| 1 | Excavating, supplying and filling of local earth (including royalty) by mechanical transport upto a lead of 5km also including ramming and watering of the earth in layers not exceeding 20 cm in trenches, plinth, sides of foundation etc. complete. DSR 2.25a |
| 2 | 1:4:8 (1 Cement : 4 coarse sand (zone-III) derived from natural sources : 8 graded stone aggregate 40 mm nominal size derived from natural sources) DSR 4.1.8 |
| 3 | Brick work with common burnt clay F.P.S. (non modular) bricks of class designation 7.5 in foundation and plinth in Cement mortar 1:6 (1 cement : 6 coarse sand) : DSR 6.1.2 |
| 4 | Brick work with common burnt clay F.P.S. (non modular) bricks of super structure class designation 7.5 in superstructure above plinth level up to floor V level in all shapes and sizes in Cement mortar 1:6 (1 cement : 6 coarse sand) DSR 6.4.1 |
| 5 | 12mm Cement plaster with cement mortar in proportion of '1:6 cement & coarse sand of single coat for interior plastering upto floor two level including internal rounded angles chamfers, and rounded angles not exceeding 80mm. ln girth and linished even and smooth. PWD SOR Ch. 13 itom 1 |
| 6 | Reinforced cement concrete work in beams, suspended floors, roofs having slope up to 15° landings, balconies, shelves, chajjas, lintels, bands, plain window sills, staircases and spiral stair cases above plinthlevel up to floor five level, excluding the cost of centering, shuttering, finishing and reinforcement with 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) derived from natural sources : 3 graded stone aggregate20 mm nominal size derived from natural sources). DSR 5.3 |
| 7 | Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete upto plinth level/ above plinth (TMT bars of grade Fe-500D or more.. DSR 4.1.3 |
| 8 | Centering and shuttering including strutting, propping etc. Retaining walls, return walls, walls (any thickness) including attached pilasters, buttresses, plinth and string courses fillets, kerbs and steps etc.DSR 4.3.2 |
| 9 | 1:2:4 (1 cement : 2 coarse sand (zone-III) derived from natural sources : 4 graded stone aggregate 20 mm nominal size derived from natural sources) DSR 4.1.3 |
| 10 | Fine dressing of the ground. DSR -2020 itom-2.7 |
| 11 | Anti termite treatment of lawn area through premise 30.50% I P. one liter premise diluted in 499 liters water and applying solution @ 1.00 litre solution par sqm lawn or bed area.(two application) i/c cost of chemical)and as per direction of officer-in-charge.and as per direction of officer-in-charge.DSR -2020 itom-2.56 |
| 12 | Providing and laying Neelgiri/Mexican grass turf with earth 50mm to 60mm thickness of existing ground prepared with proper level and ramming with tools wooden (Dhurmos) and than rolling the surface with light roller make the surface smoothen and light waterning with sprinkler and maintenance for 30 days or more till the grass establish properly, as per direction of officer-in-charge.DSR- 2020 itom-2.33 |
| 13 | Structural steel work riveted, bolted or welded in built up sections, trusses and framed work, including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer all complete. DSR 10.2 |
| 14 | Providing corrugated G.S. sheet roofing including vertical / curved surface fixed with polymer coated J or L hooks, bolts and nuts 8 mm diameter with bitumen and G.I. limpet washers or with G.I. limpet washers filled with white lead, including a coat of approved steel primer and two coats of approved paint on overlapping of sheets complete (up to any pitch in horizontal/ vertical or curved surfaces), excluding the cost of purlins, rafters and trusses and including cutting to size and shape wherever required. 0.63 mm thick with zinc coating not less than 275 gm/ m² DSR 12.1.3 |
| 15 | Providing and fixing Chlorinated Polyvinyl Chloride (CPVC) pipes, having thermal stability for hot & cold water supply including all CPVC plain & brass threaded fittings. This includes jointing of pipes & fittings with one step CPVC solvent cement, trenching, refilling & testing of joints complete as per direction of Engineerin-Charge. External work. PWD SOR Ch.-23 itom no 3 (C) |
| 16 | Fullway Gate Valve. PWD SOR Ch.-21 itom no 120 |
| 17 | CPVC Plain Tee. PWD SOR Ch.-21 itom no 23 |
| 18 | UNISON Mild Steel Manual Pitch Roller, Capa city 1000 kilogramUNISON (UNISON GARDEN ROLL ER 2 TON 4MM) |
| 19 | Disposal of malva 05 km cartege loading & unloding as directed by EIC |
| 20 | P&F of Inauguration stone Board SiZE 0.90x3.00 |
| 21 | Add GST 18% |
| 22 | Add rs. estemate figer amount Please Enable Macros to View BoQ information |