Petroleum and Natural Gas Boards / Undertakings / PSU Closing in 7 days TDR #56180932

Tender For Hiring Of Agencies For Gas Connectivity Works To Industrial And Commercial Consumer On 18 Months Annual Rate Contract (Arc) Basis For Giridh-Dhanbad, Saraikela-Kharsawan West Singhbhum, Dewas, Raisensehore-Shajapur (Rss), Meerut, Taj Trape

Issued by Boards / Undertakings / PSU · Ghaziabad, Uttar Pradesh
Tender Value
Ref. Documents
Estimated cost
Bid Submission
17 Jul 2026
7 days left
EMD
20 Lakhs
Bank guarantee accepted
Document Fee
Ref. Documents
Non-refundable
Tender Type
Online

Tender Overview

Competition Type
NCB
Bidding Type
Tender
Location / State
Ghaziabad → Uttar Pradesh
EMD Exemption
Available
Quantity
Not Available

Project Description

Tender for Hiring Of Agencies For Gas Connectivity Works To Industrial And Commercial Consumer On 18 Months Annual Rate Contract (Arc) Basis For Giridh-Dhanbad, Saraikela-Kharsawan West Singhbhum, Dewas, Raisensehore-Shajapur (Rss), Meerut, Taj Trapezium Zone (Ttz), Puri-Ganjam-Nayagarh, Sundergarh Jharsuguda Geographical Areas (Gas) Of Gail Gas Limited.

BOQ

Name of Work:- HIRING OF AGENCIES FOR GAS CONNECTIVITY WORKS TO INDUSTRIAL AND COMMERCIAL CONSUMER ON 18 MONTHS ANNUAL RATE CONTRACT (ARC) BASIS FOR GIRIDH-DHANBAD, SARAIKELA-KHARSAWAN WEST SINGHBHUM, DEWAS, RAISENSEHORE-SHAJAPUR (RSS), MEERUT, TAJ TRAPEZIUM ZONE (TTZ), PURI-GANJAM-NAYAGARH, SUNDERGARH JHARSUGUDA GEOGRAPHICAL AREAS (GAs) OF GAIL GAS LIMITED.
Sl. No. Item Description
1Ground Connectivity Works
2Laying of MDPE pipeline by any method in any type of soil strata upto 20m length from charged Pipeline to Customer premise including connection of Transistion Fitting at customer end. For pipeline laid more than 20m, payment for additonal length shall be covered in SOR no.2 in ruuning meters more than 20m.
3PE 20mm dia
4PE 32mm dia
5PE 63mm dia
6PE 90mm dia.
7Survey, Pit Excavtion in all types of soills/PCC/RCC/Paver block/Ashpalt/Whitetopping etc., charged pipeline identification, Hook up activities, Online tapping either by Saddle / Tee / extension by Coupler for connecting the Pipeline laid as per above SOR 1.1 including fittings, Backfilling. Restoration shall be paid through other SOR
8Connectiviy for PE 20mm dia laid under 1a.
9Connectiviy for PE 32mm dia laid under 1a.
10Connectiviy for PE 63mm dia laid under 1a.
11Connectiviy for PE 90mm dia laid under 1a.
12PE PIPELINE
13PE Pipe Laying in any type of surface like unprepared surface (Katcha surface)/ Normal Surface/ Hard surface/Rock surface etc using open cut/ Moling (without Casing)/ Moling (with Casing)/ Horizontal Directional Drilling technique (with and without casing pipe) methodology. HDD at Hard Rock shall be paid through different SOR.
14Receipt. Loading. unloading. storing. reloading. tranportation. unloading. stringing and laying of PE100. SDR11 line pipes of all sizes including. proper stacking. identification.and supply of accessories of all sizes & thickness like PE Bends. Couplers. Endcaps. Tee. Reducer. CS / GI to PE Fittings (i.e. Transition Fittings of sizes 20 mm to 90 mm). Warning Mat etc. Handling. Stringing / uncoiling. aligning of the PE line pipe on the pipeline Right-of-Use / route. laying / installation of PE line pipe alongwith required accessories as mentioned above as per specification wherever required depending on site condition including execution of all works; Storeage of material in contractor's store. fabrication. access for construction procurement and supply of all materials. consumables. equipments. labour and other inputs.
15In the case of free issue items. the scope also includes. receiving and loading from Owner's designated store. transportation. unloading and stacking of free issue items at Contractor's store. -Laying of all PE pipe (PE 100 SDR11). Including supply of HDPE casing pipe (in case of HDD (with case).Moling(with case) . Couplers. End caps etc. (Ref. of Particular job specification).Survey of under ground utilities. execution of the work as per specification. including excavation of pits moling with the hole size not exceeding 20% of the pipe dia. jointing and insertion of carrier pipe with casing. testing & commissioning and restoration of the pits to original condition. submission of As-Built Graph as per specifications and the instruction of Engineer-in-charge.
16Casing details is as given below:-1. For 20/32 mm PE pipe (in 75 mm dia. HDPE Casing Pipe. PE 63/80 PN6.0).2. For 63 mm PE pipe (in 125 mm dia. HDPE Casing Pipe. PE 63/80 PN6.0).
17Carrying out all temporary. ancillary. auxiliary works required to make the PE pipeline ready for commissioning as per drawings. Specifications. scope of work indicated in PJS and other provisions of tender/ contract documents and instructions of Engineer-in-charge. including but not limited to carrying out the following works:Surveying of route and detours required at the time of execution. preparation of construction drawings showing survey details and submit same to Owner for review / approval.
18Carrying out preliminary activities such as preperation of drawings wherever required for crossing etc.Preparation and getting approval of schedules. execution procedures. drawings/ sketches/ wherever required. making trial pits to determine the underground utilities/ services etc.. restoration of the abandoned trial pits to original condition.
19Stacking and installation of construction markers. clearing. fencing. grubbing. cutting of trees. full filling all the requirements of various statutory/ environment authorities to the entire satisfaction of concerned authorities. grading of work area.
20Barricading the work area as per local authorities norms & to the satisfaction of Owner/ Eingineer -in- charge. installation of safety signs.Barricading the pipeline construction area prior to execution of the works as per drawing enclosed with tender/ contract documents and to the entire satisfaction of owner / engineer- in -charge.
21Laying using open trench without casing includes survey of under ground utilities (through trial pits). execution of work as per specification including Trenching to all depths by excavation in all types of soils including soft/ rocky strata and different type of pavement / footpath / roads etc. including rock breaking. chiselling or otherwise cutting etc. as required and storing excavated soil. reusable materials at designated area as directed by Engineer in charge and to a width to accommodate the pipeline as per the relevant standard/ specification etc.
22The minimum depth of the top of pipeline shall be 1.0 m measured from top of pipeline to the top of undisturbed surface of the soil or as per Specification/ OISD- 226 & PNGRB latest guidelines whichever is higher.Dewatering of trenches / pits if required as per site condition. Repairing of all damaged utilities if any. and payment of any compensation (if claimed by owner / other utility agencies)Uncoiling / stringing & aligning of PE pipes. clamping. jointing of the pipe ends / fittings / valves by qualified personnel using approved electro-fusion techniques as per specification.Note:- Coordinates to be taken for implementation for GIS for Valve pit, Fusion welding location and MRS.
23Installation / lowering the pipeline in trench to required depth as per PJS. Technical Specification & drawings. supply & placement of HDPE Yellow colour warning mat (refer PJS) over the pipeline along the complete route as per standard drawings. data sheets & technical specifications. padding around pipeline including supply of suitable padding material duly approved by EIC. Backfilling to its original condition with excavated earth / borrowed select soil/sand duly approved by EIC & its compaction & crowning. At certain specific area of ROU. trench shall be backfilled & compacted and shall be made ready for motorable and no seperate payment shall be admissible against this activity.All tiles / slabs / curb stones etc removed during excavation shall be placed properly.Restoration shall be carried as per separate SOR item mentioned elsewhere in the SOR or to be done by Owner / concerned authorities.
24The scope of work against this item also include Electro-fusion jointing of valves. fittings wherever required and as directed by Engineer-in-charge.The scope of work against laying of 20 mm pipe also includes works like making of PCC pedastal of grade (1:2:4) and size ( (300mm(L)X200mm(W) XHeight (H)). (H>=300mm & will be as per site condition) ). supply and installation of GI Sleeve (Heavy (C-Class) as per IS-1239). filling of sand and installation of TF (along with supply).
25Pneumatic testing. purging with nitrogen and commissioning as per specification and approved procedures providing all tools and tackles. nitrogen. instruments. manpower and other related accessories and as per the instructions of the Engineer-in-charge.
26Final clean-up of right-of-use or area disturbed by contractor during their construction activities for laying of pipeline works and disposal of debris and surplus material to designated disposal areas and backfilling of trench and compaction of the same as per satisfaction of Owner and / or as directed by Engineer–in–charge.
27Maintaining the completed pipelines and installation for any defect or failures during defect liability period (i.e. 12 months from date of completion of work).Handing over the completed works to Owner for their operation/ use. reconciliation of material area wise and obtaining \\"no objection certificate\\" from Owner/ PMC.Preparation and submission of Daily progress report. Laying Graphs / PE line cards on daily basis.
28On completion of gas charging of pipelines. Preparation and submission of As-built drawings. crossings details. termination. utility graphs and deviation statements.In case. the minimum required depth is not possible due to site condition. necessary mitigation measures with minimum permissible top cover shall be carried out by the contractor in consultation with EIC as per PNGRB Guidelines. without any time and cost implecation to owner.
29Submission of all documents required for contract closure in numbers as mentioned in contract.Any other activities not mentioned / covered explicitly above. but otherwise required for satisfactory completion / operation / safety / statutory / maintenance of the works shall also be covered under the scope of work and has to be completed by the Contractor within specified schedule at no extra cost to Owner. All the work shall be executed in accordance with the provision of contract.
3020 mm PE 100 pipe
3132 mm PE 100 pipe
3263 mm PE 100 pipe
3390 mm PE 100 pipe
34NOTE i) The lengths of pipelines are tentative. ii) For restoration of asphalt / concrete roads. the item for construction of asphalt top / concrete top / Tiles/Stone slab/Paver Blocks/Curb Stones shall be paid separately as per the rates quoted for the same elsewhere in the SOR 2.4.
35GPR Survey for identification of pipeline
36Laying of Pipeline by HDD in Rock Terrain
3732 mm PE 100 pipe
3863 mm PE 100 pipe
3990 mm PE 100 pipe
40Restoration
41Restoration of the roads. pavements. channels. footpaths. tiles. stones etc. to original condition including supply of the approved quality material required. as per local authorities norms. obtaining NOC from concerned local authorities / land owners / third party inspection agencies (if any) designated by owner and to the satisfaction of Engineer-in-charge.
42Asphalting
43Cement Concrete
44Tiles/Stone slab/Paver Blocks/Curb Stones
45Brick Soling / Channels. etc.
46Installation of valve in pit including supply of valves
47Supply of isolation valves (as per data sheet) and installtion of valves in the valve pits as per typical drawing and specification enclosed and instructions of Engineer-in-charge. Payment of valve pits shall be paid separately as per SOR 2.6.
48PE Valve 20 mm dia
49PE Valve 32 mm dia
50PE Valve 63 mm dia
51PE Valve 90 mm dia
52Construction of Valve Pits as per the enclosed tender drawing and specification. The item includes supply of all the material including Pre-cast RCC cover. shuttering. reinforcement. labour. curing etc as per the drawings. specification and instruction of EIC.
53Type-I having Internal size of Minimum 1000 x 1000mm
54Type-II having Internal size of Minimum 600 x 600mm
55Note: The tender drawing enclosed is only for reference purpose and contractor shall be required to prepare drawings (in line with reference tender drawing) for specific sizes of Valve pits and the same shall be approved by EIC.
56Fabrication & Installation of Markers
57RCC Route Markers
58Supply, fabrication and installation of RCC route markers as per the attached drawing in technical volume, along the route including all associated civil works such as excavation and construction in all types of soils, construction and pedestals and grouting with concrete.
59Pole Markers with Foundation
60Supply, fabrication and installation of plate markers as per the attached drawings in technical volume including all associated civil works such as excavation and construction in all types of soils, construction and pedestals and grouting with concrete, cleaning, stencil let.
61Warning Plate Markers
62Supply, fabrication and installation of plate markers, including application of approved color and quality of primer and paint, stencil letter cutting of lettering, numbers, direction, etc. as per the attached drawing in technical volume to be installed near regulator.
63Excavation of Hard rock/surface
64Excavation of trench or pits, wherever hard rock presence is exceeding 1.5 m in any direction of the trench and excavation of trench or pits in Malba/Multiple layers of asphalt/ brick / PCC/RCC etc and removable only by pneumatic chisel / drill as per the specifications and direction of EIC. The rates are payable over and above the Laying rates as per relevant SOR no. 2.1
65Cutting of PCC/RCC surface with thickness more than 12\\" or Continuous asphalt multi-layer/ Malba/ Brick / Boulders more than 24\\".(Malba shall be considered as a strata where soil is in mixed form of debris/building rubbish or discarded pieces of bricks/stones )
66Rock Cutting encountered while excavation of trenches for item 2.1 of SOR, not exceeding 1.5 meter in width, and lift upto 1.5 meter, including getting out the excavated soil and disposal of excavated soil as directed within a lead of 50 meter. In case of rocky soil, the bedding shall be done with approved/ good quality packing sand, subject to the approval of the EIC, the size distribution of the sand / shall be the same as per soil. The packing sand shall be placed to a minimum thickness of 150mm around the pipe in case of rocky terrain.
67Note: i) The quantities mentioned are indicative only. ii) For all the supply items mentioned above, procurement shall be made as per specification after due approval of engineer- in - charge.
68Liaisoning with Land Owning Agencies for Permission
69Submission of applications as per approved drawings (Initial Route survey, prepartion of drawing, measuring and providing details of surface type shall be in scope of contractor), obtaining and submission of demand note, coordination, Liaisoning, obtaining written permission from land owing agencies like NHAI, AAI,Indian Railways and any other government agencies resposible for maintaining public lands and agencies owing Private lands etc. (all fee paid to authorities excluding demand charges or Bank Guarantees shall be reimbursed against documentary evidence). Permissions required from various authorities like NHAI / Railways / Irrigation (Canal) etc. falling enroute shall be inclusive in the item rate. No separate liasion charges against construction of valve chambers is payable and is included in laying rates.
70Construction of RCC structure for protection of service line for drain/nallah Crossings
71Construction of Non suspended slabs/pavement slabs including pedestal/ramp etc.using reinforced cement concrete of M-25 grade (Concrete shall be design mix/nominal mix with 20 mm & down size graded crushed stone aggregates) to protect the PE pipe laid. All necessary form work, finishing the top surface rough/smooth as required in any position, shape, level and thickness etc. shall be as specified and directed by EIC. The rates shall include grouting of pockets, supply of all material, tools, reinforcement steel etc.
72Preservation of Pipeline
73Preservation of pipeline sections and associated facilities (in event of delay in comissioning, other unforeseen reasons) including supply of nitrogen, all consumables, all equipment, man-power, etc. complete as per the requirements of specifications, other provisions of tender/ contract documents and instructions of Engineer-in-charge.
74By filling and pressurizing with nitrogen to a pressure of 2 bar(g) for a period of one month or part thereof.
75For 20 mm Pipeline
76For 32 mm Pipeline
77For 63 mm Pipeline
78For every additional period of one month or part thereof Limited to 6 month
79For 20 mm Pipeline
80For 32 mm Pipeline
81For 63 mm Pipeline
82Notes: i) The above length is not for a single section but for no. of sections. ii) All accessrious ie; End caps and two nos tappings of 3/4 inches, PG to be considered per section and rate for the same shall be quoted by bidder under this item.iii) If month is partially complete, payment shall be made on prorata basis.iv) Scope includes pressure holding for a period of 6 months or as per EIC and jointing of PE pipe (if required) due to damage by any means and further filling of nitrogen for pressure holding.v) Length given are tantative may change as per site requirments.
83CIVIL WORKS
84Earth Work
85Earth in excavation and filling to the grades and levels shown in the approved drawings in all kinds of conditions including for Road embakments, using approved quality good earth from designated borrow area, for all heights and depths including clearing and stripping (min. 150 mm) of the area marked for filling, taking spot levels, consolidating the exposed natural soil surface, excavating the earth from borrow area loading, transporting & unloading, spreading in layers not exceeding 150 mm thickness, breaking clods, watering (if reqd.), ramming and compacting by manual/ mechanical means to give minimum 92% of modified Proctor's density of earth, testing & dressing including disposal of all unserviceable material all complete as per specifications and directions of Engineer-in-charge.
86(Rate to include cost of all labour, tools, tackles, equipment, hire chanrges, cost of borrow earth by way of royalties, right of way, cess etc., as applicable with all bye works and sundry works).
87PCC 1:2:4
881 Cement : 2 Coarse sand : 4 stone aggregate 20mm nominal size.
89PCC 1:4:8
901 Cement : 4 Coarse sand : 8 stone aggregate 40mm nominal size.
91(Rate to include cost of all labour, tools, tackles, equipment, hire charges, supply of all materials, shuttering, earthwork in excavation and backfilling using approved earth in all conditions etc. with all bye works and sundry works.)
92Reinforced Cement Concrete
93Providing and laying reinforced cement of grade M-25 with 20mm and down grade crushed stone aggregate in all types of structures like foundations, pedestals, pedestal bases, pipe supports, sleepers, column, equipment foundation, Non suspended slabs/pavement slabs, ramps, cable trench inlcuding construction joints, bitumen painting on surface in contact with soil, supplying and fixing reinforcing steel, shuttering, inserts, finishes, grounting etc. at all depths and heights complete as per drawings, specifications and direction of the Engineer-in-charge.
94Rate to include cost of all labour, tools, tackles, equipment, hire charges, supply of all maerials such as minimum 43 grade cement including sulphate resistant cement for sub-structures, R/F steel, Inserts, bolts, conduits, bitumen, other minor constrcution materials, shuttering, stanging, earthwork in excavation and backfilling using serviceable earth in all conditions, shorting bailing and pumping out water, testing of concrete, curing etc. with all bye works and sundry works.
95Concrete Pavement
96Providing and laying reinforced cement concrete of (M-25 grade) with 20mm and down grade crushed stone aggregate in pavement, including preparation of base (i.e. compacted subgrade, 200 thk sand and 50 thk PCC M-10 grade), leaving pockets if necessary, making recess, projections, fixing inserts conduit pipes (GI, PVC, HDPE, etc.) laying in alternate panels, filling the gaps between the panels with bitumen etc., making slopes, finishing edges, leaving bars for pedestals & sleepers including providing sand fill isolation , shuttering, providing and fixing reinforcing steel, curing, chipping and modification works etc. as specified in any shape, thickness, position and finishing the top surface smooth as per requirement etc. all complete as per drawings, specifications and directions of the Engineer-in-charge.
97Concrete Pavement- 150mm thick (Type-I)
98Brick Work
99Providing brick work with brick class designation M-7.5 of IS:1077 in cm1:4 (1 cement : 4 sand) in steps, walls, retaining walls and load bearing structures drains, or any shape with all lead, depths & height including curring, scaffolding, etc., as per specifications and drawings with all bye-works and direction of the Enfineer-in-charge.
100(Rate to include cost of all labour, tools, tackles, equipment, hire charges, supply of all materials such as minimum 43 grade cement, bricks, finishes, bitumen, other minor constrcution materials, shuttering, staging, masonry work, plastering, painting etc. with all bye-works and sundry works).
101Note: The quantites of individual item can varied as per site requirement.The payment will be made as per actual certified measurement at site.
102Laying of Brick layer/ Concrete
103Providing single layer of Brick / Concrete / or impact resistant tape to entire width of trench above Warning Mat placed in trench over the laid pipeline as per OISD 226, standard drawing, specification and instruction of Owner. (Rate to include cost of all labour, tools, tackles, equipment, hire charges & supply of all materials, etc)
104Brick Layer for width of PE pipeline trench as per drawing (75 mm thk.)
105Concrete for width of PE pipeline trench as per drawing (80 mm thk.)
106Demolition of PCC work below plinth level
107Demolishing plain cement concrete (PCC) work (taking all necessary safety precautions) for all depths below plinth level including supply of all tools & tackles, necessary scaffolding, propping, underpinning, etc. , disposal of unserviceable material outside the boundary limits keeping the owner indemnified of any liabilities from statutory/ local bodies, all complete work as specified and directed.
108Excavation for foundation works
109Excavation as per plan, upto 3 meters and upto any lead in all conditions, backfilling using serviceable earth and disposal of surplus and unserviceable earth. Soil to be levelled and neatly dressed complete in all respect as per scope of work, technical specification and directions of EIC.
110Upto 3.0 Mtrs
111Dismantling of RCC & cutting of reinforcement (Thickness above 3”)
112Structural Works
113Supplying, fabricating & fixing steel structural cage fabricated from Angle conforming to IS:808 & fixing of GI weldmesh made from 3mm GI wire @ 75 mm bothways to structural steel frame by means of welding/bolting, including applying two coats of approved quality of synthetic enamel paint over a priming coat of in approved shade including supply of all raw materials, bolts, electrodes, transportation, including Hilti arrangement ,locking arrangement for fixing of posts etc complete as per enclosed drawing, technical specifications, scope of works and directions of the Engineer-In-Charge. Note:- Material shall be supplied and fabricated as per site condition and Contractor have to take quantity approval from EIC/OWNER prior to commencement of work and order placement.
114MRS / Metering Skid/Wall Mounted MRS.
115Installation of MRS / Metering Skid on foundation
116Receiving and taking over, handling, loading, transportation and unloading of MRS / Metering Skid from Owner's designated stockyards to site, installation at foundation and hooking up with PE pipe including all works as required to complete the job as per the drawings and specification, scope of work mentioned in tender doucment. The scope includes supply of transition fittings,GI Sleeve, other MDPE and CS fittings as required and various associated works to commission MRS / Metering Skid. (Note:- The installation included CS piping work included welding, testing, NDT etc.,however payment for the CS piping work along with accessories supply will be paid in SOR item 7.0 to 25.0 respectively.)
117Note: 1) Amount towards civil work shall be payable as per related SOR items. 2) Rate to include cost of all labour, tools, tackles, equipment, hire charges.3) All fittings and consumables including Bolts, nuts, washer, U-clamps, gaskets etc. if required during installation shall be procured and supplied by the Contractor within the rate quoted. These items shall not be separately measured and paid.
118MRS / Metering Skid <2000 SCMD
119MRS / Metering Skid 2000-5000 SCMD
120MRS / Metering Skid 5000-20000 SCMD
121MRS / Metering Skid >20000 SCMD
122Installation of Wall Mounted Metering System (Meter, Regulator & Accessory) locked in cage
123Receiving and taking over, handling, loading, transportation and unloading of all items for Wall Mounted Metering System (Meter, Regulator & Accessory) from Owner's designated stockyards to site, installation on wall and hooking up with PE pipe including all works as required to complete the job as per the drawings and specification, scope of work mentioned in tender doucment.The scope includes supply of items required as per the drawing in scope of work (Details of drawings as PJS) viz. transition fittings, GI/Concrete Sleeves and other MDPE and CS fittings etc. as required and various associated works.(Only Meters and Regulators shall be provided as free issue) and all associated works (For CS pipe and other items refer sl. no. 7.0 to 25.0) to commission Wall Mounted Metering System. Note : Installation works included CS piping work, Testing etc.,however payment for the CS piping work along accessories will be paid in diiferent SOR item
124Note: 1) Amount towards civil work shall be payable as per relevant SOR items. 2) Rate to include cost of all labour, tools, tackles, equipment, hire charges .3) All fittings (those are not mentioned in SOR item 7.0 to 25.0) and consumables including Bolts, nuts, washer, U-clamps, gaskets etc. if required during installation shall be procured and supplied by the Contractor within the rate quoted. These items shall not be separately measured and paid.4)The wall mounted Metering System to be kept in cage with locking facility, However payment for Structural work will be paid against SOR item 4.0
125The Typical Design of MRS/Metering System are as per \\"Standardized metering system Design, Selection & Installation philosophy for supply of PNG to Industrial and Commercial Customers of GAIL Gas.\\"Note: -The sizes mentioned in drawings are indicative & may vary as per actual requirment at site .
126Wall Mounted Metering System < 200 SCMD
127Wall Mounted Metering System 200-500 SCMD
128Wall mounted Metering System 500 to 2000 SCMD
129Wall mounted Metering System >2000 SCMD
130Note: i) The quantities mentioned are indicative only. ii) For all the supply items mentioned above, procurement shall be made as per specification after due approval of engineer- in - charge.
131Installation of Wall Mounted Metering System (Pre-assemble)
132Receiving and taking over, handling, loading, transportation and unloading of all items for Wall Mounted Metering System (Pre-assembled as per standard drawing Attached in PJS Drawing ) from Owner's designated stockyards to site, installation on wall and hooking up with PE pipe including all works as required to complete the job as per the drawings and specification, scope of work mentioned in tender doucment.The scope includes supply of transition fittings, Sleeves and other MDPE and CS fittings etc. as required and various associated works, however, the Metering System assembly ( As per drawing ) shall be provided as free issue by GAIL Gas. Installtion work done by Contractor along supply of consumables including Bolts, nuts, washer, U-clamps, gaskets etc. if required during installation shall be procured and supplied by the Contractor within the rate quoted.
133Note: 1) Amount towards civil work shall be payable as per related SOR items 3.0. 2) Rate to include cost of all labour, tools, tackles, equipment, hire charges .3) The wall mounted Metering System to be kept in cage with locking facility, However payment for Structural work will be paid against SOR item 4.0
134Installation of GI Pipe 2\\" - 1\\" size with isolation valve for commercial meter inlet connection from TF
135Removal of MRS/ Metering Skids, Wall Mounted MRS/Metering System (all capacities) from existing consumer's premise,
136Removal of MRS/ Metering Skids, Wall Mounted Metering System (all capacities) from existing consumer's premise for shifting to another site/store. The scope of work also includes excavation to retrive PE pipe line , disconnection of existing pipe lines (PE & Steel).
137Note:- Transportaion of removed metering skid/Wall mounted Metering System to store shall be payble under SOR item no.5.4.2. However, if this skid is being shifted directly to new location for installation at new customer premises then transportation to be claimed from 5.1 & 5.2 as applicable.
138Transportaion of removed metering skid/Wall mounted Metering System to store
139Conversion of Commercial Appliances/Industrial :
140Conversions of all types of commercial appliances to NG based appliances. Supply & changing of the nozzles /jets and associated controls for Non-domestic appliances (imported appliances included) with proper tools and tackles. Cleaning and performing minor maintenance, greasing etc. of the appliance. Testing and showing the performance to the customer, signing of joint meter records (JMR) and instructing the customer on use & safety norms, complete as per specifications & to satisfaction of owner / Engineer in Charge and includes supply of reinforced rubber hose with requisite pressure rating.Supply of Appliance valve is also included.
141Installation of ASTM A106, Gr. B, Seamless, BE , NB, XS pipes of various dia
142ASTM A106, Gr. B, Seamless, PE , 1/2\\" NB, S160 , their fittings and installation of meter and regulator (as applicable)
143ASTM A106, Gr. B, Seamless, PE , 1\\" NB, XS , their fittings and installation of meter and regulator (as applicable)
144ASTM A106, Gr. B, Seamless, PE, 1.5\\" NB, XS , their fittings and installation of meter and regulator (as applicable)
145ASTM A106, Gr. B (Charpy), Seamless, BE , 2\\" NB, XS , their fittings and installation of meter and regulator (as applicable)
146ASTM A106, Gr. B (Charpy), Seamless, BE , 3\\" NB,XS , their fittings and installation of meter and regulator (as applicable)
147ASTM A106, Gr. B (Charpy), Seamless, BE , 4\\" NB,XS , their fittings and installation of meter and regulator (as applicable)
148Note:a). Supply & Installation of required size of brass fittings (which are not included in SOR item 8.0 to 23.0) in all type of meters (supplied by GAIL GAS LTD. ) shall be in scope of contractor.b). All butt welded fittings end shall generally match with connecting pipe wall thickness. However, in case of misalignment, Contractor shall have to do end preparation without any extra cost. c). Payment of radiography of joints (4\\" and below ) shall be paid seperately under SOR item for RADIOGRAPHY mentioned elsewhere in this SOR 25.0d). All type of piping works shall be carried out as per piping material specification (PMS).e). Complete Carbon Steel Piping Work with painting including all fittings, flanges and supply of all required gaskets, studs bolts & nuts etc.
149Supply of CARBON STEEL PIPES as per Technical Specification and as directed by EIC
150ASTM A106, Gr. B, Seamless, PE , 1/2\\" NB, S160
151ASTM A106, Gr. B, Seamless, PE , 1\\" NB, XS
152ASTM A106, Gr. B, Seamless, PE, 1.5\\" NB, XS
153ASTM A106, Gr. B (Charpy), Seamless, BE , 2\\" NB, XS
154ASTM A106, Gr. B (Charpy), Seamless, BE , 3\\" NB,XS
155ASTM A106, Gr. B (Charpy), Seamless, BE , 4\\" NB,XS
156Supply of Pressure Gauges as per Technical Specification and as directed by EIC
157RANGE 0-100 MBAR - 4\\"- DIAL SIZE
158RANGE 0-1 BAR - 4\\"- DIAL SIZE
159RANGE 0-4 BAR - 4\\"- DIAL SIZE
160RANGE 0-6 BAR - 4\\"- DIAL SIZE
161RANGE 0-30 BAR - 4\\"- DIAL SIZE
162Supply of Conical Stainer
163As per Technical Specification and as directed by EIC.Note: - Conical Stainer may be free issue by Gail Gas Ltd., It is Discretion of Gail Gas Ltd. to excute the SOR or Free Issue the material.
164Supply of Check valve/NRVAs per Technical Specification and as directed by EIC.
1652\\", 150# FE,FB
1663\\", 150# FE,FB
1674\\", 150# FE,FB
168Supply of Flanges Weld Neck(End Thickness to match pipe thickness)
1691\\" , 150#, B-16.5 , A105 ,125 AARH,SW,RF
1701.5\\" , 150#, B-16.5 , A105 ,125 AARH,SW,RF
1712\\",150#, B-16.5, A105 (Charpy), 125 AARH, RF
1723\\",150#, B-16.5, A105 (Charpy), 125 AARH, RF
1734\\",150#, B-16.5, A105 (Charpy), 125 AARH, RF
174Supply of Blind FlangesAs per Technical Specification and as directed by EIC.
1752\\",150#, B-16.5, A105 (Charpy), 125 AARH, RF
1763\\",150#, B-16.5, A105 (Charpy), 125 AARH, RF
1774\\",150#, B-16.5, A105 (Charpy), 125 AARH, RF
178Supply of End Caps
1792\\", XS, A 234 Gr. WPB (Charpy), BW
1803\\", XS, A 234 Gr. WPB (Charpy), BW
1814\\", XS, A 234 Gr. WPB (Charpy), BW
182Supply of FLANGE END GLOBE VALVES, MAOP- 4 BARAs per Technical Specification and as directed by EIC.
183Supply of Ball ValvesAs per Technical Specification and as directed by EIC.
1841/2\\",800#, Sockolet Welded/Threaded Valve
1851\\",800#, Sockolet Welded/Threaded Valve
1862\\",150#,FE, FB,
1873\\",150#,FE, FB,
1884\\",150#,FE, FB,
189Supply of Isolation Ball Valve And Appliance Valve as per Technical Specification and as directed by EIC
190Isolation Ball Valve ½\\" max. 6 bar (g)
191Isolation Ball Valve 1\\" max. 6 bar (g)
192Isolation Ball Valve 1.5\\" max. 6 bar (g)
193Isolation Ball Valve 2\\" max. 6 bar (g)
194Isolation Ball Valve 3\\" max. 6 bar (g)
195Supply of SOCKOLET (A105, SW) As per Technical Specification and as directed by EIC.
1962\\" x ½\\"
1972\\" x 1\\"
1983\\" x ½\\"
1993\\" x 1\\"
2004\\" x ½\\"
2014\\" x 1\\"
202Supply of Reducer (A 234 Gr. WPB (Charpy), BW)
2031.5\\" x 1\\", XS x XS, A105, SW,3000#, B-16.11
2042\\"x1\\", XS x XS, A 234 Gr. WPB (Charpy), BW, B-16.9
2052\\" X 1.5\\", XS , A 234 Gr. WPB (Charpy), BW, B-16.9
2063\\"x1\\", XS x XS, A 234 Gr. WPB (Charpy), BW, B-16.9
2073\\" X 1.5\\", XS , A 234 Gr. WPB (Charpy), BW, B-16.9
2083\\" x 2\\" , STD x XS, A 234 Gr. WPB (Charpy), BW, B-16.9
2094\\" x 3\\" , STD x XS, A 234 Gr. WPB (Charpy), BW, B-16.9
210Supply of Tee, Equal / Reducing Tee
2111\\", XS, SW, 3000#, B-16.11
2121.5\\", XS, A105, SW, 3000#, B-16.11
2132\\" x 1.5\\", XS , A234, Gr. WPB (Charpy), B-16.9, BW
2142\\", XS , A234, Gr. WPB (Charpy), B-16.9, BW
2153\\", STD , A234, Gr. WPB (Charpy), B-16.9, BW
2164\\" STD x XS, A234, Gr. WPB (Charpy), B-16.9, BW
217Supply of ELBOW, 90° Elbow
218½\\", XS, SW, 3000#, ASTM A105,B-16.11
2191\\", XS, SW, 3000#, ASTM A105,B-16.11
2201.5\\", XS, SW, 3000#, ASTM A105,B-16.11
2212\\", XS, BW, A234, Gr. WPB (Charpy), B-16.9, 1.5D
2223\\", STD, BW, A234, Gr. WPB (Charpy), B-16.9, 1.5D
2234\\", XS, BW, A234, Gr. WPB (Charpy), B-16.9, 1.5D
224Supply of Spectacle Blind AS PER SPECIFICATION
225Spectacle Blind 2\\"
226Spectacle Blind 3\\"
227Spectacle Blind 4\\"
228Supply of Internal/external piping support (AS PER Tender)
229TYPE-1, SIDE WALL MOUNTED AS PER DRAWING
230TYPE-2, GROUND BASED AS PER DRAWING
231TYPE-3, CEILING MOUNTED AS PER DRAWING
232WELDING OF JOINTS - Butt Weld Joints
2331/2\\" (WELDING OF JOINTS)
2341\\" (WELDING OF JOINTS)
2351.5\\" (WELDING OF JOINTS)
2362\\" (WELDING OF JOINTS)
2373\\" (WELDING OF JOINTS)
2384\\" (WELDING OF JOINTS)
239Note: i) All butt welded fittings end shall generally match with connecting pipe wall thickness however in case of misalignment Contractor shall have to do end preparation without any extra cost.ii) All coupling, nipples etc. as required shall be supplied by contractor but no separate payments shall be made as it is covered under erection rate.
240RADIOGRAPHY OF JOINTS
241Performance of radiographic inspection by gamma radiation as per scope of work and as per specifications in piping of all types and thickness including providing/hiring of all necessary equipments, supply of all consumables, and whatever else even though not expressely mentioned but required to perform the work as per specifications and instructions of Engineer-in-Charge (full circle re-radiography of the repaired joint and additional radiography necessitated due to poor performance of contractor's welder shall be carried out by the Contractor at his own cost and shall not be paid extra by Company). Radiographs shall be submitted to the Engineer-in-Charge for acceptance, whose decision shall be final and binding.
242Note- i). 4\\" & Below and all butt weld joint are radiography / X-ray shall be done at every joint and shall be carried out as per API 1104 (latest edition) / M/s GAIL Gas Ltd. specification / OISD / PNGRB and same shall be approved by Engineer–in–charge (EIC)/RCM.ii). All socket weld joint MPT/UT/DPT shall be done at every joint nd shall be carried out as per API 1104 (latest edition)/M/s GAIL Gas Ltd. specification / OISD / PNGRB and same shall be approved by Engineer–in–charge (EIC)/ RCM.
2431/2\\" (RADIOGRAPHY of Joints as Above)
2441\\" (RADIOGRAPHY of Joints as Above)
2451.5\\" (RADIOGRAPHY of Joints as Above)
2462\\" (RADIOGRAPHY of Joints as Above)
2473\\" (RADIOGRAPHY of Joints as Above)
2484\\" (RADIOGRAPHY of Joints as Above)
249Note: i) Quantities mentioned against each above item of SOR Items are tentative and may increase or decrease during execution of work depending upon site requirement. Contractor required to supply materials after assessing the site requirement and in multiple lot or as per Release Order/ Sub Purchase Order wise. All material either in multiple lot or as per Release Order/ Sub Purchase Order wise or as decided by EIC shall be supplied by bidder within the quoted price.(ii) The quantites of individual item can varied as per site requirement.The payment will be made as per actual certified measurement at site. For the supply items the quantities shall be procured after approval from client/ consultant/EIC.(iii) The bidder must indicate currency(ies) against each quoted item of the SOR.(iv) The total amount shall also be given by the bidder in the quoted currency(ies).(v) Some of the may / may not be execute as per site requirements.
250Ground Connectivity Works
251Laying of MDPE pipeline by any method in any type of soil strata upto 20m length from charged Pipeline to Customer premise including connection of Transistion Fitting at customer end. For pipeline laid more than 20m, payment for additonal length shall be covered in SOR no.2 in ruuning meters more than 20m.
252PE 20mm dia
253PE 32mm dia
254PE 63mm dia
255PE 90mm dia.
256Survey, Pit Excavtion in all types of soills/PCC/RCC/Paver block/Ashpalt/Whitetopping etc., charged pipeline identification, Hook up activities, Online tapping either by Saddle / Tee / extension by Coupler for connecting the Pipeline laid as per above SOR 1.1 including fittings, Backfilling. Restoration shall be paid through other SOR
257Connectiviy for PE 20mm dia laid under 1a.
258Connectiviy for PE 32mm dia laid under 1a.
259Connectiviy for PE 63mm dia laid under 1a.
260Connectiviy for PE 90mm dia laid under 1a.
261PE PIPELINE
262PE Pipe Laying in any type of surface like unprepared surface (Katcha surface)/ Normal Surface/ Hard surface/Rock surface etc using open cut/ Moling (without Casing)/ Moling (with Casing)/ Horizontal Directional Drilling technique (with and without casing pipe) methodology. HDD at Hard Rock shall be paid through different SOR.
263Receipt. Loading. unloading. storing. reloading. tranportation. unloading. stringing and laying of PE100. SDR11 line pipes of all sizes including. proper stacking. identification.and supply of accessories of all sizes & thickness like PE Bends. Couplers. Endcaps. Tee. Reducer. CS / GI to PE Fittings (i.e. Transition Fittings of sizes 20 mm to 90 mm). Warning Mat etc. Handling. Stringing / uncoiling. aligning of the PE line pipe on the pipeline Right-of-Use / route. laying / installation of PE line pipe alongwith required accessories as mentioned above as per specification wherever required depending on site condition including execution of all works; Storeage of material in contractor's store. fabrication. access for construction procurement and supply of all materials. consumables. equipments. labour and other inputs.
264In the case of free issue items. the scope also includes. receiving and loading from Owner's designated store. transportation. unloading and stacking of free issue items at Contractor's store. -Laying of all PE pipe (PE 100 SDR11). Including supply of HDPE casing pipe (in case of HDD (with case).Moling(with case) . Couplers. End caps etc. (Ref. of Particular job specification).Survey of under ground utilities. execution of the work as per specification. including excavation of pits moling with the hole size not exceeding 20% of the pipe dia. jointing and insertion of carrier pipe with casing. testing & commissioning and restoration of the pits to original condition. submission of As-Built Graph as per specifications and the instruction of Engineer-in-charge.
265Casing details is as given below:-1. For 20/32 mm PE pipe (in 75 mm dia. HDPE Casing Pipe. PE 63/80 PN6.0).2. For 63 mm PE pipe (in 125 mm dia. HDPE Casing Pipe. PE 63/80 PN6.0).
266Carrying out all temporary. ancillary. auxiliary works required to make the PE pipeline ready for commissioning as per drawings. Specifications. scope of work indicated in PJS and other provisions of tender/ contract documents and instructions of Engineer-in-charge. including but not limited to carrying out the following works:Surveying of route and detours required at the time of execution. preparation of construction drawings showing survey details and submit same to Owner for review / approval.
267Carrying out preliminary activities such as preperation of drawings wherever required for crossing etc.Preparation and getting approval of schedules. execution procedures. drawings/ sketches/ wherever required. making trial pits to determine the underground utilities/ services etc.. restoration of the abandoned trial pits to original condition.
268Stacking and installation of construction markers. clearing. fencing. grubbing. cutting of trees. full filling all the requirements of various statutory/ environment authorities to the entire satisfaction of concerned authorities. grading of work area.
269Barricading the work area as per local authorities norms & to the satisfaction of Owner/ Eingineer -in- charge. installation of safety signs.Barricading the pipeline construction area prior to execution of the works as per drawing enclosed with tender/ contract documents and to the entire satisfaction of owner / engineer- in -charge.
270Laying using open trench without casing includes survey of under ground utilities (through trial pits). execution of work as per specification including Trenching to all depths by excavation in all types of soils including soft/ rocky strata and different type of pavement / footpath / roads etc. including rock breaking. chiselling or otherwise cutting etc. as required and storing excavated soil. reusable materials at designated area as directed by Engineer in charge and to a width to accommodate the pipeline as per the relevant standard/ specification etc.
271The minimum depth of the top of pipeline shall be 1.0 m measured from top of pipeline to the top of undisturbed surface of the soil or as per Specification/ OISD- 226 & PNGRB latest guidelines whichever is higher.Dewatering of trenches / pits if required as per site condition. Repairing of all damaged utilities if any. and payment of any compensation (if claimed by owner / other utility agencies)Uncoiling / stringing & aligning of PE pipes. clamping. jointing of the pipe ends / fittings / valves by qualified personnel using approved electro-fusion techniques as per specification.Note:- Coordinates to be taken for implementation for GIS for Valve pit, Fusion welding location and MRS.
272Installation / lowering the pipeline in trench to required depth as per PJS. Technical Specification & drawings. supply & placement of HDPE Yellow colour warning mat (refer PJS) over the pipeline along the complete route as per standard drawings. data sheets & technical specifications. padding around pipeline including supply of suitable padding material duly approved by EIC. Backfilling to its original condition with excavated earth / borrowed select soil/sand duly approved by EIC & its compaction & crowning. At certain specific area of ROU. trench shall be backfilled & compacted and shall be made ready for motorable and no seperate payment shall be admissible against this activity.All tiles / slabs / curb stones etc removed during excavation shall be placed properly.Restoration shall be carried as per separate SOR item mentioned elsewhere in the SOR or to be done by Owner / concerned authorities.
273The scope of work against this item also include Electro-fusion jointing of valves. fittings wherever required and as directed by Engineer-in-charge.The scope of work against laying of 20 mm pipe also includes works like making of PCC pedastal of grade (1:2:4) and size ( (300mm(L)X200mm(W) XHeight (H)). (H>=300mm & will be as per site condition) ). supply and installation of GI Sleeve (Heavy (C-Class) as per IS-1239). filling of sand and installation of TF (along with supply).
274Pneumatic testing. purging with nitrogen and commissioning as per specification and approved procedures providing all tools and tackles. nitrogen. instruments. manpower and other related accessories and as per the instructions of the Engineer-in-charge.
275Final clean-up of right-of-use or area disturbed by contractor during their construction activities for laying of pipeline works and disposal of debris and surplus material to designated disposal areas and backfilling of trench and compaction of the same as per satisfaction of Owner and / or as directed by Engineer–in–charge.
276Maintaining the completed pipelines and installation for any defect or failures during defect liability period (i.e. 12 months from date of completion of work).Handing over the completed works to Owner for their operation/ use. reconciliation of material area wise and obtaining \\"no objection certificate\\" from Owner/ PMC.Preparation and submission of Daily progress report. Laying Graphs / PE line cards on daily basis.
277On completion of gas charging of pipelines. Preparation and submission of As-built drawings. crossings details. termination. utility graphs and deviation statements.In case. the minimum required depth is not possible due to site condition. necessary mitigation measures with minimum permissible top cover shall be carried out by the contractor in consultation with EIC as per PNGRB Guidelines. without any time and cost implecation to owner.
278Submission of all documents required for contract closure in numbers as mentioned in contract.Any other activities not mentioned / covered explicitly above. but otherwise required for satisfactory completion / operation / safety / statutory / maintenance of the works shall also be covered under the scope of work and has to be completed by the Contractor within specified schedule at no extra cost to Owner. All the work shall be executed in accordance with the provision of contract.
27920 mm PE 100 pipe
28032 mm PE 100 pipe
28163 mm PE 100 pipe
28290 mm PE 100 pipe
283NOTE i) The lengths of pipelines are tentative. ii) For restoration of asphalt / concrete roads. the item for construction of asphalt top / concrete top / Tiles/Stone slab/Paver Blocks/Curb Stones shall be paid separately as per the rates quoted for the same elsewhere in the SOR 2.4.
284GPR Survey for identification of pipeline
285Laying of Pipeline by HDD in Rock Terrain
28632 mm PE 100 pipe
28763 mm PE 100 pipe
28890 mm PE 100 pipe
289Restoration
290Restoration of the roads. pavements. channels. footpaths. tiles. stones etc. to original condition including supply of the approved quality material required. as per local authorities norms. obtaining NOC from concerned local authorities / land owners / third party inspection agencies (if any) designated by owner and to the satisfaction of Engineer-in-charge.
291Asphalting
292Cement Concrete
293Tiles/Stone slab/Paver Blocks/Curb Stones
294Brick Soling / Channels. etc.
295Installation of valve in pit including supply of valves
296Supply of isolation valves (as per data sheet) and installtion of valves in the valve pits as per typical drawing and specification enclosed and instructions of Engineer-in-charge. Payment of valve pits shall be paid separately as per SOR 2.6.
297PE Valve 20 mm dia
298PE Valve 32 mm dia
299PE Valve 63 mm dia
300PE Valve 90 mm dia
301Construction of Valve Pits as per the enclosed tender drawing and specification. The item includes supply of all the material including Pre-cast RCC cover. shuttering. reinforcement. labour. curing etc as per the drawings. specification and instruction of EIC.
302Type-I having Internal size of Minimum 1000 x 1000mm
303Type-II having Internal size of Minimum 600 x 600mm
304Note: The tender drawing enclosed is only for reference purpose and contractor shall be required to prepare drawings (in line with reference tender drawing) for specific sizes of Valve pits and the same shall be approved by EIC.
305Fabrication & Installation of Markers
306RCC Route Markers
307Supply, fabrication and installation of RCC route markers as per the attached drawing in technical volume, along the route including all associated civil works such as excavation and construction in all types of soils, construction and pedestals and grouting with concrete.
308Pole Markers with Foundation
309Supply, fabrication and installation of plate markers as per the attached drawings in technical volume including all associated civil works such as excavation and construction in all types of soils, construction and pedestals and grouting with concrete, cleaning, stencil let.
310Warning Plate Markers
311Supply, fabrication and installation of plate markers, including application of approved color and quality of primer and paint, stencil letter cutting of lettering, numbers, direction, etc. as per the attached drawing in technical volume to be installed near regulator.
312Excavation of Hard rock/surface
313Excavation of trench or pits, wherever hard rock presence is exceeding 1.5 m in any direction of the trench and excavation of trench or pits in Malba/Multiple layers of asphalt/ brick / PCC/RCC etc and removable only by pneumatic chisel / drill as per the specifications and direction of EIC. The rates are payable over and above the Laying rates as per relevant SOR no. 2.1
314Cutting of PCC/RCC surface with thickness more than 12\\" or Continuous asphalt multi-layer/ Malba/ Brick / Boulders more than 24\\".(Malba shall be considered as a strata where soil is in mixed form of debris/building rubbish or discarded pieces of bricks/stones )
315Rock Cutting encountered while excavation of trenches for item 2.1 of SOR, not exceeding 1.5 meter in width, and lift upto 1.5 meter, including getting out the excavated soil and disposal of excavated soil as directed within a lead of 50 meter. In case of rocky soil, the bedding shall be done with approved/ good quality packing sand, subject to the approval of the EIC, the size distribution of the sand / shall be the same as per soil. The packing sand shall be placed to a minimum thickness of 150mm around the pipe in case of rocky terrain.
316Note: i) The quantities mentioned are indicative only. ii) For all the supply items mentioned above, procurement shall be made as per specification after due approval of engineer- in - charge.
317Liaisoning with Land Owning Agencies for Permission
318Submission of applications as per approved drawings (Initial Route survey, prepartion of drawing, measuring and providing details of surface type shall be in scope of contractor), obtaining and submission of demand note, coordination, Liaisoning, obtaining written permission from land owing agencies like NHAI, AAI,Indian Railways and any other government agencies resposible for maintaining public lands and agencies owing Private lands etc. (all fee paid to authorities excluding demand charges or Bank Guarantees shall be reimbursed against documentary evidence). Permissions required from various authorities like NHAI / Railways / Irrigation (Canal) etc. falling enroute shall be inclusive in the item rate. No separate liasion charges against construction of valve chambers is payable and is included in laying rates.
319Construction of RCC structure for protection of service line for drain/nallah Crossings
320Construction of Non suspended slabs/pavement slabs including pedestal/ramp etc.using reinforced cement concrete of M-25 grade (Concrete shall be design mix/nominal mix with 20 mm & down size graded crushed stone aggregates) to protect the PE pipe laid. All necessary form work, finishing the top surface rough/smooth as required in any position, shape, level and thickness etc. shall be as specified and directed by EIC. The rates shall include grouting of pockets, supply of all material, tools, reinforcement steel etc.
321Preservation of Pipeline
322Preservation of pipeline sections and associated facilities (in event of delay in comissioning, other unforeseen reasons) including supply of nitrogen, all consumables, all equipment, man-power, etc. complete as per the requirements of specifications, other provisions of tender/ contract documents and instructions of Engineer-in-charge.
323By filling and pressurizing with nitrogen to a pressure of 2 bar(g) for a period of one month or part thereof.
324For 20 mm Pipeline
325For 32 mm Pipeline
326For 63 mm Pipeline
327For every additional period of one month or part thereof Limited to 6 month
328For 20 mm Pipeline
329For 32 mm Pipeline
330For 63 mm Pipeline
331Notes: i) The above length is not for a single section but for no. of sections. ii) All accessrious ie; End caps and two nos tappings of 3/4 inches, PG to be considered per section and rate for the same shall be quoted by bidder under this item.iii) If month is partially complete, payment shall be made on prorata basis.iv) Scope includes pressure holding for a period of 6 months or as per EIC and jointing of PE pipe (if required) due to damage by any means and further filling of nitrogen for pressure holding.v) Length given are tantative may change as per site requirments.
332CIVIL WORKS
333Earth Work
334Earth in excavation and filling to the grades and levels shown in the approved drawings in all kinds of conditions including for Road embakments, using approved quality good earth from designated borrow area, for all heights and depths including clearing and stripping (min. 150 mm) of the area marked for filling, taking spot levels, consolidating the exposed natural soil surface, excavating the earth from borrow area loading, transporting & unloading, spreading in layers not exceeding 150 mm thickness, breaking clods, watering (if reqd.), ramming and compacting by manual/ mechanical means to give minimum 92% of modified Proctor's density of earth, testing & dressing including disposal of all unserviceable material all complete as per specifications and directions of Engineer-in-charge.
335(Rate to include cost of all labour, tools, tackles, equipment, hire chanrges, cost of borrow earth by way of royalties, right of way, cess etc., as applicable with all bye works and sundry works).
336PCC 1:2:4
3371 Cement : 2 Coarse sand : 4 stone aggregate 20mm nominal size.
338PCC 1:4:8
3391 Cement : 4 Coarse sand : 8 stone aggregate 40mm nominal size.
340(Rate to include cost of all labour, tools, tackles, equipment, hire charges, supply of all materials, shuttering, earthwork in excavation and backfilling using approved earth in all conditions etc. with all bye works and sundry works.)
341Reinforced Cement Concrete
342Providing and laying reinforced cement of grade M-25 with 20mm and down grade crushed stone aggregate in all types of structures like foundations, pedestals, pedestal bases, pipe supports, sleepers, column, equipment foundation, Non suspended slabs/pavement slabs, ramps, cable trench inlcuding construction joints, bitumen painting on surface in contact with soil, supplying and fixing reinforcing steel, shuttering, inserts, finishes, grounting etc. at all depths and heights complete as per drawings, specifications and direction of the Engineer-in-charge.
343Rate to include cost of all labour, tools, tackles, equipment, hire charges, supply of all maerials such as minimum 43 grade cement including sulphate resistant cement for sub-structures, R/F steel, Inserts, bolts, conduits, bitumen, other minor constrcution materials, shuttering, stanging, earthwork in excavation and backfilling using serviceable earth in all conditions, shorting bailing and pumping out water, testing of concrete, curing etc. with all bye works and sundry works.
344Concrete Pavement
345Providing and laying reinforced cement concrete of (M-25 grade) with 20mm and down grade crushed stone aggregate in pavement, including preparation of base (i.e. compacted subgrade, 200 thk sand and 50 thk PCC M-10 grade), leaving pockets if necessary, making recess, projections, fixing inserts conduit pipes (GI, PVC, HDPE, etc.) laying in alternate panels, filling the gaps between the panels with bitumen etc., making slopes, finishing edges, leaving bars for pedestals & sleepers including providing sand fill isolation , shuttering, providing and fixing reinforcing steel, curing, chipping and modification works etc. as specified in any shape, thickness, position and finishing the top surface smooth as per requirement etc. all complete as per drawings, specifications and directions of the Engineer-in-charge.
346Concrete Pavement- 150mm thick (Type-I)
347Brick Work
348Providing brick work with brick class designation M-7.5 of IS:1077 in cm1:4 (1 cement : 4 sand) in steps, walls, retaining walls and load bearing structures drains, or any shape with all lead, depths & height including curring, scaffolding, etc., as per specifications and drawings with all bye-works and direction of the Enfineer-in-charge.
349(Rate to include cost of all labour, tools, tackles, equipment, hire charges, supply of all materials such as minimum 43 grade cement, bricks, finishes, bitumen, other minor constrcution materials, shuttering, staging, masonry work, plastering, painting etc. with all bye-works and sundry works).
350Note: The quantites of individual item can varied as per site requirement.The payment will be made as per actual certified measurement at site.
351Laying of Brick layer/ Concrete
352Providing single layer of Brick / Concrete / or impact resistant tape to entire width of trench above Warning Mat placed in trench over the laid pipeline as per OISD 226, standard drawing, specification and instruction of Owner. (Rate to include cost of all labour, tools, tackles, equipment, hire charges & supply of all materials, etc)
353Brick Layer for width of PE pipeline trench as per drawing (75 mm thk.)
354Concrete for width of PE pipeline trench as per drawing (80 mm thk.)
355Demolition of PCC work below plinth level
356Demolishing plain cement concrete (PCC) work (taking all necessary safety precautions) for all depths below plinth level including supply of all tools & tackles, necessary scaffolding, propping, underpinning, etc. , disposal of unserviceable material outside the boundary limits keeping the owner indemnified of any liabilities from statutory/ local bodies, all complete work as specified and directed.
357Excavation for foundation works
358Excavation as per plan, upto 3 meters and upto any lead in all conditions, backfilling using serviceable earth and disposal of surplus and unserviceable earth. Soil to be levelled and neatly dressed complete in all respect as per scope of work, technical specification and directions of EIC.
359Upto 3.0 Mtrs
360Dismantling of RCC & cutting of reinforcement (Thickness above 3”)
361Structural Works
362Supplying, fabricating & fixing steel structural cage fabricated from Angle conforming to IS:808 & fixing of GI weldmesh made from 3mm GI wire @ 75 mm bothways to structural steel frame by means of welding/bolting, including applying two coats of approved quality of synthetic enamel paint over a priming coat of in approved shade including supply of all raw materials, bolts, electrodes, transportation, including Hilti arrangement ,locking arrangement for fixing of posts etc complete as per enclosed drawing, technical specifications, scope of works and directions of the Engineer-In-Charge. Note:- Material shall be supplied and fabricated as per site condition and Contractor have to take quantity approval from EIC/OWNER prior to commencement of work and order placement.
363MRS / Metering Skid/Wall Mounted MRS.
364Installation of MRS / Metering Skid on foundation
365Receiving and taking over, handling, loading, transportation and unloading of MRS / Metering Skid from Owner's designated stockyards to site, installation at foundation and hooking up with PE pipe including all works as required to complete the job as per the drawings and specification, scope of work mentioned in tender doucment. The scope includes supply of transition fittings,GI Sleeve, other MDPE and CS fittings as required and various associated works to commission MRS / Metering Skid. (Note:- The installation included CS piping work included welding, testing, NDT etc.,however payment for the CS piping work along with accessories supply will be paid in SOR item 7.0 to 25.0 respectively.)
366Note: 1) Amount towards civil work shall be payable as per related SOR items. 2) Rate to include cost of all labour, tools, tackles, equipment, hire charges.3) All fittings and consumables including Bolts, nuts, washer, U-clamps, gaskets etc. if required during installation shall be procured and supplied by the Contractor within the rate quoted. These items shall not be separately measured and paid.
367MRS / Metering Skid <2000 SCMD
368MRS / Metering Skid 2000-5000 SCMD
369MRS / Metering Skid 5000-20000 SCMD
370MRS / Metering Skid >20000 SCMD
371Installation of Wall Mounted Metering System (Meter, Regulator & Accessory) locked in cage
372Receiving and taking over, handling, loading, transportation and unloading of all items for Wall Mounted Metering System (Meter, Regulator & Accessory) from Owner's designated stockyards to site, installation on wall and hooking up with PE pipe including all works as required to complete the job as per the drawings and specification, scope of work mentioned in tender doucment.The scope includes supply of items required as per the drawing in scope of work (Details of drawings as PJS) viz. transition fittings, GI/Concrete Sleeves and other MDPE and CS fittings etc. as required and various associated works.(Only Meters and Regulators shall be provided as free issue) and all associated works (For CS pipe and other items refer sl. no. 7.0 to 25.0) to commission Wall Mounted Metering System. Note : Installation works included CS piping work, Testing etc.,however payment for the CS piping work along accessories will be paid in diiferent SOR item
373Note: 1) Amount towards civil work shall be payable as per relevant SOR items. 2) Rate to include cost of all labour, tools, tackles, equipment, hire charges .3) All fittings (those are not mentioned in SOR item 7.0 to 25.0) and consumables including Bolts, nuts, washer, U-clamps, gaskets etc. if required during installation shall be procured and supplied by the Contractor within the rate quoted. These items shall not be separately measured and paid.4)The wall mounted Metering System to be kept in cage with locking facility, However payment for Structural work will be paid against SOR item 4.0
374The Typical Design of MRS/Metering System are as per \\"Standardized metering system Design, Selection & Installation philosophy for supply of PNG to Industrial and Commercial Customers of GAIL Gas.\\"Note: -The sizes mentioned in drawings are indicative & may vary as per actual requirment at site .
375Wall Mounted Metering System < 200 SCMD
376Wall Mounted Metering System 200-500 SCMD
377Wall mounted Metering System 500 to 2000 SCMD
378Wall mounted Metering System >2000 SCMD
379Note: i) The quantities mentioned are indicative only. ii) For all the supply items mentioned above, procurement shall be made as per specification after due approval of engineer- in - charge.
380Installation of Wall Mounted Metering System (Pre-assemble)
381Receiving and taking over, handling, loading, transportation and unloading of all items for Wall Mounted Metering System (Pre-assembled as per standard drawing Attached in PJS Drawing ) from Owner's designated stockyards to site, installation on wall and hooking up with PE pipe including all works as required to complete the job as per the drawings and specification, scope of work mentioned in tender doucment.The scope includes supply of transition fittings, Sleeves and other MDPE and CS fittings etc. as required and various associated works, however, the Metering System assembly ( As per drawing ) shall be provided as free issue by GAIL Gas. Installtion work done by Contractor along supply of consumables including Bolts, nuts, washer, U-clamps, gaskets etc. if required during installation shall be procured and supplied by the Contractor within the rate quoted.
382Note: 1) Amount towards civil work shall be payable as per related SOR items 3.0. 2) Rate to include cost of all labour, tools, tackles, equipment, hire charges .3) The wall mounted Metering System to be kept in cage with locking facility, However payment for Structural work will be paid against SOR item 4.0
383Installation of GI Pipe 2\\" - 1\\" size with isolation valve for commercial meter inlet connection from TF
384Removal of MRS/ Metering Skids, Wall Mounted MRS/Metering System (all capacities) from existing consumer's premise,
385Removal of MRS/ Metering Skids, Wall Mounted Metering System (all capacities) from existing consumer's premise for shifting to another site/store. The scope of work also includes excavation to retrive PE pipe line , disconnection of existing pipe lines (PE & Steel).
386Note:- Transportaion of removed metering skid/Wall mounted Metering System to store shall be payble under SOR item no.5.4.2. However, if this skid is being shifted directly to new location for installation at new customer premises then transportation to be claimed from 5.1 & 5.2 as applicable.
387Transportaion of removed metering skid/Wall mounted Metering System to store
388Conversion of Commercial Appliances/Industrial :
389Conversions of all types of commercial appliances to NG based appliances. Supply & changing of the nozzles /jets and associated controls for Non-domestic appliances (imported appliances included) with proper tools and tackles. Cleaning and performing minor maintenance, greasing etc. of the appliance. Testing and showing the performance to the customer, signing of joint meter records (JMR) and instructing the customer on use & safety norms, complete as per specifications & to satisfaction of owner / Engineer in Charge and includes supply of reinforced rubber hose with requisite pressure rating.Supply of Appliance valve is also included.
390Installation of ASTM A106, Gr. B, Seamless, BE , NB, XS pipes of various dia
391ASTM A106, Gr. B, Seamless, PE , 1/2\\" NB, S160 , their fittings and installation of meter and regulator (as applicable)
392ASTM A106, Gr. B, Seamless, PE , 1\\" NB, XS , their fittings and installation of meter and regulator (as applicable)
393ASTM A106, Gr. B, Seamless, PE, 1.5\\" NB, XS , their fittings and installation of meter and regulator (as applicable)
394ASTM A106, Gr. B (Charpy), Seamless, BE , 2\\" NB, XS , their fittings and installation of meter and regulator (as applicable)
395ASTM A106, Gr. B (Charpy), Seamless, BE , 3\\" NB,XS , their fittings and installation of meter and regulator (as applicable)
396ASTM A106, Gr. B (Charpy), Seamless, BE , 4\\" NB,XS , their fittings and installation of meter and regulator (as applicable)
397Note:a). Supply & Installation of required size of brass fittings (which are not included in SOR item 8.0 to 23.0) in all type of meters (supplied by GAIL GAS LTD. ) shall be in scope of contractor.b). All butt welded fittings end shall generally match with connecting pipe wall thickness. However, in case of misalignment, Contractor shall have to do end preparation without any extra cost. c). Payment of radiography of joints (4\\" and below ) shall be paid seperately under SOR item for RADIOGRAPHY mentioned elsewhere in this SOR 25.0d). All type of piping works shall be carried out as per piping material specification (PMS).e). Complete Carbon Steel Piping Work with painting including all fittings, flanges and supply of all required gaskets, studs bolts & nuts etc.
398Supply of CARBON STEEL PIPES as per Technical Specification and as directed by EIC
399ASTM A106, Gr. B, Seamless, PE , 1/2\\" NB, S160
400ASTM A106, Gr. B, Seamless, PE , 1\\" NB, XS
401ASTM A106, Gr. B, Seamless, PE, 1.5\\" NB, XS
402ASTM A106, Gr. B (Charpy), Seamless, BE , 2\\" NB, XS
403ASTM A106, Gr. B (Charpy), Seamless, BE , 3\\" NB,XS
404ASTM A106, Gr. B (Charpy), Seamless, BE , 4\\" NB,XS
405Supply of Pressure Gauges as per Technical Specification and as directed by EIC
406RANGE 0-100 MBAR - 4\\"- DIAL SIZE
407RANGE 0-1 BAR - 4\\"- DIAL SIZE
408RANGE 0-4 BAR - 4\\"- DIAL SIZE
409RANGE 0-6 BAR - 4\\"- DIAL SIZE
410RANGE 0-30 BAR - 4\\"- DIAL SIZE
411Supply of Conical Stainer
412As per Technical Specification and as directed by EIC.Note: - Conical Stainer may be free issue by Gail Gas Ltd., It is Discretion of Gail Gas Ltd. to excute the SOR or Free Issue the material.
413Supply of Check valve/NRVAs per Technical Specification and as directed by EIC.
4142\\", 150# FE,FB
4153\\", 150# FE,FB
4164\\", 150# FE,FB
417Supply of Flanges Weld Neck(End Thickness to match pipe thickness)
4181\\" , 150#, B-16.5 , A105 ,125 AARH,SW,RF
4191.5\\" , 150#, B-16.5 , A105 ,125 AARH,SW,RF
4202\\",150#, B-16.5, A105 (Charpy), 125 AARH, RF
4213\\",150#, B-16.5, A105 (Charpy), 125 AARH, RF
4224\\",150#, B-16.5, A105 (Charpy), 125 AARH, RF
423Supply of Blind FlangesAs per Technical Specification and as directed by EIC.
4242\\",150#, B-16.5, A105 (Charpy), 125 AARH, RF
4253\\",150#, B-16.5, A105 (Charpy), 125 AARH, RF
4264\\",150#, B-16.5, A105 (Charpy), 125 AARH, RF
427Supply of End Caps
4282\\", XS, A 234 Gr. WPB (Charpy), BW
4293\\", XS, A 234 Gr. WPB (Charpy), BW
4304\\", XS, A 234 Gr. WPB (Charpy), BW
431Supply of FLANGE END GLOBE VALVES, MAOP- 4 BARAs per Technical Specification and as directed by EIC.
432Supply of Ball ValvesAs per Technical Specification and as directed by EIC.
4331/2\\",800#, Sockolet Welded/Threaded Valve
4341\\",800#, Sockolet Welded/Threaded Valve
4352\\",150#,FE, FB,
4363\\",150#,FE, FB,
4374\\",150#,FE, FB,
438Supply of Isolation Ball Valve And Appliance Valve as per Technical Specification and as directed by EIC
439Isolation Ball Valve ½\\" max. 6 bar (g)
440Isolation Ball Valve 1\\" max. 6 bar (g)
441Isolation Ball Valve 1.5\\" max. 6 bar (g)
442Isolation Ball Valve 2\\" max. 6 bar (g)
443Isolation Ball Valve 3\\" max. 6 bar (g)
444Supply of SOCKOLET (A105, SW) As per Technical Specification and as directed by EIC.
4452\\" x ½\\"
4462\\" x 1\\"
4473\\" x ½\\"
4483\\" x 1\\"
4494\\" x ½\\"
4504\\" x 1\\"
451Supply of Reducer (A 234 Gr. WPB (Charpy), BW)
4521.5\\" x 1\\", XS x XS, A105, SW,3000#, B-16.11
4532\\"x1\\", XS x XS, A 234 Gr. WPB (Charpy), BW, B-16.9
4542\\" X 1.5\\", XS , A 234 Gr. WPB (Charpy), BW, B-16.9
4553\\"x1\\", XS x XS, A 234 Gr. WPB (Charpy), BW, B-16.9
4563\\" X 1.5\\", XS , A 234 Gr. WPB (Charpy), BW, B-16.9
4573\\" x 2\\" , STD x XS, A 234 Gr. WPB (Charpy), BW, B-16.9
4584\\" x 3\\" , STD x XS, A 234 Gr. WPB (Charpy), BW, B-16.9
459Supply of Tee, Equal / Reducing Tee
4601\\", XS, SW, 3000#, B-16.11
4611.5\\", XS, A105, SW, 3000#, B-16.11
4622\\" x 1.5\\", XS , A234, Gr. WPB (Charpy), B-16.9, BW
4632\\", XS , A234, Gr. WPB (Charpy), B-16.9, BW
4643\\", STD , A234, Gr. WPB (Charpy), B-16.9, BW
4654\\" STD x XS, A234, Gr. WPB (Charpy), B-16.9, BW
466Supply of ELBOW, 90° Elbow
467½\\", XS, SW, 3000#, ASTM A105,B-16.11
4681\\", XS, SW, 3000#, ASTM A105,B-16.11
4691.5\\", XS, SW, 3000#, ASTM A105,B-16.11
4702\\", XS, BW, A234, Gr. WPB (Charpy), B-16.9, 1.5D
4713\\", STD, BW, A234, Gr. WPB (Charpy), B-16.9, 1.5D
4724\\", XS, BW, A234, Gr. WPB (Charpy), B-16.9, 1.5D
473Supply of Spectacle Blind AS PER SPECIFICATION
474Spectacle Blind 2\\"
475Spectacle Blind 3\\"
476Spectacle Blind 4\\"
477Supply of Internal/external piping support (AS PER Tender)
478TYPE-1, SIDE WALL MOUNTED AS PER DRAWING
479TYPE-2, GROUND BASED AS PER DRAWING
480TYPE-3, CEILING MOUNTED AS PER DRAWING
481WELDING OF JOINTS - Butt Weld Joints
4821/2\\" (WELDING OF JOINTS)
4831\\" (WELDING OF JOINTS)
4841.5\\" (WELDING OF JOINTS)
4852\\" (WELDING OF JOINTS)
4863\\" (WELDING OF JOINTS)
4874\\" (WELDING OF JOINTS)
488Note: i) All butt welded fittings end shall generally match with connecting pipe wall thickness however in case of misalignment Contractor shall have to do end preparation without any extra cost.ii) All coupling, nipples etc. as required shall be supplied by contractor but no separate payments shall be made as it is covered under erection rate.
489RADIOGRAPHY OF JOINTS
490Performance of radiographic inspection by gamma radiation as per scope of work and as per specifications in piping of all types and thickness including providing/hiring of all necessary equipments, supply of all consumables, and whatever else even though not expressely mentioned but required to perform the work as per specifications and instructions of Engineer-in-Charge (full circle re-radiography of the repaired joint and additional radiography necessitated due to poor performance of contractor's welder shall be carried out by the Contractor at his own cost and shall not be paid extra by Company). Radiographs shall be submitted to the Engineer-in-Charge for acceptance, whose decision shall be final and binding.
491Note- i). 4\\" & Below and all butt weld joint are radiography / X-ray shall be done at every joint and shall be carried out as per API 1104 (latest edition) / M/s GAIL Gas Ltd. specification / OISD / PNGRB and same shall be approved by Engineer–in–charge (EIC)/RCM.ii). All socket weld joint MPT/UT/DPT shall be done at every joint nd shall be carried out as per API 1104 (latest edition)/M/s GAIL Gas Ltd. specification / OISD / PNGRB and same shall be approved by Engineer–in–charge (EIC)/ RCM.
4921/2\\" (RADIOGRAPHY of Joints as Above)
4931\\" (RADIOGRAPHY of Joints as Above)
4941.5\\" (RADIOGRAPHY of Joints as Above)
4952\\" (RADIOGRAPHY of Joints as Above)
4963\\" (RADIOGRAPHY of Joints as Above)
4974\\" (RADIOGRAPHY of Joints as Above)
498Note: i) Quantities mentioned against each above item of SOR Items are tentative and may increase or decrease during execution of work depending upon site requirement. Contractor required to supply materials after assessing the site requirement and in multiple lot or as per Release Order/ Sub Purchase Order wise. All material either in multiple lot or as per Release Order/ Sub Purchase Order wise or as decided by EIC shall be supplied by bidder within the quoted price.(ii) The quantites of individual item can varied as per site requirement.The payment will be made as per actual certified measurement at site. For the supply items the quantities shall be procured after approval from client/ consultant/EIC.(iii) The bidder must indicate currency(ies) against each quoted item of the SOR.(iv) The total amount shall also be given by the bidder in the quoted currency(ies).(v) Some of the may / may not be execute as per site requirements.
499Ground Connectivity Works
500Laying of MDPE pipeline by any method in any type of soil strata upto 20m length from charged Pipeline to Customer premise including connection of Transistion Fitting at customer end. For pipeline laid more than 20m, payment for additonal length shall be covered in SOR no.2 in ruuning meters more than 20m.
501PE 20mm dia
502PE 32mm dia
503PE 63mm dia
504PE 90mm dia.
505Survey, Pit Excavtion in all types of soills/PCC/RCC/Paver block/Ashpalt/Whitetopping etc., charged pipeline identification, Hook up activities, Online tapping either by Saddle / Tee / extension by Coupler for connecting the Pipeline laid as per above SOR 1.1 including fittings, Backfilling. Restoration shall be paid through other SOR
506Connectiviy for PE 20mm dia laid under 1a.
507Connectiviy for PE 32mm dia laid under 1a.
508Connectiviy for PE 63mm dia laid under 1a.
509Connectiviy for PE 90mm dia laid under 1a.
510PE PIPELINE
511PE Pipe Laying in any type of surface like unprepared surface (Katcha surface)/ Normal Surface/ Hard surface/Rock surface etc using open cut/ Moling (without Casing)/ Moling (with Casing)/ Horizontal Directional Drilling technique (with and without casing pipe) methodology. HDD at Hard Rock shall be paid through different SOR.
512Receipt. Loading. unloading. storing. reloading. tranportation. unloading. stringing and laying of PE100. SDR11 line pipes of all sizes including. proper stacking. identification.and supply of accessories of all sizes & thickness like PE Bends. Couplers. Endcaps. Tee. Reducer. CS / GI to PE Fittings (i.e. Transition Fittings of sizes 20 mm to 90 mm). Warning Mat etc. Handling. Stringing / uncoiling. aligning of the PE line pipe on the pipeline Right-of-Use / route. laying / installation of PE line pipe alongwith required accessories as mentioned above as per specification wherever required depending on site condition including execution of all works; Storeage of material in contractor's store. fabrication. access for construction procurement and supply of all materials. consumables. equipments. labour and other inputs.
513In the case of free issue items. the scope also includes. receiving and loading from Owner's designated store. transportation. unloading and stacking of free issue items at Contractor's store. -Laying of all PE pipe (PE 100 SDR11). Including supply of HDPE casing pipe (in case of HDD (with case).Moling(with case) . Couplers. End caps etc. (Ref. of Particular job specification).Survey of under ground utilities. execution of the work as per specification. including excavation of pits moling with the hole size not exceeding 20% of the pipe dia. jointing and insertion of carrier pipe with casing. testing & commissioning and restoration of the pits to original condition. submission of As-Built Graph as per specifications and the instruction of Engineer-in-charge.
514Casing details is as given below:-1. For 20/32 mm PE pipe (in 75 mm dia. HDPE Casing Pipe. PE 63/80 PN6.0).2. For 63 mm PE pipe (in 125 mm dia. HDPE Casing Pipe. PE 63/80 PN6.0).
515Carrying out all temporary. ancillary. auxiliary works required to make the PE pipeline ready for commissioning as per drawings. Specifications. scope of work indicated in PJS and other provisions of tender/ contract documents and instructions of Engineer-in-charge. including but not limited to carrying out the following works:Surveying of route and detours required at the time of execution. preparation of construction drawings showing survey details and submit same to Owner for review / approval.
516Carrying out preliminary activities such as preperation of drawings wherever required for crossing etc.Preparation and getting approval of schedules. execution procedures. drawings/ sketches/ wherever required. making trial pits to determine the underground utilities/ services etc.. restoration of the abandoned trial pits to original condition.
517Stacking and installation of construction markers. clearing. fencing. grubbing. cutting of trees. full filling all the requirements of various statutory/ environment authorities to the entire satisfaction of concerned authorities. grading of work area.
518Barricading the work area as per local authorities norms & to the satisfaction of Owner/ Eingineer -in- charge. installation of safety signs.Barricading the pipeline construction area prior to execution of the works as per drawing enclosed with tender/ contract documents and to the entire satisfaction of owner / engineer- in -charge.
519Laying using open trench without casing includes survey of under ground utilities (through trial pits). execution of work as per specification including Trenching to all depths by excavation in all types of soils including soft/ rocky strata and different type of pavement / footpath / roads etc. including rock breaking. chiselling or otherwise cutting etc. as required and storing excavated soil. reusable materials at designated area as directed by Engineer in charge and to a width to accommodate the pipeline as per the relevant standard/ specification etc.
520The minimum depth of the top of pipeline shall be 1.0 m measured from top of pipeline to the top of undisturbed surface of the soil or as per Specification/ OISD- 226 & PNGRB latest guidelines whichever is higher.Dewatering of trenches / pits if required as per site condition. Repairing of all damaged utilities if any. and payment of any compensation (if claimed by owner / other utility agencies)Uncoiling / stringing & aligning of PE pipes. clamping. jointing of the pipe ends / fittings / valves by qualified personnel using approved electro-fusion techniques as per specification.Note:- Coordinates to be taken for implementation for GIS for Valve pit, Fusion welding location and MRS.
521Installation / lowering the pipeline in trench to required depth as per PJS. Technical Specification & drawings. supply & placement of HDPE Yellow colour warning mat (refer PJS) over the pipeline along the complete route as per standard drawings. data sheets & technical specifications. padding around pipeline including supply of suitable padding material duly approved by EIC. Backfilling to its original condition with excavated earth / borrowed select soil/sand duly approved by EIC & its compaction & crowning. At certain specific area of ROU. trench shall be backfilled & compacted and shall be made ready for motorable and no seperate payment shall be admissible against this activity.All tiles / slabs / curb stones etc removed during excavation shall be placed properly.Restoration shall be carried as per separate SOR item mentioned elsewhere in the SOR or to be done by Owner / concerned authorities.
522The scope of work against this item also include Electro-fusion jointing of valves. fittings wherever required and as directed by Engineer-in-charge.The scope of work against laying of 20 mm pipe also includes works like making of PCC pedastal of grade (1:2:4) and size ( (300mm(L)X200mm(W) XHeight (H)). (H>=300mm & will be as per site condition) ). supply and installation of GI Sleeve (Heavy (C-Class) as per IS-1239). filling of sand and installation of TF (along with supply).
523Pneumatic testing. purging with nitrogen and commissioning as per specification and approved procedures providing all tools and tackles. nitrogen. instruments. manpower and other related accessories and as per the instructions of the Engineer-in-charge.
524Final clean-up of right-of-use or area disturbed by contractor during their construction activities for laying of pipeline works and disposal of debris and surplus material to designated disposal areas and backfilling of trench and compaction of the same as per satisfaction of Owner and / or as directed by Engineer–in–charge.
525Maintaining the completed pipelines and installation for any defect or failures during defect liability period (i.e. 12 months from date of completion of work).Handing over the completed works to Owner for their operation/ use. reconciliation of material area wise and obtaining \\"no objection certificate\\" from Owner/ PMC.Preparation and submission of Daily progress report. Laying Graphs / PE line cards on daily basis.
526On completion of gas charging of pipelines. Preparation and submission of As-built drawings. crossings details. termination. utility graphs and deviation statements.In case. the minimum required depth is not possible due to site condition. necessary mitigation measures with minimum permissible top cover shall be carried out by the contractor in consultation with EIC as per PNGRB Guidelines. without any time and cost implecation to owner.
527Submission of all documents required for contract closure in numbers as mentioned in contract.Any other activities not mentioned / covered explicitly above. but otherwise required for satisfactory completion / operation / safety / statutory / maintenance of the works shall also be covered under the scope of work and has to be completed by the Contractor within specified schedule at no extra cost to Owner. All the work shall be executed in accordance with the provision of contract.
52820 mm PE 100 pipe
52932 mm PE 100 pipe
53063 mm PE 100 pipe
53190 mm PE 100 pipe
532NOTE i) The lengths of pipelines are tentative. ii) For restoration of asphalt / concrete roads. the item for construction of asphalt top / concrete top / Tiles/Stone slab/Paver Blocks/Curb Stones shall be paid separately as per the rates quoted for the same elsewhere in the SOR 2.4.
533GPR Survey for identification of pipeline
534Laying of Pipeline by HDD in Rock Terrain
53532 mm PE 100 pipe
53663 mm PE 100 pipe
53790 mm PE 100 pipe
538Restoration
539Restoration of the roads. pavements. channels. footpaths. tiles. stones etc. to original condition including supply of the approved quality material required. as per local authorities norms. obtaining NOC from concerned local authorities / land owners / third party inspection agencies (if any) designated by owner and to the satisfaction of Engineer-in-charge.
540Asphalting
541Cement Concrete
542Tiles/Stone slab/Paver Blocks/Curb Stones
543Brick Soling / Channels. etc.
544Installation of valve in pit including supply of valves
545Supply of isolation valves (as per data sheet) and installtion of valves in the valve pits as per typical drawing and specification enclosed and instructions of Engineer-in-charge. Payment of valve pits shall be paid separately as per SOR 2.6.
546PE Valve 20 mm dia
547PE Valve 32 mm dia
548PE Valve 63 mm dia
549PE Valve 90 mm dia
550Construction of Valve Pits as per the enclosed tender drawing and specification. The item includes supply of all the material including Pre-cast RCC cover. shuttering. reinforcement. labour. curing etc as per the drawings. specification and instruction of EIC.
551Type-I having Internal size of Minimum 1000 x 1000mm
552Type-II having Internal size of Minimum 600 x 600mm
553Note: The tender drawing enclosed is only for reference purpose and contractor shall be required to prepare drawings (in line with reference tender drawing) for specific sizes of Valve pits and the same shall be approved by EIC.
554Fabrication & Installation of Markers
555RCC Route Markers
556Supply, fabrication and installation of RCC route markers as per the attached drawing in technical volume, along the route including all associated civil works such as excavation and construction in all types of soils, construction and pedestals and grouting with concrete.
557Pole Markers with Foundation
558Supply, fabrication and installation of plate markers as per the attached drawings in technical volume including all associated civil works such as excavation and construction in all types of soils, construction and pedestals and grouting with concrete, cleaning, stencil let.
559Warning Plate Markers
560Supply, fabrication and installation of plate markers, including application of approved color and quality of primer and paint, stencil letter cutting of lettering, numbers, direction, etc. as per the attached drawing in technical volume to be installed near regulator.
561Excavation of Hard rock/surface
562Excavation of trench or pits, wherever hard rock presence is exceeding 1.5 m in any direction of the trench and excavation of trench or pits in Malba/Multiple layers of asphalt/ brick / PCC/RCC etc and removable only by pneumatic chisel / drill as per the specifications and direction of EIC. The rates are payable over and above the Laying rates as per relevant SOR no. 2.1
563Cutting of PCC/RCC surface with thickness more than 12\\" or Continuous asphalt multi-layer/ Malba/ Brick / Boulders more than 24\\".(Malba shall be considered as a strata where soil is in mixed form of debris/building rubbish or discarded pieces of bricks/stones )
564Rock Cutting encountered while excavation of trenches for item 2.1 of SOR, not exceeding 1.5 meter in width, and lift upto 1.5 meter, including getting out the excavated soil and disposal of excavated soil as directed within a lead of 50 meter. In case of rocky soil, the bedding shall be done with approved/ good quality packing sand, subject to the approval of the EIC, the size distribution of the sand / shall be the same as per soil. The packing sand shall be placed to a minimum thickness of 150mm around the pipe in case of rocky terrain.
565Note: i) The quantities mentioned are indicative only. ii) For all the supply items mentioned above, procurement shall be made as per specification after due approval of engineer- in - charge.
566Liaisoning with Land Owning Agencies for Permission
567Submission of applications as per approved drawings (Initial Route survey, prepartion of drawing, measuring and providing details of surface type shall be in scope of contractor), obtaining and submission of demand note, coordination, Liaisoning, obtaining written permission from land owing agencies like NHAI, AAI,Indian Railways and any other government agencies resposible for maintaining public lands and agencies owing Private lands etc. (all fee paid to authorities excluding demand charges or Bank Guarantees shall be reimbursed against documentary evidence). Permissions required from various authorities like NHAI / Railways / Irrigation (Canal) etc. falling enroute shall be inclusive in the item rate. No separate liasion charges against construction of valve chambers is payable and is included in laying rates.
568Construction of RCC structure for protection of service line for drain/nallah Crossings
569Construction of Non suspended slabs/pavement slabs including pedestal/ramp etc.using reinforced cement concrete of M-25 grade (Concrete shall be design mix/nominal mix with 20 mm & down size graded crushed stone aggregates) to protect the PE pipe laid. All necessary form work, finishing the top surface rough/smooth as required in any position, shape, level and thickness etc. shall be as specified and directed by EIC. The rates shall include grouting of pockets, supply of all material, tools, reinforcement steel etc.
570Preservation of Pipeline
571Preservation of pipeline sections and associated facilities (in event of delay in comissioning, other unforeseen reasons) including supply of nitrogen, all consumables, all equipment, man-power, etc. complete as per the requirements of specifications, other provisions of tender/ contract documents and instructions of Engineer-in-charge.
572By filling and pressurizing with nitrogen to a pressure of 2 bar(g) for a period of one month or part thereof.
573For 20 mm Pipeline
574For 32 mm Pipeline
575For 63 mm Pipeline
576For every additional period of one month or part thereof Limited to 6 month
577For 20 mm Pipeline
578For 32 mm Pipeline
579For 63 mm Pipeline
580Notes: i) The above length is not for a single section but for no. of sections. ii) All accessrious ie; End caps and two nos tappings of 3/4 inches, PG to be considered per section and rate for the same shall be quoted by bidder under this item.iii) If month is partially complete, payment shall be made on prorata basis.iv) Scope includes pressure holding for a period of 6 months or as per EIC and jointing of PE pipe (if required) due to damage by any means and further filling of nitrogen for pressure holding.v) Length given are tantative may change as per site requirments.
581CIVIL WORKS
582Earth Work
583Earth in excavation and filling to the grades and levels shown in the approved drawings in all kinds of conditions including for Road embakments, using approved quality good earth from designated borrow area, for all heights and depths including clearing and stripping (min. 150 mm) of the area marked for filling, taking spot levels, consolidating the exposed natural soil surface, excavating the earth from borrow area loading, transporting & unloading, spreading in layers not exceeding 150 mm thickness, breaking clods, watering (if reqd.), ramming and compacting by manual/ mechanical means to give minimum 92% of modified Proctor's density of earth, testing & dressing including disposal of all unserviceable material all complete as per specifications and directions of Engineer-in-charge.
584(Rate to include cost of all labour, tools, tackles, equipment, hire chanrges, cost of borrow earth by way of royalties, right of way, cess etc., as applicable with all bye works and sundry works).
585PCC 1:2:4
5861 Cement : 2 Coarse sand : 4 stone aggregate 20mm nominal size.
587PCC 1:4:8
5881 Cement : 4 Coarse sand : 8 stone aggregate 40mm nominal size.
589(Rate to include cost of all labour, tools, tackles, equipment, hire charges, supply of all materials, shuttering, earthwork in excavation and backfilling using approved earth in all conditions etc. with all bye works and sundry works.)
590Reinforced Cement Concrete
591Providing and laying reinforced cement of grade M-25 with 20mm and down grade crushed stone aggregate in all types of structures like foundations, pedestals, pedestal bases, pipe supports, sleepers, column, equipment foundation, Non suspended slabs/pavement slabs, ramps, cable trench inlcuding construction joints, bitumen painting on surface in contact with soil, supplying and fixing reinforcing steel, shuttering, inserts, finishes, grounting etc. at all depths and heights complete as per drawings, specifications and direction of the Engineer-in-charge.
592Rate to include cost of all labour, tools, tackles, equipment, hire charges, supply of all maerials such as minimum 43 grade cement including sulphate resistant cement for sub-structures, R/F steel, Inserts, bolts, conduits, bitumen, other minor constrcution materials, shuttering, stanging, earthwork in excavation and backfilling using serviceable earth in all conditions, shorting bailing and pumping out water, testing of concrete, curing etc. with all bye works and sundry works.
593Concrete Pavement
594Providing and laying reinforced cement concrete of (M-25 grade) with 20mm and down grade crushed stone aggregate in pavement, including preparation of base (i.e. compacted subgrade, 200 thk sand and 50 thk PCC M-10 grade), leaving pockets if necessary, making recess, projections, fixing inserts conduit pipes (GI, PVC, HDPE, etc.) laying in alternate panels, filling the gaps between the panels with bitumen etc., making slopes, finishing edges, leaving bars for pedestals & sleepers including providing sand fill isolation , shuttering, providing and fixing reinforcing steel, curing, chipping and modification works etc. as specified in any shape, thickness, position and finishing the top surface smooth as per requirement etc. all complete as per drawings, specifications and directions of the Engineer-in-charge.
595Concrete Pavement- 150mm thick (Type-I)
596Brick Work
597Providing brick work with brick class designation M-7.5 of IS:1077 in cm1:4 (1 cement : 4 sand) in steps, walls, retaining walls and load bearing structures drains, or any shape with all lead, depths & height including curring, scaffolding, etc., as per specifications and drawings with all bye-works and direction of the Enfineer-in-charge.
598(Rate to include cost of all labour, tools, tackles, equipment, hire charges, supply of all materials such as minimum 43 grade cement, bricks, finishes, bitumen, other minor constrcution materials, shuttering, staging, masonry work, plastering, painting etc. with all bye-works and sundry works).
599Note: The quantites of individual item can varied as per site requirement.The payment will be made as per actual certified measurement at site.
600Laying of Brick layer/ Concrete
601Providing single layer of Brick / Concrete / or impact resistant tape to entire width of trench above Warning Mat placed in trench over the laid pipeline as per OISD 226, standard drawing, specification and instruction of Owner. (Rate to include cost of all labour, tools, tackles, equipment, hire charges & supply of all materials, etc)
602Brick Layer for width of PE pipeline trench as per drawing (75 mm thk.)
603Concrete for width of PE pipeline trench as per drawing (80 mm thk.)
604Demolition of PCC work below plinth level
605Demolishing plain cement concrete (PCC) work (taking all necessary safety precautions) for all depths below plinth level including supply of all tools & tackles, necessary scaffolding, propping, underpinning, etc. , disposal of unserviceable material outside the boundary limits keeping the owner indemnified of any liabilities from statutory/ local bodies, all complete work as specified and directed.
606Excavation for foundation works
607Excavation as per plan, upto 3 meters and upto any lead in all conditions, backfilling using serviceable earth and disposal of surplus and unserviceable earth. Soil to be levelled and neatly dressed complete in all respect as per scope of work, technical specification and directions of EIC.
608Upto 3.0 Mtrs
609Dismantling of RCC & cutting of reinforcement (Thickness above 3”)
610Structural Works
611Supplying, fabricating & fixing steel structural cage fabricated from Angle conforming to IS:808 & fixing of GI weldmesh made from 3mm GI wire @ 75 mm bothways to structural steel frame by means of welding/bolting, including applying two coats of approved quality of synthetic enamel paint over a priming coat of in approved shade including supply of all raw materials, bolts, electrodes, transportation, including Hilti arrangement ,locking arrangement for fixing of posts etc complete as per enclosed drawing, technical specifications, scope of works and directions of the Engineer-In-Charge. Note:- Material shall be supplied and fabricated as per site condition and Contractor have to take quantity approval from EIC/OWNER prior to commencement of work and order placement.
612MRS / Metering Skid/Wall Mounted MRS.
613Installation of MRS / Metering Skid on foundation
614Receiving and taking over, handling, loading, transportation and unloading of MRS / Metering Skid from Owner's designated stockyards to site, installation at foundation and hooking up with PE pipe including all works as required to complete the job as per the drawings and specification, scope of work mentioned in tender doucment. The scope includes supply of transition fittings,GI Sleeve, other MDPE and CS fittings as required and various associated works to commission MRS / Metering Skid. (Note:- The installation included CS piping work included welding, testing, NDT etc.,however payment for the CS piping work along with accessories supply will be paid in SOR item 7.0 to 25.0 respectively.)
615Note: 1) Amount towards civil work shall be payable as per related SOR items. 2) Rate to include cost of all labour, tools, tackles, equipment, hire charges.3) All fittings and consumables including Bolts, nuts, washer, U-clamps, gaskets etc. if required during installation shall be procured and supplied by the Contractor within the rate quoted. These items shall not be separately measured and paid.
616MRS / Metering Skid <2000 SCMD
617MRS / Metering Skid 2000-5000 SCMD
618MRS / Metering Skid 5000-20000 SCMD
619MRS / Metering Skid >20000 SCMD
620Installation of Wall Mounted Metering System (Meter, Regulator & Accessory) locked in cage
621Receiving and taking over, handling, loading, transportation and unloading of all items for Wall Mounted Metering System (Meter, Regulator & Accessory) from Owner's designated stockyards to site, installation on wall and hooking up with PE pipe including all works as required to complete the job as per the drawings and specification, scope of work mentioned in tender doucment.The scope includes supply of items required as per the drawing in scope of work (Details of drawings as PJS) viz. transition fittings, GI/Concrete Sleeves and other MDPE and CS fittings etc. as required and various associated works.(Only Meters and Regulators shall be provided as free issue) and all associated works (For CS pipe and other items refer sl. no. 7.0 to 25.0) to commission Wall Mounted Metering System. Note : Installation works included CS piping work, Testing etc.,however payment for the CS piping work along accessories will be paid in diiferent SOR item
