing Laying And Fitting Of Hdpe Pipes Of Gravity Main And Distribution System, Steel Wire Rope Crossing And Construction Of Anchor Block Of Water Supply Scheme Khari And Water Supply Scheme Dalgote Under Sasci.(Permanent Restoration Of Water Supply Schemes Of Hydraulic Division Ramban)
BOQ
| Sl. No. | Item Description |
| 1 | Earth work in excavation by manual means in trenches for foundations, drains, pipes, cables etc. (not exceeding 1.5 m in width) and for shafts, wells, cesspits and the like not exceeding 10 sqm on plan, including dressing of sides and ramming of bottoms lift upto 1.5 m, including getting out excavated earth and disposal of surplus excavated earth as directed:all kinds of soil : |
| 2 | Earth work in excavation by manual means in trenches for foundations, drains, pipes, cables etc. (not exceeding 1.5 m in width) and for shafts, wells, cesspits and the like not exceeding 10 sqm on plan, including dressing of sides and ramming of bottoms lift upto 1.5 m, including getting out excavated earth and disposal of surplus excavated earth as directed by engineer in charge :all kinds of soil : |
| 3 | Providing and laying in position specified grade of reinforced cement concrete including curing but excluding the cost of centering, shuttering, finishing and reinforcement. All works upto plinth level 1:2:4 (1cement: 2coarse sand: 4 graded stone aggregate 20mm nomina lsize) |
| 4 | Steel reinforcementfor R.C.C. work including straightening,cutting, bending, placing in position and binding all complete upto plinth levelCold twisted bars |
| 5 | Providing and fixing HDPE pipes (all clases) complete with necessary fitting of pipe special as per BIS specification excluding the trenching and refilling etc PE-80,PN-10 IS : 4984: 2016. HDPE pipe 50 mm dia |
| 6 | Providing and fixing HDPE pipes (all clases) complete with necessary fitting of pipe special as per BIS specification excluding the trenching and refilling etc PE-80,PN-10 IS : 4984: 2016. HDPE pipe 40 mm dia |
| 7 | Providing and fixing HDPE pipes (all clases) complete with necessary fitting of pipe special as per BIS specification excluding the trenching and refilling etc PE-80,PN-10 IS : 4984: 2016. HDPE pipe 25 mm dia |
| 8 | Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundations etc. , lead upto 50 m and lift upto 1.5 m. |
| 9 | Providing and fixing of steel wire rope 12 mm dia |
| 10 | Labour engaged for stretching of steel wire rope |
| 11 | Hire charges for providing and operating chain pully block ( including supporting frame/tripod arrangement) Complete with skilled operator, lifting and lowering of materials all tools as directed by the Engineer Incharge. |
| 12 | Providing and fixing of U- clamps ( complete job). |
| 13 | Providing and fixing of Flat Iron clamps/hooks (complete job) |
| 14 | Centering and shuttering including strutting, propping etc. and removal of form for: Foundations, footings, bases of columns etc. for mass concrete. |
| 15 | Carriage of Cement from nearest source to site of work Av. 1000 mtr by manual means. |
| 16 | Carriage of Steel from nearest source to site of work Av. 1000 mtr by manual means. |
| 17 | Carriage of Sand from source to site of work Av. 150 Km by Mechanical Transport and 1000 Mtr by Manual Means. |
| 18 | Carriage of Stone Aggregate 20mm Nominal Size from source to site of work Av. 40 Km by Mechanical Transport and 1000 mtr by Manual Means. |
| 19 | Carriage of HDPE Pipe from Jammu to site of work Av. 150 Km by Mechanical Transport and 3000 mtr by Manual Means. |
| 20 | Carriage of HDPE Pipe from Jammu to site of work Av. 150 Km by Mechanical Transport and 8000 mtr by Manual Means. Please Enable Macros to View BoQ information |
AI Tender Summary
Tender Timeline
Tender Published
Tender notice published.
CompletedBid Submission Deadline
Online submission via eProcurement portal.
Upcoming · 8 daysBid Opening Date
Technical bids will be opened and evaluated.
Upcoming · 9 daysTender Documents
Download All (ZIP) ↓We takes all possible care for accurate & authentic tender information. However users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender