| 1 | Earth work in Excavation in hard soil or gravelly soil within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge. |
| 2 | Cutting in disintegrated rock not requiring blasting to be removed by pick axes and crow bars and depositing materials within 50m initial lead and 1.5m initial lift including rough dressing as per direction and specification of the department including stacking the useful materials separately as per the direction of the Engineer-in-charge. |
| 3 | Providing filling manualy with aproved quality sand in layers not exceeding 150mm thick including watering ramming to proper density with cost,conveyance,royalty,taxces of materials ,labour & T&P etc complete as per direction of Engineer-In-Charge. |
| 4 | Providing Cement Concrete (1:3:6) with 40mm size clean crusher broken granite metal of approved quality from approved quarry including hoisting lowering & levelling in position ramming using vibrator to proper slope and levelling with cost conveyance taxes royality, labour of all materials and including hire & running charges of machineries T&P required for the work including supplying & cess as per the specifiction and direction of Engineer-in- charge (Crusher Broken ) |
| 5 | Providing Cement Concrete (1:4:8) with 40mm size clean hand broken granite metal of approved quality from approved quarry including hoisting lowering & levelling in position to required level in each layer not exceeding 15cm thick in foundation including frame work where necessary ramming using vibrator to proper slope and levelling curing dewatering with cost conveyance taxes royality, labour of all materials and including hire & running charges of machineries T&P required for the work including supplying & working of pumps and cess as per the specifiction and direction of Engineer-in- charge |
| 6 | Construction of Unreinforced Plain cement concrete Pavement over prepared base with cement @400 kg per cum with using 20mm & down graded size crusher chips quarried & free from weathered skin of approved quality including hoisting, lowering, laying the concrete in position to proper slope and level compacting in layers and finishing the exposed surface smooth for required time including cost, conveyance, royalty and other taxes of all materials complete as directed by the Engineer-in-charge. |
| 7 | Construction of embankment with approved material obtained from borrow pits with all lifts and leads, transporting to site by mechanical means within a lead of 5kms, spreading, grading to required slope and compacting to meet requirement of table 300-2 & Clause 305 of MoSRT&H Specifications for Road & Bridge works(4th Revision) including hire and running charges of Roller and all other machineries , cost, conveyance & royality of materials , T&P and Cess required for the work etc complete as per specification & direction of Engineer-in-Charge. |
| 8 | Providing and laying Reinforced cement concrete (1:1.5:3) with 12mm size clean crusher broken granite chips aggregate of approved quality from approved quarry including hoisting, lowering & levelling in position to required level in each layer not exceeding 15cm thick including frame work where necessary ramming using vibrator to proper slope and levelling curing dewatering if necessary with cost, conveyance taxes royalty labour of all materials and including hire and running charges of machinaries T&P required for the work including supplying and working of pumps and cess as per the specification and direction of Engineer-in-charge. (RCC WORK ) |
| 9 | Straighting bent up or coiled rods cutting,bending,cranking,hooking,welding or jointing(if required) the M.S. rods or tor steel & binding wires & tying the grills hoisting,lowering & placing in proper position as required for RCC works with cost,conveyance & taxes of MS rods or tor steel & binding wires of 18 to 20 gauge & labour withy all T&P required for the work etc. complete in all respect as per specification & direction of the Engineer-in-charge. (Weight of binding wires will not be considered for payment & payment will be made on weight of M.S. rods or tor steel only). Please Enable Macros to View BoQ information |