| 1 | [10.100.2]Cement Concrete 1:8:16 Flooring 2. Cement Concrete 1:8:16 with stone aggregate 40 mm size in foundation and plinth. [Through Rate] |
| 2 | [16.18]Gachi pilchi (done with silt clearance and berm dressing) with thickness of 30 cm (joints to be broken) by mechanical/ mannual means. [Through Rate] |
| 3 | [21.95.8]Providing lowering cutting jointing and testing RCC pipe class NP3 as per IS-458-2003 with spigot and socketed joints manufactured with ISI marked sulphate resistance cement as per ISI 12330 with rubber rings ISI marked antiternmite as required at site in to trenches for all depths and laying out the same to correct alignment gradients and levels including dressing and trimming and cutting of concrete beds and side of trenches, if required jointing with rubber rings in trenches and jointing with 1:3/2 cement sand mortar and with end dowels filled with 1:3/2 cement sand mortar and finishing the joints at an angle of 45 degree with faces of spigot of socket joints cutting and finishing the cut surface to a uniform finish etc. as fully described in item No. 21.38, item 21.44, item 21.45, and item 21.46 including cartage loading and unloading complete in all respects. the internal diametric of the sewer being: 8. 900 mm [Through Rate] |
| 4 | [3.1.1]By Mechanical Transport including loading, unloading and stacking 1. Lime, moorum, building rubbish [4km] |
| 5 | [4.12.1]Earth work in excavation by mechanical means (Hydraulic excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including getting out and disposal of excavated earth lead up to 50 m and lift up to 1.5 m, as directed by Engineer-in-charge. 1. All kinds of soil [Through Rate] |
| 6 | [5.23.2]Demolishing cement concrete manually/ by mechanical means including disposal of material within 50 metres lead as per direction of Engineer - in - charge. 2. Nominal concrete 1:2:4 or leaner mix (i/c equivalent design mix) [Through Rate] |
| 7 | [5.7.2]Demolishing brick work manually/ by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer-in-charge. 2. In lime mortar with old mughal bricks [Through Rate] |
| 8 | [6.1.2]Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work below plinth level and up to Floor IV level: 2. 1:2:4 (1 cement : 2 coarse sand (zone-III) : 4 graded stone aggregate 20 mm nominal size) [Through Rate] |
| 9 | [6.14.1]Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level : 1. 1:1.5:3 (1 cement : 1.5 coarse sand (zone-III): 3 graded stone aggregate 20 mm nominal size) [Through Rate] |
| 10 | [6.15.1]Reinforced cement concrete work in walls (any thickness), including attached pilasters, buttresses, plinth and string courses, fillets, columns, pillars, piers, abutments, posts and struts etc. above plinth level up to floor four level, excluding cost of centering, shuttering, finishing and reinforcement : 1. 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) : 3 graded stone aggregate 20 mm nominal size) [Through Rate] |
| 11 | [6.30.2]Centering and shuttering including strutting, propping etc. and removal of form for 2. Walls (any thickness) including attached pilasters, buttresses, plinth and string courses etc. [Through Rate] |
| 12 | [6.30.4]Centering and shuttering including strutting, propping etc. and removal of form for 4. Shelves (Cast in situ) [Through Rate] |
| 13 | [6.33.6]Steel reinforcement for R.C.C. work, where not included in the complete rate of RCC, including straightening, cutting, bending, placing in position, binding, wastage, overlaps, welded joints, spacer bars, chairs, stays, hangers and annealed steel wire etc. complete in all respect below plinth level Note: Reinforcement shall be measured in length including hooks, if any, separately for different diameters as actually used in work , excluding overlaps. Wastage, overlaps, couplings, welded joints, spacer bars, chairs, stays, hangers and annealed steel wire or other methods of binding & placing shall not be measured and cost of these items shall be deemed to be included in the rates for reinforcement. 6. Thermo-Mechanically Treated bars of grade Fe-500D or more [Through Rate] |
| 14 | [9.57.3]Providing and fixing on wall face Unplasticised Rigid PVC rain water pipes conforming to IS : 13592 Type A, including jointing with seal ring conforming to IS : 5382, leaving 10 mm gap for thermal expansion, (i) Single socketed pipes. 3. 150 mm diameter [Through Rate] Please Enable Macros to View BoQ information |