| 1 | Fitting and erecting one HT PSC Single Pole in position, including fitting cross arm, digging and back filling pit in ordinary soil (as per standards), drawing sufficient length of GI earthing leads from F clamp through V cross arm to the ground for earthing (excluding provision of earthing). |
| 2 | Labour charges for loading HT A type pole from the stacking place and unloading the same at work site (transportation by any vehicle). |
| 3 | Providing Cable Tie |
| 4 | Dismantling (without damage) one LT PSC/RCC pole after disconnecting stays, strut etc. attached thereon and stacking the same. |
| 5 | Dismantling one damaged LT PSC/RCC Strut pole including removal of clamps and stacking. |
| 6 | Dismantling (without damage) LT stay including digging pit in all classes of soil and backfilling. |
| 7 | Dismantling (without damage) one km LT single phase 2 wire OH line conductor by dismantling cross arms, insulators and stacking the conductors in rolls properly. |
| 8 | Dismantling (without damage) one km LT three phase 4 wire OH line conductor by dismantling cross arms, insulators and stacking the conductors in rolls properly. |
| 9 | Dismantling (without damage) one km LT additional conductor line by dismantling cross arms, insulators and stacking the conductors in rolls properly. |
| 10 | Disconnecting and lowering down the single phase WP service connection with guy wire from the OH line and reconnecting the same after completing the line work. |
| 11 | Dismantling one damaged LT PSC/RCC pole after disconnecting stays, strut etc. attached thereon and stacking the same. |
| 12 | Dismantling (without damage) one LT PSC/RCC Strut pole including removal of clamps and stacking. |
| 13 | Disconnecting and lowering down the three phase WP service connection with guy wire from the OH line and reconnecting the same after completing the line work. |
| 14 | Dismantling one ordinary street light/CFL/LED fitting from existing pole and refitting the same on newly erected pole including disconnecting and reconnecting wires. |
| 15 | Fitting one LT 4 line cross arm on HT or LT existing poles including fitting insulators and binding the same with LT Line. |
| 16 | Providing concrete muffing of size 0.45x0. 45x1.5m (0.5m above GL and 1m below GL). Excavation 0.45x0.45x1m, concrete (1:3:6, 20mm)0.45x0.45x1.5m, Plastering (1:3) 12mm0.45x0.45mx5sides. |
| 17 | Additional rate for excavation of Pit for A type pole in Laterite. |
| 18 | Additional rate for excavation of Pit for A type pole in Hard Laterite. |
| 19 | Providing one Coil Earth using No.8 GI-earth wire (50mm dia, 115 turns) including digging separate pit (0.45x0.45x1.5m) at standard distance away from the pole/structure in ordinary soil & backfilling. |
| 20 | Providing/Inserting 2 line spacer on the existing LT OH line. |
| 21 | Providing/Inserting 3 line spacer on the existing LT OH line. |
| 22 | Fitting and erecting one HT A type Single Pole in position, including fitting cross arm, digging and back filling pit in ordinary soil (as per standards), drawing sufficient length of GI earthing leads from F clamp through V cross arm to the ground for earthing (excluding provision of earthing). |
| 23 | Fitting and providing one HT Stay for 11kV pole, including digging and back filling pit in ordinary soil. |
| 24 | Additional rate for excavation of one Pit for HT Pole/HT Stay in Laterite. |
| 25 | Fitting and providing one HT Fly stay for 11kV pole using HT PSC pole including digging and back filling pits in ordinary soil, drawing sufficient length of GI earth leads to the ground for earthing (excluding provision of earthing). |
| 26 | Labour charges for loading HT PSC pole from the stacking place and unloading the same at work site (transportation by any vehicle). |
| 27 | Stringing of 11 kV Aerial bunched cable of size 3 x 120+ 1 x 95 sqmm with bare/insulated Messenger through existing poles |
| 28 | Transporting poles by hired vehicle to a distance upto 5km and carrying upto 4 numbers of poles excluding loading& unloading charges. |
| 29 | Fitting and providing one Strut using A type pole, including digging and back filling pit in ordinary soil. |
| 30 | Fitting one set AB switch on existing DP, giving connection and drawing sufficient length of GI earthing leads to the ground for earthing, excluding provision of earthing. |
| 31 | Fitting one Additional2.4m/3m Channel cross arm (100x50x6mm), in existing 11kV DP including conveyance of materials. |
| 32 | Drilling hole of various sizes on existing Channel/Cross Arm. |
| 33 | Providing one Earth using GI earth pipe of size 38.1mm dia, 2.5m length including digging separate pit (0.45x0.45x2.5m) at standard distance (1.5m) away from the pole/structure in ordinary soil & backfilling the pit with 15cm alternate layer of charcoal, salt and sand up to 90cm from the bottom. including the cost of 20kg salt, 25kg charcoal, excluding supply of earth pipe. |
| 34 | Providing one Earth using GI earth pipe of size 38.1mm dia, 2.5m length including digging separate pit (0.45x0.45x2.5m) at a minimum distance of 1.5m away from the pole/structure and maintaining standard distance between different earth pipes in ordinary soil & backfilling. |
| 35 | Dismantling one 1x40W fluorescent tube fitting from the existing pole and refitting the same on newly erected pole including disconnecting and reconnecting wires. |
| 36 | Additional rate for excavation of one Pit for HT Pole/HT Stay in Hard Laterite. |
| 37 | Fitting and providing one Strut using HT PSC pole including digging and back filling pit in ordinary soil. |
| 38 | Erection of suspension clamp for 11KV ABC of any size |
| 39 | Fiting One No MVT on existing cross arm excluding termination work (for One phase) of any rating for 11 kV AB Cable |
| 40 | Doing one cable end termination on HT ABC of sizes Up to 3x150+1x120 sqmm and connecting to existing MVT or other terminals,using the cable end termination kit supplied departmentally including charges for cable jointer etc. Please Enable Macros to View BoQ information |