| 1 | Item no 1) Designing (aesthetically) andconstructing RCC ESR/ RCC sumps in M-300 mix of required capacity including excavation in all types of strata foundation concrete container walls bottom slab top RCC roof slab / or dome 20mm etc complete |
| 2 | Add For Hilly Airea |
| 3 | Item no 2) Providing and supplying in standard lengths Polyethelene Pipes, confirming to IS 4984 / 14151 / 12786 / 13488 with nesessary jointing material like mechanical connector i. e. thread / insert joint / quick release coupler joint / compression fitting joint or flanged joint excluding coupler/specials, including transportation and freight charges,inspection charges, loading / unloading charges,conveyance to the departmental stores & stacking etc 1) 63mm dia HDPE Pipe 8Kg |
| 4 | 50mm dia HDPE Pipe 8Kg |
| 5 | Item no 3) Excavation for foundation in earth soil of all types of sand, gravel, soft murum including removing the excavated materialsupto a distance of 50 Mt. Beyond the building area and lift up to 1.50meters, stacking and spreading as directed including dewateringUnless provided else where preparing the bed for foundation and necessary back filling ramming watering complete excluding shoring and strutting. |
| 6 | Item no 4) Excavation for foundation / pipe trenches insoft rock and old cement and lime masonry foundation asphalt road including removing the excavated material upto a distance of 50 M beyond the area and lifts as below, stacking as directed by Engineer-in-charge, normal dewatering, preparing the bed for foundation andexcluding backfilling, etc. complete |
| 7 | Item No.5)Lowering, Laying and Jointing HDPE/MDPE pipes in proper position including allspecials by compression fitting/electrofusion and butt fusion jointing procedure as per relevent ISCode complete with all materials for jointingprocedure like Electrofusion machine, Electricheater/butt fusion welding machine with hydraulic etc..1) 63mm dia HDPE Pipe 8Kg |
| 8 | 50mm dia HDPE Pipe 8Kg |
| 9 | Item No.5)Refilling the trenches from excavated stuff with soft material in 15 cm layers with all leads & lifts including consolidation surcharging etc complete |
| 10 | Item no 6) Providing double flange sluice valve confirming for IS- 14846 including worn geararrangements as per test pressure, stainlesssteel spindle, caps, including inspectioncharges, transportation upto departmentalstore, unloading, stacking excluding GSTlevied by GOI & GOM in all respect etc.complete. 1)50mm Sluice Valve |
| 11 | b) Air valve 15mm dia |
| 12 | Item No.7)Hydraulic testing of H. D. P. E./ M. D. P. E. pipe line to specified pressure including cost of all materials and labour and water for testing for specified length including cutting, placing end cap making arrangement for filling safe water using reciprocating type pumps which should be able to provide specified test pressure gauges and other necessary equipments, labour, operation charges, etc. required for testing. etc 1) 63mm dia HDPE Pipe 8Kg |
| 13 | 2) 50mm dia HDPE Pipe 8Kg |
| 14 | Item no 8) Providing and laying in situ cement concrete in proportion M-15 of trap metal for foundation and bedding including bailing out water manually, formwork, etc complete. |
| 15 | Item no 9)Providing & fixing Name board fitting charges etc complete. |
| 16 | Add 18% GST Please Enable Macros to View BoQ information |