622Note: 1) Amount towards civil work shall be payable as per relevant SOR items. 2) Rate to include cost of all labour, tools, tackles, equipment, hire charges .3) All fittings (those are not mentioned in SOR item 7.0 to 25.0) and consumables including Bolts, nuts, washer, U-clamps, gaskets etc. if required during installation shall be procured and supplied by the Contractor within the rate quoted. These items shall not be separately measured and paid.4)The wall mounted Metering System to be kept in cage with locking facility, However payment for Structural work will be paid against SOR item 4.0
623The Typical Design of MRS/Metering System are as per \\"Standardized metering system Design, Selection & Installation philosophy for supply of PNG to Industrial and Commercial Customers of GAIL Gas.\\"Note: -The sizes mentioned in drawings are indicative & may vary as per actual requirment at site .
624Wall Mounted Metering System < 200 SCMD
625Wall Mounted Metering System 200-500 SCMD
626Wall mounted Metering System 500 to 2000 SCMD
627Wall mounted Metering System >2000 SCMD
628Note: i) The quantities mentioned are indicative only. ii) For all the supply items mentioned above, procurement shall be made as per specification after due approval of engineer- in - charge.
629Installation of Wall Mounted Metering System (Pre-assemble)
630Receiving and taking over, handling, loading, transportation and unloading of all items for Wall Mounted Metering System (Pre-assembled as per standard drawing Attached in PJS Drawing ) from Owner's designated stockyards to site, installation on wall and hooking up with PE pipe including all works as required to complete the job as per the drawings and specification, scope of work mentioned in tender doucment.The scope includes supply of transition fittings, Sleeves and other MDPE and CS fittings etc. as required and various associated works, however, the Metering System assembly ( As per drawing ) shall be provided as free issue by GAIL Gas. Installtion work done by Contractor along supply of consumables including Bolts, nuts, washer, U-clamps, gaskets etc. if required during installation shall be procured and supplied by the Contractor within the rate quoted.
631Note: 1) Amount towards civil work shall be payable as per related SOR items 3.0. 2) Rate to include cost of all labour, tools, tackles, equipment, hire charges .3) The wall mounted Metering System to be kept in cage with locking facility, However payment for Structural work will be paid against SOR item 4.0
632Installation of GI Pipe 2\\" - 1\\" size with isolation valve for commercial meter inlet connection from TF
633Removal of MRS/ Metering Skids, Wall Mounted MRS/Metering System (all capacities) from existing consumer's premise,
634Removal of MRS/ Metering Skids, Wall Mounted Metering System (all capacities) from existing consumer's premise for shifting to another site/store. The scope of work also includes excavation to retrive PE pipe line , disconnection of existing pipe lines (PE & Steel).
635Note:- Transportaion of removed metering skid/Wall mounted Metering System to store shall be payble under SOR item no.5.4.2. However, if this skid is being shifted directly to new location for installation at new customer premises then transportation to be claimed from 5.1 & 5.2 as applicable.
636Transportaion of removed metering skid/Wall mounted Metering System to store
637Conversion of Commercial Appliances/Industrial :
638Conversions of all types of commercial appliances to NG based appliances. Supply & changing of the nozzles /jets and associated controls for Non-domestic appliances (imported appliances included) with proper tools and tackles. Cleaning and performing minor maintenance, greasing etc. of the appliance. Testing and showing the performance to the customer, signing of joint meter records (JMR) and instructing the customer on use & safety norms, complete as per specifications & to satisfaction of owner / Engineer in Charge and includes supply of reinforced rubber hose with requisite pressure rating.Supply of Appliance valve is also included.
639Installation of ASTM A106, Gr. B, Seamless, BE , NB, XS pipes of various dia
640ASTM A106, Gr. B, Seamless, PE , 1/2\\" NB, S160 , their fittings and installation of meter and regulator (as applicable)
641ASTM A106, Gr. B, Seamless, PE , 1\\" NB, XS , their fittings and installation of meter and regulator (as applicable)
642ASTM A106, Gr. B, Seamless, PE, 1.5\\" NB, XS , their fittings and installation of meter and regulator (as applicable)
643ASTM A106, Gr. B (Charpy), Seamless, BE , 2\\" NB, XS , their fittings and installation of meter and regulator (as applicable)
644ASTM A106, Gr. B (Charpy), Seamless, BE , 3\\" NB,XS , their fittings and installation of meter and regulator (as applicable)
645ASTM A106, Gr. B (Charpy), Seamless, BE , 4\\" NB,XS , their fittings and installation of meter and regulator (as applicable)
646Note:a). Supply & Installation of required size of brass fittings (which are not included in SOR item 8.0 to 23.0) in all type of meters (supplied by GAIL GAS LTD. ) shall be in scope of contractor.b). All butt welded fittings end shall generally match with connecting pipe wall thickness. However, in case of misalignment, Contractor shall have to do end preparation without any extra cost. c). Payment of radiography of joints (4\\" and below ) shall be paid seperately under SOR item for RADIOGRAPHY mentioned elsewhere in this SOR 25.0d). All type of piping works shall be carried out as per piping material specification (PMS).e). Complete Carbon Steel Piping Work with painting including all fittings, flanges and supply of all required gaskets, studs bolts & nuts etc.
647Supply of CARBON STEEL PIPES as per Technical Specification and as directed by EIC
648ASTM A106, Gr. B, Seamless, PE , 1/2\\" NB, S160
649ASTM A106, Gr. B, Seamless, PE , 1\\" NB, XS
650ASTM A106, Gr. B, Seamless, PE, 1.5\\" NB, XS
651ASTM A106, Gr. B (Charpy), Seamless, BE , 2\\" NB, XS
652ASTM A106, Gr. B (Charpy), Seamless, BE , 3\\" NB,XS
653ASTM A106, Gr. B (Charpy), Seamless, BE , 4\\" NB,XS
654Supply of Pressure Gauges as per Technical Specification and as directed by EIC
655RANGE 0-100 MBAR - 4\\"- DIAL SIZE
656RANGE 0-1 BAR - 4\\"- DIAL SIZE
657RANGE 0-4 BAR - 4\\"- DIAL SIZE
658RANGE 0-6 BAR - 4\\"- DIAL SIZE
659RANGE 0-30 BAR - 4\\"- DIAL SIZE
660Supply of Conical Stainer
661As per Technical Specification and as directed by EIC.Note: - Conical Stainer may be free issue by Gail Gas Ltd., It is Discretion of Gail Gas Ltd. to excute the SOR or Free Issue the material.
662Supply of Check valve/NRVAs per Technical Specification and as directed by EIC.
6632\\", 150# FE,FB
6643\\", 150# FE,FB
6654\\", 150# FE,FB
666Supply of Flanges Weld Neck(End Thickness to match pipe thickness)
6671\\" , 150#, B-16.5 , A105 ,125 AARH,SW,RF
6681.5\\" , 150#, B-16.5 , A105 ,125 AARH,SW,RF
6692\\",150#, B-16.5, A105 (Charpy), 125 AARH, RF
6703\\",150#, B-16.5, A105 (Charpy), 125 AARH, RF
6714\\",150#, B-16.5, A105 (Charpy), 125 AARH, RF
672Supply of Blind FlangesAs per Technical Specification and as directed by EIC.
6732\\",150#, B-16.5, A105 (Charpy), 125 AARH, RF
6743\\",150#, B-16.5, A105 (Charpy), 125 AARH, RF
6754\\",150#, B-16.5, A105 (Charpy), 125 AARH, RF
676Supply of End Caps
6772\\", XS, A 234 Gr. WPB (Charpy), BW
6783\\", XS, A 234 Gr. WPB (Charpy), BW
6794\\", XS, A 234 Gr. WPB (Charpy), BW
680Supply of FLANGE END GLOBE VALVES, MAOP- 4 BARAs per Technical Specification and as directed by EIC.
681Supply of Ball ValvesAs per Technical Specification and as directed by EIC.
6821/2\\",800#, Sockolet Welded/Threaded Valve
6831\\",800#, Sockolet Welded/Threaded Valve
6842\\",150#,FE, FB,
6853\\",150#,FE, FB,
6864\\",150#,FE, FB,
687Supply of Isolation Ball Valve And Appliance Valve as per Technical Specification and as directed by EIC
688Isolation Ball Valve ½\\" max. 6 bar (g)
689Isolation Ball Valve 1\\" max. 6 bar (g)
690Isolation Ball Valve 1.5\\" max. 6 bar (g)
691Isolation Ball Valve 2\\" max. 6 bar (g)
692Isolation Ball Valve 3\\" max. 6 bar (g)
693Supply of SOCKOLET (A105, SW) As per Technical Specification and as directed by EIC.
6942\\" x ½\\"
6952\\" x 1\\"
6963\\" x ½\\"
6973\\" x 1\\"
6984\\" x ½\\"
6994\\" x 1\\"
700Supply of Reducer (A 234 Gr. WPB (Charpy), BW)
7011.5\\" x 1\\", XS x XS, A105, SW,3000#, B-16.11
7022\\"x1\\", XS x XS, A 234 Gr. WPB (Charpy), BW, B-16.9
7032\\" X 1.5\\", XS , A 234 Gr. WPB (Charpy), BW, B-16.9
7043\\"x1\\", XS x XS, A 234 Gr. WPB (Charpy), BW, B-16.9
7053\\" X 1.5\\", XS , A 234 Gr. WPB (Charpy), BW, B-16.9
7063\\" x 2\\" , STD x XS, A 234 Gr. WPB (Charpy), BW, B-16.9
7074\\" x 3\\" , STD x XS, A 234 Gr. WPB (Charpy), BW, B-16.9
708Supply of Tee, Equal / Reducing Tee
7091\\", XS, SW, 3000#, B-16.11
7101.5\\", XS, A105, SW, 3000#, B-16.11
7112\\" x 1.5\\", XS , A234, Gr. WPB (Charpy), B-16.9, BW
7122\\", XS , A234, Gr. WPB (Charpy), B-16.9, BW
7133\\", STD , A234, Gr. WPB (Charpy), B-16.9, BW
7144\\" STD x XS, A234, Gr. WPB (Charpy), B-16.9, BW
715Supply of ELBOW, 90° Elbow
716½\\", XS, SW, 3000#, ASTM A105,B-16.11
7171\\", XS, SW, 3000#, ASTM A105,B-16.11
7181.5\\", XS, SW, 3000#, ASTM A105,B-16.11
7192\\", XS, BW, A234, Gr. WPB (Charpy), B-16.9, 1.5D
7203\\", STD, BW, A234, Gr. WPB (Charpy), B-16.9, 1.5D
7214\\", XS, BW, A234, Gr. WPB (Charpy), B-16.9, 1.5D
722Supply of Spectacle Blind AS PER SPECIFICATION
723Spectacle Blind 2\\"
724Spectacle Blind 3\\"
725Spectacle Blind 4\\"
726Supply of Internal/external piping support (AS PER Tender)
727TYPE-1, SIDE WALL MOUNTED AS PER DRAWING
728TYPE-2, GROUND BASED AS PER DRAWING
729TYPE-3, CEILING MOUNTED AS PER DRAWING
730WELDING OF JOINTS - Butt Weld Joints
7311/2\\" (WELDING OF JOINTS)
7321\\" (WELDING OF JOINTS)
7331.5\\" (WELDING OF JOINTS)
7342\\" (WELDING OF JOINTS)
7353\\" (WELDING OF JOINTS)
7364\\" (WELDING OF JOINTS)
737Note: i) All butt welded fittings end shall generally match with connecting pipe wall thickness however in case of misalignment Contractor shall have to do end preparation without any extra cost.ii) All coupling, nipples etc. as required shall be supplied by contractor but no separate payments shall be made as it is covered under erection rate.
738RADIOGRAPHY OF JOINTS
739Performance of radiographic inspection by gamma radiation as per scope of work and as per specifications in piping of all types and thickness including providing/hiring of all necessary equipments, supply of all consumables, and whatever else even though not expressely mentioned but required to perform the work as per specifications and instructions of Engineer-in-Charge (full circle re-radiography of the repaired joint and additional radiography necessitated due to poor performance of contractor's welder shall be carried out by the Contractor at his own cost and shall not be paid extra by Company). Radiographs shall be submitted to the Engineer-in-Charge for acceptance, whose decision shall be final and binding.
740Note- i). 4\\" & Below and all butt weld joint are radiography / X-ray shall be done at every joint and shall be carried out as per API 1104 (latest edition) / M/s GAIL Gas Ltd. specification / OISD / PNGRB and same shall be approved by Engineer–in–charge (EIC)/RCM.ii). All socket weld joint MPT/UT/DPT shall be done at every joint nd shall be carried out as per API 1104 (latest edition)/M/s GAIL Gas Ltd. specification / OISD / PNGRB and same shall be approved by Engineer–in–charge (EIC)/ RCM.
7411/2\\" (RADIOGRAPHY of Joints as Above)
7421\\" (RADIOGRAPHY of Joints as Above)
7431.5\\" (RADIOGRAPHY of Joints as Above)
7442\\" (RADIOGRAPHY of Joints as Above)
7453\\" (RADIOGRAPHY of Joints as Above)
7464\\" (RADIOGRAPHY of Joints as Above)
747Note: i) Quantities mentioned against each above item of SOR Items are tentative and may increase or decrease during execution of work depending upon site requirement. Contractor required to supply materials after assessing the site requirement and in multiple lot or as per Release Order/ Sub Purchase Order wise. All material either in multiple lot or as per Release Order/ Sub Purchase Order wise or as decided by EIC shall be supplied by bidder within the quoted price.(ii) The quantites of individual item can varied as per site requirement.The payment will be made as per actual certified measurement at site. For the supply items the quantities shall be procured after approval from client/ consultant/EIC.(iii) The bidder must indicate currency(ies) against each quoted item of the SOR.(iv) The total amount shall also be given by the bidder in the quoted currency(ies).(v) Some of the may / may not be execute as per site requirements.
748Ground Connectivity Works
749Laying of MDPE pipeline by any method in any type of soil strata upto 20m length from charged Pipeline to Customer premise including connection of Transistion Fitting at customer end. For pipeline laid more than 20m, payment for additonal length shall be covered in SOR no.2 in ruuning meters more than 20m.
750PE 20mm dia
751PE 32mm dia
752PE 63mm dia
753PE 90mm dia.
754Survey, Pit Excavtion in all types of soills/PCC/RCC/Paver block/Ashpalt/Whitetopping etc., charged pipeline identification, Hook up activities, Online tapping either by Saddle / Tee / extension by Coupler for connecting the Pipeline laid as per above SOR 1.1 including fittings, Backfilling. Restoration shall be paid through other SOR
755Connectiviy for PE 20mm dia laid under 1a.
756Connectiviy for PE 32mm dia laid under 1a.
757Connectiviy for PE 63mm dia laid under 1a.
758Connectiviy for PE 90mm dia laid under 1a.
759PE PIPELINE
760PE Pipe Laying in any type of surface like unprepared surface (Katcha surface)/ Normal Surface/ Hard surface/Rock surface etc using open cut/ Moling (without Casing)/ Moling (with Casing)/ Horizontal Directional Drilling technique (with and without casing pipe) methodology. HDD at Hard Rock shall be paid through different SOR.
761Receipt. Loading. unloading. storing. reloading. tranportation. unloading. stringing and laying of PE100. SDR11 line pipes of all sizes including. proper stacking. identification.and supply of accessories of all sizes & thickness like PE Bends. Couplers. Endcaps. Tee. Reducer. CS / GI to PE Fittings (i.e. Transition Fittings of sizes 20 mm to 90 mm). Warning Mat etc. Handling. Stringing / uncoiling. aligning of the PE line pipe on the pipeline Right-of-Use / route. laying / installation of PE line pipe alongwith required accessories as mentioned above as per specification wherever required depending on site condition including execution of all works; Storeage of material in contractor's store. fabrication. access for construction procurement and supply of all materials. consumables. equipments. labour and other inputs.
762In the case of free issue items. the scope also includes. receiving and loading from Owner's designated store. transportation. unloading and stacking of free issue items at Contractor's store. -Laying of all PE pipe (PE 100 SDR11). Including supply of HDPE casing pipe (in case of HDD (with case).Moling(with case) . Couplers. End caps etc. (Ref. of Particular job specification).Survey of under ground utilities. execution of the work as per specification. including excavation of pits moling with the hole size not exceeding 20% of the pipe dia. jointing and insertion of carrier pipe with casing. testing & commissioning and restoration of the pits to original condition. submission of As-Built Graph as per specifications and the instruction of Engineer-in-charge.
763Casing details is as given below:-1. For 20/32 mm PE pipe (in 75 mm dia. HDPE Casing Pipe. PE 63/80 PN6.0).2. For 63 mm PE pipe (in 125 mm dia. HDPE Casing Pipe. PE 63/80 PN6.0).
764Carrying out all temporary. ancillary. auxiliary works required to make the PE pipeline ready for commissioning as per drawings. Specifications. scope of work indicated in PJS and other provisions of tender/ contract documents and instructions of Engineer-in-charge. including but not limited to carrying out the following works:Surveying of route and detours required at the time of execution. preparation of construction drawings showing survey details and submit same to Owner for review / approval.
765Carrying out preliminary activities such as preperation of drawings wherever required for crossing etc.Preparation and getting approval of schedules. execution procedures. drawings/ sketches/ wherever required. making trial pits to determine the underground utilities/ services etc.. restoration of the abandoned trial pits to original condition.
766Stacking and installation of construction markers. clearing. fencing. grubbing. cutting of trees. full filling all the requirements of various statutory/ environment authorities to the entire satisfaction of concerned authorities. grading of work area.
767Barricading the work area as per local authorities norms & to the satisfaction of Owner/ Eingineer -in- charge. installation of safety signs.Barricading the pipeline construction area prior to execution of the works as per drawing enclosed with tender/ contract documents and to the entire satisfaction of owner / engineer- in -charge.
768Laying using open trench without casing includes survey of under ground utilities (through trial pits). execution of work as per specification including Trenching to all depths by excavation in all types of soils including soft/ rocky strata and different type of pavement / footpath / roads etc. including rock breaking. chiselling or otherwise cutting etc. as required and storing excavated soil. reusable materials at designated area as directed by Engineer in charge and to a width to accommodate the pipeline as per the relevant standard/ specification etc.
769The minimum depth of the top of pipeline shall be 1.0 m measured from top of pipeline to the top of undisturbed surface of the soil or as per Specification/ OISD- 226 & PNGRB latest guidelines whichever is higher.Dewatering of trenches / pits if required as per site condition. Repairing of all damaged utilities if any. and payment of any compensation (if claimed by owner / other utility agencies)Uncoiling / stringing & aligning of PE pipes. clamping. jointing of the pipe ends / fittings / valves by qualified personnel using approved electro-fusion techniques as per specification.Note:- Coordinates to be taken for implementation for GIS for Valve pit, Fusion welding location and MRS.
770Installation / lowering the pipeline in trench to required depth as per PJS. Technical Specification & drawings. supply & placement of HDPE Yellow colour warning mat (refer PJS) over the pipeline along the complete route as per standard drawings. data sheets & technical specifications. padding around pipeline including supply of suitable padding material duly approved by EIC. Backfilling to its original condition with excavated earth / borrowed select soil/sand duly approved by EIC & its compaction & crowning. At certain specific area of ROU. trench shall be backfilled & compacted and shall be made ready for motorable and no seperate payment shall be admissible against this activity.All tiles / slabs / curb stones etc removed during excavation shall be placed properly.Restoration shall be carried as per separate SOR item mentioned elsewhere in the SOR or to be done by Owner / concerned authorities.
771The scope of work against this item also include Electro-fusion jointing of valves. fittings wherever required and as directed by Engineer-in-charge.The scope of work against laying of 20 mm pipe also includes works like making of PCC pedastal of grade (1:2:4) and size ( (300mm(L)X200mm(W) XHeight (H)). (H>=300mm & will be as per site condition) ). supply and installation of GI Sleeve (Heavy (C-Class) as per IS-1239). filling of sand and installation of TF (along with supply).
772Pneumatic testing. purging with nitrogen and commissioning as per specification and approved procedures providing all tools and tackles. nitrogen. instruments. manpower and other related accessories and as per the instructions of the Engineer-in-charge.
773Final clean-up of right-of-use or area disturbed by contractor during their construction activities for laying of pipeline works and disposal of debris and surplus material to designated disposal areas and backfilling of trench and compaction of the same as per satisfaction of Owner and / or as directed by Engineer–in–charge.
774Maintaining the completed pipelines and installation for any defect or failures during defect liability period (i.e. 12 months from date of completion of work).Handing over the completed works to Owner for their operation/ use. reconciliation of material area wise and obtaining \\"no objection certificate\\" from Owner/ PMC.Preparation and submission of Daily progress report. Laying Graphs / PE line cards on daily basis.
775On completion of gas charging of pipelines. Preparation and submission of As-built drawings. crossings details. termination. utility graphs and deviation statements.In case. the minimum required depth is not possible due to site condition. necessary mitigation measures with minimum permissible top cover shall be carried out by the contractor in consultation with EIC as per PNGRB Guidelines. without any time and cost implecation to owner.
776Submission of all documents required for contract closure in numbers as mentioned in contract.Any other activities not mentioned / covered explicitly above. but otherwise required for satisfactory completion / operation / safety / statutory / maintenance of the works shall also be covered under the scope of work and has to be completed by the Contractor within specified schedule at no extra cost to Owner. All the work shall be executed in accordance with the provision of contract.
77720 mm PE 100 pipe
77832 mm PE 100 pipe
77963 mm PE 100 pipe
78090 mm PE 100 pipe
781NOTE i) The lengths of pipelines are tentative. ii) For restoration of asphalt / concrete roads. the item for construction of asphalt top / concrete top / Tiles/Stone slab/Paver Blocks/Curb Stones shall be paid separately as per the rates quoted for the same elsewhere in the SOR 2.4.
782GPR Survey for identification of pipeline
783Laying of Pipeline by HDD in Rock Terrain
78432 mm PE 100 pipe
78563 mm PE 100 pipe
78690 mm PE 100 pipe
787Restoration
788Restoration of the roads. pavements. channels. footpaths. tiles. stones etc. to original condition including supply of the approved quality material required. as per local authorities norms. obtaining NOC from concerned local authorities / land owners / third party inspection agencies (if any) designated by owner and to the satisfaction of Engineer-in-charge.
789Asphalting
790Cement Concrete
791Tiles/Stone slab/Paver Blocks/Curb Stones
792Brick Soling / Channels. etc.
793Installation of valve in pit including supply of valves
794Supply of isolation valves (as per data sheet) and installtion of valves in the valve pits as per typical drawing and specification enclosed and instructions of Engineer-in-charge. Payment of valve pits shall be paid separately as per SOR 2.6.
795PE Valve 20 mm dia
796PE Valve 32 mm dia
797PE Valve 63 mm dia
798PE Valve 90 mm dia
799Construction of Valve Pits as per the enclosed tender drawing and specification. The item includes supply of all the material including Pre-cast RCC cover. shuttering. reinforcement. labour. curing etc as per the drawings. specification and instruction of EIC.
800Type-I having Internal size of Minimum 1000 x 1000mm
801Type-II having Internal size of Minimum 600 x 600mm
802Note: The tender drawing enclosed is only for reference purpose and contractor shall be required to prepare drawings (in line with reference tender drawing) for specific sizes of Valve pits and the same shall be approved by EIC.
803Fabrication & Installation of Markers
804RCC Route Markers
805Supply, fabrication and installation of RCC route markers as per the attached drawing in technical volume, along the route including all associated civil works such as excavation and construction in all types of soils, construction and pedestals and grouting with concrete.
806Pole Markers with Foundation
807Supply, fabrication and installation of plate markers as per the attached drawings in technical volume including all associated civil works such as excavation and construction in all types of soils, construction and pedestals and grouting with concrete, cleaning, stencil let.
808Warning Plate Markers
809Supply, fabrication and installation of plate markers, including application of approved color and quality of primer and paint, stencil letter cutting of lettering, numbers, direction, etc. as per the attached drawing in technical volume to be installed near regulator.
810Excavation of Hard rock/surface
811Excavation of trench or pits, wherever hard rock presence is exceeding 1.5 m in any direction of the trench and excavation of trench or pits in Malba/Multiple layers of asphalt/ brick / PCC/RCC etc and removable only by pneumatic chisel / drill as per the specifications and direction of EIC. The rates are payable over and above the Laying rates as per relevant SOR no. 2.1
812Cutting of PCC/RCC surface with thickness more than 12\\" or Continuous asphalt multi-layer/ Malba/ Brick / Boulders more than 24\\".(Malba shall be considered as a strata where soil is in mixed form of debris/building rubbish or discarded pieces of bricks/stones )
813Rock Cutting encountered while excavation of trenches for item 2.1 of SOR, not exceeding 1.5 meter in width, and lift upto 1.5 meter, including getting out the excavated soil and disposal of excavated soil as directed within a lead of 50 meter. In case of rocky soil, the bedding shall be done with approved/ good quality packing sand, subject to the approval of the EIC, the size distribution of the sand / shall be the same as per soil. The packing sand shall be placed to a minimum thickness of 150mm around the pipe in case of rocky terrain.
814Note: i) The quantities mentioned are indicative only. ii) For all the supply items mentioned above, procurement shall be made as per specification after due approval of engineer- in - charge.
815Liaisoning with Land Owning Agencies for Permission
816Submission of applications as per approved drawings (Initial Route survey, prepartion of drawing, measuring and providing details of surface type shall be in scope of contractor), obtaining and submission of demand note, coordination, Liaisoning, obtaining written permission from land owing agencies like NHAI, AAI,Indian Railways and any other government agencies resposible for maintaining public lands and agencies owing Private lands etc. (all fee paid to authorities excluding demand charges or Bank Guarantees shall be reimbursed against documentary evidence). Permissions required from various authorities like NHAI / Railways / Irrigation (Canal) etc. falling enroute shall be inclusive in the item rate. No separate liasion charges against construction of valve chambers is payable and is included in laying rates.
817Construction of RCC structure for protection of service line for drain/nallah Crossings
818Construction of Non suspended slabs/pavement slabs including pedestal/ramp etc.using reinforced cement concrete of M-25 grade (Concrete shall be design mix/nominal mix with 20 mm & down size graded crushed stone aggregates) to protect the PE pipe laid. All necessary form work, finishing the top surface rough/smooth as required in any position, shape, level and thickness etc. shall be as specified and directed by EIC. The rates shall include grouting of pockets, supply of all material, tools, reinforcement steel etc.
819Preservation of Pipeline
820Preservation of pipeline sections and associated facilities (in event of delay in comissioning, other unforeseen reasons) including supply of nitrogen, all consumables, all equipment, man-power, etc. complete as per the requirements of specifications, other provisions of tender/ contract documents and instructions of Engineer-in-charge.
821By filling and pressurizing with nitrogen to a pressure of 2 bar(g) for a period of one month or part thereof.
822For 20 mm Pipeline
823For 32 mm Pipeline
824For 63 mm Pipeline
825For every additional period of one month or part thereof Limited to 6 month
826For 20 mm Pipeline
827For 32 mm Pipeline
828For 63 mm Pipeline
829Notes: i) The above length is not for a single section but for no. of sections. ii) All accessrious ie; End caps and two nos tappings of 3/4 inches, PG to be considered per section and rate for the same shall be quoted by bidder under this item.iii) If month is partially complete, payment shall be made on prorata basis.iv) Scope includes pressure holding for a period of 6 months or as per EIC and jointing of PE pipe (if required) due to damage by any means and further filling of nitrogen for pressure holding.v) Length given are tantative may change as per site requirments.
830CIVIL WORKS
831Earth Work
832Earth in excavation and filling to the grades and levels shown in the approved drawings in all kinds of conditions including for Road embakments, using approved quality good earth from designated borrow area, for all heights and depths including clearing and stripping (min. 150 mm) of the area marked for filling, taking spot levels, consolidating the exposed natural soil surface, excavating the earth from borrow area loading, transporting & unloading, spreading in layers not exceeding 150 mm thickness, breaking clods, watering (if reqd.), ramming and compacting by manual/ mechanical means to give minimum 92% of modified Proctor's density of earth, testing & dressing including disposal of all unserviceable material all complete as per specifications and directions of Engineer-in-charge.
833(Rate to include cost of all labour, tools, tackles, equipment, hire chanrges, cost of borrow earth by way of royalties, right of way, cess etc., as applicable with all bye works and sundry works).
834PCC 1:2:4
8351 Cement : 2 Coarse sand : 4 stone aggregate 20mm nominal size.
836PCC 1:4:8
8371 Cement : 4 Coarse sand : 8 stone aggregate 40mm nominal size.
838(Rate to include cost of all labour, tools, tackles, equipment, hire charges, supply of all materials, shuttering, earthwork in excavation and backfilling using approved earth in all conditions etc. with all bye works and sundry works.)
839Reinforced Cement Concrete
840Providing and laying reinforced cement of grade M-25 with 20mm and down grade crushed stone aggregate in all types of structures like foundations, pedestals, pedestal bases, pipe supports, sleepers, column, equipment foundation, Non suspended slabs/pavement slabs, ramps, cable trench inlcuding construction joints, bitumen painting on surface in contact with soil, supplying and fixing reinforcing steel, shuttering, inserts, finishes, grounting etc. at all depths and heights complete as per drawings, specifications and direction of the Engineer-in-charge.
841Rate to include cost of all labour, tools, tackles, equipment, hire charges, supply of all maerials such as minimum 43 grade cement including sulphate resistant cement for sub-structures, R/F steel, Inserts, bolts, conduits, bitumen, other minor constrcution materials, shuttering, stanging, earthwork in excavation and backfilling using serviceable earth in all conditions, shorting bailing and pumping out water, testing of concrete, curing etc. with all bye works and sundry works.
842Concrete Pavement
843Providing and laying reinforced cement concrete of (M-25 grade) with 20mm and down grade crushed stone aggregate in pavement, including preparation of base (i.e. compacted subgrade, 200 thk sand and 50 thk PCC M-10 grade), leaving pockets if necessary, making recess, projections, fixing inserts conduit pipes (GI, PVC, HDPE, etc.) laying in alternate panels, filling the gaps between the panels with bitumen etc., making slopes, finishing edges, leaving bars for pedestals & sleepers including providing sand fill isolation , shuttering, providing and fixing reinforcing steel, curing, chipping and modification works etc. as specified in any shape, thickness, position and finishing the top surface smooth as per requirement etc. all complete as per drawings, specifications and directions of the Engineer-in-charge.
844Concrete Pavement- 150mm thick (Type-I)
845Brick Work
846Providing brick work with brick class designation M-7.5 of IS:1077 in cm1:4 (1 cement : 4 sand) in steps, walls, retaining walls and load bearing structures drains, or any shape with all lead, depths & height including curring, scaffolding, etc., as per specifications and drawings with all bye-works and direction of the Enfineer-in-charge.
847(Rate to include cost of all labour, tools, tackles, equipment, hire charges, supply of all materials such as minimum 43 grade cement, bricks, finishes, bitumen, other minor constrcution materials, shuttering, staging, masonry work, plastering, painting etc. with all bye-works and sundry works).
848Note: The quantites of individual item can varied as per site requirement.The payment will be made as per actual certified measurement at site.
849Laying of Brick layer/ Concrete
850Providing single layer of Brick / Concrete / or impact resistant tape to entire width of trench above Warning Mat placed in trench over the laid pipeline as per OISD 226, standard drawing, specification and instruction of Owner. (Rate to include cost of all labour, tools, tackles, equipment, hire charges & supply of all materials, etc)
851Brick Layer for width of PE pipeline trench as per drawing (75 mm thk.)
852Concrete for width of PE pipeline trench as per drawing (80 mm thk.)
853Demolition of PCC work below plinth level
854Demolishing plain cement concrete (PCC) work (taking all necessary safety precautions) for all depths below plinth level including supply of all tools & tackles, necessary scaffolding, propping, underpinning, etc. , disposal of unserviceable material outside the boundary limits keeping the owner indemnified of any liabilities from statutory/ local bodies, all complete work as specified and directed.
855Excavation for foundation works
856Excavation as per plan, upto 3 meters and upto any lead in all conditions, backfilling using serviceable earth and disposal of surplus and unserviceable earth. Soil to be levelled and neatly dressed complete in all respect as per scope of work, technical specification and directions of EIC.
857Upto 3.0 Mtrs
858Dismantling of RCC & cutting of reinforcement (Thickness above 3”)
859Structural Works
860Supplying, fabricating & fixing steel structural cage fabricated from Angle conforming to IS:808 & fixing of GI weldmesh made from 3mm GI wire @ 75 mm bothways to structural steel frame by means of welding/bolting, including applying two coats of approved quality of synthetic enamel paint over a priming coat of in approved shade including supply of all raw materials, bolts, electrodes, transportation, including Hilti arrangement ,locking arrangement for fixing of posts etc complete as per enclosed drawing, technical specifications, scope of works and directions of the Engineer-In-Charge. Note:- Material shall be supplied and fabricated as per site condition and Contractor have to take quantity approval from EIC/OWNER prior to commencement of work and order placement.
861MRS / Metering Skid/Wall Mounted MRS.
862Installation of MRS / Metering Skid on foundation
863Receiving and taking over, handling, loading, transportation and unloading of MRS / Metering Skid from Owner's designated stockyards to site, installation at foundation and hooking up with PE pipe including all works as required to complete the job as per the drawings and specification, scope of work mentioned in tender doucment. The scope includes supply of transition fittings,GI Sleeve, other MDPE and CS fittings as required and various associated works to commission MRS / Metering Skid. (Note:- The installation included CS piping work included welding, testing, NDT etc.,however payment for the CS piping work along with accessories supply will be paid in SOR item 7.0 to 25.0 respectively.)
864Note: 1) Amount towards civil work shall be payable as per related SOR items. 2) Rate to include cost of all labour, tools, tackles, equipment, hire charges.3) All fittings and consumables including Bolts, nuts, washer, U-clamps, gaskets etc. if required during installation shall be procured and supplied by the Contractor within the rate quoted. These items shall not be separately measured and paid.
865MRS / Metering Skid <2000 SCMD
866MRS / Metering Skid 2000-5000 SCMD
867MRS / Metering Skid 5000-20000 SCMD
868MRS / Metering Skid >20000 SCMD
869Installation of Wall Mounted Metering System (Meter, Regulator & Accessory) locked in cage
870Receiving and taking over, handling, loading, transportation and unloading of all items for Wall Mounted Metering System (Meter, Regulator & Accessory) from Owner's designated stockyards to site, installation on wall and hooking up with PE pipe including all works as required to complete the job as per the drawings and specification, scope of work mentioned in tender doucment.The scope includes supply of items required as per the drawing in scope of work (Details of drawings as PJS) viz. transition fittings, GI/Concrete Sleeves and other MDPE and CS fittings etc. as required and various associated works.(Only Meters and Regulators shall be provided as free issue) and all associated works (For CS pipe and other items refer sl. no. 7.0 to 25.0) to commission Wall Mounted Metering System. Note : Installation works included CS piping work, Testing etc.,however payment for the CS piping work along accessories will be paid in diiferent SOR item
871Note: 1) Amount towards civil work shall be payable as per relevant SOR items. 2) Rate to include cost of all labour, tools, tackles, equipment, hire charges .3) All fittings (those are not mentioned in SOR item 7.0 to 25.0) and consumables including Bolts, nuts, washer, U-clamps, gaskets etc. if required during installation shall be procured and supplied by the Contractor within the rate quoted. These items shall not be separately measured and paid.4)The wall mounted Metering System to be kept in cage with locking facility, However payment for Structural work will be paid against SOR item 4.0
872The Typical Design of MRS/Metering System are as per \\"Standardized metering system Design, Selection & Installation philosophy for supply of PNG to Industrial and Commercial Customers of GAIL Gas.\\"Note: -The sizes mentioned in drawings are indicative & may vary as per actual requirment at site .
873Wall Mounted Metering System < 200 SCMD
874Wall Mounted Metering System 200-500 SCMD
875Wall mounted Metering System 500 to 2000 SCMD
876Wall mounted Metering System >2000 SCMD
877Note: i) The quantities mentioned are indicative only. ii) For all the supply items mentioned above, procurement shall be made as per specification after due approval of engineer- in - charge.
878Installation of Wall Mounted Metering System (Pre-assemble)
879Receiving and taking over, handling, loading, transportation and unloading of all items for Wall Mounted Metering System (Pre-assembled as per standard drawing Attached in PJS Drawing ) from Owner's designated stockyards to site, installation on wall and hooking up with PE pipe including all works as required to complete the job as per the drawings and specification, scope of work mentioned in tender doucment.The scope includes supply of transition fittings, Sleeves and other MDPE and CS fittings etc. as required and various associated works, however, the Metering System assembly ( As per drawing ) shall be provided as free issue by GAIL Gas. Installtion work done by Contractor along supply of consumables including Bolts, nuts, washer, U-clamps, gaskets etc. if required during installation shall be procured and supplied by the Contractor within the rate quoted.
880Note: 1) Amount towards civil work shall be payable as per related SOR items 3.0. 2) Rate to include cost of all labour, tools, tackles, equipment, hire charges .3) The wall mounted Metering System to be kept in cage with locking facility, However payment for Structural work will be paid against SOR item 4.0
881Installation of GI Pipe 2\\" - 1\\" size with isolation valve for commercial meter inlet connection from TF
882Removal of MRS/ Metering Skids, Wall Mounted MRS/Metering System (all capacities) from existing consumer's premise,
883Removal of MRS/ Metering Skids, Wall Mounted Metering System (all capacities) from existing consumer's premise for shifting to another site/store. The scope of work also includes excavation to retrive PE pipe line , disconnection of existing pipe lines (PE & Steel).
884Note:- Transportaion of removed metering skid/Wall mounted Metering System to store shall be payble under SOR item no.5.4.2. However, if this skid is being shifted directly to new location for installation at new customer premises then transportation to be claimed from 5.1 & 5.2 as applicable.
885Transportaion of removed metering skid/Wall mounted Metering System to store
886Conversion of Commercial Appliances/Industrial :
887Conversions of all types of commercial appliances to NG based appliances. Supply & changing of the nozzles /jets and associated controls for Non-domestic appliances (imported appliances included) with proper tools and tackles. Cleaning and performing minor maintenance, greasing etc. of the appliance. Testing and showing the performance to the customer, signing of joint meter records (JMR) and instructing the customer on use & safety norms, complete as per specifications & to satisfaction of owner / Engineer in Charge and includes supply of reinforced rubber hose with requisite pressure rating.Supply of Appliance valve is also included.
888Installation of ASTM A106, Gr. B, Seamless, BE , NB, XS pipes of various dia
889ASTM A106, Gr. B, Seamless, PE , 1/2\\" NB, S160 , their fittings and installation of meter and regulator (as applicable)
890ASTM A106, Gr. B, Seamless, PE , 1\\" NB, XS , their fittings and installation of meter and regulator (as applicable)
891ASTM A106, Gr. B, Seamless, PE, 1.5\\" NB, XS , their fittings and installation of meter and regulator (as applicable)
892ASTM A106, Gr. B (Charpy), Seamless, BE , 2\\" NB, XS , their fittings and installation of meter and regulator (as applicable)
893ASTM A106, Gr. B (Charpy), Seamless, BE , 3\\" NB,XS , their fittings and installation of meter and regulator (as applicable)
894ASTM A106, Gr. B (Charpy), Seamless, BE , 4\\" NB,XS , their fittings and installation of meter and regulator (as applicable)
895Note:a). Supply & Installation of required size of brass fittings (which are not included in SOR item 8.0 to 23.0) in all type of meters (supplied by GAIL GAS LTD. ) shall be in scope of contractor.b). All butt welded fittings end shall generally match with connecting pipe wall thickness. However, in case of misalignment, Contractor shall have to do end preparation without any extra cost. c). Payment of radiography of joints (4\\" and below ) shall be paid seperately under SOR item for RADIOGRAPHY mentioned elsewhere in this SOR 25.0d). All type of piping works shall be carried out as per piping material specification (PMS).e). Complete Carbon Steel Piping Work with painting including all fittings, flanges and supply of all required gaskets, studs bolts & nuts etc.
896Supply of CARBON STEEL PIPES as per Technical Specification and as directed by EIC
897ASTM A106, Gr. B, Seamless, PE , 1/2\\" NB, S160
898ASTM A106, Gr. B, Seamless, PE , 1\\" NB, XS
899ASTM A106, Gr. B, Seamless, PE, 1.5\\" NB, XS
900ASTM A106, Gr. B (Charpy), Seamless, BE , 2\\" NB, XS
901ASTM A106, Gr. B (Charpy), Seamless, BE , 3\\" NB,XS
902ASTM A106, Gr. B (Charpy), Seamless, BE , 4\\" NB,XS
903Supply of Pressure Gauges as per Technical Specification and as directed by EIC
904RANGE 0-100 MBAR - 4\\"- DIAL SIZE
905RANGE 0-1 BAR - 4\\"- DIAL SIZE
906RANGE 0-4 BAR - 4\\"- DIAL SIZE
907RANGE 0-6 BAR - 4\\"- DIAL SIZE
908RANGE 0-30 BAR - 4\\"- DIAL SIZE
909Supply of Conical Stainer
910As per Technical Specification and as directed by EIC.Note: - Conical Stainer may be free issue by Gail Gas Ltd., It is Discretion of Gail Gas Ltd. to excute the SOR or Free Issue the material.
911Supply of Check valve/NRVAs per Technical Specification and as directed by EIC.
9122\\", 150# FE,FB
9133\\", 150# FE,FB
9144\\", 150# FE,FB
915Supply of Flanges Weld Neck(End Thickness to match pipe thickness)
9161\\" , 150#, B-16.5 , A105 ,125 AARH,SW,RF
9171.5\\" , 150#, B-16.5 , A105 ,125 AARH,SW,RF
9182\\",150#, B-16.5, A105 (Charpy), 125 AARH, RF
9193\\",150#, B-16.5, A105 (Charpy), 125 AARH, RF
9204\\",150#, B-16.5, A105 (Charpy), 125 AARH, RF
921Supply of Blind FlangesAs per Technical Specification and as directed by EIC.
9222\\",150#, B-16.5, A105 (Charpy), 125 AARH, RF
9233\\",150#, B-16.5, A105 (Charpy), 125 AARH, RF
9244\\",150#, B-16.5, A105 (Charpy), 125 AARH, RF
925Supply of End Caps
9262\\", XS, A 234 Gr. WPB (Charpy), BW
9273\\", XS, A 234 Gr. WPB (Charpy), BW
9284\\", XS, A 234 Gr. WPB (Charpy), BW
929Supply of FLANGE END GLOBE VALVES, MAOP- 4 BARAs per Technical Specification and as directed by EIC.
930Supply of Ball ValvesAs per Technical Specification and as directed by EIC.
9311/2\\",800#, Sockolet Welded/Threaded Valve
9321\\",800#, Sockolet Welded/Threaded Valve
9332\\",150#,FE, FB,
9343\\",150#,FE, FB,
9354\\",150#,FE, FB,
936Supply of Isolation Ball Valve And Appliance Valve as per Technical Specification and as directed by EIC
937Isolation Ball Valve ½\\" max. 6 bar (g)
938Isolation Ball Valve 1\\" max. 6 bar (g)
939Isolation Ball Valve 1.5\\" max. 6 bar (g)
940Isolation Ball Valve 2\\" max. 6 bar (g)
941Isolation Ball Valve 3\\" max. 6 bar (g)
942Supply of SOCKOLET (A105, SW) As per Technical Specification and as directed by EIC.
9432\\" x ½\\"
9442\\" x 1\\"
9453\\" x ½\\"
9463\\" x 1\\"
9474\\" x ½\\"
9484\\" x 1\\"
949Supply of Reducer (A 234 Gr. WPB (Charpy), BW)
9501.5\\" x 1\\", XS x XS, A105, SW,3000#, B-16.11
9512\\"x1\\", XS x XS, A 234 Gr. WPB (Charpy), BW, B-16.9
9522\\" X 1.5\\", XS , A 234 Gr. WPB (Charpy), BW, B-16.9
9533\\"x1\\", XS x XS, A 234 Gr. WPB (Charpy), BW, B-16.9
9543\\" X 1.5\\", XS , A 234 Gr. WPB (Charpy), BW, B-16.9
9553\\" x 2\\" , STD x XS, A 234 Gr. WPB (Charpy), BW, B-16.9
9564\\" x 3\\" , STD x XS, A 234 Gr. WPB (Charpy), BW, B-16.9
957Supply of Tee, Equal / Reducing Tee
9581\\", XS, SW, 3000#, B-16.11
9591.5\\", XS, A105, SW, 3000#, B-16.11
9602\\" x 1.5\\", XS , A234, Gr. WPB (Charpy), B-16.9, BW
9612\\", XS , A234, Gr. WPB (Charpy), B-16.9, BW
9623\\", STD , A234, Gr. WPB (Charpy), B-16.9, BW
9634\\" STD x XS, A234, Gr. WPB (Charpy), B-16.9, BW
964Supply of ELBOW, 90° Elbow
965½\\", XS, SW, 3000#, ASTM A105,B-16.11
9661\\", XS, SW, 3000#, ASTM A105,B-16.11
9671.5\\", XS, SW, 3000#, ASTM A105,B-16.11
9682\\", XS, BW, A234, Gr. WPB (Charpy), B-16.9, 1.5D
9693\\", STD, BW, A234, Gr. WPB (Charpy), B-16.9, 1.5D
9704\\", XS, BW, A234, Gr. WPB (Charpy), B-16.9, 1.5D
971Supply of Spectacle Blind AS PER SPECIFICATION
972Spectacle Blind 2\\"
973Spectacle Blind 3\\"
974Spectacle Blind 4\\"
975Supply of Internal/external piping support (AS PER Tender)
976TYPE-1, SIDE WALL MOUNTED AS PER DRAWING
977TYPE-2, GROUND BASED AS PER DRAWING
978TYPE-3, CEILING MOUNTED AS PER DRAWING
979WELDING OF JOINTS - Butt Weld Joints
9801/2\\" (WELDING OF JOINTS)
9811\\" (WELDING OF JOINTS)
9821.5\\" (WELDING OF JOINTS)
9832\\" (WELDING OF JOINTS)
9843\\" (WELDING OF JOINTS)
9854\\" (WELDING OF JOINTS)
986Note: i) All butt welded fittings end shall generally match with connecting pipe wall thickness however in case of misalignment Contractor shall have to do end preparation without any extra cost.ii) All coupling, nipples etc. as required shall be supplied by contractor but no separate payments shall be made as it is covered under erection rate.
987RADIOGRAPHY OF JOINTS
988Performance of radiographic inspection by gamma radiation as per scope of work and as per specifications in piping of all types and thickness including providing/hiring of all necessary equipments, supply of all consumables, and whatever else even though not expressely mentioned but required to perform the work as per specifications and instructions of Engineer-in-Charge (full circle re-radiography of the repaired joint and additional radiography necessitated due to poor performance of contractor's welder shall be carried out by the Contractor at his own cost and shall not be paid extra by Company). Radiographs shall be submitted to the Engineer-in-Charge for acceptance, whose decision shall be final and binding.
989Note- i). 4\\" & Below and all butt weld joint are radiography / X-ray shall be done at every joint and shall be carried out as per API 1104 (latest edition) / M/s GAIL Gas Ltd. specification / OISD / PNGRB and same shall be approved by Engineer–in–charge (EIC)/RCM.ii). All socket weld joint MPT/UT/DPT shall be done at every joint nd shall be carried out as per API 1104 (latest edition)/M/s GAIL Gas Ltd. specification / OISD / PNGRB and same shall be approved by Engineer–in–charge (EIC)/ RCM.
9901/2\\" (RADIOGRAPHY of Joints as Above)
9911\\" (RADIOGRAPHY of Joints as Above)
9921.5\\" (RADIOGRAPHY of Joints as Above)
9932\\" (RADIOGRAPHY of Joints as Above)
9943\\" (RADIOGRAPHY of Joints as Above)
9954\\" (RADIOGRAPHY of Joints as Above)
996Note: i) Quantities mentioned against each above item of SOR Items are tentative and may increase or decrease during execution of work depending upon site requirement. Contractor required to supply materials after assessing the site requirement and in multiple lot or as per Release Order/ Sub Purchase Order wise. All material either in multiple lot or as per Release Order/ Sub Purchase Order wise or as decided by EIC shall be supplied by bidder within the quoted price.(ii) The quantites of individual item can varied as per site requirement.The payment will be made as per actual certified measurement at site. For the supply items the quantities shall be procured after approval from client/ consultant/EIC.(iii) The bidder must indicate currency(ies) against each quoted item of the SOR.(iv) The total amount shall also be given by the bidder in the quoted currency(ies).(v) Some of the may / may not be execute as per site requirements.
997Ground Connectivity Works
998Laying of MDPE pipeline by any method in any type of soil strata upto 20m length from charged Pipeline to Customer premise including connection of Transistion Fitting at customer end. For pipeline laid more than 20m, payment for additonal length shall be covered in SOR no.2 in ruuning meters more than 20m.
999PE 20mm dia
1000PE 32mm dia
