| 1 | Earthwork in excavation for structures as per drawing and MoRTH specifications Clause 304.1 including setting out, construction of shoring and bracing, removal of stumps and other deleterious material and disposal upto a lead of 50 m, dressing of sides and bottom and backfilling in trenches with excavated suitable material.Ordinary soil Upto 3 m depth |
| 2 | Providing concrete for plain/reinforced concrete in open foundations complete as per drawings and MoRTH specifications Clause 1702, 1703, 2102 & 2104 P.C.C grade M 15 Nominal mix (1:2.5:5) |
| 3 | Stone masonry in cement mortar for substructure complete as per drawing & MoRTH specification Clauses 1402, 1405 & 2200 Random rubble masonry In 1:4 cement mortar |
| 4 | Plain/reinforced cement concrete in substructure complete as per drawings and MoRTH specification Clauses 1700 and 2200 P.C.C grade M 15 Nominal mix (1:2.5:5) |
| 5 | Providing PCC M-20 architectural coping on the top of wing wall, return wall etc. complete as per drawing and MoRTH specification Clauses 1313, 1411 and 2206.6 50 mm thick |
| 6 | Pointing with cement mortar (1:3) on Stone work as per drawing and MoRTH specification Clauses 1406 and 2200 |
| 7 | Providing and laying reinforced cement concrete pipe NP4 for culverts on first class bedding of granular material in single row including fixing collar with cement mortar 1:2 but excluding excavation, protection works, backfilling, concrete and masonry works in head walls and parapets Clause 2905.(1000MM) |
| 8 | Construction of embankment with approved material obtained from borrow pits with a lift upto 1.5 m, transporting to site, spreading, grading to required slope and compacting to meet requirement of Tables 300-1 and 300-2 with a lead upto 50 m as per MoRTH Specification Clause 305.3 |
| 9 | Providing laying spreading and compacting specified graded sand, gravel (crushed stone) as per Table 400-1,400-2 or any other course material as per design mix, as per CBR in sub base course including premixing the material at OMC in wet mix plant, carriage of mixed material spreading in uniform layers with motor grader F.E loader on a prepared base and compacting with vibratory roller to achieve desired density (as per I.S.2720) including all material, labor, machinery, lighting guarding, barricading and maintenance of diversion complete.[MoRTH specification : Clause 401]. By mechanical means.For Grading-IV Material |
| 10 | Providing, laying, spreading and compacting stone aggregates of specific sizes to water bound macadam specification including spreading in uniform thickness, hand packing, rolling with smooth wheel roller 80-100 kN in stages to proper grade and camber, applying and brooming, stone screening to fill-up the interstices of coarse aggregate, watering and compacting to the required density Grading 2 as per MoRTH Specification Clause 404. using Crusher borken aggregateBy Mechanical Means |
| 11 | Construction of un-reinforced, plain cement concrete pavement, thickness as per design, over a prepared sub base, with 43 grade cement or any other type as per Clause 602.2.2 M30 (Grade), coarse and fine aggregates conforming to IS:383, maximum size of coarse aggregate not exceeding 25 mm, mixed in a concrete mixer of not less than 0.5 cum capacity and appropriate weigh batcher using approved mix design, laid in approved fixed Side Formwork (steel channel, laying and fixing of 125 micron thick polythene film, wedges, steel plates including levelling the formwork as per drawing), spreading the concrete with shovels, rakes, compacted using needle, screed and plate vibrators and finished in continuous operation including provision of contraction and expansion, construction joints, applying debonding strips, primer, sealant near approaches to bridge/culvert and construction joints, admixtures as approved, curing of concrete slabs for 14-days, using water finishing to lines and grade as per drawing and MoRTH Specification Clause 602 including vaccum dewatering process with all required equipments (Dowel Bars will be paid seprately) |
| 12 | Providing and Fixing of Dowel Bars of Mild Steel confirming to IS : 432 of specified length and diameters as per MoRTH Specification IRC 15 & 58 including cutting, placing in position across transverse joint with proper spacing, providing with PVC sleeve complete as per drawing, technical specification and as per direction of the Engineer-in-charge. Please Enable Macros to View BoQ information |