1001PE 63mm dia
1002PE 90mm dia.
1003Survey, Pit Excavtion in all types of soills/PCC/RCC/Paver block/Ashpalt/Whitetopping etc., charged pipeline identification, Hook up activities, Online tapping either by Saddle / Tee / extension by Coupler for connecting the Pipeline laid as per above SOR 1.1 including fittings, Backfilling. Restoration shall be paid through other SOR
1004Connectiviy for PE 20mm dia laid under 1a.
1005Connectiviy for PE 32mm dia laid under 1a.
1006Connectiviy for PE 63mm dia laid under 1a.
1007Connectiviy for PE 90mm dia laid under 1a.
1008PE PIPELINE
1009PE Pipe Laying in any type of surface like unprepared surface (Katcha surface)/ Normal Surface/ Hard surface/Rock surface etc using open cut/ Moling (without Casing)/ Moling (with Casing)/ Horizontal Directional Drilling technique (with and without casing pipe) methodology. HDD at Hard Rock shall be paid through different SOR.
1010Receipt. Loading. unloading. storing. reloading. tranportation. unloading. stringing and laying of PE100. SDR11 line pipes of all sizes including. proper stacking. identification.and supply of accessories of all sizes & thickness like PE Bends. Couplers. Endcaps. Tee. Reducer. CS / GI to PE Fittings (i.e. Transition Fittings of sizes 20 mm to 90 mm). Warning Mat etc. Handling. Stringing / uncoiling. aligning of the PE line pipe on the pipeline Right-of-Use / route. laying / installation of PE line pipe alongwith required accessories as mentioned above as per specification wherever required depending on site condition including execution of all works; Storeage of material in contractor's store. fabrication. access for construction procurement and supply of all materials. consumables. equipments. labour and other inputs.
1011In the case of free issue items. the scope also includes. receiving and loading from Owner's designated store. transportation. unloading and stacking of free issue items at Contractor's store. -Laying of all PE pipe (PE 100 SDR11). Including supply of HDPE casing pipe (in case of HDD (with case).Moling(with case) . Couplers. End caps etc. (Ref. of Particular job specification).Survey of under ground utilities. execution of the work as per specification. including excavation of pits moling with the hole size not exceeding 20% of the pipe dia. jointing and insertion of carrier pipe with casing. testing & commissioning and restoration of the pits to original condition. submission of As-Built Graph as per specifications and the instruction of Engineer-in-charge.
1012Casing details is as given below:-1. For 20/32 mm PE pipe (in 75 mm dia. HDPE Casing Pipe. PE 63/80 PN6.0).2. For 63 mm PE pipe (in 125 mm dia. HDPE Casing Pipe. PE 63/80 PN6.0).
1013Carrying out all temporary. ancillary. auxiliary works required to make the PE pipeline ready for commissioning as per drawings. Specifications. scope of work indicated in PJS and other provisions of tender/ contract documents and instructions of Engineer-in-charge. including but not limited to carrying out the following works:Surveying of route and detours required at the time of execution. preparation of construction drawings showing survey details and submit same to Owner for review / approval.
1014Carrying out preliminary activities such as preperation of drawings wherever required for crossing etc.Preparation and getting approval of schedules. execution procedures. drawings/ sketches/ wherever required. making trial pits to determine the underground utilities/ services etc.. restoration of the abandoned trial pits to original condition.
1015Stacking and installation of construction markers. clearing. fencing. grubbing. cutting of trees. full filling all the requirements of various statutory/ environment authorities to the entire satisfaction of concerned authorities. grading of work area.
1016Barricading the work area as per local authorities norms & to the satisfaction of Owner/ Eingineer -in- charge. installation of safety signs.Barricading the pipeline construction area prior to execution of the works as per drawing enclosed with tender/ contract documents and to the entire satisfaction of owner / engineer- in -charge.
1017Laying using open trench without casing includes survey of under ground utilities (through trial pits). execution of work as per specification including Trenching to all depths by excavation in all types of soils including soft/ rocky strata and different type of pavement / footpath / roads etc. including rock breaking. chiselling or otherwise cutting etc. as required and storing excavated soil. reusable materials at designated area as directed by Engineer in charge and to a width to accommodate the pipeline as per the relevant standard/ specification etc.
1018The minimum depth of the top of pipeline shall be 1.0 m measured from top of pipeline to the top of undisturbed surface of the soil or as per Specification/ OISD- 226 & PNGRB latest guidelines whichever is higher.Dewatering of trenches / pits if required as per site condition. Repairing of all damaged utilities if any. and payment of any compensation (if claimed by owner / other utility agencies)Uncoiling / stringing & aligning of PE pipes. clamping. jointing of the pipe ends / fittings / valves by qualified personnel using approved electro-fusion techniques as per specification.Note:- Coordinates to be taken for implementation for GIS for Valve pit, Fusion welding location and MRS.
1019Installation / lowering the pipeline in trench to required depth as per PJS. Technical Specification & drawings. supply & placement of HDPE Yellow colour warning mat (refer PJS) over the pipeline along the complete route as per standard drawings. data sheets & technical specifications. padding around pipeline including supply of suitable padding material duly approved by EIC. Backfilling to its original condition with excavated earth / borrowed select soil/sand duly approved by EIC & its compaction & crowning. At certain specific area of ROU. trench shall be backfilled & compacted and shall be made ready for motorable and no seperate payment shall be admissible against this activity.All tiles / slabs / curb stones etc removed during excavation shall be placed properly.Restoration shall be carried as per separate SOR item mentioned elsewhere in the SOR or to be done by Owner / concerned authorities.
1020The scope of work against this item also include Electro-fusion jointing of valves. fittings wherever required and as directed by Engineer-in-charge.The scope of work against laying of 20 mm pipe also includes works like making of PCC pedastal of grade (1:2:4) and size ( (300mm(L)X200mm(W) XHeight (H)). (H>=300mm & will be as per site condition) ). supply and installation of GI Sleeve (Heavy (C-Class) as per IS-1239). filling of sand and installation of TF (along with supply).
1021Pneumatic testing. purging with nitrogen and commissioning as per specification and approved procedures providing all tools and tackles. nitrogen. instruments. manpower and other related accessories and as per the instructions of the Engineer-in-charge.
1022Final clean-up of right-of-use or area disturbed by contractor during their construction activities for laying of pipeline works and disposal of debris and surplus material to designated disposal areas and backfilling of trench and compaction of the same as per satisfaction of Owner and / or as directed by Engineer–in–charge.
1023Maintaining the completed pipelines and installation for any defect or failures during defect liability period (i.e. 12 months from date of completion of work).Handing over the completed works to Owner for their operation/ use. reconciliation of material area wise and obtaining \\"no objection certificate\\" from Owner/ PMC.Preparation and submission of Daily progress report. Laying Graphs / PE line cards on daily basis.
1024On completion of gas charging of pipelines. Preparation and submission of As-built drawings. crossings details. termination. utility graphs and deviation statements.In case. the minimum required depth is not possible due to site condition. necessary mitigation measures with minimum permissible top cover shall be carried out by the contractor in consultation with EIC as per PNGRB Guidelines. without any time and cost implecation to owner.
1025Submission of all documents required for contract closure in numbers as mentioned in contract.Any other activities not mentioned / covered explicitly above. but otherwise required for satisfactory completion / operation / safety / statutory / maintenance of the works shall also be covered under the scope of work and has to be completed by the Contractor within specified schedule at no extra cost to Owner. All the work shall be executed in accordance with the provision of contract.
102620 mm PE 100 pipe
102732 mm PE 100 pipe
102863 mm PE 100 pipe
102990 mm PE 100 pipe
1030NOTE i) The lengths of pipelines are tentative. ii) For restoration of asphalt / concrete roads. the item for construction of asphalt top / concrete top / Tiles/Stone slab/Paver Blocks/Curb Stones shall be paid separately as per the rates quoted for the same elsewhere in the SOR 2.4.
1031GPR Survey for identification of pipeline
1032Laying of Pipeline by HDD in Rock Terrain
103332 mm PE 100 pipe
103463 mm PE 100 pipe
103590 mm PE 100 pipe
1036Restoration
1037Restoration of the roads. pavements. channels. footpaths. tiles. stones etc. to original condition including supply of the approved quality material required. as per local authorities norms. obtaining NOC from concerned local authorities / land owners / third party inspection agencies (if any) designated by owner and to the satisfaction of Engineer-in-charge.
1038Asphalting
1039Cement Concrete
1040Tiles/Stone slab/Paver Blocks/Curb Stones
1041Brick Soling / Channels. etc.
1042Installation of valve in pit including supply of valves
1043Supply of isolation valves (as per data sheet) and installtion of valves in the valve pits as per typical drawing and specification enclosed and instructions of Engineer-in-charge. Payment of valve pits shall be paid separately as per SOR 2.6.
1044PE Valve 20 mm dia
1045PE Valve 32 mm dia
1046PE Valve 63 mm dia
1047PE Valve 90 mm dia
1048Construction of Valve Pits as per the enclosed tender drawing and specification. The item includes supply of all the material including Pre-cast RCC cover. shuttering. reinforcement. labour. curing etc as per the drawings. specification and instruction of EIC.
1049Type-I having Internal size of Minimum 1000 x 1000mm
1050Type-II having Internal size of Minimum 600 x 600mm
1051Note: The tender drawing enclosed is only for reference purpose and contractor shall be required to prepare drawings (in line with reference tender drawing) for specific sizes of Valve pits and the same shall be approved by EIC.
1052Fabrication & Installation of Markers
1053RCC Route Markers
1054Supply, fabrication and installation of RCC route markers as per the attached drawing in technical volume, along the route including all associated civil works such as excavation and construction in all types of soils, construction and pedestals and grouting with concrete.
1055Pole Markers with Foundation
1056Supply, fabrication and installation of plate markers as per the attached drawings in technical volume including all associated civil works such as excavation and construction in all types of soils, construction and pedestals and grouting with concrete, cleaning, stencil let.
1057Warning Plate Markers
1058Supply, fabrication and installation of plate markers, including application of approved color and quality of primer and paint, stencil letter cutting of lettering, numbers, direction, etc. as per the attached drawing in technical volume to be installed near regulator.
1059Excavation of Hard rock/surface
1060Excavation of trench or pits, wherever hard rock presence is exceeding 1.5 m in any direction of the trench and excavation of trench or pits in Malba/Multiple layers of asphalt/ brick / PCC/RCC etc and removable only by pneumatic chisel / drill as per the specifications and direction of EIC. The rates are payable over and above the Laying rates as per relevant SOR no. 2.1
1061Cutting of PCC/RCC surface with thickness more than 12\\" or Continuous asphalt multi-layer/ Malba/ Brick / Boulders more than 24\\".(Malba shall be considered as a strata where soil is in mixed form of debris/building rubbish or discarded pieces of bricks/stones )
1062Rock Cutting encountered while excavation of trenches for item 2.1 of SOR, not exceeding 1.5 meter in width, and lift upto 1.5 meter, including getting out the excavated soil and disposal of excavated soil as directed within a lead of 50 meter. In case of rocky soil, the bedding shall be done with approved/ good quality packing sand, subject to the approval of the EIC, the size distribution of the sand / shall be the same as per soil. The packing sand shall be placed to a minimum thickness of 150mm around the pipe in case of rocky terrain.
1063Note: i) The quantities mentioned are indicative only. ii) For all the supply items mentioned above, procurement shall be made as per specification after due approval of engineer- in - charge.
1064Liaisoning with Land Owning Agencies for Permission
1065Submission of applications as per approved drawings (Initial Route survey, prepartion of drawing, measuring and providing details of surface type shall be in scope of contractor), obtaining and submission of demand note, coordination, Liaisoning, obtaining written permission from land owing agencies like NHAI, AAI,Indian Railways and any other government agencies resposible for maintaining public lands and agencies owing Private lands etc. (all fee paid to authorities excluding demand charges or Bank Guarantees shall be reimbursed against documentary evidence). Permissions required from various authorities like NHAI / Railways / Irrigation (Canal) etc. falling enroute shall be inclusive in the item rate. No separate liasion charges against construction of valve chambers is payable and is included in laying rates.
1066Construction of RCC structure for protection of service line for drain/nallah Crossings
1067Construction of Non suspended slabs/pavement slabs including pedestal/ramp etc.using reinforced cement concrete of M-25 grade (Concrete shall be design mix/nominal mix with 20 mm & down size graded crushed stone aggregates) to protect the PE pipe laid. All necessary form work, finishing the top surface rough/smooth as required in any position, shape, level and thickness etc. shall be as specified and directed by EIC. The rates shall include grouting of pockets, supply of all material, tools, reinforcement steel etc.
1068Preservation of Pipeline
1069Preservation of pipeline sections and associated facilities (in event of delay in comissioning, other unforeseen reasons) including supply of nitrogen, all consumables, all equipment, man-power, etc. complete as per the requirements of specifications, other provisions of tender/ contract documents and instructions of Engineer-in-charge.
1070By filling and pressurizing with nitrogen to a pressure of 2 bar(g) for a period of one month or part thereof.
1071For 20 mm Pipeline
1072For 32 mm Pipeline
1073For 63 mm Pipeline
1074For every additional period of one month or part thereof Limited to 6 month
1075For 20 mm Pipeline
1076For 32 mm Pipeline
1077For 63 mm Pipeline
1078Notes: i) The above length is not for a single section but for no. of sections. ii) All accessrious ie; End caps and two nos tappings of 3/4 inches, PG to be considered per section and rate for the same shall be quoted by bidder under this item.iii) If month is partially complete, payment shall be made on prorata basis.iv) Scope includes pressure holding for a period of 6 months or as per EIC and jointing of PE pipe (if required) due to damage by any means and further filling of nitrogen for pressure holding.v) Length given are tantative may change as per site requirments.
1079CIVIL WORKS
1080Earth Work
1081Earth in excavation and filling to the grades and levels shown in the approved drawings in all kinds of conditions including for Road embakments, using approved quality good earth from designated borrow area, for all heights and depths including clearing and stripping (min. 150 mm) of the area marked for filling, taking spot levels, consolidating the exposed natural soil surface, excavating the earth from borrow area loading, transporting & unloading, spreading in layers not exceeding 150 mm thickness, breaking clods, watering (if reqd.), ramming and compacting by manual/ mechanical means to give minimum 92% of modified Proctor's density of earth, testing & dressing including disposal of all unserviceable material all complete as per specifications and directions of Engineer-in-charge.
1082(Rate to include cost of all labour, tools, tackles, equipment, hire chanrges, cost of borrow earth by way of royalties, right of way, cess etc., as applicable with all bye works and sundry works).
1083PCC 1:2:4
10841 Cement : 2 Coarse sand : 4 stone aggregate 20mm nominal size.
1085PCC 1:4:8
10861 Cement : 4 Coarse sand : 8 stone aggregate 40mm nominal size.
1087(Rate to include cost of all labour, tools, tackles, equipment, hire charges, supply of all materials, shuttering, earthwork in excavation and backfilling using approved earth in all conditions etc. with all bye works and sundry works.)
1088Reinforced Cement Concrete
1089Providing and laying reinforced cement of grade M-25 with 20mm and down grade crushed stone aggregate in all types of structures like foundations, pedestals, pedestal bases, pipe supports, sleepers, column, equipment foundation, Non suspended slabs/pavement slabs, ramps, cable trench inlcuding construction joints, bitumen painting on surface in contact with soil, supplying and fixing reinforcing steel, shuttering, inserts, finishes, grounting etc. at all depths and heights complete as per drawings, specifications and direction of the Engineer-in-charge.
1090Rate to include cost of all labour, tools, tackles, equipment, hire charges, supply of all maerials such as minimum 43 grade cement including sulphate resistant cement for sub-structures, R/F steel, Inserts, bolts, conduits, bitumen, other minor constrcution materials, shuttering, stanging, earthwork in excavation and backfilling using serviceable earth in all conditions, shorting bailing and pumping out water, testing of concrete, curing etc. with all bye works and sundry works.
1091Concrete Pavement
1092Providing and laying reinforced cement concrete of (M-25 grade) with 20mm and down grade crushed stone aggregate in pavement, including preparation of base (i.e. compacted subgrade, 200 thk sand and 50 thk PCC M-10 grade), leaving pockets if necessary, making recess, projections, fixing inserts conduit pipes (GI, PVC, HDPE, etc.) laying in alternate panels, filling the gaps between the panels with bitumen etc., making slopes, finishing edges, leaving bars for pedestals & sleepers including providing sand fill isolation , shuttering, providing and fixing reinforcing steel, curing, chipping and modification works etc. as specified in any shape, thickness, position and finishing the top surface smooth as per requirement etc. all complete as per drawings, specifications and directions of the Engineer-in-charge.
1093Concrete Pavement- 150mm thick (Type-I)
1094Brick Work
1095Providing brick work with brick class designation M-7.5 of IS:1077 in cm1:4 (1 cement : 4 sand) in steps, walls, retaining walls and load bearing structures drains, or any shape with all lead, depths & height including curring, scaffolding, etc., as per specifications and drawings with all bye-works and direction of the Enfineer-in-charge.
1096(Rate to include cost of all labour, tools, tackles, equipment, hire charges, supply of all materials such as minimum 43 grade cement, bricks, finishes, bitumen, other minor constrcution materials, shuttering, staging, masonry work, plastering, painting etc. with all bye-works and sundry works).
1097Note: The quantites of individual item can varied as per site requirement.The payment will be made as per actual certified measurement at site.
1098Laying of Brick layer/ Concrete
1099Providing single layer of Brick / Concrete / or impact resistant tape to entire width of trench above Warning Mat placed in trench over the laid pipeline as per OISD 226, standard drawing, specification and instruction of Owner. (Rate to include cost of all labour, tools, tackles, equipment, hire charges & supply of all materials, etc)
1100Brick Layer for width of PE pipeline trench as per drawing (75 mm thk.)
1101Concrete for width of PE pipeline trench as per drawing (80 mm thk.)
1102Demolition of PCC work below plinth level
1103Demolishing plain cement concrete (PCC) work (taking all necessary safety precautions) for all depths below plinth level including supply of all tools & tackles, necessary scaffolding, propping, underpinning, etc. , disposal of unserviceable material outside the boundary limits keeping the owner indemnified of any liabilities from statutory/ local bodies, all complete work as specified and directed.
1104Excavation for foundation works
1105Excavation as per plan, upto 3 meters and upto any lead in all conditions, backfilling using serviceable earth and disposal of surplus and unserviceable earth. Soil to be levelled and neatly dressed complete in all respect as per scope of work, technical specification and directions of EIC.
1106Upto 3.0 Mtrs
1107Dismantling of RCC & cutting of reinforcement (Thickness above 3”)
1108Structural Works
1109Supplying, fabricating & fixing steel structural cage fabricated from Angle conforming to IS:808 & fixing of GI weldmesh made from 3mm GI wire @ 75 mm bothways to structural steel frame by means of welding/bolting, including applying two coats of approved quality of synthetic enamel paint over a priming coat of in approved shade including supply of all raw materials, bolts, electrodes, transportation, including Hilti arrangement ,locking arrangement for fixing of posts etc complete as per enclosed drawing, technical specifications, scope of works and directions of the Engineer-In-Charge. Note:- Material shall be supplied and fabricated as per site condition and Contractor have to take quantity approval from EIC/OWNER prior to commencement of work and order placement.
1110MRS / Metering Skid/Wall Mounted MRS.
1111Installation of MRS / Metering Skid on foundation
1112Receiving and taking over, handling, loading, transportation and unloading of MRS / Metering Skid from Owner's designated stockyards to site, installation at foundation and hooking up with PE pipe including all works as required to complete the job as per the drawings and specification, scope of work mentioned in tender doucment. The scope includes supply of transition fittings,GI Sleeve, other MDPE and CS fittings as required and various associated works to commission MRS / Metering Skid. (Note:- The installation included CS piping work included welding, testing, NDT etc.,however payment for the CS piping work along with accessories supply will be paid in SOR item 7.0 to 25.0 respectively.)
1113Note: 1) Amount towards civil work shall be payable as per related SOR items. 2) Rate to include cost of all labour, tools, tackles, equipment, hire charges.3) All fittings and consumables including Bolts, nuts, washer, U-clamps, gaskets etc. if required during installation shall be procured and supplied by the Contractor within the rate quoted. These items shall not be separately measured and paid.
1114MRS / Metering Skid <2000 SCMD
1115MRS / Metering Skid 2000-5000 SCMD
1116MRS / Metering Skid 5000-20000 SCMD
1117MRS / Metering Skid >20000 SCMD
1118Installation of Wall Mounted Metering System (Meter, Regulator & Accessory) locked in cage
1119Receiving and taking over, handling, loading, transportation and unloading of all items for Wall Mounted Metering System (Meter, Regulator & Accessory) from Owner's designated stockyards to site, installation on wall and hooking up with PE pipe including all works as required to complete the job as per the drawings and specification, scope of work mentioned in tender doucment.The scope includes supply of items required as per the drawing in scope of work (Details of drawings as PJS) viz. transition fittings, GI/Concrete Sleeves and other MDPE and CS fittings etc. as required and various associated works.(Only Meters and Regulators shall be provided as free issue) and all associated works (For CS pipe and other items refer sl. no. 7.0 to 25.0) to commission Wall Mounted Metering System. Note : Installation works included CS piping work, Testing etc.,however payment for the CS piping work along accessories will be paid in diiferent SOR item
1120Note: 1) Amount towards civil work shall be payable as per relevant SOR items. 2) Rate to include cost of all labour, tools, tackles, equipment, hire charges .3) All fittings (those are not mentioned in SOR item 7.0 to 25.0) and consumables including Bolts, nuts, washer, U-clamps, gaskets etc. if required during installation shall be procured and supplied by the Contractor within the rate quoted. These items shall not be separately measured and paid.4)The wall mounted Metering System to be kept in cage with locking facility, However payment for Structural work will be paid against SOR item 4.0
1121The Typical Design of MRS/Metering System are as per \\"Standardized metering system Design, Selection & Installation philosophy for supply of PNG to Industrial and Commercial Customers of GAIL Gas.\\"Note: -The sizes mentioned in drawings are indicative & may vary as per actual requirment at site .
1122Wall Mounted Metering System < 200 SCMD
1123Wall Mounted Metering System 200-500 SCMD
1124Wall mounted Metering System 500 to 2000 SCMD
1125Wall mounted Metering System >2000 SCMD
1126Note: i) The quantities mentioned are indicative only. ii) For all the supply items mentioned above, procurement shall be made as per specification after due approval of engineer- in - charge.
1127Installation of Wall Mounted Metering System (Pre-assemble)
1128Receiving and taking over, handling, loading, transportation and unloading of all items for Wall Mounted Metering System (Pre-assembled as per standard drawing Attached in PJS Drawing ) from Owner's designated stockyards to site, installation on wall and hooking up with PE pipe including all works as required to complete the job as per the drawings and specification, scope of work mentioned in tender doucment.The scope includes supply of transition fittings, Sleeves and other MDPE and CS fittings etc. as required and various associated works, however, the Metering System assembly ( As per drawing ) shall be provided as free issue by GAIL Gas. Installtion work done by Contractor along supply of consumables including Bolts, nuts, washer, U-clamps, gaskets etc. if required during installation shall be procured and supplied by the Contractor within the rate quoted.
1129Note: 1) Amount towards civil work shall be payable as per related SOR items 3.0. 2) Rate to include cost of all labour, tools, tackles, equipment, hire charges .3) The wall mounted Metering System to be kept in cage with locking facility, However payment for Structural work will be paid against SOR item 4.0
1130Installation of GI Pipe 2\\" - 1\\" size with isolation valve for commercial meter inlet connection from TF
1131Removal of MRS/ Metering Skids, Wall Mounted MRS/Metering System (all capacities) from existing consumer's premise,
1132Removal of MRS/ Metering Skids, Wall Mounted Metering System (all capacities) from existing consumer's premise for shifting to another site/store. The scope of work also includes excavation to retrive PE pipe line , disconnection of existing pipe lines (PE & Steel).
1133Note:- Transportaion of removed metering skid/Wall mounted Metering System to store shall be payble under SOR item no.5.4.2. However, if this skid is being shifted directly to new location for installation at new customer premises then transportation to be claimed from 5.1 & 5.2 as applicable.
1134Transportaion of removed metering skid/Wall mounted Metering System to store
1135Conversion of Commercial Appliances/Industrial :
1136Conversions of all types of commercial appliances to NG based appliances. Supply & changing of the nozzles /jets and associated controls for Non-domestic appliances (imported appliances included) with proper tools and tackles. Cleaning and performing minor maintenance, greasing etc. of the appliance. Testing and showing the performance to the customer, signing of joint meter records (JMR) and instructing the customer on use & safety norms, complete as per specifications & to satisfaction of owner / Engineer in Charge and includes supply of reinforced rubber hose with requisite pressure rating.Supply of Appliance valve is also included.
1137Installation of ASTM A106, Gr. B, Seamless, BE , NB, XS pipes of various dia
1138ASTM A106, Gr. B, Seamless, PE , 1/2\\" NB, S160 , their fittings and installation of meter and regulator (as applicable)
1139ASTM A106, Gr. B, Seamless, PE , 1\\" NB, XS , their fittings and installation of meter and regulator (as applicable)
1140ASTM A106, Gr. B, Seamless, PE, 1.5\\" NB, XS , their fittings and installation of meter and regulator (as applicable)
1141ASTM A106, Gr. B (Charpy), Seamless, BE , 2\\" NB, XS , their fittings and installation of meter and regulator (as applicable)
1142ASTM A106, Gr. B (Charpy), Seamless, BE , 3\\" NB,XS , their fittings and installation of meter and regulator (as applicable)
1143ASTM A106, Gr. B (Charpy), Seamless, BE , 4\\" NB,XS , their fittings and installation of meter and regulator (as applicable)
1144Note:a). Supply & Installation of required size of brass fittings (which are not included in SOR item 8.0 to 23.0) in all type of meters (supplied by GAIL GAS LTD. ) shall be in scope of contractor.b). All butt welded fittings end shall generally match with connecting pipe wall thickness. However, in case of misalignment, Contractor shall have to do end preparation without any extra cost. c). Payment of radiography of joints (4\\" and below ) shall be paid seperately under SOR item for RADIOGRAPHY mentioned elsewhere in this SOR 25.0d). All type of piping works shall be carried out as per piping material specification (PMS).e). Complete Carbon Steel Piping Work with painting including all fittings, flanges and supply of all required gaskets, studs bolts & nuts etc.
1145Supply of CARBON STEEL PIPES as per Technical Specification and as directed by EIC
1146ASTM A106, Gr. B, Seamless, PE , 1/2\\" NB, S160
1147ASTM A106, Gr. B, Seamless, PE , 1\\" NB, XS
1148ASTM A106, Gr. B, Seamless, PE, 1.5\\" NB, XS
1149ASTM A106, Gr. B (Charpy), Seamless, BE , 2\\" NB, XS
1150ASTM A106, Gr. B (Charpy), Seamless, BE , 3\\" NB,XS
1151ASTM A106, Gr. B (Charpy), Seamless, BE , 4\\" NB,XS
1152Supply of Pressure Gauges as per Technical Specification and as directed by EIC
1153RANGE 0-100 MBAR - 4\\"- DIAL SIZE
1154RANGE 0-1 BAR - 4\\"- DIAL SIZE
1155RANGE 0-4 BAR - 4\\"- DIAL SIZE
1156RANGE 0-6 BAR - 4\\"- DIAL SIZE
1157RANGE 0-30 BAR - 4\\"- DIAL SIZE
1158Supply of Conical Stainer
1159As per Technical Specification and as directed by EIC.Note: - Conical Stainer may be free issue by Gail Gas Ltd., It is Discretion of Gail Gas Ltd. to excute the SOR or Free Issue the material.
1160Supply of Check valve/NRVAs per Technical Specification and as directed by EIC.
11612\\", 150# FE,FB
11623\\", 150# FE,FB
11634\\", 150# FE,FB
1164Supply of Flanges Weld Neck(End Thickness to match pipe thickness)
11651\\" , 150#, B-16.5 , A105 ,125 AARH,SW,RF
11661.5\\" , 150#, B-16.5 , A105 ,125 AARH,SW,RF
11672\\",150#, B-16.5, A105 (Charpy), 125 AARH, RF
11683\\",150#, B-16.5, A105 (Charpy), 125 AARH, RF
11694\\",150#, B-16.5, A105 (Charpy), 125 AARH, RF
1170Supply of Blind FlangesAs per Technical Specification and as directed by EIC.
11712\\",150#, B-16.5, A105 (Charpy), 125 AARH, RF
11723\\",150#, B-16.5, A105 (Charpy), 125 AARH, RF
11734\\",150#, B-16.5, A105 (Charpy), 125 AARH, RF
1174Supply of End Caps
11752\\", XS, A 234 Gr. WPB (Charpy), BW
11763\\", XS, A 234 Gr. WPB (Charpy), BW
11774\\", XS, A 234 Gr. WPB (Charpy), BW
1178Supply of FLANGE END GLOBE VALVES, MAOP- 4 BARAs per Technical Specification and as directed by EIC.
1179Supply of Ball ValvesAs per Technical Specification and as directed by EIC.
11801/2\\",800#, Sockolet Welded/Threaded Valve
11811\\",800#, Sockolet Welded/Threaded Valve
11822\\",150#,FE, FB,
11833\\",150#,FE, FB,
11844\\",150#,FE, FB,
1185Supply of Isolation Ball Valve And Appliance Valve as per Technical Specification and as directed by EIC
1186Isolation Ball Valve ½\\" max. 6 bar (g)
1187Isolation Ball Valve 1\\" max. 6 bar (g)
1188Isolation Ball Valve 1.5\\" max. 6 bar (g)
1189Isolation Ball Valve 2\\" max. 6 bar (g)
1190Isolation Ball Valve 3\\" max. 6 bar (g)
1191Supply of SOCKOLET (A105, SW) As per Technical Specification and as directed by EIC.
11922\\" x ½\\"
11932\\" x 1\\"
11943\\" x ½\\"
11953\\" x 1\\"
11964\\" x ½\\"
11974\\" x 1\\"
1198Supply of Reducer (A 234 Gr. WPB (Charpy), BW)
11991.5\\" x 1\\", XS x XS, A105, SW,3000#, B-16.11
12002\\"x1\\", XS x XS, A 234 Gr. WPB (Charpy), BW, B-16.9
12012\\" X 1.5\\", XS , A 234 Gr. WPB (Charpy), BW, B-16.9
12023\\"x1\\", XS x XS, A 234 Gr. WPB (Charpy), BW, B-16.9
12033\\" X 1.5\\", XS , A 234 Gr. WPB (Charpy), BW, B-16.9
12043\\" x 2\\" , STD x XS, A 234 Gr. WPB (Charpy), BW, B-16.9
12054\\" x 3\\" , STD x XS, A 234 Gr. WPB (Charpy), BW, B-16.9
1206Supply of Tee, Equal / Reducing Tee
12071\\", XS, SW, 3000#, B-16.11
12081.5\\", XS, A105, SW, 3000#, B-16.11
12092\\" x 1.5\\", XS , A234, Gr. WPB (Charpy), B-16.9, BW
12102\\", XS , A234, Gr. WPB (Charpy), B-16.9, BW
12113\\", STD , A234, Gr. WPB (Charpy), B-16.9, BW
12124\\" STD x XS, A234, Gr. WPB (Charpy), B-16.9, BW
1213Supply of ELBOW, 90° Elbow
1214½\\", XS, SW, 3000#, ASTM A105,B-16.11
12151\\", XS, SW, 3000#, ASTM A105,B-16.11
12161.5\\", XS, SW, 3000#, ASTM A105,B-16.11
12172\\", XS, BW, A234, Gr. WPB (Charpy), B-16.9, 1.5D
12183\\", STD, BW, A234, Gr. WPB (Charpy), B-16.9, 1.5D
12194\\", XS, BW, A234, Gr. WPB (Charpy), B-16.9, 1.5D
1220Supply of Spectacle Blind AS PER SPECIFICATION
1221Spectacle Blind 2\\"
1222Spectacle Blind 3\\"
1223Spectacle Blind 4\\"
1224Supply of Internal/external piping support (AS PER Tender)
1225TYPE-1, SIDE WALL MOUNTED AS PER DRAWING
1226TYPE-2, GROUND BASED AS PER DRAWING
1227TYPE-3, CEILING MOUNTED AS PER DRAWING
1228WELDING OF JOINTS - Butt Weld Joints
12291/2\\" (WELDING OF JOINTS)
12301\\" (WELDING OF JOINTS)
12311.5\\" (WELDING OF JOINTS)
12322\\" (WELDING OF JOINTS)
12333\\" (WELDING OF JOINTS)
12344\\" (WELDING OF JOINTS)
1235Note: i) All butt welded fittings end shall generally match with connecting pipe wall thickness however in case of misalignment Contractor shall have to do end preparation without any extra cost.ii) All coupling, nipples etc. as required shall be supplied by contractor but no separate payments shall be made as it is covered under erection rate.
1236RADIOGRAPHY OF JOINTS
1237Performance of radiographic inspection by gamma radiation as per scope of work and as per specifications in piping of all types and thickness including providing/hiring of all necessary equipments, supply of all consumables, and whatever else even though not expressely mentioned but required to perform the work as per specifications and instructions of Engineer-in-Charge (full circle re-radiography of the repaired joint and additional radiography necessitated due to poor performance of contractor's welder shall be carried out by the Contractor at his own cost and shall not be paid extra by Company). Radiographs shall be submitted to the Engineer-in-Charge for acceptance, whose decision shall be final and binding.
1238Note- i). 4\\" & Below and all butt weld joint are radiography / X-ray shall be done at every joint and shall be carried out as per API 1104 (latest edition) / M/s GAIL Gas Ltd. specification / OISD / PNGRB and same shall be approved by Engineer–in–charge (EIC)/RCM.ii). All socket weld joint MPT/UT/DPT shall be done at every joint nd shall be carried out as per API 1104 (latest edition)/M/s GAIL Gas Ltd. specification / OISD / PNGRB and same shall be approved by Engineer–in–charge (EIC)/ RCM.
12391/2\\" (RADIOGRAPHY of Joints as Above)
12401\\" (RADIOGRAPHY of Joints as Above)
12411.5\\" (RADIOGRAPHY of Joints as Above)
12422\\" (RADIOGRAPHY of Joints as Above)
12433\\" (RADIOGRAPHY of Joints as Above)
12444\\" (RADIOGRAPHY of Joints as Above)
1245Note: i) Quantities mentioned against each above item of SOR Items are tentative and may increase or decrease during execution of work depending upon site requirement. Contractor required to supply materials after assessing the site requirement and in multiple lot or as per Release Order/ Sub Purchase Order wise. All material either in multiple lot or as per Release Order/ Sub Purchase Order wise or as decided by EIC shall be supplied by bidder within the quoted price.(ii) The quantites of individual item can varied as per site requirement.The payment will be made as per actual certified measurement at site. For the supply items the quantities shall be procured after approval from client/ consultant/EIC.(iii) The bidder must indicate currency(ies) against each quoted item of the SOR.(iv) The total amount shall also be given by the bidder in the quoted currency(ies).(v) Some of the may / may not be execute as per site requirements.
1246Ground Connectivity Works
1247Laying of MDPE pipeline by any method in any type of soil strata upto 20m length from charged Pipeline to Customer premise including connection of Transistion Fitting at customer end. For pipeline laid more than 20m, payment for additonal length shall be covered in SOR no.2 in ruuning meters more than 20m.
1248PE 20mm dia
1249PE 32mm dia
1250PE 63mm dia
1251PE 90mm dia.
1252Survey, Pit Excavtion in all types of soills/PCC/RCC/Paver block/Ashpalt/Whitetopping etc., charged pipeline identification, Hook up activities, Online tapping either by Saddle / Tee / extension by Coupler for connecting the Pipeline laid as per above SOR 1.1 including fittings, Backfilling. Restoration shall be paid through other SOR
1253Connectiviy for PE 20mm dia laid under 1a.
1254Connectiviy for PE 32mm dia laid under 1a.
1255Connectiviy for PE 63mm dia laid under 1a.
1256Connectiviy for PE 90mm dia laid under 1a.
1257PE PIPELINE
1258PE Pipe Laying in any type of surface like unprepared surface (Katcha surface)/ Normal Surface/ Hard surface/Rock surface etc using open cut/ Moling (without Casing)/ Moling (with Casing)/ Horizontal Directional Drilling technique (with and without casing pipe) methodology. HDD at Hard Rock shall be paid through different SOR.
1259Receipt. Loading. unloading. storing. reloading. tranportation. unloading. stringing and laying of PE100. SDR11 line pipes of all sizes including. proper stacking. identification.and supply of accessories of all sizes & thickness like PE Bends. Couplers. Endcaps. Tee. Reducer. CS / GI to PE Fittings (i.e. Transition Fittings of sizes 20 mm to 90 mm). Warning Mat etc. Handling. Stringing / uncoiling. aligning of the PE line pipe on the pipeline Right-of-Use / route. laying / installation of PE line pipe alongwith required accessories as mentioned above as per specification wherever required depending on site condition including execution of all works; Storeage of material in contractor's store. fabrication. access for construction procurement and supply of all materials. consumables. equipments. labour and other inputs.
1260In the case of free issue items. the scope also includes. receiving and loading from Owner's designated store. transportation. unloading and stacking of free issue items at Contractor's store. -Laying of all PE pipe (PE 100 SDR11). Including supply of HDPE casing pipe (in case of HDD (with case).Moling(with case) . Couplers. End caps etc. (Ref. of Particular job specification).Survey of under ground utilities. execution of the work as per specification. including excavation of pits moling with the hole size not exceeding 20% of the pipe dia. jointing and insertion of carrier pipe with casing. testing & commissioning and restoration of the pits to original condition. submission of As-Built Graph as per specifications and the instruction of Engineer-in-charge.
1261Casing details is as given below:-1. For 20/32 mm PE pipe (in 75 mm dia. HDPE Casing Pipe. PE 63/80 PN6.0).2. For 63 mm PE pipe (in 125 mm dia. HDPE Casing Pipe. PE 63/80 PN6.0).
1262Carrying out all temporary. ancillary. auxiliary works required to make the PE pipeline ready for commissioning as per drawings. Specifications. scope of work indicated in PJS and other provisions of tender/ contract documents and instructions of Engineer-in-charge. including but not limited to carrying out the following works:Surveying of route and detours required at the time of execution. preparation of construction drawings showing survey details and submit same to Owner for review / approval.
1263Carrying out preliminary activities such as preperation of drawings wherever required for crossing etc.Preparation and getting approval of schedules. execution procedures. drawings/ sketches/ wherever required. making trial pits to determine the underground utilities/ services etc.. restoration of the abandoned trial pits to original condition.
1264Stacking and installation of construction markers. clearing. fencing. grubbing. cutting of trees. full filling all the requirements of various statutory/ environment authorities to the entire satisfaction of concerned authorities. grading of work area.
1265Barricading the work area as per local authorities norms & to the satisfaction of Owner/ Eingineer -in- charge. installation of safety signs.Barricading the pipeline construction area prior to execution of the works as per drawing enclosed with tender/ contract documents and to the entire satisfaction of owner / engineer- in -charge.
1266Laying using open trench without casing includes survey of under ground utilities (through trial pits). execution of work as per specification including Trenching to all depths by excavation in all types of soils including soft/ rocky strata and different type of pavement / footpath / roads etc. including rock breaking. chiselling or otherwise cutting etc. as required and storing excavated soil. reusable materials at designated area as directed by Engineer in charge and to a width to accommodate the pipeline as per the relevant standard/ specification etc.
1267The minimum depth of the top of pipeline shall be 1.0 m measured from top of pipeline to the top of undisturbed surface of the soil or as per Specification/ OISD- 226 & PNGRB latest guidelines whichever is higher.Dewatering of trenches / pits if required as per site condition. Repairing of all damaged utilities if any. and payment of any compensation (if claimed by owner / other utility agencies)Uncoiling / stringing & aligning of PE pipes. clamping. jointing of the pipe ends / fittings / valves by qualified personnel using approved electro-fusion techniques as per specification.Note:- Coordinates to be taken for implementation for GIS for Valve pit, Fusion welding location and MRS.
1268Installation / lowering the pipeline in trench to required depth as per PJS. Technical Specification & drawings. supply & placement of HDPE Yellow colour warning mat (refer PJS) over the pipeline along the complete route as per standard drawings. data sheets & technical specifications. padding around pipeline including supply of suitable padding material duly approved by EIC. Backfilling to its original condition with excavated earth / borrowed select soil/sand duly approved by EIC & its compaction & crowning. At certain specific area of ROU. trench shall be backfilled & compacted and shall be made ready for motorable and no seperate payment shall be admissible against this activity.All tiles / slabs / curb stones etc removed during excavation shall be placed properly.Restoration shall be carried as per separate SOR item mentioned elsewhere in the SOR or to be done by Owner / concerned authorities.
1269The scope of work against this item also include Electro-fusion jointing of valves. fittings wherever required and as directed by Engineer-in-charge.The scope of work against laying of 20 mm pipe also includes works like making of PCC pedastal of grade (1:2:4) and size ( (300mm(L)X200mm(W) XHeight (H)). (H>=300mm & will be as per site condition) ). supply and installation of GI Sleeve (Heavy (C-Class) as per IS-1239). filling of sand and installation of TF (along with supply).
1270Pneumatic testing. purging with nitrogen and commissioning as per specification and approved procedures providing all tools and tackles. nitrogen. instruments. manpower and other related accessories and as per the instructions of the Engineer-in-charge.
1271Final clean-up of right-of-use or area disturbed by contractor during their construction activities for laying of pipeline works and disposal of debris and surplus material to designated disposal areas and backfilling of trench and compaction of the same as per satisfaction of Owner and / or as directed by Engineer–in–charge.
1272Maintaining the completed pipelines and installation for any defect or failures during defect liability period (i.e. 12 months from date of completion of work).Handing over the completed works to Owner for their operation/ use. reconciliation of material area wise and obtaining \\"no objection certificate\\" from Owner/ PMC.Preparation and submission of Daily progress report. Laying Graphs / PE line cards on daily basis.
1273On completion of gas charging of pipelines. Preparation and submission of As-built drawings. crossings details. termination. utility graphs and deviation statements.In case. the minimum required depth is not possible due to site condition. necessary mitigation measures with minimum permissible top cover shall be carried out by the contractor in consultation with EIC as per PNGRB Guidelines. without any time and cost implecation to owner.
1274Submission of all documents required for contract closure in numbers as mentioned in contract.Any other activities not mentioned / covered explicitly above. but otherwise required for satisfactory completion / operation / safety / statutory / maintenance of the works shall also be covered under the scope of work and has to be completed by the Contractor within specified schedule at no extra cost to Owner. All the work shall be executed in accordance with the provision of contract.
127520 mm PE 100 pipe
127632 mm PE 100 pipe
127763 mm PE 100 pipe
127890 mm PE 100 pipe
1279NOTE i) The lengths of pipelines are tentative. ii) For restoration of asphalt / concrete roads. the item for construction of asphalt top / concrete top / Tiles/Stone slab/Paver Blocks/Curb Stones shall be paid separately as per the rates quoted for the same elsewhere in the SOR 2.4.
1280GPR Survey for identification of pipeline
1281Laying of Pipeline by HDD in Rock Terrain
128232 mm PE 100 pipe
128363 mm PE 100 pipe
128490 mm PE 100 pipe
1285Restoration
1286Restoration of the roads. pavements. channels. footpaths. tiles. stones etc. to original condition including supply of the approved quality material required. as per local authorities norms. obtaining NOC from concerned local authorities / land owners / third party inspection agencies (if any) designated by owner and to the satisfaction of Engineer-in-charge.
1287Asphalting
1288Cement Concrete
1289Tiles/Stone slab/Paver Blocks/Curb Stones
1290Brick Soling / Channels. etc.
1291Installation of valve in pit including supply of valves
1292Supply of isolation valves (as per data sheet) and installtion of valves in the valve pits as per typical drawing and specification enclosed and instructions of Engineer-in-charge. Payment of valve pits shall be paid separately as per SOR 2.6.
1293PE Valve 20 mm dia
1294PE Valve 32 mm dia
1295PE Valve 63 mm dia
1296PE Valve 90 mm dia
1297Construction of Valve Pits as per the enclosed tender drawing and specification. The item includes supply of all the material including Pre-cast RCC cover. shuttering. reinforcement. labour. curing etc as per the drawings. specification and instruction of EIC.
1298Type-I having Internal size of Minimum 1000 x 1000mm
1299Type-II having Internal size of Minimum 600 x 600mm
1300Note: The tender drawing enclosed is only for reference purpose and contractor shall be required to prepare drawings (in line with reference tender drawing) for specific sizes of Valve pits and the same shall be approved by EIC.
1301Fabrication & Installation of Markers
1302RCC Route Markers
1303Supply, fabrication and installation of RCC route markers as per the attached drawing in technical volume, along the route including all associated civil works such as excavation and construction in all types of soils, construction and pedestals and grouting with concrete.
1304Pole Markers with Foundation
1305Supply, fabrication and installation of plate markers as per the attached drawings in technical volume including all associated civil works such as excavation and construction in all types of soils, construction and pedestals and grouting with concrete, cleaning, stencil let.
1306Warning Plate Markers
1307Supply, fabrication and installation of plate markers, including application of approved color and quality of primer and paint, stencil letter cutting of lettering, numbers, direction, etc. as per the attached drawing in technical volume to be installed near regulator.
1308Excavation of Hard rock/surface
1309Excavation of trench or pits, wherever hard rock presence is exceeding 1.5 m in any direction of the trench and excavation of trench or pits in Malba/Multiple layers of asphalt/ brick / PCC/RCC etc and removable only by pneumatic chisel / drill as per the specifications and direction of EIC. The rates are payable over and above the Laying rates as per relevant SOR no. 2.1
1310Cutting of PCC/RCC surface with thickness more than 12\\" or Continuous asphalt multi-layer/ Malba/ Brick / Boulders more than 24\\".(Malba shall be considered as a strata where soil is in mixed form of debris/building rubbish or discarded pieces of bricks/stones )
1311Rock Cutting encountered while excavation of trenches for item 2.1 of SOR, not exceeding 1.5 meter in width, and lift upto 1.5 meter, including getting out the excavated soil and disposal of excavated soil as directed within a lead of 50 meter. In case of rocky soil, the bedding shall be done with approved/ good quality packing sand, subject to the approval of the EIC, the size distribution of the sand / shall be the same as per soil. The packing sand shall be placed to a minimum thickness of 150mm around the pipe in case of rocky terrain.
1312Note: i) The quantities mentioned are indicative only. ii) For all the supply items mentioned above, procurement shall be made as per specification after due approval of engineer- in - charge.
1313Liaisoning with Land Owning Agencies for Permission
1314Submission of applications as per approved drawings (Initial Route survey, prepartion of drawing, measuring and providing details of surface type shall be in scope of contractor), obtaining and submission of demand note, coordination, Liaisoning, obtaining written permission from land owing agencies like NHAI, AAI,Indian Railways and any other government agencies resposible for maintaining public lands and agencies owing Private lands etc. (all fee paid to authorities excluding demand charges or Bank Guarantees shall be reimbursed against documentary evidence). Permissions required from various authorities like NHAI / Railways / Irrigation (Canal) etc. falling enroute shall be inclusive in the item rate. No separate liasion charges against construction of valve chambers is payable and is included in laying rates.
1315Construction of RCC structure for protection of service line for drain/nallah Crossings
1316Construction of Non suspended slabs/pavement slabs including pedestal/ramp etc.using reinforced cement concrete of M-25 grade (Concrete shall be design mix/nominal mix with 20 mm & down size graded crushed stone aggregates) to protect the PE pipe laid. All necessary form work, finishing the top surface rough/smooth as required in any position, shape, level and thickness etc. shall be as specified and directed by EIC. The rates shall include grouting of pockets, supply of all material, tools, reinforcement steel etc.
1317Preservation of Pipeline
1318Preservation of pipeline sections and associated facilities (in event of delay in comissioning, other unforeseen reasons) including supply of nitrogen, all consumables, all equipment, man-power, etc. complete as per the requirements of specifications, other provisions of tender/ contract documents and instructions of Engineer-in-charge.
1319By filling and pressurizing with nitrogen to a pressure of 2 bar(g) for a period of one month or part thereof.
1320For 20 mm Pipeline
1321For 32 mm Pipeline
1322For 63 mm Pipeline
1323For every additional period of one month or part thereof Limited to 6 month
1324For 20 mm Pipeline
1325For 32 mm Pipeline
1326For 63 mm Pipeline
1327Notes: i) The above length is not for a single section but for no. of sections. ii) All accessrious ie; End caps and two nos tappings of 3/4 inches, PG to be considered per section and rate for the same shall be quoted by bidder under this item.iii) If month is partially complete, payment shall be made on prorata basis.iv) Scope includes pressure holding for a period of 6 months or as per EIC and jointing of PE pipe (if required) due to damage by any means and further filling of nitrogen for pressure holding.v) Length given are tantative may change as per site requirments.
1328CIVIL WORKS
1329Earth Work
1330Earth in excavation and filling to the grades and levels shown in the approved drawings in all kinds of conditions including for Road embakments, using approved quality good earth from designated borrow area, for all heights and depths including clearing and stripping (min. 150 mm) of the area marked for filling, taking spot levels, consolidating the exposed natural soil surface, excavating the earth from borrow area loading, transporting & unloading, spreading in layers not exceeding 150 mm thickness, breaking clods, watering (if reqd.), ramming and compacting by manual/ mechanical means to give minimum 92% of modified Proctor's density of earth, testing & dressing including disposal of all unserviceable material all complete as per specifications and directions of Engineer-in-charge.
1331(Rate to include cost of all labour, tools, tackles, equipment, hire chanrges, cost of borrow earth by way of royalties, right of way, cess etc., as applicable with all bye works and sundry works).
1332PCC 1:2:4
13331 Cement : 2 Coarse sand : 4 stone aggregate 20mm nominal size.
1334PCC 1:4:8
13351 Cement : 4 Coarse sand : 8 stone aggregate 40mm nominal size.
1336(Rate to include cost of all labour, tools, tackles, equipment, hire charges, supply of all materials, shuttering, earthwork in excavation and backfilling using approved earth in all conditions etc. with all bye works and sundry works.)
1337Reinforced Cement Concrete
1338Providing and laying reinforced cement of grade M-25 with 20mm and down grade crushed stone aggregate in all types of structures like foundations, pedestals, pedestal bases, pipe supports, sleepers, column, equipment foundation, Non suspended slabs/pavement slabs, ramps, cable trench inlcuding construction joints, bitumen painting on surface in contact with soil, supplying and fixing reinforcing steel, shuttering, inserts, finishes, grounting etc. at all depths and heights complete as per drawings, specifications and direction of the Engineer-in-charge.
1339Rate to include cost of all labour, tools, tackles, equipment, hire charges, supply of all maerials such as minimum 43 grade cement including sulphate resistant cement for sub-structures, R/F steel, Inserts, bolts, conduits, bitumen, other minor constrcution materials, shuttering, stanging, earthwork in excavation and backfilling using serviceable earth in all conditions, shorting bailing and pumping out water, testing of concrete, curing etc. with all bye works and sundry works.
1340Concrete Pavement
1341Providing and laying reinforced cement concrete of (M-25 grade) with 20mm and down grade crushed stone aggregate in pavement, including preparation of base (i.e. compacted subgrade, 200 thk sand and 50 thk PCC M-10 grade), leaving pockets if necessary, making recess, projections, fixing inserts conduit pipes (GI, PVC, HDPE, etc.) laying in alternate panels, filling the gaps between the panels with bitumen etc., making slopes, finishing edges, leaving bars for pedestals & sleepers including providing sand fill isolation , shuttering, providing and fixing reinforcing steel, curing, chipping and modification works etc. as specified in any shape, thickness, position and finishing the top surface smooth as per requirement etc. all complete as per drawings, specifications and directions of the Engineer-in-charge.
1342Concrete Pavement- 150mm thick (Type-I)
1343Brick Work
1344Providing brick work with brick class designation M-7.5 of IS:1077 in cm1:4 (1 cement : 4 sand) in steps, walls, retaining walls and load bearing structures drains, or any shape with all lead, depths & height including curring, scaffolding, etc., as per specifications and drawings with all bye-works and direction of the Enfineer-in-charge.
1345(Rate to include cost of all labour, tools, tackles, equipment, hire charges, supply of all materials such as minimum 43 grade cement, bricks, finishes, bitumen, other minor constrcution materials, shuttering, staging, masonry work, plastering, painting etc. with all bye-works and sundry works).
1346Note: The quantites of individual item can varied as per site requirement.The payment will be made as per actual certified measurement at site.
1347Laying of Brick layer/ Concrete
1348Providing single layer of Brick / Concrete / or impact resistant tape to entire width of trench above Warning Mat placed in trench over the laid pipeline as per OISD 226, standard drawing, specification and instruction of Owner. (Rate to include cost of all labour, tools, tackles, equipment, hire charges & supply of all materials, etc)
1349Brick Layer for width of PE pipeline trench as per drawing (75 mm thk.)
1350Concrete for width of PE pipeline trench as per drawing (80 mm thk.)
1351Demolition of PCC work below plinth level
1352Demolishing plain cement concrete (PCC) work (taking all necessary safety precautions) for all depths below plinth level including supply of all tools & tackles, necessary scaffolding, propping, underpinning, etc. , disposal of unserviceable material outside the boundary limits keeping the owner indemnified of any liabilities from statutory/ local bodies, all complete work as specified and directed.
1353Excavation for foundation works
1354Excavation as per plan, upto 3 meters and upto any lead in all conditions, backfilling using serviceable earth and disposal of surplus and unserviceable earth. Soil to be levelled and neatly dressed complete in all respect as per scope of work, technical specification and directions of EIC.
1355Upto 3.0 Mtrs
1356Dismantling of RCC & cutting of reinforcement (Thickness above 3”)
1357Structural Works
1358Supplying, fabricating & fixing steel structural cage fabricated from Angle conforming to IS:808 & fixing of GI weldmesh made from 3mm GI wire @ 75 mm bothways to structural steel frame by means of welding/bolting, including applying two coats of approved quality of synthetic enamel paint over a priming coat of in approved shade including supply of all raw materials, bolts, electrodes, transportation, including Hilti arrangement ,locking arrangement for fixing of posts etc complete as per enclosed drawing, technical specifications, scope of works and directions of the Engineer-In-Charge. Note:- Material shall be supplied and fabricated as per site condition and Contractor have to take quantity approval from EIC/OWNER prior to commencement of work and order placement.
1359MRS / Metering Skid/Wall Mounted MRS.
1360Installation of MRS / Metering Skid on foundation
1361Receiving and taking over, handling, loading, transportation and unloading of MRS / Metering Skid from Owner's designated stockyards to site, installation at foundation and hooking up with PE pipe including all works as required to complete the job as per the drawings and specification, scope of work mentioned in tender doucment. The scope includes supply of transition fittings,GI Sleeve, other MDPE and CS fittings as required and various associated works to commission MRS / Metering Skid. (Note:- The installation included CS piping work included welding, testing, NDT etc.,however payment for the CS piping work along with accessories supply will be paid in SOR item 7.0 to 25.0 respectively.)
1362Note: 1) Amount towards civil work shall be payable as per related SOR items. 2) Rate to include cost of all labour, tools, tackles, equipment, hire charges.3) All fittings and consumables including Bolts, nuts, washer, U-clamps, gaskets etc. if required during installation shall be procured and supplied by the Contractor within the rate quoted. These items shall not be separately measured and paid.
1363MRS / Metering Skid <2000 SCMD
1364MRS / Metering Skid 2000-5000 SCMD
1365MRS / Metering Skid 5000-20000 SCMD
1366MRS / Metering Skid >20000 SCMD
1367Installation of Wall Mounted Metering System (Meter, Regulator & Accessory) locked in cage
1368Receiving and taking over, handling, loading, transportation and unloading of all items for Wall Mounted Metering System (Meter, Regulator & Accessory) from Owner's designated stockyards to site, installation on wall and hooking up with PE pipe including all works as required to complete the job as per the drawings and specification, scope of work mentioned in tender doucment.The scope includes supply of items required as per the drawing in scope of work (Details of drawings as PJS) viz. transition fittings, GI/Concrete Sleeves and other MDPE and CS fittings etc. as required and various associated works.(Only Meters and Regulators shall be provided as free issue) and all associated works (For CS pipe and other items refer sl. no. 7.0 to 25.0) to commission Wall Mounted Metering System. Note : Installation works included CS piping work, Testing etc.,however payment for the CS piping work along accessories will be paid in diiferent SOR item
1369Note: 1) Amount towards civil work shall be payable as per relevant SOR items. 2) Rate to include cost of all labour, tools, tackles, equipment, hire charges .3) All fittings (those are not mentioned in SOR item 7.0 to 25.0) and consumables including Bolts, nuts, washer, U-clamps, gaskets etc. if required during installation shall be procured and supplied by the Contractor within the rate quoted. These items shall not be separately measured and paid.4)The wall mounted Metering System to be kept in cage with locking facility, However payment for Structural work will be paid against SOR item 4.0
1370The Typical Design of MRS/Metering System are as per \\"Standardized metering system Design, Selection & Installation philosophy for supply of PNG to Industrial and Commercial Customers of GAIL Gas.\\"Note: -The sizes mentioned in drawings are indicative & may vary as per actual requirment at site .
1371Wall Mounted Metering System < 200 SCMD
1372Wall Mounted Metering System 200-500 SCMD
1373Wall mounted Metering System 500 to 2000 SCMD
1374Wall mounted Metering System >2000 SCMD
1375Note: i) The quantities mentioned are indicative only. ii) For all the supply items mentioned above, procurement shall be made as per specification after due approval of engineer- in - charge.
1376Installation of Wall Mounted Metering System (Pre-assemble)
1377Receiving and taking over, handling, loading, transportation and unloading of all items for Wall Mounted Metering System (Pre-assembled as per standard drawing Attached in PJS Drawing ) from Owner's designated stockyards to site, installation on wall and hooking up with PE pipe including all works as required to complete the job as per the drawings and specification, scope of work mentioned in tender doucment.The scope includes supply of transition fittings, Sleeves and other MDPE and CS fittings etc. as required and various associated works, however, the Metering System assembly ( As per drawing ) shall be provided as free issue by GAIL Gas. Installtion work done by Contractor along supply of consumables including Bolts, nuts, washer, U-clamps, gaskets etc. if required during installation shall be procured and supplied by the Contractor within the rate quoted.
1378Note: 1) Amount towards civil work shall be payable as per related SOR items 3.0. 2) Rate to include cost of all labour, tools, tackles, equipment, hire charges .3) The wall mounted Metering System to be kept in cage with locking facility, However payment for Structural work will be paid against SOR item 4.0
1379Installation of GI Pipe 2\\" - 1\\" size with isolation valve for commercial meter inlet connection from TF
1380Removal of MRS/ Metering Skids, Wall Mounted MRS/Metering System (all capacities) from existing consumer's premise,
1381Removal of MRS/ Metering Skids, Wall Mounted Metering System (all capacities) from existing consumer's premise for shifting to another site/store. The scope of work also includes excavation to retrive PE pipe line , disconnection of existing pipe lines (PE & Steel).
1382Note:- Transportaion of removed metering skid/Wall mounted Metering System to store shall be payble under SOR item no.5.4.2. However, if this skid is being shifted directly to new location for installation at new customer premises then transportation to be claimed from 5.1 & 5.2 as applicable.
1383Transportaion of removed metering skid/Wall mounted Metering System to store
1384Conversion of Commercial Appliances/Industrial :
1385Conversions of all types of commercial appliances to NG based appliances. Supply & changing of the nozzles /jets and associated controls for Non-domestic appliances (imported appliances included) with proper tools and tackles. Cleaning and performing minor maintenance, greasing etc. of the appliance. Testing and showing the performance to the customer, signing of joint meter records (JMR) and instructing the customer on use & safety norms, complete as per specifications & to satisfaction of owner / Engineer in Charge and includes supply of reinforced rubber hose with requisite pressure rating.Supply of Appliance valve is also included.
1386Installation of ASTM A106, Gr. B, Seamless, BE , NB, XS pipes of various dia
1387ASTM A106, Gr. B, Seamless, PE , 1/2\\" NB, S160 , their fittings and installation of meter and regulator (as applicable)
1388ASTM A106, Gr. B, Seamless, PE , 1\\" NB, XS , their fittings and installation of meter and regulator (as applicable)
1389ASTM A106, Gr. B, Seamless, PE, 1.5\\" NB, XS , their fittings and installation of meter and regulator (as applicable)
1390ASTM A106, Gr. B (Charpy), Seamless, BE , 2\\" NB, XS , their fittings and installation of meter and regulator (as applicable)
1391ASTM A106, Gr. B (Charpy), Seamless, BE , 3\\" NB,XS , their fittings and installation of meter and regulator (as applicable)
1392ASTM A106, Gr. B (Charpy), Seamless, BE , 4\\" NB,XS , their fittings and installation of meter and regulator (as applicable)
1393Note:a). Supply & Installation of required size of brass fittings (which are not included in SOR item 8.0 to 23.0) in all type of meters (supplied by GAIL GAS LTD. ) shall be in scope of contractor.b). All butt welded fittings end shall generally match with connecting pipe wall thickness. However, in case of misalignment, Contractor shall have to do end preparation without any extra cost. c). Payment of radiography of joints (4\\" and below ) shall be paid seperately under SOR item for RADIOGRAPHY mentioned elsewhere in this SOR 25.0d). All type of piping works shall be carried out as per piping material specification (PMS).e). Complete Carbon Steel Piping Work with painting including all fittings, flanges and supply of all required gaskets, studs bolts & nuts etc.
1394Supply of CARBON STEEL PIPES as per Technical Specification and as directed by EIC
1395ASTM A106, Gr. B, Seamless, PE , 1/2\\" NB, S160
1396ASTM A106, Gr. B, Seamless, PE , 1\\" NB, XS
1397ASTM A106, Gr. B, Seamless, PE, 1.5\\" NB, XS
1398ASTM A106, Gr. B (Charpy), Seamless, BE , 2\\" NB, XS
1399ASTM A106, Gr. B (Charpy), Seamless, BE , 3\\" NB,XS
1400ASTM A106, Gr. B (Charpy), Seamless, BE , 4\\" NB,XS
1401Supply of Pressure Gauges as per Technical Specification and as directed by EIC
1402RANGE 0-100 MBAR - 4\\"- DIAL SIZE
1403RANGE 0-1 BAR - 4\\"- DIAL SIZE
1404RANGE 0-4 BAR - 4\\"- DIAL SIZE
1405RANGE 0-6 BAR - 4\\"- DIAL SIZE
1406RANGE 0-30 BAR - 4\\"- DIAL SIZE
1407Supply of Conical Stainer
1408As per Technical Specification and as directed by EIC.Note: - Conical Stainer may be free issue by Gail Gas Ltd., It is Discretion of Gail Gas Ltd. to excute the SOR or Free Issue the material.
1409Supply of Check valve/NRVAs per Technical Specification and as directed by EIC.
14102\\", 150# FE,FB
14113\\", 150# FE,FB
14124\\", 150# FE,FB
1413Supply of Flanges Weld Neck(End Thickness to match pipe thickness)
14141\\" , 150#, B-16.5 , A105 ,125 AARH,SW,RF
14151.5\\" , 150#, B-16.5 , A105 ,125 AARH,SW,RF
14162\\",150#, B-16.5, A105 (Charpy), 125 AARH, RF
14173\\",150#, B-16.5, A105 (Charpy), 125 AARH, RF
14184\\",150#, B-16.5, A105 (Charpy), 125 AARH, RF
1419Supply of Blind FlangesAs per Technical Specification and as directed by EIC.
14202\\",150#, B-16.5, A105 (Charpy), 125 AARH, RF
14213\\",150#, B-16.5, A105 (Charpy), 125 AARH, RF
14224\\",150#, B-16.5, A105 (Charpy), 125 AARH, RF
1423Supply of End Caps
14242\\", XS, A 234 Gr. WPB (Charpy), BW
14253\\", XS, A 234 Gr. WPB (Charpy), BW
14264\\", XS, A 234 Gr. WPB (Charpy), BW
1427Supply of FLANGE END GLOBE VALVES, MAOP- 4 BARAs per Technical Specification and as directed by EIC.
1428Supply of Ball ValvesAs per Technical Specification and as directed by EIC.
14291/2\\",800#, Sockolet Welded/Threaded Valve
14301\\",800#, Sockolet Welded/Threaded Valve
14312\\",150#,FE, FB,
14323\\",150#,FE, FB,
14334\\",150#,FE, FB,
1434Supply of Isolation Ball Valve And Appliance Valve as per Technical Specification and as directed by EIC
1435Isolation Ball Valve ½\\" max. 6 bar (g)
1436Isolation Ball Valve 1\\" max. 6 bar (g)
1437Isolation Ball Valve 1.5\\" max. 6 bar (g)
1438Isolation Ball Valve 2\\" max. 6 bar (g)
1439Isolation Ball Valve 3\\" max. 6 bar (g)
1440Supply of SOCKOLET (A105, SW) As per Technical Specification and as directed by EIC.
14412\\" x ½\\"
14422\\" x 1\\"
14433\\" x ½\\"
14443\\" x 1\\"
14454\\" x ½\\"
14464\\" x 1\\"
1447Supply of Reducer (A 234 Gr. WPB (Charpy), BW)
14481.5\\" x 1\\", XS x XS, A105, SW,3000#, B-16.11
14492\\"x1\\", XS x XS, A 234 Gr. WPB (Charpy), BW, B-16.9
14502\\" X 1.5\\", XS , A 234 Gr. WPB (Charpy), BW, B-16.9
14513\\"x1\\", XS x XS, A 234 Gr. WPB (Charpy), BW, B-16.9
14523\\" X 1.5\\", XS , A 234 Gr. WPB (Charpy), BW, B-16.9
14533\\" x 2\\" , STD x XS, A 234 Gr. WPB (Charpy), BW, B-16.9
14544\\" x 3\\" , STD x XS, A 234 Gr. WPB (Charpy), BW, B-16.9
1455Supply of Tee, Equal / Reducing Tee
14561\\", XS, SW, 3000#, B-16.11
14571.5\\", XS, A105, SW, 3000#, B-16.11
14582\\" x 1.5\\", XS , A234, Gr. WPB (Charpy), B-16.9, BW
14592\\", XS , A234, Gr. WPB (Charpy), B-16.9, BW
14603\\", STD , A234, Gr. WPB (Charpy), B-16.9, BW
14614\\" STD x XS, A234, Gr. WPB (Charpy), B-16.9, BW
1462Supply of ELBOW, 90° Elbow
1463½\\", XS, SW, 3000#, ASTM A105,B-16.11
14641\\", XS, SW, 3000#, ASTM A105,B-16.11
14651.5\\", XS, SW, 3000#, ASTM A105,B-16.11
14662\\", XS, BW, A234, Gr. WPB (Charpy), B-16.9, 1.5D
14673\\", STD, BW, A234, Gr. WPB (Charpy), B-16.9, 1.5D
14684\\", XS, BW, A234, Gr. WPB (Charpy), B-16.9, 1.5D
1469Supply of Spectacle Blind AS PER SPECIFICATION
1470Spectacle Blind 2\\"
1471Spectacle Blind 3\\"
1472Spectacle Blind 4\\"
1473Supply of Internal/external piping support (AS PER Tender)
1474TYPE-1, SIDE WALL MOUNTED AS PER DRAWING
1475TYPE-2, GROUND BASED AS PER DRAWING
1476TYPE-3, CEILING MOUNTED AS PER DRAWING
1477WELDING OF JOINTS - Butt Weld Joints
14781/2\\" (WELDING OF JOINTS)
14791\\" (WELDING OF JOINTS)
14801.5\\" (WELDING OF JOINTS)
14812\\" (WELDING OF JOINTS)
14823\\" (WELDING OF JOINTS)
14834\\" (WELDING OF JOINTS)
1484Note: i) All butt welded fittings end shall generally match with connecting pipe wall thickness however in case of misalignment Contractor shall have to do end preparation without any extra cost.ii) All coupling, nipples etc. as required shall be supplied by contractor but no separate payments shall be made as it is covered under erection rate.
1485RADIOGRAPHY OF JOINTS
1486Performance of radiographic inspection by gamma radiation as per scope of work and as per specifications in piping of all types and thickness including providing/hiring of all necessary equipments, supply of all consumables, and whatever else even though not expressely mentioned but required to perform the work as per specifications and instructions of Engineer-in-Charge (full circle re-radiography of the repaired joint and additional radiography necessitated due to poor performance of contractor's welder shall be carried out by the Contractor at his own cost and shall not be paid extra by Company). Radiographs shall be submitted to the Engineer-in-Charge for acceptance, whose decision shall be final and binding.
1487Note- i). 4\\" & Below and all butt weld joint are radiography / X-ray shall be done at every joint and shall be carried out as per API 1104 (latest edition) / M/s GAIL Gas Ltd. specification / OISD / PNGRB and same shall be approved by Engineer–in–charge (EIC)/RCM.ii). All socket weld joint MPT/UT/DPT shall be done at every joint nd shall be carried out as per API 1104 (latest edition)/M/s GAIL Gas Ltd. specification / OISD / PNGRB and same shall be approved by Engineer–in–charge (EIC)/ RCM.
14881/2\\" (RADIOGRAPHY of Joints as Above)
14891\\" (RADIOGRAPHY of Joints as Above)
14901.5\\" (RADIOGRAPHY of Joints as Above)
14912\\" (RADIOGRAPHY of Joints as Above)
14923\\" (RADIOGRAPHY of Joints as Above)
14934\\" (RADIOGRAPHY of Joints as Above)
1494Note: i) Quantities mentioned against each above item of SOR Items are tentative and may increase or decrease during execution of work depending upon site requirement. Contractor required to supply materials after assessing the site requirement and in multiple lot or as per Release Order/ Sub Purchase Order wise. All material either in multiple lot or as per Release Order/ Sub Purchase Order wise or as decided by EIC shall be supplied by bidder within the quoted price.(ii) The quantites of individual item can varied as per site requirement.The payment will be made as per actual certified measurement at site. For the supply items the quantities shall be procured after approval from client/ consultant/EIC.(iii) The bidder must indicate currency(ies) against each quoted item of the SOR.(iv) The total amount shall also be given by the bidder in the quoted currency(ies).(v) Some of the may / may not be execute as per site requirements.
1495Ground Connectivity Works
1496Laying of MDPE pipeline by any method in any type of soil strata upto 20m length from charged Pipeline to Customer premise including connection of Transistion Fitting at customer end. For pipeline laid more than 20m, payment for additonal length shall be covered in SOR no.2 in ruuning meters more than 20m.
1497PE 20mm dia
1498PE 32mm dia
1499PE 63mm dia
1500PE 90mm dia.
1501Survey, Pit Excavtion in all types of soills/PCC/RCC/Paver block/Ashpalt/Whitetopping etc., charged pipeline identification, Hook up activities, Online tapping either by Saddle / Tee / extension by Coupler for connecting the Pipeline laid as per above SOR 1.1 including fittings, Backfilling. Restoration shall be paid through other SOR
1502Connectiviy for PE 20mm dia laid under 1a.
1503Connectiviy for PE 32mm dia laid under 1a.
1504Connectiviy for PE 63mm dia laid under 1a.
1505Connectiviy for PE 90mm dia laid under 1a.
1506PE PIPELINE
1507PE Pipe Laying in any type of surface like unprepared surface (Katcha surface)/ Normal Surface/ Hard surface/Rock surface etc using open cut/ Moling (without Casing)/ Moling (with Casing)/ Horizontal Directional Drilling technique (with and without casing pipe) methodology. HDD at Hard Rock shall be paid through different SOR.
1508Receipt. Loading. unloading. storing. reloading. tranportation. unloading. stringing and laying of PE100. SDR11 line pipes of all sizes including. proper stacking. identification.and supply of accessories of all sizes & thickness like PE Bends. Couplers. Endcaps. Tee. Reducer. CS / GI to PE Fittings (i.e. Transition Fittings of sizes 20 mm to 90 mm). Warning Mat etc. Handling. Stringing / uncoiling. aligning of the PE line pipe on the pipeline Right-of-Use / route. laying / installation of PE line pipe alongwith required accessories as mentioned above as per specification wherever required depending on site condition including execution of all works; Storeage of material in contractor's store. fabrication. access for construction procurement and supply of all materials. consumables. equipments. labour and other inputs.
1509In the case of free issue items. the scope also includes. receiving and loading from Owner's designated store. transportation. unloading and stacking of free issue items at Contractor's store. -Laying of all PE pipe (PE 100 SDR11). Including supply of HDPE casing pipe (in case of HDD (with case).Moling(with case) . Couplers. End caps etc. (Ref. of Particular job specification).Survey of under ground utilities. execution of the work as per specification. including excavation of pits moling with the hole size not exceeding 20% of the pipe dia. jointing and insertion of carrier pipe with casing. testing & commissioning and restoration of the pits to original condition. submission of As-Built Graph as per specifications and the instruction of Engineer-in-charge.
1510Casing details is as given below:-1. For 20/32 mm PE pipe (in 75 mm dia. HDPE Casing Pipe. PE 63/80 PN6.0).2. For 63 mm PE pipe (in 125 mm dia. HDPE Casing Pipe. PE 63/80 PN6.0).
1511Carrying out all temporary. ancillary. auxiliary works required to make the PE pipeline ready for commissioning as per drawings. Specifications. scope of work indicated in PJS and other provisions of tender/ contract documents and instructions of Engineer-in-charge. including but not limited to carrying out the following works:Surveying of route and detours required at the time of execution. preparation of construction drawings showing survey details and submit same to Owner for review / approval.
1512Carrying out preliminary activities such as preperation of drawings wherever required for crossing etc.Preparation and getting approval of schedules. execution procedures. drawings/ sketches/ wherever required. making trial pits to determine the underground utilities/ services etc.. restoration of the abandoned trial pits to original condition.
1513Stacking and installation of construction markers. clearing. fencing. grubbing. cutting of trees. full filling all the requirements of various statutory/ environment authorities to the entire satisfaction of concerned authorities. grading of work area.
1514Barricading the work area as per local authorities norms & to the satisfaction of Owner/ Eingineer -in- charge. installation of safety signs.Barricading the pipeline construction area prior to execution of the works as per drawing enclosed with tender/ contract documents and to the entire satisfaction of owner / engineer- in -charge.
1515Laying using open trench without casing includes survey of under ground utilities (through trial pits). execution of work as per specification including Trenching to all depths by excavation in all types of soils including soft/ rocky strata and different type of pavement / footpath / roads etc. including rock breaking. chiselling or otherwise cutting etc. as required and storing excavated soil. reusable materials at designated area as directed by Engineer in charge and to a width to accommodate the pipeline as per the relevant standard/ specification etc.
1516The minimum depth of the top of pipeline shall be 1.0 m measured from top of pipeline to the top of undisturbed surface of the soil or as per Specification/ OISD- 226 & PNGRB latest guidelines whichever is higher.Dewatering of trenches / pits if required as per site condition. Repairing of all damaged utilities if any. and payment of any compensation (if claimed by owner / other utility agencies)Uncoiling / stringing & aligning of PE pipes. clamping. jointing of the pipe ends / fittings / valves by qualified personnel using approved electro-fusion techniques as per specification.Note:- Coordinates to be taken for implementation for GIS for Valve pit, Fusion welding location and MRS.
1517Installation / lowering the pipeline in trench to required depth as per PJS. Technical Specification & drawings. supply & placement of HDPE Yellow colour warning mat (refer PJS) over the pipeline along the complete route as per standard drawings. data sheets & technical specifications. padding around pipeline including supply of suitable padding material duly approved by EIC. Backfilling to its original condition with excavated earth / borrowed select soil/sand duly approved by EIC & its compaction & crowning. At certain specific area of ROU. trench shall be backfilled & compacted and shall be made ready for motorable and no seperate payment shall be admissible against this activity.All tiles / slabs / curb stones etc removed during excavation shall be placed properly.Restoration shall be carried as per separate SOR item mentioned elsewhere in the SOR or to be done by Owner / concerned authorities.
1518The scope of work against this item also include Electro-fusion jointing of valves. fittings wherever required and as directed by Engineer-in-charge.The scope of work against laying of 20 mm pipe also includes works like making of PCC pedastal of grade (1:2:4) and size ( (300mm(L)X200mm(W) XHeight (H)). (H>=300mm & will be as per site condition) ). supply and installation of GI Sleeve (Heavy (C-Class) as per IS-1239). filling of sand and installation of TF (along with supply).
1519Pneumatic testing. purging with nitrogen and commissioning as per specification and approved procedures providing all tools and tackles. nitrogen. instruments. manpower and other related accessories and as per the instructions of the Engineer-in-charge.
1520Final clean-up of right-of-use or area disturbed by contractor during their construction activities for laying of pipeline works and disposal of debris and surplus material to designated disposal areas and backfilling of trench and compaction of the same as per satisfaction of Owner and / or as directed by Engineer–in–charge.
1521Maintaining the completed pipelines and installation for any defect or failures during defect liability period (i.e. 12 months from date of completion of work).Handing over the completed works to Owner for their operation/ use. reconciliation of material area wise and obtaining \\"no objection certificate\\" from Owner/ PMC.Preparation and submission of Daily progress report. Laying Graphs / PE line cards on daily basis.
1522On completion of gas charging of pipelines. Preparation and submission of As-built drawings. crossings details. termination. utility graphs and deviation statements.In case. the minimum required depth is not possible due to site condition. necessary mitigation measures with minimum permissible top cover shall be carried out by the contractor in consultation with EIC as per PNGRB Guidelines. without any time and cost implecation to owner.
1523Submission of all documents required for contract closure in numbers as mentioned in contract.Any other activities not mentioned / covered explicitly above. but otherwise required for satisfactory completion / operation / safety / statutory / maintenance of the works shall also be covered under the scope of work and has to be completed by the Contractor within specified schedule at no extra cost to Owner. All the work shall be executed in accordance with the provision of contract.
152420 mm PE 100 pipe
152532 mm PE 100 pipe
152663 mm PE 100 pipe
152790 mm PE 100 pipe
1528NOTE i) The lengths of pipelines are tentative. ii) For restoration of asphalt / concrete roads. the item for construction of asphalt top / concrete top / Tiles/Stone slab/Paver Blocks/Curb Stones shall be paid separately as per the rates quoted for the same elsewhere in the SOR 2.4.
1529GPR Survey for identification of pipeline
1530Laying of Pipeline by HDD in Rock Terrain
153132 mm PE 100 pipe
153263 mm PE 100 pipe
153390 mm PE 100 pipe
1534Restoration
1535Restoration of the roads. pavements. channels. footpaths. tiles. stones etc. to original condition including supply of the approved quality material required. as per local authorities norms. obtaining NOC from concerned local authorities / land owners / third party inspection agencies (if any) designated by owner and to the satisfaction of Engineer-in-charge.
1536Asphalting
1537Cement Concrete
1538Tiles/Stone slab/Paver Blocks/Curb Stones
1539Brick Soling / Channels. etc.
1540Installation of valve in pit including supply of valves
1541Supply of isolation valves (as per data sheet) and installtion of valves in the valve pits as per typical drawing and specification enclosed and instructions of Engineer-in-charge. Payment of valve pits shall be paid separately as per SOR 2.6.
1542PE Valve 20 mm dia
1543PE Valve 32 mm dia
1544PE Valve 63 mm dia
1545PE Valve 90 mm dia
1546Construction of Valve Pits as per the enclosed tender drawing and specification. The item includes supply of all the material including Pre-cast RCC cover. shuttering. reinforcement. labour. curing etc as per the drawings. specification and instruction of EIC.
1547Type-I having Internal size of Minimum 1000 x 1000mm
1548Type-II having Internal size of Minimum 600 x 600mm
1549Note: The tender drawing enclosed is only for reference purpose and contractor shall be required to prepare drawings (in line with reference tender drawing) for specific sizes of Valve pits and the same shall be approved by EIC.
1550Fabrication & Installation of Markers
1551RCC Route Markers
1552Supply, fabrication and installation of RCC route markers as per the attached drawing in technical volume, along the route including all associated civil works such as excavation and construction in all types of soils, construction and pedestals and grouting with concrete.
1553Pole Markers with Foundation
1554Supply, fabrication and installation of plate markers as per the attached drawings in technical volume including all associated civil works such as excavation and construction in all types of soils, construction and pedestals and grouting with concrete, cleaning, stencil let.
1555Warning Plate Markers
1556Supply, fabrication and installation of plate markers, including application of approved color and quality of primer and paint, stencil letter cutting of lettering, numbers, direction, etc. as per the attached drawing in technical volume to be installed near regulator.
1557Excavation of Hard rock/surface
1558Excavation of trench or pits, wherever hard rock presence is exceeding 1.5 m in any direction of the trench and excavation of trench or pits in Malba/Multiple layers of asphalt/ brick / PCC/RCC etc and removable only by pneumatic chisel / drill as per the specifications and direction of EIC. The rates are payable over and above the Laying rates as per relevant SOR no. 2.1
1559Cutting of PCC/RCC surface with thickness more than 12\\" or Continuous asphalt multi-layer/ Malba/ Brick / Boulders more than 24\\".(Malba shall be considered as a strata where soil is in mixed form of debris/building rubbish or discarded pieces of bricks/stones )
1560Rock Cutting encountered while excavation of trenches for item 2.1 of SOR, not exceeding 1.5 meter in width, and lift upto 1.5 meter, including getting out the excavated soil and disposal of excavated soil as directed within a lead of 50 meter. In case of rocky soil, the bedding shall be done with approved/ good quality packing sand, subject to the approval of the EIC, the size distribution of the sand / shall be the same as per soil. The packing sand shall be placed to a minimum thickness of 150mm around the pipe in case of rocky terrain.
1561Note: i) The quantities mentioned are indicative only. ii) For all the supply items mentioned above, procurement shall be made as per specification after due approval of engineer- in - charge.
1562Liaisoning with Land Owning Agencies for Permission
1563Submission of applications as per approved drawings (Initial Route survey, prepartion of drawing, measuring and providing details of surface type shall be in scope of contractor), obtaining and submission of demand note, coordination, Liaisoning, obtaining written permission from land owing agencies like NHAI, AAI,Indian Railways and any other government agencies resposible for maintaining public lands and agencies owing Private lands etc. (all fee paid to authorities excluding demand charges or Bank Guarantees shall be reimbursed against documentary evidence). Permissions required from various authorities like NHAI / Railways / Irrigation (Canal) etc. falling enroute shall be inclusive in the item rate. No separate liasion charges against construction of valve chambers is payable and is included in laying rates.
1564Construction of RCC structure for protection of service line for drain/nallah Crossings
1565Construction of Non suspended slabs/pavement slabs including pedestal/ramp etc.using reinforced cement concrete of M-25 grade (Concrete shall be design mix/nominal mix with 20 mm & down size graded crushed stone aggregates) to protect the PE pipe laid. All necessary form work, finishing the top surface rough/smooth as required in any position, shape, level and thickness etc. shall be as specified and directed by EIC. The rates shall include grouting of pockets, supply of all material, tools, reinforcement steel etc.
1566Preservation of Pipeline
1567Preservation of pipeline sections and associated facilities (in event of delay in comissioning, other unforeseen reasons) including supply of nitrogen, all consumables, all equipment, man-power, etc. complete as per the requirements of specifications, other provisions of tender/ contract documents and instructions of Engineer-in-charge.
1568By filling and pressurizing with nitrogen to a pressure of 2 bar(g) for a period of one month or part thereof.
1569For 20 mm Pipeline
1570For 32 mm Pipeline
1571For 63 mm Pipeline
1572For every additional period of one month or part thereof Limited to 6 month
1573For 20 mm Pipeline
1574For 32 mm Pipeline
1575For 63 mm Pipeline
1576Notes: i) The above length is not for a single section but for no. of sections. ii) All accessrious ie; End caps and two nos tappings of 3/4 inches, PG to be considered per section and rate for the same shall be quoted by bidder under this item.iii) If month is partially complete, payment shall be made on prorata basis.iv) Scope includes pressure holding for a period of 6 months or as per EIC and jointing of PE pipe (if required) due to damage by any means and further filling of nitrogen for pressure holding.v) Length given are tantative may change as per site requirments.
1577CIVIL WORKS
1578Earth Work
1579Earth in excavation and filling to the grades and levels shown in the approved drawings in all kinds of conditions including for Road embakments, using approved quality good earth from designated borrow area, for all heights and depths including clearing and stripping (min. 150 mm) of the area marked for filling, taking spot levels, consolidating the exposed natural soil surface, excavating the earth from borrow area loading, transporting & unloading, spreading in layers not exceeding 150 mm thickness, breaking clods, watering (if reqd.), ramming and compacting by manual/ mechanical means to give minimum 92% of modified Proctor's density of earth, testing & dressing including disposal of all unserviceable material all complete as per specifications and directions of Engineer-in-charge.
1580(Rate to include cost of all labour, tools, tackles, equipment, hire chanrges, cost of borrow earth by way of royalties, right of way, cess etc., as applicable with all bye works and sundry works).
1581PCC 1:2:4
15821 Cement : 2 Coarse sand : 4 stone aggregate 20mm nominal size.
1583PCC 1:4:8
15841 Cement : 4 Coarse sand : 8 stone aggregate 40mm nominal size.
1585(Rate to include cost of all labour, tools, tackles, equipment, hire charges, supply of all materials, shuttering, earthwork in excavation and backfilling using approved earth in all conditions etc. with all bye works and sundry works.)
1586Reinforced Cement Concrete
1587Providing and laying reinforced cement of grade M-25 with 20mm and down grade crushed stone aggregate in all types of structures like foundations, pedestals, pedestal bases, pipe supports, sleepers, column, equipment foundation, Non suspended slabs/pavement slabs, ramps, cable trench inlcuding construction joints, bitumen painting on surface in contact with soil, supplying and fixing reinforcing steel, shuttering, inserts, finishes, grounting etc. at all depths and heights complete as per drawings, specifications and direction of the Engineer-in-charge.
1588Rate to include cost of all labour, tools, tackles, equipment, hire charges, supply of all maerials such as minimum 43 grade cement including sulphate resistant cement for sub-structures, R/F steel, Inserts, bolts, conduits, bitumen, other minor constrcution materials, shuttering, stanging, earthwork in excavation and backfilling using serviceable earth in all conditions, shorting bailing and pumping out water, testing of concrete, curing etc. with all bye works and sundry works.
1589Concrete Pavement
1590Providing and laying reinforced cement concrete of (M-25 grade) with 20mm and down grade crushed stone aggregate in pavement, including preparation of base (i.e. compacted subgrade, 200 thk sand and 50 thk PCC M-10 grade), leaving pockets if necessary, making recess, projections, fixing inserts conduit pipes (GI, PVC, HDPE, etc.) laying in alternate panels, filling the gaps between the panels with bitumen etc., making slopes, finishing edges, leaving bars for pedestals & sleepers including providing sand fill isolation , shuttering, providing and fixing reinforcing steel, curing, chipping and modification works etc. as specified in any shape, thickness, position and finishing the top surface smooth as per requirement etc. all complete as per drawings, specifications and directions of the Engineer-in-charge.
1591Concrete Pavement- 150mm thick (Type-I)
1592Brick Work
1593Providing brick work with brick class designation M-7.5 of IS:1077 in cm1:4 (1 cement : 4 sand) in steps, walls, retaining walls and load bearing structures drains, or any shape with all lead, depths & height including curring, scaffolding, etc., as per specifications and drawings with all bye-works and direction of the Enfineer-in-charge.
1594(Rate to include cost of all labour, tools, tackles, equipment, hire charges, supply of all materials such as minimum 43 grade cement, bricks, finishes, bitumen, other minor constrcution materials, shuttering, staging, masonry work, plastering, painting etc. with all bye-works and sundry works).
1595Note: The quantites of individual item can varied as per site requirement.The payment will be made as per actual certified measurement at site.
1596Laying of Brick layer/ Concrete
1597Providing single layer of Brick / Concrete / or impact resistant tape to entire width of trench above Warning Mat placed in trench over the laid pipeline as per OISD 226, standard drawing, specification and instruction of Owner. (Rate to include cost of all labour, tools, tackles, equipment, hire charges & supply of all materials, etc)
1598Brick Layer for width of PE pipeline trench as per drawing (75 mm thk.)
1599Concrete for width of PE pipeline trench as per drawing (80 mm thk.)
1600Demolition of PCC work below plinth level
1601Demolishing plain cement concrete (PCC) work (taking all necessary safety precautions) for all depths below plinth level including supply of all tools & tackles, necessary scaffolding, propping, underpinning, etc. , disposal of unserviceable material outside the boundary limits keeping the owner indemnified of any liabilities from statutory/ local bodies, all complete work as specified and directed.
1602Excavation for foundation works
1603Excavation as per plan, upto 3 meters and upto any lead in all conditions, backfilling using serviceable earth and disposal of surplus and unserviceable earth. Soil to be levelled and neatly dressed complete in all respect as per scope of work, technical specification and directions of EIC.
1604Upto 3.0 Mtrs
1605Dismantling of RCC & cutting of reinforcement (Thickness above 3”)
1606Structural Works
1607Supplying, fabricating & fixing steel structural cage fabricated from Angle conforming to IS:808 & fixing of GI weldmesh made from 3mm GI wire @ 75 mm bothways to structural steel frame by means of welding/bolting, including applying two coats of approved quality of synthetic enamel paint over a priming coat of in approved shade including supply of all raw materials, bolts, electrodes, transportation, including Hilti arrangement ,locking arrangement for fixing of posts etc complete as per enclosed drawing, technical specifications, scope of works and directions of the Engineer-In-Charge. Note:- Material shall be supplied and fabricated as per site condition and Contractor have to take quantity approval from EIC/OWNER prior to commencement of work and order placement.
1608MRS / Metering Skid/Wall Mounted MRS.
1609Installation of MRS / Metering Skid on foundation
1610Receiving and taking over, handling, loading, transportation and unloading of MRS / Metering Skid from Owner's designated stockyards to site, installation at foundation and hooking up with PE pipe including all works as required to complete the job as per the drawings and specification, scope of work mentioned in tender doucment. The scope includes supply of transition fittings,GI Sleeve, other MDPE and CS fittings as required and various associated works to commission MRS / Metering Skid. (Note:- The installation included CS piping work included welding, testing, NDT etc.,however payment for the CS piping work along with accessories supply will be paid in SOR item 7.0 to 25.0 respectively.)
1611Note: 1) Amount towards civil work shall be payable as per related SOR items. 2) Rate to include cost of all labour, tools, tackles, equipment, hire charges.3) All fittings and consumables including Bolts, nuts, washer, U-clamps, gaskets etc. if required during installation shall be procured and supplied by the Contractor within the rate quoted. These items shall not be separately measured and paid.
1612MRS / Metering Skid <2000 SCMD
1613MRS / Metering Skid 2000-5000 SCMD
1614MRS / Metering Skid 5000-20000 SCMD
1615MRS / Metering Skid >20000 SCMD
1616Installation of Wall Mounted Metering System (Meter, Regulator & Accessory) locked in cage
1617Receiving and taking over, handling, loading, transportation and unloading of all items for Wall Mounted Metering System (Meter, Regulator & Accessory) from Owner's designated stockyards to site, installation on wall and hooking up with PE pipe including all works as required to complete the job as per the drawings and specification, scope of work mentioned in tender doucment.The scope includes supply of items required as per the drawing in scope of work (Details of drawings as PJS) viz. transition fittings, GI/Concrete Sleeves and other MDPE and CS fittings etc. as required and various associated works.(Only Meters and Regulators shall be provided as free issue) and all associated works (For CS pipe and other items refer sl. no. 7.0 to 25.0) to commission Wall Mounted Metering System. Note : Installation works included CS piping work, Testing etc.,however payment for the CS piping work along accessories will be paid in diiferent SOR item
1618Note: 1) Amount towards civil work shall be payable as per relevant SOR items. 2) Rate to include cost of all labour, tools, tackles, equipment, hire charges .3) All fittings (those are not mentioned in SOR item 7.0 to 25.0) and consumables including Bolts, nuts, washer, U-clamps, gaskets etc. if required during installation shall be procured and supplied by the Contractor within the rate quoted. These items shall not be separately measured and paid.4)The wall mounted Metering System to be kept in cage with locking facility, However payment for Structural work will be paid against SOR item 4.0
1619The Typical Design of MRS/Metering System are as per \\"Standardized metering system Design, Selection & Installation philosophy for supply of PNG to Industrial and Commercial Customers of GAIL Gas.\\"Note: -The sizes mentioned in drawings are indicative & may vary as per actual requirment at site .
1620Wall Mounted Metering System < 200 SCMD
1621Wall Mounted Metering System 200-500 SCMD
1622Wall mounted Metering System 500 to 2000 SCMD
1623Wall mounted Metering System >2000 SCMD
1624Note: i) The quantities mentioned are indicative only. ii) For all the supply items mentioned above, procurement shall be made as per specification after due approval of engineer- in - charge.
1625Installation of Wall Mounted Metering System (Pre-assemble)
1626Receiving and taking over, handling, loading, transportation and unloading of all items for Wall Mounted Metering System (Pre-assembled as per standard drawing Attached in PJS Drawing ) from Owner's designated stockyards to site, installation on wall and hooking up with PE pipe including all works as required to complete the job as per the drawings and specification, scope of work mentioned in tender doucment.The scope includes supply of transition fittings, Sleeves and other MDPE and CS fittings etc. as required and various associated works, however, the Metering System assembly ( As per drawing ) shall be provided as free issue by GAIL Gas. Installtion work done by Contractor along supply of consumables including Bolts, nuts, washer, U-clamps, gaskets etc. if required during installation shall be procured and supplied by the Contractor within the rate quoted.
1627Note: 1) Amount towards civil work shall be payable as per related SOR items 3.0. 2) Rate to include cost of all labour, tools, tackles, equipment, hire charges .3) The wall mounted Metering System to be kept in cage with locking facility, However payment for Structural work will be paid against SOR item 4.0
1628Installation of GI Pipe 2\\" - 1\\" size with isolation valve for commercial meter inlet connection from TF
1629Removal of MRS/ Metering Skids, Wall Mounted MRS/Metering System (all capacities) from existing consumer's premise,
1630Removal of MRS/ Metering Skids, Wall Mounted Metering System (all capacities) from existing consumer's premise for shifting to another site/store. The scope of work also includes excavation to retrive PE pipe line , disconnection of existing pipe lines (PE & Steel).
1631Note:- Transportaion of removed metering skid/Wall mounted Metering System to store shall be payble under SOR item no.5.4.2. However, if this skid is being shifted directly to new location for installation at new customer premises then transportation to be claimed from 5.1 & 5.2 as applicable.
1632Transportaion of removed metering skid/Wall mounted Metering System to store
1633Conversion of Commercial Appliances/Industrial :
1634Conversions of all types of commercial appliances to NG based appliances. Supply & changing of the nozzles /jets and associated controls for Non-domestic appliances (imported appliances included) with proper tools and tackles. Cleaning and performing minor maintenance, greasing etc. of the appliance. Testing and showing the performance to the customer, signing of joint meter records (JMR) and instructing the customer on use & safety norms, complete as per specifications & to satisfaction of owner / Engineer in Charge and includes supply of reinforced rubber hose with requisite pressure rating.Supply of Appliance valve is also included.
1635Installation of ASTM A106, Gr. B, Seamless, BE , NB, XS pipes of various dia
1636ASTM A106, Gr. B, Seamless, PE , 1/2\\" NB, S160 , their fittings and installation of meter and regulator (as applicable)
1637ASTM A106, Gr. B, Seamless, PE , 1\\" NB, XS , their fittings and installation of meter and regulator (as applicable)
1638ASTM A106, Gr. B, Seamless, PE, 1.5\\" NB, XS , their fittings and installation of meter and regulator (as applicable)
1639ASTM A106, Gr. B (Charpy), Seamless, BE , 2\\" NB, XS , their fittings and installation of meter and regulator (as applicable)
1640ASTM A106, Gr. B (Charpy), Seamless, BE , 3\\" NB,XS , their fittings and installation of meter and regulator (as applicable)
1641ASTM A106, Gr. B (Charpy), Seamless, BE , 4\\" NB,XS , their fittings and installation of meter and regulator (as applicable)
1642Note:a). Supply & Installation of required size of brass fittings (which are not included in SOR item 8.0 to 23.0) in all type of meters (supplied by GAIL GAS LTD. ) shall be in scope of contractor.b). All butt welded fittings end shall generally match with connecting pipe wall thickness. However, in case of misalignment, Contractor shall have to do end preparation without any extra cost. c). Payment of radiography of joints (4\\" and below ) shall be paid seperately under SOR item for RADIOGRAPHY mentioned elsewhere in this SOR 25.0d). All type of piping works shall be carried out as per piping material specification (PMS).e). Complete Carbon Steel Piping Work with painting including all fittings, flanges and supply of all required gaskets, studs bolts & nuts etc.
1643Supply of CARBON STEEL PIPES as per Technical Specification and as directed by EIC
1644ASTM A106, Gr. B, Seamless, PE , 1/2\\" NB, S160
1645ASTM A106, Gr. B, Seamless, PE , 1\\" NB, XS
1646ASTM A106, Gr. B, Seamless, PE, 1.5\\" NB, XS
1647ASTM A106, Gr. B (Charpy), Seamless, BE , 2\\" NB, XS
1648ASTM A106, Gr. B (Charpy), Seamless, BE , 3\\" NB,XS
1649ASTM A106, Gr. B (Charpy), Seamless, BE , 4\\" NB,XS
1650Supply of Pressure Gauges as per Technical Specification and as directed by EIC
1651RANGE 0-100 MBAR - 4\\"- DIAL SIZE
1652RANGE 0-1 BAR - 4\\"- DIAL SIZE
1653RANGE 0-4 BAR - 4\\"- DIAL SIZE
1654RANGE 0-6 BAR - 4\\"- DIAL SIZE
1655RANGE 0-30 BAR - 4\\"- DIAL SIZE
1656Supply of Conical Stainer
1657As per Technical Specification and as directed by EIC.Note: - Conical Stainer may be free issue by Gail Gas Ltd., It is Discretion of Gail Gas Ltd. to excute the SOR or Free Issue the material.
1658Supply of Check valve/NRVAs per Technical Specification and as directed by EIC.
16592\\", 150# FE,FB
16603\\", 150# FE,FB
16614\\", 150# FE,FB
1662Supply of Flanges Weld Neck(End Thickness to match pipe thickness)
16631\\" , 150#, B-16.5 , A105 ,125 AARH,SW,RF
16641.5\\" , 150#, B-16.5 , A105 ,125 AARH,SW,RF
16652\\",150#, B-16.5, A105 (Charpy), 125 AARH, RF
16663\\",150#, B-16.5, A105 (Charpy), 125 AARH, RF
16674\\",150#, B-16.5, A105 (Charpy), 125 AARH, RF
1668Supply of Blind FlangesAs per Technical Specification and as directed by EIC.
16692\\",150#, B-16.5, A105 (Charpy), 125 AARH, RF
16703\\",150#, B-16.5, A105 (Charpy), 125 AARH, RF
16714\\",150#, B-16.5, A105 (Charpy), 125 AARH, RF
1672Supply of End Caps
16732\\", XS, A 234 Gr. WPB (Charpy), BW
16743\\", XS, A 234 Gr. WPB (Charpy), BW
16754\\", XS, A 234 Gr. WPB (Charpy), BW
1676Supply of FLANGE END GLOBE VALVES, MAOP- 4 BARAs per Technical Specification and as directed by EIC.
1677Supply of Ball ValvesAs per Technical Specification and as directed by EIC.
16781/2\\",800#, Sockolet Welded/Threaded Valve
16791\\",800#, Sockolet Welded/Threaded Valve
16802\\",150#,FE, FB,
16813\\",150#,FE, FB,
16824\\",150#,FE, FB,
1683Supply of Isolation Ball Valve And Appliance Valve as per Technical Specification and as directed by EIC
1684Isolation Ball Valve ½\\" max. 6 bar (g)
1685Isolation Ball Valve 1\\" max. 6 bar (g)
1686Isolation Ball Valve 1.5\\" max. 6 bar (g)
1687Isolation Ball Valve 2\\" max. 6 bar (g)
1688Isolation Ball Valve 3\\" max. 6 bar (g)
1689Supply of SOCKOLET (A105, SW) As per Technical Specification and as directed by EIC.
16902\\" x ½\\"
16912\\" x 1\\"
16923\\" x ½\\"
16933\\" x 1\\"
16944\\" x ½\\"
16954\\" x 1\\"
1696Supply of Reducer (A 234 Gr. WPB (Charpy), BW)
16971.5\\" x 1\\", XS x XS, A105, SW,3000#, B-16.11
16982\\"x1\\", XS x XS, A 234 Gr. WPB (Charpy), BW, B-16.9
16992\\" X 1.5\\", XS , A 234 Gr. WPB (Charpy), BW, B-16.9
17003\\"x1\\", XS x XS, A 234 Gr. WPB (Charpy), BW, B-16.9
17013\\" X 1.5\\", XS , A 234 Gr. WPB (Charpy), BW, B-16.9
17023\\" x 2\\" , STD x XS, A 234 Gr. WPB (Charpy), BW, B-16.9
17034\\" x 3\\" , STD x XS, A 234 Gr. WPB (Charpy), BW, B-16.9
1704Supply of Tee, Equal / Reducing Tee
17051\\", XS, SW, 3000#, B-16.11
17061.5\\", XS, A105, SW, 3000#, B-16.11
17072\\" x 1.5\\", XS , A234, Gr. WPB (Charpy), B-16.9, BW
17082\\", XS , A234, Gr. WPB (Charpy), B-16.9, BW
17093\\", STD , A234, Gr. WPB (Charpy), B-16.9, BW
17104\\" STD x XS, A234, Gr. WPB (Charpy), B-16.9, BW
1711Supply of ELBOW, 90° Elbow
1712½\\", XS, SW, 3000#, ASTM A105,B-16.11
17131\\", XS, SW, 3000#, ASTM A105,B-16.11
17141.5\\", XS, SW, 3000#, ASTM A105,B-16.11
17152\\", XS, BW, A234, Gr. WPB (Charpy), B-16.9, 1.5D
17163\\", STD, BW, A234, Gr. WPB (Charpy), B-16.9, 1.5D
17174\\", XS, BW, A234, Gr. WPB (Charpy), B-16.9, 1.5D
1718Supply of Spectacle Blind AS PER SPECIFICATION
1719Spectacle Blind 2\\"
1720Spectacle Blind 3\\"
1721Spectacle Blind 4\\"
1722Supply of Internal/external piping support (AS PER Tender)
1723TYPE-1, SIDE WALL MOUNTED AS PER DRAWING
1724TYPE-2, GROUND BASED AS PER DRAWING
1725TYPE-3, CEILING MOUNTED AS PER DRAWING
1726WELDING OF JOINTS - Butt Weld Joints
17271/2\\" (WELDING OF JOINTS)
17281\\" (WELDING OF JOINTS)
17291.5\\" (WELDING OF JOINTS)
17302\\" (WELDING OF JOINTS)
17313\\" (WELDING OF JOINTS)
17324\\" (WELDING OF JOINTS)
1733Note: i) All butt welded fittings end shall generally match with connecting pipe wall thickness however in case of misalignment Contractor shall have to do end preparation without any extra cost.ii) All coupling, nipples etc. as required shall be supplied by contractor but no separate payments shall be made as it is covered under erection rate.
1734RADIOGRAPHY OF JOINTS
1735Performance of radiographic inspection by gamma radiation as per scope of work and as per specifications in piping of all types and thickness including providing/hiring of all necessary equipments, supply of all consumables, and whatever else even though not expressely mentioned but required to perform the work as per specifications and instructions of Engineer-in-Charge (full circle re-radiography of the repaired joint and additional radiography necessitated due to poor performance of contractor's welder shall be carried out by the Contractor at his own cost and shall not be paid extra by Company). Radiographs shall be submitted to the Engineer-in-Charge for acceptance, whose decision shall be final and binding.
1736Note- i). 4\\" & Below and all butt weld joint are radiography / X-ray shall be done at every joint and shall be carried out as per API 1104 (latest edition) / M/s GAIL Gas Ltd. specification / OISD / PNGRB and same shall be approved by Engineer–in–charge (EIC)/RCM.ii). All socket weld joint MPT/UT/DPT shall be done at every joint nd shall be carried out as per API 1104 (latest edition)/M/s GAIL Gas Ltd. specification / OISD / PNGRB and same shall be approved by Engineer–in–charge (EIC)/ RCM.
17371/2\\" (RADIOGRAPHY of Joints as Above)
17381\\" (RADIOGRAPHY of Joints as Above)
17391.5\\" (RADIOGRAPHY of Joints as Above)
17402\\" (RADIOGRAPHY of Joints as Above)
17413\\" (RADIOGRAPHY of Joints as Above)
17424\\" (RADIOGRAPHY of Joints as Above)
1743Note: i) Quantities mentioned against each above item of SOR Items are tentative and may increase or decrease during execution of work depending upon site requirement. Contractor required to supply materials after assessing the site requirement and in multiple lot or as per Release Order/ Sub Purchase Order wise. All material either in multiple lot or as per Release Order/ Sub Purchase Order wise or as decided by EIC shall be supplied by bidder within the quoted price.(ii) The quantites of individual item can varied as per site requirement.The payment will be made as per actual certified measurement at site. For the supply items the quantities shall be procured after approval from client/ consultant/EIC.(iii) The bidder must indicate currency(ies) against each quoted item of the SOR.(iv) The total amount shall also be given by the bidder in the quoted currency(ies).(v) Some of the may / may not be execute as per site requirements.
1744Ground Connectivity Works
1745Laying of MDPE pipeline by any method in any type of soil strata upto 20m length from charged Pipeline to Customer premise including connection of Transistion Fitting at customer end. For pipeline laid more than 20m, payment for additonal length shall be covered in SOR no.2 in ruuning meters more than 20m.
1746PE 20mm dia
1747PE 32mm dia
1748PE 63mm dia
1749PE 90mm dia.
1750Survey, Pit Excavtion in all types of soills/PCC/RCC/Paver block/Ashpalt/Whitetopping etc., charged pipeline identification, Hook up activities, Online tapping either by Saddle / Tee / extension by Coupler for connecting the Pipeline laid as per above SOR 1.1 including fittings, Backfilling. Restoration shall be paid through other SOR
1751Connectiviy for PE 20mm dia laid under 1a.
1752Connectiviy for PE 32mm dia laid under 1a.
1753Connectiviy for PE 63mm dia laid under 1a.
1754Connectiviy for PE 90mm dia laid under 1a.
1755PE PIPELINE
1756PE Pipe Laying in any type of surface like unprepared surface (Katcha surface)/ Normal Surface/ Hard surface/Rock surface etc using open cut/ Moling (without Casing)/ Moling (with Casing)/ Horizontal Directional Drilling technique (with and without casing pipe) methodology. HDD at Hard Rock shall be paid through different SOR.
1757Receipt. Loading. unloading. storing. reloading. tranportation. unloading. stringing and laying of PE100. SDR11 line pipes of all sizes including. proper stacking. identification.and supply of accessories of all sizes & thickness like PE Bends. Couplers. Endcaps. Tee. Reducer. CS / GI to PE Fittings (i.e. Transition Fittings of sizes 20 mm to 90 mm). Warning Mat etc. Handling. Stringing / uncoiling. aligning of the PE line pipe on the pipeline Right-of-Use / route. laying / installation of PE line pipe alongwith required accessories as mentioned above as per specification wherever required depending on site condition including execution of all works; Storeage of material in contractor's store. fabrication. access for construction procurement and supply of all materials. consumables. equipments. labour and other inputs.
1758In the case of free issue items. the scope also includes. receiving and loading from Owner's designated store. transportation. unloading and stacking of free issue items at Contractor's store. -Laying of all PE pipe (PE 100 SDR11). Including supply of HDPE casing pipe (in case of HDD (with case).Moling(with case) . Couplers. End caps etc. (Ref. of Particular job specification).Survey of under ground utilities. execution of the work as per specification. including excavation of pits moling with the hole size not exceeding 20% of the pipe dia. jointing and insertion of carrier pipe with casing. testing & commissioning and restoration of the pits to original condition. submission of As-Built Graph as per specifications and the instruction of Engineer-in-charge.
1759Casing details is as given below:-1. For 20/32 mm PE pipe (in 75 mm dia. HDPE Casing Pipe. PE 63/80 PN6.0).2. For 63 mm PE pipe (in 125 mm dia. HDPE Casing Pipe. PE 63/80 PN6.0).
1760Carrying out all temporary. ancillary. auxiliary works required to make the PE pipeline ready for commissioning as per drawings. Specifications. scope of work indicated in PJS and other provisions of tender/ contract documents and instructions of Engineer-in-charge. including but not limited to carrying out the following works:Surveying of route and detours required at the time of execution. preparation of construction drawings showing survey details and submit same to Owner for review / approval.
1761Carrying out preliminary activities such as preperation of drawings wherever required for crossing etc.Preparation and getting approval of schedules. execution procedures. drawings/ sketches/ wherever required. making trial pits to determine the underground utilities/ services etc.. restoration of the abandoned trial pits to original condition.
1762Stacking and installation of construction markers. clearing. fencing. grubbing. cutting of trees. full filling all the requirements of various statutory/ environment authorities to the entire satisfaction of concerned authorities. grading of work area.
1763Barricading the work area as per local authorities norms & to the satisfaction of Owner/ Eingineer -in- charge. installation of safety signs.Barricading the pipeline construction area prior to execution of the works as per drawing enclosed with tender/ contract documents and to the entire satisfaction of owner / engineer- in -charge.
1764Laying using open trench without casing includes survey of under ground utilities (through trial pits). execution of work as per specification including Trenching to all depths by excavation in all types of soils including soft/ rocky strata and different type of pavement / footpath / roads etc. including rock breaking. chiselling or otherwise cutting etc. as required and storing excavated soil. reusable materials at designated area as directed by Engineer in charge and to a width to accommodate the pipeline as per the relevant standard/ specification etc.
1765The minimum depth of the top of pipeline shall be 1.0 m measured from top of pipeline to the top of undisturbed surface of the soil or as per Specification/ OISD- 226 & PNGRB latest guidelines whichever is higher.Dewatering of trenches / pits if required as per site condition. Repairing of all damaged utilities if any. and payment of any compensation (if claimed by owner / other utility agencies)Uncoiling / stringing & aligning of PE pipes. clamping. jointing of the pipe ends / fittings / valves by qualified personnel using approved electro-fusion techniques as per specification.Note:- Coordinates to be taken for implementation for GIS for Valve pit, Fusion welding location and MRS.
1766Installation / lowering the pipeline in trench to required depth as per PJS. Technical Specification & drawings. supply & placement of HDPE Yellow colour warning mat (refer PJS) over the pipeline along the complete route as per standard drawings. data sheets & technical specifications. padding around pipeline including supply of suitable padding material duly approved by EIC. Backfilling to its original condition with excavated earth / borrowed select soil/sand duly approved by EIC & its compaction & crowning. At certain specific area of ROU. trench shall be backfilled & compacted and shall be made ready for motorable and no seperate payment shall be admissible against this activity.All tiles / slabs / curb stones etc removed during excavation shall be placed properly.Restoration shall be carried as per separate SOR item mentioned elsewhere in the SOR or to be done by Owner / concerned authorities.
1767The scope of work against this item also include Electro-fusion jointing of valves. fittings wherever required and as directed by Engineer-in-charge.The scope of work against laying of 20 mm pipe also includes works like making of PCC pedastal of grade (1:2:4) and size ( (300mm(L)X200mm(W) XHeight (H)). (H>=300mm & will be as per site condition) ). supply and installation of GI Sleeve (Heavy (C-Class) as per IS-1239). filling of sand and installation of TF (along with supply).
1768Pneumatic testing. purging with nitrogen and commissioning as per specification and approved procedures providing all tools and tackles. nitrogen. instruments. manpower and other related accessories and as per the instructions of the Engineer-in-charge.
1769Final clean-up of right-of-use or area disturbed by contractor during their construction activities for laying of pipeline works and disposal of debris and surplus material to designated disposal areas and backfilling of trench and compaction of the same as per satisfaction of Owner and / or as directed by Engineer–in–charge.
1770Maintaining the completed pipelines and installation for any defect or failures during defect liability period (i.e. 12 months from date of completion of work).Handing over the completed works to Owner for their operation/ use. reconciliation of material area wise and obtaining \\"no objection certificate\\" from Owner/ PMC.Preparation and submission of Daily progress report. Laying Graphs / PE line cards on daily basis.
1771On completion of gas charging of pipelines. Preparation and submission of As-built drawings. crossings details. termination. utility graphs and deviation statements.In case. the minimum required depth is not possible due to site condition. necessary mitigation measures with minimum permissible top cover shall be carried out by the contractor in consultation with EIC as per PNGRB Guidelines. without any time and cost implecation to owner.
1772Submission of all documents required for contract closure in numbers as mentioned in contract.Any other activities not mentioned / covered explicitly above. but otherwise required for satisfactory completion / operation / safety / statutory / maintenance of the works shall also be covered under the scope of work and has to be completed by the Contractor within specified schedule at no extra cost to Owner. All the work shall be executed in accordance with the provision of contract.
177320 mm PE 100 pipe
177432 mm PE 100 pipe
177563 mm PE 100 pipe
177690 mm PE 100 pipe
1777NOTE i) The lengths of pipelines are tentative. ii) For restoration of asphalt / concrete roads. the item for construction of asphalt top / concrete top / Tiles/Stone slab/Paver Blocks/Curb Stones shall be paid separately as per the rates quoted for the same elsewhere in the SOR 2.4.
1778GPR Survey for identification of pipeline
1779Laying of Pipeline by HDD in Rock Terrain
178032 mm PE 100 pipe
178163 mm PE 100 pipe
178290 mm PE 100 pipe
1783Restoration
1784Restoration of the roads. pavements. channels. footpaths. tiles. stones etc. to original condition including supply of the approved quality material required. as per local authorities norms. obtaining NOC from concerned local authorities / land owners / third party inspection agencies (if any) designated by owner and to the satisfaction of Engineer-in-charge.
1785Asphalting
1786Cement Concrete
1787Tiles/Stone slab/Paver Blocks/Curb Stones
1788Brick Soling / Channels. etc.
1789Installation of valve in pit including supply of valves
1790Supply of isolation valves (as per data sheet) and installtion of valves in the valve pits as per typical drawing and specification enclosed and instructions of Engineer-in-charge. Payment of valve pits shall be paid separately as per SOR 2.6.
1791PE Valve 20 mm dia
1792PE Valve 32 mm dia
1793PE Valve 63 mm dia
1794PE Valve 90 mm dia
1795Construction of Valve Pits as per the enclosed tender drawing and specification. The item includes supply of all the material including Pre-cast RCC cover. shuttering. reinforcement. labour. curing etc as per the drawings. specification and instruction of EIC.
1796Type-I having Internal size of Minimum 1000 x 1000mm
1797Type-II having Internal size of Minimum 600 x 600mm
1798Note: The tender drawing enclosed is only for reference purpose and contractor shall be required to prepare drawings (in line with reference tender drawing) for specific sizes of Valve pits and the same shall be approved by EIC.
1799Fabrication & Installation of Markers
1800RCC Route Markers
1801Supply, fabrication and installation of RCC route markers as per the attached drawing in technical volume, along the route including all associated civil works such as excavation and construction in all types of soils, construction and pedestals and grouting with concrete.
1802Pole Markers with Foundation
1803Supply, fabrication and installation of plate markers as per the attached drawings in technical volume including all associated civil works such as excavation and construction in all types of soils, construction and pedestals and grouting with concrete, cleaning, stencil let.
1804Warning Plate Markers
1805Supply, fabrication and installation of plate markers, including application of approved color and quality of primer and paint, stencil letter cutting of lettering, numbers, direction, etc. as per the attached drawing in technical volume to be installed near regulator.
1806Excavation of Hard rock/surface
1807Excavation of trench or pits, wherever hard rock presence is exceeding 1.5 m in any direction of the trench and excavation of trench or pits in Malba/Multiple layers of asphalt/ brick / PCC/RCC etc and removable only by pneumatic chisel / drill as per the specifications and direction of EIC. The rates are payable over and above the Laying rates as per relevant SOR no. 2.1
1808Cutting of PCC/RCC surface with thickness more than 12\\" or Continuous asphalt multi-layer/ Malba/ Brick / Boulders more than 24\\".(Malba shall be considered as a strata where soil is in mixed form of debris/building rubbish or discarded pieces of bricks/stones )
1809Rock Cutting encountered while excavation of trenches for item 2.1 of SOR, not exceeding 1.5 meter in width, and lift upto 1.5 meter, including getting out the excavated soil and disposal of excavated soil as directed within a lead of 50 meter. In case of rocky soil, the bedding shall be done with approved/ good quality packing sand, subject to the approval of the EIC, the size distribution of the sand / shall be the same as per soil. The packing sand shall be placed to a minimum thickness of 150mm around the pipe in case of rocky terrain.
1810Note: i) The quantities mentioned are indicative only. ii) For all the supply items mentioned above, procurement shall be made as per specification after due approval of engineer- in - charge.
1811Liaisoning with Land Owning Agencies for Permission
1812Submission of applications as per approved drawings (Initial Route survey, prepartion of drawing, measuring and providing details of surface type shall be in scope of contractor), obtaining and submission of demand note, coordination, Liaisoning, obtaining written permission from land owing agencies like NHAI, AAI,Indian Railways and any other government agencies resposible for maintaining public lands and agencies owing Private lands etc. (all fee paid to authorities excluding demand charges or Bank Guarantees shall be reimbursed against documentary evidence). Permissions required from various authorities like NHAI / Railways / Irrigation (Canal) etc. falling enroute shall be inclusive in the item rate. No separate liasion charges against construction of valve chambers is payable and is included in laying rates.
1813Construction of RCC structure for protection of service line for drain/nallah Crossings
1814Construction of Non suspended slabs/pavement slabs including pedestal/ramp etc.using reinforced cement concrete of M-25 grade (Concrete shall be design mix/nominal mix with 20 mm & down size graded crushed stone aggregates) to protect the PE pipe laid. All necessary form work, finishing the top surface rough/smooth as required in any position, shape, level and thickness etc. shall be as specified and directed by EIC. The rates shall include grouting of pockets, supply of all material, tools, reinforcement steel etc.
1815Preservation of Pipeline
1816Preservation of pipeline sections and associated facilities (in event of delay in comissioning, other unforeseen reasons) including supply of nitrogen, all consumables, all equipment, man-power, etc. complete as per the requirements of specifications, other provisions of tender/ contract documents and instructions of Engineer-in-charge.
1817By filling and pressurizing with nitrogen to a pressure of 2 bar(g) for a period of one month or part thereof.
1818For 20 mm Pipeline
1819For 32 mm Pipeline
1820For 63 mm Pipeline
1821For every additional period of one month or part thereof Limited to 6 month
1822For 20 mm Pipeline
1823For 32 mm Pipeline
1824For 63 mm Pipeline
1825Notes: i) The above length is not for a single section but for no. of sections. ii) All accessrious ie; End caps and two nos tappings of 3/4 inches, PG to be considered per section and rate for the same shall be quoted by bidder under this item.iii) If month is partially complete, payment shall be made on prorata basis.iv) Scope includes pressure holding for a period of 6 months or as per EIC and jointing of PE pipe (if required) due to damage by any means and further filling of nitrogen for pressure holding.v) Length given are tantative may change as per site requirments.
1826CIVIL WORKS
1827Earth Work
1828Earth in excavation and filling to the grades and levels shown in the approved drawings in all kinds of conditions including for Road embakments, using approved quality good earth from designated borrow area, for all heights and depths including clearing and stripping (min. 150 mm) of the area marked for filling, taking spot levels, consolidating the exposed natural soil surface, excavating the earth from borrow area loading, transporting & unloading, spreading in layers not exceeding 150 mm thickness, breaking clods, watering (if reqd.), ramming and compacting by manual/ mechanical means to give minimum 92% of modified Proctor's density of earth, testing & dressing including disposal of all unserviceable material all complete as per specifications and directions of Engineer-in-charge.
1829(Rate to include cost of all labour, tools, tackles, equipment, hire chanrges, cost of borrow earth by way of royalties, right of way, cess etc., as applicable with all bye works and sundry works).
1830PCC 1:2:4
18311 Cement : 2 Coarse sand : 4 stone aggregate 20mm nominal size.
1832PCC 1:4:8
18331 Cement : 4 Coarse sand : 8 stone aggregate 40mm nominal size.
1834(Rate to include cost of all labour, tools, tackles, equipment, hire charges, supply of all materials, shuttering, earthwork in excavation and backfilling using approved earth in all conditions etc. with all bye works and sundry works.)
1835Reinforced Cement Concrete
1836Providing and laying reinforced cement of grade M-25 with 20mm and down grade crushed stone aggregate in all types of structures like foundations, pedestals, pedestal bases, pipe supports, sleepers, column, equipment foundation, Non suspended slabs/pavement slabs, ramps, cable trench inlcuding construction joints, bitumen painting on surface in contact with soil, supplying and fixing reinforcing steel, shuttering, inserts, finishes, grounting etc. at all depths and heights complete as per drawings, specifications and direction of the Engineer-in-charge.
1837Rate to include cost of all labour, tools, tackles, equipment, hire charges, supply of all maerials such as minimum 43 grade cement including sulphate resistant cement for sub-structures, R/F steel, Inserts, bolts, conduits, bitumen, other minor constrcution materials, shuttering, stanging, earthwork in excavation and backfilling using serviceable earth in all conditions, shorting bailing and pumping out water, testing of concrete, curing etc. with all bye works and sundry works.
1838Concrete Pavement
1839Providing and laying reinforced cement concrete of (M-25 grade) with 20mm and down grade crushed stone aggregate in pavement, including preparation of base (i.e. compacted subgrade, 200 thk sand and 50 thk PCC M-10 grade), leaving pockets if necessary, making recess, projections, fixing inserts conduit pipes (GI, PVC, HDPE, etc.) laying in alternate panels, filling the gaps between the panels with bitumen etc., making slopes, finishing edges, leaving bars for pedestals & sleepers including providing sand fill isolation , shuttering, providing and fixing reinforcing steel, curing, chipping and modification works etc. as specified in any shape, thickness, position and finishing the top surface smooth as per requirement etc. all complete as per drawings, specifications and directions of the Engineer-in-charge.
1840Concrete Pavement- 150mm thick (Type-I)
1841Brick Work
1842Providing brick work with brick class designation M-7.5 of IS:1077 in cm1:4 (1 cement : 4 sand) in steps, walls, retaining walls and load bearing structures drains, or any shape with all lead, depths & height including curring, scaffolding, etc., as per specifications and drawings with all bye-works and direction of the Enfineer-in-charge.
1843(Rate to include cost of all labour, tools, tackles, equipment, hire charges, supply of all materials such as minimum 43 grade cement, bricks, finishes, bitumen, other minor constrcution materials, shuttering, staging, masonry work, plastering, painting etc. with all bye-works and sundry works).
1844Note: The quantites of individual item can varied as per site requirement.The payment will be made as per actual certified measurement at site.
1845Laying of Brick layer/ Concrete
1846Providing single layer of Brick / Concrete / or impact resistant tape to entire width of trench above Warning Mat placed in trench over the laid pipeline as per OISD 226, standard drawing, specification and instruction of Owner. (Rate to include cost of all labour, tools, tackles, equipment, hire charges & supply of all materials, etc)
1847Brick Layer for width of PE pipeline trench as per drawing (75 mm thk.)
1848Concrete for width of PE pipeline trench as per drawing (80 mm thk.)
1849Demolition of PCC work below plinth level
1850Demolishing plain cement concrete (PCC) work (taking all necessary safety precautions) for all depths below plinth level including supply of all tools & tackles, necessary scaffolding, propping, underpinning, etc. , disposal of unserviceable material outside the boundary limits keeping the owner indemnified of any liabilities from statutory/ local bodies, all complete work as specified and directed.
1851Excavation for foundation works
1852Excavation as per plan, upto 3 meters and upto any lead in all conditions, backfilling using serviceable earth and disposal of surplus and unserviceable earth. Soil to be levelled and neatly dressed complete in all respect as per scope of work, technical specification and directions of EIC.
1853Upto 3.0 Mtrs
1854Dismantling of RCC & cutting of reinforcement (Thickness above 3”)
1855Structural Works
1856Supplying, fabricating & fixing steel structural cage fabricated from Angle conforming to IS:808 & fixing of GI weldmesh made from 3mm GI wire @ 75 mm bothways to structural steel frame by means of welding/bolting, including applying two coats of approved quality of synthetic enamel paint over a priming coat of in approved shade including supply of all raw materials, bolts, electrodes, transportation, including Hilti arrangement ,locking arrangement for fixing of posts etc complete as per enclosed drawing, technical specifications, scope of works and directions of the Engineer-In-Charge. Note:- Material shall be supplied and fabricated as per site condition and Contractor have to take quantity approval from EIC/OWNER prior to commencement of work and order placement.
1857MRS / Metering Skid/Wall Mounted MRS.
1858Installation of MRS / Metering Skid on foundation
1859Receiving and taking over, handling, loading, transportation and unloading of MRS / Metering Skid from Owner's designated stockyards to site, installation at foundation and hooking up with PE pipe including all works as required to complete the job as per the drawings and specification, scope of work mentioned in tender doucment. The scope includes supply of transition fittings,GI Sleeve, other MDPE and CS fittings as required and various associated works to commission MRS / Metering Skid. (Note:- The installation included CS piping work included welding, testing, NDT etc.,however payment for the CS piping work along with accessories supply will be paid in SOR item 7.0 to 25.0 respectively.)
1860Note: 1) Amount towards civil work shall be payable as per related SOR items. 2) Rate to include cost of all labour, tools, tackles, equipment, hire charges.3) All fittings and consumables including Bolts, nuts, washer, U-clamps, gaskets etc. if required during installation shall be procured and supplied by the Contractor within the rate quoted. These items shall not be separately measured and paid.
1861MRS / Metering Skid <2000 SCMD
1862MRS / Metering Skid 2000-5000 SCMD
1863MRS / Metering Skid 5000-20000 SCMD
1864MRS / Metering Skid >20000 SCMD
1865Installation of Wall Mounted Metering System (Meter, Regulator & Accessory) locked in cage
1866Receiving and taking over, handling, loading, transportation and unloading of all items for Wall Mounted Metering System (Meter, Regulator & Accessory) from Owner's designated stockyards to site, installation on wall and hooking up with PE pipe including all works as required to complete the job as per the drawings and specification, scope of work mentioned in tender doucment.The scope includes supply of items required as per the drawing in scope of work (Details of drawings as PJS) viz. transition fittings, GI/Concrete Sleeves and other MDPE and CS fittings etc. as required and various associated works.(Only Meters and Regulators shall be provided as free issue) and all associated works (For CS pipe and other items refer sl. no. 7.0 to 25.0) to commission Wall Mounted Metering System. Note : Installation works included CS piping work, Testing etc.,however payment for the CS piping work along accessories will be paid in diiferent SOR item
1867Note: 1) Amount towards civil work shall be payable as per relevant SOR items. 2) Rate to include cost of all labour, tools, tackles, equipment, hire charges .3) All fittings (those are not mentioned in SOR item 7.0 to 25.0) and consumables including Bolts, nuts, washer, U-clamps, gaskets etc. if required during installation shall be procured and supplied by the Contractor within the rate quoted. These items shall not be separately measured and paid.4)The wall mounted Metering System to be kept in cage with locking facility, However payment for Structural work will be paid against SOR item 4.0
1868The Typical Design of MRS/Metering System are as per \\"Standardized metering system Design, Selection & Installation philosophy for supply of PNG to Industrial and Commercial Customers of GAIL Gas.\\"Note: -The sizes mentioned in drawings are indicative & may vary as per actual requirment at site .
1869Wall Mounted Metering System < 200 SCMD
1870Wall Mounted Metering System 200-500 SCMD
1871Wall mounted Metering System 500 to 2000 SCMD
1872Wall mounted Metering System >2000 SCMD
1873Note: i) The quantities mentioned are indicative only. ii) For all the supply items mentioned above, procurement shall be made as per specification after due approval of engineer- in - charge.
1874Installation of Wall Mounted Metering System (Pre-assemble)
1875Receiving and taking over, handling, loading, transportation and unloading of all items for Wall Mounted Metering System (Pre-assembled as per standard drawing Attached in PJS Drawing ) from Owner's designated stockyards to site, installation on wall and hooking up with PE pipe including all works as required to complete the job as per the drawings and specification, scope of work mentioned in tender doucment.The scope includes supply of transition fittings, Sleeves and other MDPE and CS fittings etc. as required and various associated works, however, the Metering System assembly ( As per drawing ) shall be provided as free issue by GAIL Gas. Installtion work done by Contractor along supply of consumables including Bolts, nuts, washer, U-clamps, gaskets etc. if required during installation shall be procured and supplied by the Contractor within the rate quoted.
1876Note: 1) Amount towards civil work shall be payable as per related SOR items 3.0. 2) Rate to include cost of all labour, tools, tackles, equipment, hire charges .3) The wall mounted Metering System to be kept in cage with locking facility, However payment for Structural work will be paid against SOR item 4.0
1877Installation of GI Pipe 2\\" - 1\\" size with isolation valve for commercial meter inlet connection from TF
1878Removal of MRS/ Metering Skids, Wall Mounted MRS/Metering System (all capacities) from existing consumer's premise,
1879Removal of MRS/ Metering Skids, Wall Mounted Metering System (all capacities) from existing consumer's premise for shifting to another site/store. The scope of work also includes excavation to retrive PE pipe line , disconnection of existing pipe lines (PE & Steel).
1880Note:- Transportaion of removed metering skid/Wall mounted Metering System to store shall be payble under SOR item no.5.4.2. However, if this skid is being shifted directly to new location for installation at new customer premises then transportation to be claimed from 5.1 & 5.2 as applicable.
1881Transportaion of removed metering skid/Wall mounted Metering System to store
1882Conversion of Commercial Appliances/Industrial :
1883Conversions of all types of commercial appliances to NG based appliances. Supply & changing of the nozzles /jets and associated controls for Non-domestic appliances (imported appliances included) with proper tools and tackles. Cleaning and performing minor maintenance, greasing etc. of the appliance. Testing and showing the performance to the customer, signing of joint meter records (JMR) and instructing the customer on use & safety norms, complete as per specifications & to satisfaction of owner / Engineer in Charge and includes supply of reinforced rubber hose with requisite pressure rating.Supply of Appliance valve is also included.
1884Installation of ASTM A106, Gr. B, Seamless, BE , NB, XS pipes of various dia
1885ASTM A106, Gr. B, Seamless, PE , 1/2\\" NB, S160 , their fittings and installation of meter and regulator (as applicable)
1886ASTM A106, Gr. B, Seamless, PE , 1\\" NB, XS , their fittings and installation of meter and regulator (as applicable)
1887ASTM A106, Gr. B, Seamless, PE, 1.5\\" NB, XS , their fittings and installation of meter and regulator (as applicable)
1888ASTM A106, Gr. B (Charpy), Seamless, BE , 2\\" NB, XS , their fittings and installation of meter and regulator (as applicable)
1889ASTM A106, Gr. B (Charpy), Seamless, BE , 3\\" NB,XS , their fittings and installation of meter and regulator (as applicable)
1890ASTM A106, Gr. B (Charpy), Seamless, BE , 4\\" NB,XS , their fittings and installation of meter and regulator (as applicable)
1891Note:a). Supply & Installation of required size of brass fittings (which are not included in SOR item 8.0 to 23.0) in all type of meters (supplied by GAIL GAS LTD. ) shall be in scope of contractor.b). All butt welded fittings end shall generally match with connecting pipe wall thickness. However, in case of misalignment, Contractor shall have to do end preparation without any extra cost. c). Payment of radiography of joints (4\\" and below ) shall be paid seperately under SOR item for RADIOGRAPHY mentioned elsewhere in this SOR 25.0d). All type of piping works shall be carried out as per piping material specification (PMS).e). Complete Carbon Steel Piping Work with painting including all fittings, flanges and supply of all required gaskets, studs bolts & nuts etc.
1892Supply of CARBON STEEL PIPES as per Technical Specification and as directed by EIC
1893ASTM A106, Gr. B, Seamless, PE , 1/2\\" NB, S160
1894ASTM A106, Gr. B, Seamless, PE , 1\\" NB, XS
1895ASTM A106, Gr. B, Seamless, PE, 1.5\\" NB, XS
1896ASTM A106, Gr. B (Charpy), Seamless, BE , 2\\" NB, XS
1897ASTM A106, Gr. B (Charpy), Seamless, BE , 3\\" NB,XS
1898ASTM A106, Gr. B (Charpy), Seamless, BE , 4\\" NB,XS
1899Supply of Pressure Gauges as per Technical Specification and as directed by EIC
1900RANGE 0-100 MBAR - 4\\"- DIAL SIZE
1901RANGE 0-1 BAR - 4\\"- DIAL SIZE
1902RANGE 0-4 BAR - 4\\"- DIAL SIZE
1903RANGE 0-6 BAR - 4\\"- DIAL SIZE
1904RANGE 0-30 BAR - 4\\"- DIAL SIZE
1905Supply of Conical Stainer
1906As per Technical Specification and as directed by EIC.Note: - Conical Stainer may be free issue by Gail Gas Ltd., It is Discretion of Gail Gas Ltd. to excute the SOR or Free Issue the material.
1907Supply of Check valve/NRVAs per Technical Specification and as directed by EIC.
19082\\", 150# FE,FB
19093\\", 150# FE,FB
19104\\", 150# FE,FB
1911Supply of Flanges Weld Neck(End Thickness to match pipe thickness)
19121\\" , 150#, B-16.5 , A105 ,125 AARH,SW,RF
19131.5\\" , 150#, B-16.5 , A105 ,125 AARH,SW,RF
19142\\",150#, B-16.5, A105 (Charpy), 125 AARH, RF
19153\\",150#, B-16.5, A105 (Charpy), 125 AARH, RF
19164\\",150#, B-16.5, A105 (Charpy), 125 AARH, RF
1917Supply of Blind FlangesAs per Technical Specification and as directed by EIC.
19182\\",150#, B-16.5, A105 (Charpy), 125 AARH, RF
19193\\",150#, B-16.5, A105 (Charpy), 125 AARH, RF
19204\\",150#, B-16.5, A105 (Charpy), 125 AARH, RF
1921Supply of End Caps
19222\\", XS, A 234 Gr. WPB (Charpy), BW
19233\\", XS, A 234 Gr. WPB (Charpy), BW
19244\\", XS, A 234 Gr. WPB (Charpy), BW
1925Supply of FLANGE END GLOBE VALVES, MAOP- 4 BARAs per Technical Specification and as directed by EIC.
1926Supply of Ball ValvesAs per Technical Specification and as directed by EIC.
19271/2\\",800#, Sockolet Welded/Threaded Valve
19281\\",800#, Sockolet Welded/Threaded Valve
19292\\",150#,FE, FB,
19303\\",150#,FE, FB,
19314\\",150#,FE, FB,
1932Supply of Isolation Ball Valve And Appliance Valve as per Technical Specification and as directed by EIC
1933Isolation Ball Valve ½\\" max. 6 bar (g)
1934Isolation Ball Valve 1\\" max. 6 bar (g)
1935Isolation Ball Valve 1.5\\" max. 6 bar (g)
1936Isolation Ball Valve 2\\" max. 6 bar (g)
1937Isolation Ball Valve 3\\" max. 6 bar (g)
1938Supply of SOCKOLET (A105, SW) As per Technical Specification and as directed by EIC.
19392\\" x ½\\"
19402\\" x 1\\"
19413\\" x ½\\"
19423\\" x 1\\"
19434\\" x ½\\"
19444\\" x 1\\"
1945Supply of Reducer (A 234 Gr. WPB (Charpy), BW)
19461.5\\" x 1\\", XS x XS, A105, SW,3000#, B-16.11
19472\\"x1\\", XS x XS, A 234 Gr. WPB (Charpy), BW, B-16.9
19482\\" X 1.5\\", XS , A 234 Gr. WPB (Charpy), BW, B-16.9
19493\\"x1\\", XS x XS, A 234 Gr. WPB (Charpy), BW, B-16.9
19503\\" X 1.5\\", XS , A 234 Gr. WPB (Charpy), BW, B-16.9
19513\\" x 2\\" , STD x XS, A 234 Gr. WPB (Charpy), BW, B-16.9
19524\\" x 3\\" , STD x XS, A 234 Gr. WPB (Charpy), BW, B-16.9
1953Supply of Tee, Equal / Reducing Tee
19541\\", XS, SW, 3000#, B-16.11
19551.5\\", XS, A105, SW, 3000#, B-16.11
19562\\" x 1.5\\", XS , A234, Gr. WPB (Charpy), B-16.9, BW
19572\\", XS , A234, Gr. WPB (Charpy), B-16.9, BW
19583\\", STD , A234, Gr. WPB (Charpy), B-16.9, BW
19594\\" STD x XS, A234, Gr. WPB (Charpy), B-16.9, BW
1960Supply of ELBOW, 90° Elbow
1961½\\", XS, SW, 3000#, ASTM A105,B-16.11
19621\\", XS, SW, 3000#, ASTM A105,B-16.11
19631.5\\", XS, SW, 3000#, ASTM A105,B-16.11
19642\\", XS, BW, A234, Gr. WPB (Charpy), B-16.9, 1.5D
19653\\", STD, BW, A234, Gr. WPB (Charpy), B-16.9, 1.5D
19664\\", XS, BW, A234, Gr. WPB (Charpy), B-16.9, 1.5D
1967Supply of Spectacle Blind AS PER SPECIFICATION
1968Spectacle Blind 2\\"
1969Spectacle Blind 3\\"
1970Spectacle Blind 4\\"
1971Supply of Internal/external piping support (AS PER Tender)
1972TYPE-1, SIDE WALL MOUNTED AS PER DRAWING
1973TYPE-2, GROUND BASED AS PER DRAWING
1974TYPE-3, CEILING MOUNTED AS PER DRAWING
1975WELDING OF JOINTS - Butt Weld Joints
19761/2\\" (WELDING OF JOINTS)
19771\\" (WELDING OF JOINTS)
19781.5\\" (WELDING OF JOINTS)
19792\\" (WELDING OF JOINTS)
19803\\" (WELDING OF JOINTS)
19814\\" (WELDING OF JOINTS)
1982Note: i) All butt welded fittings end shall generally match with connecting pipe wall thickness however in case of misalignment Contractor shall have to do end preparation without any extra cost.ii) All coupling, nipples etc. as required shall be supplied by contractor but no separate payments shall be made as it is covered under erection rate.
1983RADIOGRAPHY OF JOINTS
1984Performance of radiographic inspection by gamma radiation as per scope of work and as per specifications in piping of all types and thickness including providing/hiring of all necessary equipments, supply of all consumables, and whatever else even though not expressely mentioned but required to perform the work as per specifications and instructions of Engineer-in-Charge (full circle re-radiography of the repaired joint and additional radiography necessitated due to poor performance of contractor's welder shall be carried out by the Contractor at his own cost and shall not be paid extra by Company). Radiographs shall be submitted to the Engineer-in-Charge for acceptance, whose decision shall be final and binding.
1985Note- i). 4\\" & Below and all butt weld joint are radiography / X-ray shall be done at every joint and shall be carried out as per API 1104 (latest edition) / M/s GAIL Gas Ltd. specification / OISD / PNGRB and same shall be approved by Engineer–in–charge (EIC)/RCM.ii). All socket weld joint MPT/UT/DPT shall be done at every joint nd shall be carried out as per API 1104 (latest edition)/M/s GAIL Gas Ltd. specification / OISD / PNGRB and same shall be approved by Engineer–in–charge (EIC)/ RCM.
19861/2\\" (RADIOGRAPHY of Joints as Above)
19871\\" (RADIOGRAPHY of Joints as Above)
19881.5\\" (RADIOGRAPHY of Joints as Above)
19892\\" (RADIOGRAPHY of Joints as Above)
19903\\" (RADIOGRAPHY of Joints as Above)
19914\\" (RADIOGRAPHY of Joints as Above)
1992Note: i) Quantities mentioned against each above item of SOR Items are tentative and may increase or decrease during execution of work depending upon site requirement. Contractor required to supply materials after assessing the site requirement and in multiple lot or as per Release Order/ Sub Purchase Order wise. All material either in multiple lot or as per Release Order/ Sub Purchase Order wise or as decided by EIC shall be supplied by bidder within the quoted price.(ii) The quantites of individual item can varied as per site requirement.The payment will be made as per actual certified measurement at site. For the supply items the quantities shall be procured after approval from client/ consultant/EIC.(iii) The bidder must indicate currency(ies) against each quoted item of the SOR.(iv) The total amount shall also be given by the bidder in the quoted currency(ies).(v) Some of the may / may not be execute as per site requirements. Please Enable Macros to View BoQ information

AI Tender Summary

OUR REF NO 56180932
AUTHORITY Boards / Undertakings / PSU
TENDER VALUE Ref. Documents
LAST DATE 17-07-2026
Authority
Authority Name Gas Authority Of India Limited
Work Description Tender for Hiring Of Agencies For Gas Connectivity Works To Industrial And Commercial Consumer On 18 Months Annual Rate Contract (Arc) Basis For Giridh-Dhanbad, Saraikela-Kharsawan West Singhbhum, Dewas, Raisensehore-Shajapur (Rss), Meerut, Taj Trapezium Zone (Ttz), Puri-Ganjam-Nayagarh, Sundergarh Jharsuguda Geographical Areas (Gas) Of Gail Gas Limited.
Basic Detail
Tender No GAIL GAS/NOIDA/SAI/9555/26-27/37
Bidding Type Tender
Location
City Ghaziabad
State Uttar Pradesh
Key Dates
Publish Date 26 Jun 2026
Submission Date 17 Jul 2026
Open Date 20 Jul 2026
Finance
Tender Value Ref. Documents
Tender Fee Ref. Documents
EMD 20 Lakhs
Exemption Available
Document List
0a37ec81-013e-43b1-a720-52850df6deec.html
BOQ_329146.xls
Tendernotice_1.pdf
Vol_IIIA.pdf
Vol_IIIB.pdf
Vol_II_of_III.pdf
Vol_I_of_III_R1.pdf

Unlock Full AI Tender Summary

Get instant access to the complete AI-generated analysis — scope, eligibility, timeline & more.

Instant Access Secure Free
Your details are secure and used only for document delivery.

Tender Timeline

Jun 26, 2026
11:30 IST

Tender Published

Tender notice published.

Completed
Jul 17, 2026
17:00 IST

Bid Submission Deadline

Online submission via eProcurement portal.

Upcoming · 7 days
Jul 20, 2026

Bid Opening Date

Technical bids will be opened and evaluated.

Upcoming · 10 days

Tender Documents

Download All (ZIP) ↓
html

0a37ec81-013e-43b1-a720-52850df6deec.html

xls

BOQ_329146.xls

pdf

Tendernotice_1.pdf

pdf

Vol_IIIA.pdf

pdf

Vol_IIIB.pdf

pdf

Vol_II_of_III.pdf

pdf

Vol_I_of_III_R1.pdf

Disclaimer

We takes all possible care for accurate & authentic tender information. However users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender

TenderDetail
Loading tenders